7
Public Information Newsletter Otonka Trail Phase II Drainage Channel Improvements Volume 6 October 16, 2013 Thank you to all of the residents who attended the September 26 th Public Meeting. We had a great turnout with 22 property owners represented. This newsletter is intended to address some of the questions discussed at the meeting. The City’s goal remains to assist the neighborhood with your drainage concerns. Following a review of the original plat, the easement rights for the drainage channel have been challenged. The original covenants recognized this is a natural drainageway and placed responsibility with the surrounding homeowners to keep the drainageway free of trees and debris. Until this item is resolved, final design will be suspended. The City hopes to avoid legal action and wants to work with the property owners to secure written permanent drainage easements required to carry the 100-year storm event. Once the easement item is resolved, a permanent resolution can be defined for this area. A few residents were concerned about the storm drainage entering the channel from City streets upstream. Aerial photos of this area are attached to this newsletter to illustrate the long-standing natural path of water through this area. The photos include aerials from 1940, 1962, and 1975. Each photo shows the drainage channel in the same location conveying water toward the Big Sioux River. Nearly the entire drainage basin is covered with houses and streets by 1975. The design of the subdivisions followed the same drainage rules that apply today; preserving the natural path of water as much as possible. A tributary map showing the path of water in this neighborhood is also attached for your reference. The streets and upstream development have been in place since the 1970’s. The upstream development was constructed very similar to your development. It is entirely residential housing with little change to the natural topography of the site. Another attachment to this newsletter shows the elevations along 49 th Street. The water passes through the low point at Otonka Pass. There were suggestions voiced at the last public meeting that the City evaluate redirecting the natural flow of the upstream water. If the developer south of 49th Street were required to reroute the stormwater away from this natural channel, they would have had to overcome a significant elevation change. A question was posed at the meeting about the possibility of routing flow down Otonka Trail rather than through the natural channel. The drainage model shows the total flow to be approximately 190 cubic feet per second for a 100-yr, or 1% chance, storm event. Capturing this amount of flow and rerouting it in a pipe and within the curb and gutter, a different direction than the natural flow path, would be a significant effort. In large events, curb overtopping is likely, which would cause additional front and side- yard flooding as the water passes between homes into the natural channel. The preliminary design presented at the meeting showed some design aspects that will help reduce the velocity of the water in the channel. Placing rock drop structures in the channel will help create a flatter channel slope as well as reducing the water’s energy as it flows through the rock. Resident input drove a majority of the tree removal and protection throughout the full project limits. If the project continues forward, the design will continue to progress toward final design where many more details are finalized, including type of rock, type of grass seed, channel bottom design, etc. We expect to have another public meeting in the near future to further discuss your concerns and update you on the easement discussions. We encourage you to contact us if you wish to have another individual meeting to discuss the project further. City of Sioux Falls HR Green, Inc. Andy Berg Dena Knutson Dawn Horner Principal Engineer Project Manager Project Manager 605.367.8637 605.367.8630 605.221.2654 [email protected] [email protected] Cell 605.351.2711 [email protected]

Public Information Newsletter Otonka Trail Phase II Drainage ...the Public Information Newsletter Otonka Trail Phase II Drainage Channel Improvements Volume 6 October 16, 2013 Thank

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

  • Public Information Newsletter Otonka Trail Phase II Drainage Channel Improvements

    Volume 6 October 16, 2013

    Thank you to all of the residents who attended the September 26th Public Meeting. We had a great turnout with 22 property owners represented. This newsletter is intended to address some of the questions discussed at the meeting.

    The City’s goal remains to assist the neighborhood with your drainage concerns. Following a review of the original plat, the easement rights for the drainage channel have been challenged. The original covenants recognized this is a natural drainageway and placed responsibility with the surrounding homeowners to keep the drainageway free of trees and debris. Until this item is resolved, final design will be suspended. The City hopes to avoid legal action and wants to work with the property owners to secure written permanent drainage easements required to carry the 100-year storm event. Once the easement item is resolved, a permanent resolution can be defined for this area.

    A few residents were concerned about the storm drainage entering the channel from City streets upstream. Aerial photos of this area are attached to this newsletter to illustrate the long-standing natural path of water through this area. The photos include aerials from 1940, 1962, and 1975. Each photo shows the drainage channel in the same location conveying water toward the Big Sioux River. Nearly the entire drainage basin is covered with houses and streets by 1975. The design of the subdivisions followed the same drainage rules that apply today; preserving the natural path of water as much as possible.

    A tributary map showing the path of water in this neighborhood is also attached for your reference. The streets and upstream development have been in place since the 1970’s. The upstream development was constructed very similar to your development. It is entirely residential housing with little change to the natural topography of the site.

    Another attachment to this newsletter shows the elevations along 49th Street. The water passes through the low point at Otonka Pass. There were suggestions voiced at the last public meeting that the City evaluate redirecting the natural flow of the upstream water. If the developer south of 49th Street were required to reroute the stormwater away from this natural channel, they would have had to overcome a significant elevation change. A question was posed at the meeting about the possibility of routing flow down Otonka Trail rather than through the natural channel. The drainage model shows the total flow to be approximately 190 cubic feet per second for a 100-yr, or 1% chance, storm event. Capturing this amount of flow and rerouting it in a pipe and within the curb and gutter, a different direction than the natural flow path, would be a significant effort. In large events, curb overtopping is likely, which would cause additional front and side-yard flooding as the water passes between homes into the natural channel.

    The preliminary design presented at the meeting showed some design aspects that will help reduce the velocity of the water in the channel. Placing rock drop structures in the channel will help create a flatter channel slope as well as reducing the water’s energy as it flows through the rock. Resident input drove a majority of the tree removal and protection throughout the full project limits. If the project continues forward, the design will continue to progress toward final design where many more details are finalized, including type of rock, type of grass seed, channel bottom design, etc.

    We expect to have another public meeting in the near future to further discuss your concerns and update you on the easement discussions. We encourage you to contact us if you wish to have another individual meeting to discuss the project further.

    City of Sioux Falls HR Green, Inc. Andy Berg Dena Knutson Dawn Horner Principal Engineer Project Manager Project Manager 605.367.8637 605.367.8630 605.221.2654 [email protected] [email protected] Cell 605.351.2711 [email protected]

    mailto:[email protected]:[email protected]:[email protected]

  • 49TH

    CLIFF

    ASH GROVE THUNDERB

    IRD

    CEDAR

    54TH

    OTONKA

    CRESTVIEW

    THUNDERBIRDPIN OAK

    EDGEWOOD

    PLUM CREEK

    HICKORY HILL

    OAK RIDGE

    HILLS

    GLENVIEW

    HIGH LAND

    MOUNTAINASH

    Year: 1940 ¹1 in = 300 ft

    Otonka Channel

  • 49TH

    CLIFF

    ASH GROVE THUNDERB

    IRD

    CEDAR

    54TH

    OTONKA

    CRESTVIEW

    THUNDERBIRDPIN OAK

    EDGEWOOD

    PLUM CREEK

    HICKORY HILL

    OAK RIDGE

    HILLS

    GLENVIEW

    HIGH LAND

    MOUNTAINASH

    Year: 1962 ¹1 in = 300 ft

    Otonka Channel

  • 49TH

    CLIFF

    ASH GROVE THUNDERB

    IRD

    CEDAR

    54TH

    OTONKA

    CRESTVIEW

    THUNDERBIRDPIN OAK

    EDGEWOOD

    PLUM CREEK

    HICKORY HILL

    OAK RIDGE

    HILLS

    GLENVIEW

    HIGH LAND

    MOUNTAINASH

    Year: 1968 ¹1 in = 300 ft

    Otonka Channel

  • 49TH

    CLIFF

    ASH GROVE THUNDERB

    IRD

    CEDAR

    54TH

    OTONKA

    CRESTVIEW

    THUNDERBIRD

    PLUM CREEK

    PIN OAK

    EDGEWOOD

    HICKORY HILL

    OAK RIDGE

    HILLS

    GLENVIEW

    HIGH LAND

    MOUNTAINASH

    Year: 1975 ¹1 in = 300 ft

    Otonka Channel

  • E 49TH ST

    S C

    LIF

    F A

    VE

    S L

    EW

    IS A

    VE

    E EDGEWOOD RD

    E OTO

    NKA TRL

    E CEDAR LN

    S G

    LEN

    VIE

    W R

    D

    E PONDEROSA DR

    S A

    SH G

    RO

    VE A

    VE

    S H

    IGH

    LA

    ND

    AV

    E

    S C

    HIC

    AG

    O A

    VE

    E CRESTVIEW DR

    E 51ST ST

    S H

    ICK

    OR

    Y H

    ILL R

    D

    S O

    AK

    RID

    GE

    AV

    E

    E TOMAR RD

    S H

    ILL

    S R

    D

    S T

    HU

    ND

    ER

    BIR

    D T

    RL

    S L

    EW

    IS C

    T

    S M

    OU

    NTA

    IN A

    SH

    DR

    S T

    UT

    HIL

    L C

    T

    E 52ND ST

    E E

    LI Z

    AB

    ET

    H D

    R

    E TWIN

    OAKS

    EST

    E A

    RRO

    WHEAD P

    ASS

    E O

    TON

    KA R

    DG

    E E

    DG

    EW

    OO

    D P

    L

    E C

    ED

    AR

    PL

    S O

    TO

    NK

    A P

    AS

    S

    S THUNDERBIRD TRL

    E 52ND ST

    ®

    Data Source:\\hrgsfdc\data\50120014\GIS\MXDProjection: NAD_1983_UTM_Zone_14NAuthor: DWMDate: July 2012

    0 300150Feet

    City of Sioux Falls

    Otonka Drainage

    Issues Map

    Legend

    Drainage Areas 070512

    Existing Storm Sewer

    Drainage Arrow

  • E CEDAR PL

    S A

    SH G

    RO

    VE

    AVE

    SO

    TON

    KAPA

    SS

    S LE

    WIS

    AV

    E

    E EDGEWOOD RD

    E OTO

    NKA

    RDG

    E OTONKATRL

    E EDG

    EWO

    OD

    PL

    E TOMAR LN

    E 49TH ST

    E CRESTVIEW DR

    E ELIZABETHDR

    E EDGEWOOD RD

    STU

    THIL

    LCT

    E PON

    DEROS

    A DR

    E 52ND ST

    E 51ST ST

    S BR

    IARW

    OO

    D A

    VE

    S

    THUNDERBIRD TRL

    SH

    IGH

    LAN

    DAV

    E

    SLE

    WIS

    CT

    S BIRCHWOODAVE

    SASH

    GROVE

    AVE

    E ARR

    OWHE

    AD PASS

    SH

    ILLS

    RD

    S OAK RIDGE AVE

    E 49TH ST

    S CH

    ICA

    GO

    AV

    E

    S GLENVIEW

    RD

    S LE

    WIS

    AV

    E

    E PONDEROSA DR

    S T

    HUN

    DERB

    IRD

    TRL

    S HICKORY HILL RD

    E TOMAR RD

    S MO

    UN

    TAIN

    ASH D

    R

    E OTONKA TRL

    SW

    OO

    DW

    IND

    LN

    SCLIFF

    AVE

    S CLIFF AVE

    E TWIN OA

    KS EST

    E EDGEWOOD RD

    E CEDAR LN

    endv\Storm\Otonka Area DEM.mxdOctober 1, 2013

    Otonka Drainage

    Elevation (Feet)1550

    1470

    1390

    .

    1500

    1432

    1460

    1478

    1489 1530