Upload
stephen-mallowah
View
216
Download
0
Embed Size (px)
Citation preview
7/31/2019 Public Private Partnerships Short2(00)
1/7
Privatisation and Public-Private PartnershipsStephen O. Mallowah LLB (UNZA), LLM (UCL), MSc (SOAS)
Introduction
The use of private financing in the development of public infrastructure, although
controversial, is becoming increasingly popular around the world. This paper critically
examines some of the issues surrounding public-private partnerships (PPPs), and
discusses their impact on service delivery as well as their fiscal consequences. The firstpart of the paper defines the concept of PPPs and outlines their main characteristics. The
second part of the paper looks at the pros and cons of PPPs through various
perspectives. This is followed by an analysis of some of the experiences with PPPs in
the United Kingdom whose Private Finance Initiative (PFI) is now responsible for about
14% percent of public investment. The paper concludes with some suggestions for
effective use of PPPs.
Public-Private Partnerships - Characteristics
Public-private partnerships (PPPs) are arrangements where the private sector develops
infrastructure assets and supplies services that traditionally have been provided by
government. PPPs combine private sector capital and, sometimes, public sector capital
to improve public services or the management of public sector assets. By focusing on
public service outputs, its proponents believe they offer a more sophisticated and cost-effective approach to the management of risk by the public sector than is generally
achieved by traditional input-based public sector procurement.1
PPPs can be used to build and operate various types of infrastructure such as hospitals,
schools, prisons, roads, bridges, rail networks, and water treatment plants. The attraction
for governments is that in situations of budgetary constraints private financing can
support increased infrastructure investment without immediately adding to governmentborrowing and debt. This is coupled with the belief that the private sector can deliver
services more efficiently than the public sector, thus leading to higher quality services at
lower cost. For the private sector, PPPs provide new business opportunities.
PPPs have had the effect of significantly expanding the privatisation horizons and have
emerged as a means of obtaining private sector capital and management expertise for
infrastructure investment, to enable and overcome obstacles to privatisation. Thus in
addition to private execution and financing of public investment, PPPs have two other
important characteristics: there is an emphasis on service provision, as well as
investment, by the private sector; and significant risk is transferred from the government
to the private sector.2
1 Gerrard, Michael B, Public-Private Partnerships, Finance & Development, IMF Publications, September
2001, Volume 38, Number 32 IMF (2004) Public-Private Partnerships, Washington: Fiscal Affairs Department, World Bank and Inter-American Development Bank, March 12. p 6
1
7/31/2019 Public Private Partnerships Short2(00)
2/7
Governments have traditionally undertaken public investment by designing and
financing a project and then contracting with the private sector to build the asset, which
is then operated by the government upon completion. The PPP alternative often takes
the form of a design-build-finance-operate (DBFO) scheme where the governmentspecifies the services it wants the private sector to deliver, and the private partner
designs and builds a dedicated asset for that purpose, finances its construction, and
subsequently operates the asset and provides the services deriving from it. The private
operators can sell the services to the government e.g. prisons; or sell services directly to
the public, as with a toll road.
There are four main ways in which the private sector can raise financing for PPP
investment. First, where services are sold to the public, the private sector can go to the
market using the projected income stream from a concession (e.g., toll revenue) as
collateral. Secondly, where the government is the main purchaser of services, shadow
tolls paid by the government (i.e., payments related to the demand for services) or
service payments by the government under operating contracts (which are based on
continuity of service supply, rather than on service demand) can be used for this
purpose. Thirdly, the government may make a direct contribution to project costs; in the
form of equity (where there is profit sharing), a loan, or a subsidy (where social returns
exceed private returns). Finally, the government can also guarantee the private sector
borrowing.3
It is generally believed that private ownership is to be preferred where competitive
market prices can be established, as competition ensures goods and services areprovided at prices consumers are willing to pay, while providing a profit to the provider.
Government ownership is seen as a way of correcting market failure, but in providingservices, government faces a trade-off between quality and efficiency; it may have the
capacity to achieve a desired quality standard, but may have difficulties containing
costs. The private sector has better management skills and innovative capacity which
can be applied to reduce operational costs, but at the risk of compromising service
quality in the process. PPPs are therefore a means of combining the relative strengths of
government and private provision in a way that responds to market failure but
minimizes the risk of government failure.
For PPPs to be successfully implemented a critical success factor is the ability of the
government to write a fully specified, enforceable contract with the private sector.
These are situations where the government can clearly identify the quality of services it
wants the private sector to provide, and can translate these into measurable output
indicators. The service requirements should be consistent over time and not subject to
radical change in the short-medium term. Service payments can then be linked to
monitorable service delivery. Where the government cannot write complete contracts
because service quality is non-contractible e.g., national defence, PPPs are not
advisable. The UK has experimented with private provision of prison services with
3 Ibid p9
2
7/31/2019 Public Private Partnerships Short2(00)
3/7
mixed results; there has been innovation and the use of new technology introduced but
no significant outperformance of the public sector managed prisons.4
It is important to note that while private capital inflows and a change in management
responsibility are beneficial, significant risk transfer is a prerequisite to derive the fullbenefit from such changes. There are five primary types of risks which PPPs face:
construction risk, financial risk, performance risk, demand risk, and residual value risk.5
It is argued that transferring project risk from the government to the private sector
should not affect the cost of financing a project.6However, it is observed that private
sector borrowing generally costs more than government borrowing. The difference is
attributed to differences in default risk; the governments power to tax renders it
unlikely to default, and so can borrow at close to the risk-free interest rate to finance
risky projects. When private borrowing is substituted for government borrowing,
financing costs are likely to rise even if project risk is lower in the private sector.
Therefore for PPPs to offer a value proposition, their efficiency gains must offset higher
private sector borrowing costs.
Since risk transfer is crucial to the increased efficiency of PPPs, the government must
relieve itself of risks that it believes the private sector can manage better than the
government. It needs to price these risks, so that it knows what it has to pay the private
sector to assume them. Project-specific risk, which is diversifiable across a large
number of government or private sector projects, does not need to be priced by the
government. Market risk, which reflects underlying economic developments that affect
all projects, is not diversifiable and therefore has to be properly priced.7
The government and the private sector typically adopt different approaches to pricing
market risk. The government tends to use the social time preference rate (STPR) orsome other risk-free rate to discount future cash flows when appraising projects, while
private bidders for PPP projects include a risk premium in the discount rate they apply
to future project earnings. This results in public investment appearing as the more
attractive option. The question that arises is whether the government is under-pricing
the risk, or that the PPP costs are actually higher than the public sector costs.
Under-pricing of risk may lead to the private sector choosing techniques of production
or other project design features which are less efficient, simply because they carry lowerrisk; or compromise on the quality of construction and service supply to the extent
possible without obviously violating its contract with the government. Alternatively, the
government can overprice risk and overcompensate the private sector for taking it on,
which would raise the cost of PPPs relative to direct public investment. As
demonstrated below, this may be the case in the private funding of hospitals in Britain.
4 The Operational Performance of PFI Prisons Report by the Comptroller and Auditor General HC 700Session 2002-2003: 18 June 20035 IMF (2004) Public-Private Partnerships, op cit p116
Modigliani-Miller theorem, which says that the cost of capital depends only on the risk characteristics of aproject, and not on how it is financed.7 IMF (2004) Public-Private Partnerships, op cit p12
3
7/31/2019 Public Private Partnerships Short2(00)
4/7
Public-Private Partnerships Examples from the UKs Private Financing
Initiative
In critically analysing whether PPPs actually achieve the twin objectives of operationalefficiency and risk transfer it is useful to look at examples from Britain which has
actively embraced the concept. Since 1992 the British government has favoured paying
for public capital works through the private finance initiative (PFI). Hospitals are
designed, financed, built and operated by private sector consortiums. In return the
hospital (under a National Health Trust) pays an annual fee to cover both the capital and
financing cost, and maintenance of the hospital over the 25-35 year life of the contract.
There is evidence of strong ideological support for PFI from the government. The report
by the Comptroller and Auditor General on the PFI contract for the redevelopment of
West Middlesex University Hospital re-emphasises that there are generic benefits from
PFI deals that outweigh possible disbenefits. The report reveals that the government
would approve a PFI project that appeared slightly more expensive than conventional
procurement if there were convincing value for money reasons for proceeding with the
deal. In this case the Trust's initial financial comparison did show the PFI price slightly
higher than the cost of conventional procurement. Both the Trust and its advisers
KPMG considered the PFI option would deliver value for money taking all factors into
account. However, the initial financial comparisons were against the PFI option. The
Trust and KPMG re-appraised the figures to ensure the risks inherent in traditional
procurement were properly reflected in the public sector comparator (PSC). The final
calculations showed a risk-adjusted saving from using the PFI compared with a PSC.The re-assessed cost comparison therefore reinforced the value for money case for the
PFI deal.8
The value for money proposition espoused by proponents of PFI to build NHS hospitals
has been criticised by Allyson Pollock who argues that it is an expensive way of
building new capacity that constrains services and limits future options. The
justification for using private financethat it offers value for money through lowering
costs over the life of the project and by removing risk from NHS trustsis a sleight of
hand.9
The arguments against PFI, based on their research findings are threefold; first, in an
environment of budget surpluses which exceed the PFI deals, the argument that PFI
leads to more investment without increasing the public sector borrowing requirement is
superfluous.10 Secondly, PFI has displaced the burden of debt from central government
to NHS trusts and with it the responsibility for managing spending controls and
planning services, thereby hindering a coherent national strategy. Thirdly, the high cost
8 The PFI Contract for the Redevelopment of West Middlesex University Hospital - Report by the Comptrollerand Auditor General HC 49 Session 2002-2003: 21 November 2002, p39 Pollock, Allyson M, Jean Shaoul and Neil Vickers (2002) Private finance and value for money in NHS
hospitals: a policy in search of a rationale?, British Medical Journal, Volume 324, 18 May.p120510 Ibid, p1205the UK budget surpluses of recent years (23bn for 2000-1) have been much greater than the totalof 14bn private investment deals signed in 1997-2001.
4
7/31/2019 Public Private Partnerships Short2(00)
5/7
of PFI schemes has led to NHS trusts diverting funds from clinical budgets, selling
assets, and cutting back on bed capacity and staff in hospitals financed through PFI.
It is further argued that due to the negative impact on levels of service, proponents of
PFI have resorted to the value for money argument; PFI delivers value for moneythrough lowering costs over the life of the project because of greater private sector
efficiency and because the private sector assumes the risks that the public sector
normally carries.
Until 1991 all major capital expenditure in the NHS was funded by central government
from tax or government borrowing. Thereafter hospitals were treated as independent
business units in the public sector and were required them to generate surpluses to pay
for their use of capital through capital charges to the Treasury.11 The research further
demonstrates that the costs of raising the finance account for 39% of the total project
costs under the PFI while publicly financed capital does not incur these costs. The
annual costs of capital for PFI are almost double the estimated costs of a similar scheme
funded by public finance. On the aspect of risk, only after risk transfer was included
was the net present value of PFI less than the public sector comparator, by an
insignificant amount. Thus the contribution of risk to costs was almost the same
amount as the difference between the public sector comparator and the PFI.
The conclusion drawn is that value for money analysis seems to be a way of forcing the
numbers to stack up in favour of PFI. Even with a high discount rate (which favours
PFI), PFI costs are still higher than those of the public sector comparator. So the value
for money claims rest on risk transfer. This suggests that the function of risk transfer isto disguise the true costs of PFI and to close the difference between private finance and
the much lower costs of conventional public procurement and private finance.12
Risk is the most difficult and contentious part of the value for money methodology. The
argument is that by getting the private sector consortium to bear some of the risks
associated with the construction of the hospital and its subsequent management, a trust
enjoys greater value for money than under a publicly financed alternative, where the
trust would bear all the risks. There is no laid down mechanism for measuring and
pricing the risk, hence the iterative approach adopted in the West Middlesex Hospital
project in the quest for costs that favoured the PFI.
13
Risk transfers can be valued up to50% of the total capital cost to the private sector. Evidence suggests that the risk is
being overpriced hence leading to overpayment by the taxpayer.
The issue of whether risk is actually transferred in the first instance is not settled. In the
case of hospitals, it would be difficult for the government to walk away from a failing
hospital, or where the contractor goes bankrupt. Several failed private finance schemes
in the UK, show that ultimately the risk is not transferred and the taxpayer ends up
paying for private sector risks. Apart from financial risk, other residual risks still lurk in
11 Capital charges are included in the prices charged to purchasers and comprise depreciation, interest, and
dividends based on the current replacement value of the assets12 Pollock, op cit p120713 Ibid, p1208
5
7/31/2019 Public Private Partnerships Short2(00)
6/7
the unknown future over 30 years technology will change, consumer needs,
regulations etc. But the public sector procuring entity may still be tied down in these
long term obligations, even while services are no longer being delivered.
Conclusion
It is sometimes argued that PPPs are not genuine partnerships that properly or
efficiently share risks and liabilities between the private and public sector but are a
means to disguise conventional contracting undertakings that are subject to standard
budgeting processes as some new undertakings that are carried out off-budget. Although
carrying out an activity off budget does not necessarily imply that transparency is
impaired, governments tend to put items off budget in order to conceal them from
public scrutiny. The UK examples further demonstrate that the concept of risk transfer
may also not be as effective as touted by its proponents.
However, PPPs seem to be evolving. In an environment of budget deficits and public
sector inefficiency, they have a role to play. From their initial incarnation as merely
vehicles to provide governments with a channel through which to finance infrastructure
investment by implicit budget deficits and debts and evade expenditure controls, they
have developed into genuine partnerships aimed at properly pricing scarce public
resources and efficiently sharing and managing risks. In the words of Trevor Manuel,
the South African Minister of Finance: ...the availability of state resources for these
purpose [to meet the socioeconomic needs of all South Africans, and in particular, to
alleviate poverty] must be used to leverage much-needed private sector investment inpublic infrastructure and services. The benefits [of PPPs] do not consist in an increase
of funds, but in the better management of scarce resources. 14
The discussion above illustrates that, despite the positive rhetoric by some
commentators, there should be no presumption that the private sector (or the public
sector) can deliver projects more efficiently or effectively. Instead, decisions should be
made on their merit and outcomes are judged on the basis of the public benefits
obtained.
14
PPP Manual (National Treasury PPP Unit, 2004), quoted in: Sadka, Efraim, (2006) Public-PrivatePartnerships: A Public Economics Perspective, IMF Working Paper No. WP/06/77
6
7/31/2019 Public Private Partnerships Short2(00)
7/7
References
________________________________________________________________________
Comptroller and Auditor General (2002) The PFI Contract for the Redevelopment of West
Middlesex University Hospital, London: The Stationery Office [National Audit Office, HC 49,Session 20022003, 21 November].
Comptroller and Auditor General (2003) The Operational Performance of PFI Prisons,
London: The Stationery Office [National Audit Office, HC 700, Session 20022003, 18 June].
Gerrard, Michael B, Public-Private Partnerships, Finance & Development, IMF Publications,
September 2001, Volume 38, Number 3
IMF (2004) Public-Private Partnerships, Washington: Fiscal Affairs Department, World Bank
and Inter-American Development Bank, March 12.
Pollock, Allyson M (2004) NHS plc: The Privatisation of our Health Care, London: Verso
Pollock, Allyson M, Jean Shaoul and Neil Vickers (2002) Private finance and value formoney in NHS hospitals: a policy in search of a rationale?, British Medical Journal, Volume
324, 18 May.
Sadka, Efraim, (2006) Public-Private Partnerships: A Public Economics Perspective, IMF
Working Paper No. WP/06/77
7