Taylor Square Fire Station
Architects: HKT Architects Inc. Contractor: Boston Building & Bridge Corp.
Public Presentation, September 12, 2019
Taylor Square Fire Station
Agenda
Introduction & Scope of Work : Julie Lynch AIA, Cambridge DPW
Temporary Station: Paul Sheehan, Cambridge Fire Department
Site Logistics Plan: Jim Goulet, Boston Building and Bridge Corp.
Existing Conditions Property Survey + Vibration Monitoring: Rob Juusola AIA, Cambridge DPW
Preliminary Project Schedule: Jim Goulet
Questions and Answers
Taylor Square Fire Station
The Project Scope Includes:
• Roof replacement including a 24kW solar photovoltaic array• Ground source heat pumps including drilling three geothermal
wells in the firehouse apron• Upgrade to the electrical service, including the emergency
generator• Window replacement with higher efficiency units• Painting exterior trim.• Accessibility upgrades for public access• New rear exterior egress stair• Interior water, mechanical and electrical saving measures
Taylor Square Fire Station
Temporary Fire Station at Smith Place Interior of Temporary Apparatus Bay
Taylor Square Fire Station
Taylor Square Fire Station
Taylor Square Fire Station
Taylor Square Fire Station
Questions and Answers