PUBLIC DISCLOSURE AUTHORISED CARIBBEAN DEVELOPMENT BANK TWO HUNDRED AND FIFTY-FIRST MEETING OF THE BOARD OF DIRECTORS TO BE HELD IN THE CAYMAN ISLANDS MAY 21, 2012 PAPER BD 44/12 ROAD SAFETY PROJECT BELIZE (Presidents Recommendation No. 864) 1. The attached Report is the appraisal of a project proposal from the Government of Belize (GOBZ). The objective of the Project is to reduce deaths and serious injuries associated with road traffic accidents. This will be achieved through improving the safety of road infrastructure along a demonstration corridor; changing road user behaviour through increased awareness and understanding of the issue; traffic law enforcement support; post-crash response support; and road safety management capacity building. 2. On the basis of the Report, I recommend a loan to GOBZ of an amount not exceeding the equivalent of seven million two hundred and forty-eight thousand United States dollars [USD7.248 million (mn)] consisting of: (a) an amount not exceeding the equivalent of USD5.362 mn from the Ordinary Capital Resources of the Caribbean Development Bank (CDB); and (b) an amount not exceeding the equivalent of USD1.886 mn from CDBs Special Funds Resources, on the terms and conditions set out and referred to in Chapter 6 of the attached Report. 3. In addition, I recommend a waiver of CDBs Procurement Guidelines to permit the purchase of specified new vehicles and equipment costing up to USD385,000 without restriction to eligible countries. 4. Funds are available within CDBs existing resources and/or borrowing programme for the relevant disbursement period.

PUBLIC DISCLOSURE AUTHORISED CARIBBEAN DEVELOPMENT BANK ... · public disclosure authorised caribbean development bank two hundred and fifty-first meeting of the board of directors

  • Upload
    vanngoc

  • View
    214

  • Download
    0

Embed Size (px)

Citation preview

PUBLIC DISCLOSURE AUTHORISED

CARIBBEAN DEVELOPMENT BANK

TWO HUNDRED AND FIFTY-FIRST MEETING OF THE BOARD OF DIRECTORS

TO BE HELD IN THE CAYMAN ISLANDS

MAY 21, 2012

PAPER BD 44/12

ROAD SAFETY PROJECT – BELIZE (President’s Recommendation No. 864)

1. The attached Report is the appraisal of a project proposal from the Government of Belize (GOBZ).

The objective of the Project is to reduce deaths and serious injuries associated with road traffic accidents.

This will be achieved through improving the safety of road infrastructure along a demonstration

corridor; changing road user behaviour through increased awareness and understanding of the issue;

traffic law enforcement support; post-crash response support; and road safety management capacity

building.

2. On the basis of the Report, I recommend a loan to GOBZ of an amount not exceeding the

equivalent of seven million two hundred and forty-eight thousand United States dollars [USD7.248 million

(mn)] consisting of:

(a) an amount not exceeding the equivalent of USD5.362 mn from the Ordinary Capital

Resources of the Caribbean Development Bank (CDB); and

(b) an amount not exceeding the equivalent of USD1.886 mn from CDB’s Special Funds

Resources,

on the terms and conditions set out and referred to in Chapter 6 of the attached Report.

3. In addition, I recommend a waiver of CDB’s Procurement Guidelines to permit the purchase of

specified new vehicles and equipment costing up to USD385,000 without restriction to eligible countries.

4. Funds are available within CDB’s existing resources and/or borrowing programme for the

relevant disbursement period.

PUBLIC DISCLOSURE AUTHORISED

CARIBBEAN DEVELOPMENT BANK

APPRAISAL REPORT

ON

ROAD SAFETY PROJECT – BELIZE

Considered at the Two Hundred and Fifty-First Meeting of the

Board of Directors on May 21, 2012.

(BD 44/12)

AR 12/1 BE

Director - Tessa Williams Robertson

Projects Department

Division Chief (Ag.)

Economic Infrastructure Division - Andrew Dupigny

MAY 2012

This Document is being made publicly available in accordance with the

Bank’s Information Disclosure Policy. The Bank does not accept

responsibility for the accuracy or completeness of the Document.

Any designation or demarcation of, or reference to, a particular territory or geographic area in this Document,

is not intended to imply any opinion or judgment on the part of the Bank as to the legal or other status of any

territory or area or as to the delimitation of frontiers or boundaries.

This report was prepared by an Appraisal Team comprising:

Glen McCarvell, Operations Officer (Civil Engineer)/Coordinator; Alexander Augustine, Operations Officer (Financial

Analyst); Cheryl Dixon, Operations Officer (Environment); Ellis Elbert, Operations Officer (Social Analyst); Kent Vital,

Country Economist; George Kirnon, Legal Counsel; Idamay Denny, Operations Officer (Education); and Sonia Brewster,

Coordinating Secretary.

CURRENCY EQUIVALENT

Dollars ($) throughout refer to Belize Dollars (BZD) unless otherwise stated.

USD1.00 = BZD2.00

BZD1.00 = USD0.50

ABBREVIATIONS

AASHTO - Association of State Highway and Transportation Officials

BERT - Belize Emergency Response Team BZD - Belize Dollars

BMCs - Borrowing Member Countries

BOP - Balance of Payments

CBB - Central Bank of Belize

CDB - Caribbean Development Bank CFZ - Commercial Free Zone

CG - Central Government

CPA - Country Poverty Assessment CRF - Consolidated Revenue Fund

DOT - Department of Transport DPW - Department of Public Works

ECP - Environmental Compliance Plan

ERR - Economic Rate of Return EMP - Environmental Management Plan

EMT - Emergency Medical Technicians

FDI - Foreign Direct Investment

GDP - Gross Domestic Product

GOBZ - Government of Belize GST - General Sales Tax

HMIS - Health Management Information System

IDB - Inter-American Development Bank

IDC - Interest During Construction

iRAP - International Road Assessment Programme

KAP - Knowledge, Attitudes and Practices

km - kilometres KSI - Killed and Seriously Injured

m - metres

mn - million M&E - Monitoring and Evaluation

MFED - Ministry of Finance and Economic Development

MOEYS - Ministry of Education, Youth and Sports

MOH - Ministry of Health MOU - Memorandum of Understanding MWT - Ministry of Works and Transport

MVRTA - Motor Vehicle and Road Traffic Act

MVIA - Motor Vehicle Insurance Act

NFS - National Fire Service

NPESAP - National Poverty Elimination Strategy and Action Plans

NPV - Net Present Value NRSC - National Road Safety Committee OCR - Ordinary Capital Resources

OSC - Operational Steering Committee

(ii)

p.a. - per annum

PAHO - Pan American Health Organisation

PCR - Project Completion Report

PD - Police Department PE - Project Engineer

PM - Project Manager

PRA - Public Roads Act RPS - Road Protection Score

RSU - Road Safety Unit RTA - Road Traffic Accidents

RTI - Road Traffic Injuries

SFR - Special Funds Resources SpCF - Specific Conversion Factor

TA - Technical Assistance TL - Task Leaders

TOR - Terms of Reference TWG - Technical Working Group

USD - United States Dollar

WB - World Bank WHO - World Health Organisation

MEASURES AND EQUIVALENTS

1 hectare (ha)

1 kilometre (km) =

= 2.47 acres

0.621 mile (mi) 1 square kilometre (km

2) = 0.386 square mile (mi

2)

1 metre (m) = 3.281 feet (ft) 1 millimetre (mm) = 0.039 inch (in) 1 square metre (m

2) = 10.756 square feet (ft

2)

TABLE OF CONTENTS

COUNTRY DATA: BELIZE

LOAN AND PROJECT SUMMARY

1. STRATEGIC CONTEXT AND RATIONALE

2. PROJECT DESCRIPTION

3 FINANCING STRUCTURE AND COSTS 4. PROJECT VIABILITY

5. IMPLEMENTATION AND PROJECT MANAGEMENT

6. TERMS AND CONDITIONS

APPENDICES

1.1 SUMMARY OF BELIZE ROAD SAFETY STATISTICS

1.2 PROFILE OF BELIZE EMERGENCY RESPONSE TEAM

1.3 MACRO-SOCIAL CONTEXT 1.4 RECENT MACROECONOMIC PERFORMANCE

2.1 DETAILS OF THE PROJECT 2.2 DRAFT TERMS OF REFERENCE – COMMUNICATIONS CONSULTANT

2.3 DRAFT TERMS OF REFERENCE – CURRICULUM CONSULTANT

2.4 DRAFT TERMS OF REFERENCE – ENFORCEMENT TRAINING 2.5 DRAFT TERMS OF REFERENCE – ROAD SAFETY CONSULTANCY SERVICES

2.6 DRAFT TERMS OF REFERENCE – ROAD SAFETY TRAINING 2.7 DRAFT TERMS OF REFERENCE – ROAD SAFETY ASSESSMENT

2.8 DRAFT TERMS OF REFERENCE – CONSULTANCY SERVICES FOR THE DESIGN AND

CERTIFICATION OF ROAD SAFETY INFRASTRUCTURE WORKS

3.1 PROJECT COST, PHASING AND FINANCING PLAN

4.1 DEMONSTRATION CORRIDOR 2012 STAR RATINGS 4.2 SUMMARY OF INCREMENTAL ECONOMIC BENEFITS

4.3 ASSUMPTIONS TO THE ECONOMIC ANALYSIS

4.4 ECONOMIC RATE OF RETURN CALCULATION 5.1 MANAGEMENT STRUCTURE

5.2 DRAFT TERMS OF REFERENCE – PROJECT MANAGEMENT 5.3 PROJECT IMPLEMENTATION SCHEDULE

5.4 PROCUREMENT PLAN

5.5 ESTIMATED QUARTERLY LOAN DISBURSEMENT SCHEDULE 5.6 REPORTING REQUIREMENTS

FIGURES

1. PROJECT LOCATION MAP

2. DEMONSTRATION CORRIDOR

COUNTRY DATA: BELIZE

2007 2008 2009 2010 2011 PER CAPITA GDP (current market prices; $) 8,242 8,466 8,097 8,952 9,029e

GROSS DOMESTIC PRODUCT (GDP)

GDP at Current Market Prices ($mn)

2,553.5

2,727.0

2,698.0

2,802.0

2,906.2e Demand Components:

Consumption Expenditure

2095.5

… Gross Domestic Investment 504.1 … … … … Exports of goods and non-factor services 1,529.0 … … … … Imports of goods and non-factors ervices 1575.1 … … … …

Gross domestic savings ratio (%) 17.9 … … … …

Sectoral distribution of current GDP (%) Agriculture 12.3 12.2 … … … Mining & Quarrying 0.5 0.5 … … … Manufacturing 13.1 14.3 … … … Utilities 3.8 2.6 … … … Construction 4.0 5.2 … … … Transport & Communication 13.0 12.0 … … … Hotels & Restaurants 5.3 5.0 … … … Wholesale & Retail Trade 16.9 17.0 … … … Financial & Business Services 17.0 17.0 … … … Government Services 11.6 11.7 … … … Other Services 7.5 7.5 … … … Less Imputed Service Charge 5.0 5.0 … … …

GDP at Current Factor Cost ($mn) 2,208.1 2,363.9 … … … GDP at constant 2000 Prices ($mn) 1,954.1 2,034.8 2,060.8 2,109.1 2,145.5 Annual rate of growth in GDP (%) (0.1) 4.1 1.3 2.3 1.7

MONEY AND PRICES ($ mn) Consumer prices (av. annual % change) 2.3 6.4 (1.1) 1.0 2.6 Money supply (M1; annual % change) 12.3 0.3 1.0 (0.8) 15.7 Total domestic credit(net) 1,790.6 1,932.4 2,002.3 1,944.9 1,915.3

Private sector (net) 1563.3 1,728.4 1,799.5 1,757.6 1,752.3 Public sector (net) 227.3 204.0 202.8 187.3 163.0

Estimated Tourism Expenditure (USD mn) 283.6 272.6 251.7 260.0 …

CENTRAL GOVERNMENT FINANCES ($ mn) Current Revenues 651.5 729.4 653.9 735.7 793.8 Current Grants 0.0 0.0 0.0 0.0 0.0 Current Expenditures 636.1 617.9 661.8 676.7 714.5 Current AccountSurplus/ (Deficit) 15.4 111.5 (7.9) 59.0 79.3 Capital Revenue and Grants 114.2 71.3 44.9 24.2 15.6 Capital Expenditure and Net Lending 160.4 141.6 113.3 126.1 102.1 Overall Surplus/ (Deficit) (30.8) 41.2 (76.3) (42.9) (7.2)

BALANCE OF PAYMENTS (USD mn) Merchandise Exports (f.o.b) 425.6 480.2 383.9 475.8 567.0 Merchandise Imports (c.i.f) 642.0 788.3 620.5 649.8 735.0 Trade balance (216.4) (308.1) (236.6) (174.0) (168.0) Net Balance on services account 230.0 216.9 182.7 200.1 186.0 Income (net) (159.0) (165.2) (108.3) (158.5) (143.0) Transfers (net) 93.4 111.6 79.4 91.8 80.0 Current Account Balance (52.0) (144.8) (82.8) (40.6) (45.0) Capital and Financial Account 114.0 215.9 135.6 33.0 49.0 Net errors and omisions (39.0) (13.2) (5.5) 11.9 0.0 Overall Balance 23.0 57.9 47.3 4.3 4.0 Change in Reserves () = Increase (23.0) (57.9) (47.3) (4.3) (4.0)

TOTAL PUBLIC DEBT (USD mn) Total public debt 1,133.7 1,124.2 1,175.8 1,193.1 1,213.3

Domestic debt outstanding

Long term

Short term

161.0

166.4

160.1

183.9

190.6

… External debt outstanding 972.7 957.8 1015.7 1009.2 1022.7 Debt Service 115.1 85.2 71.1 66.2 81.4

Amortisation 60.2 44.3 34.8 27.1 37.1 Interest Payments 54.9 40.9 36.3 39.1 44.3

External debt service as % of exports of goods and services 14.0 9.8 9.8 8.8 8.7 Total debt service as % of current revenue 25.0 29.7 18.7 19.4 20.5

AVERAGE EXCHANGE RATE Dollar(s) per US dollar 2.00 2.00 2.00 2.00 2.00

Data for 2011 are provisional. (e Estimate)

COUNTRY DATA: BELIZE

2007 2008 2009 2010 2011 POPULATION Mid-Year Population ('000) 309.8 322.1 333.2 313.0 … Population Growth Rate (%) 3.3 4.0 3.4 (6.1) … Crude Birth Rate … … … … … Crude Death Rate … … … … … Infant Mortality Rate … … … … …

EDUCATION Net School Enrollment Ratio (%)

Primary

86.4

86.4

83.7

94

… Secondary 41.2 40 40.7 49 …

Primary 23 23 23 22 … Secondary 14 14 14 14 …

LABOUR FORCE Unemployment Rate (%) 8.5 8.2 13.1 23.1 …

Male … … … 16.7 … Female … … … 33.1 …

Participation Rate (%) 59.2 … … 65.7 … Male … … … 80.3 … Female … … … 51.2 …

Pupil-Teacher Ratio

COUNTRY DATA: BELIZE

1970 1980 1990 2000 2010 INDICATORS OF HUMAN DEVELOPMENT

HEALTH AND EDUCATION Life Expectancy at Birth (years) 67.6 71.

4 71.4 73.8 77.0

Male 66.9 70.4

70.4 72.6 … Female 68.3 72.

6 72.6 75.3 …

Dependency Ratio 1.17 1.03

1.03 0.93 … Male 1.19 1.0

1 1.01 0.92 …

Female 1.15 1.05

1.05 0.93 …

Human Development Index

0.614

0.648

0.687

0.739

HOUSING AND ENVIRONMENT Households with piped water (%) 19.3 45.

7 45.7 49.2 85.0

Households with access to flush toilets (%) 14.1 21.1

21.1 49.9 64.6 Households with electricity (%) … 59.4 59.4 67.2 90.0

Environmental strategy or action plan (year prepared): 2003

Source(s): Central Bank of Belize.

… not available

Data as at April 23, 2012

LOAN AND PROJECT SUMMARY

Financial Terms and Conditions Borrower: Government of Belize

(GOBZ) Amortisation Period: Ordinary Capital

Resources (OCR): 12 years Special Funds Resources

(SFR): 12 years Executing Agency: Ministry of Finance and

Economic Development

(MFED)

Grace Period: OCR: 4 years SFR: 4 years

Disbursement Period: September 1, 2012 – December 31, 2015

Source Amount (USD) OCR – Loan 5,362,000 Interest Rate: 3.84% per annum (p.a.)

variable SFR – Loan 1,886,000 Interest Rate: 2.5% p.a. Sub-Total Loan 7,248,000

Commitment Fee: 1% p.a. on the Counterpart: 1,596,000 undisbursed balance of the OCR Loan, commencing from the 60

th day after the date of

the Loan Agreement. TOTAL: 8,844,000

Project Summary Project Objective and Description:

The objective of the Project is to reduce deaths and serious injuries associated with road traffic

accidents. This will be achieved through improving the safety of road infrastructure along a

Demonstration Corridor; changing road user behaviour through increased awareness and understanding of

the issue; traffic law enforcement support; post-crash response support; and road safety management

capacity building.

The Project consists of the following:

(a) Road Safety Infrastructure.

(b) Road User Education and Awareness:

(i) Public Education and Awareness; and

(ii) Curriculum Development and Teacher Training.

(c) Road Safety Enforcement.

(d) Road Accident Emergency Services.

(e) Capacity Building:

(i) Road Safety Mentoring;

(ii) Road Safety Training; and (iii) (iii) Monitoring and Evaluation (M&E)

(f) Project Management.

(ii)

Exceptions to Caribbean Development Bank (CDB) Policies:

A waiver of the CDB’s Procurement Guidelines to permit the purchase of specified vehicles and

equipment costing up to USD385,000, without restriction to eligible countries.

CDB/Special Development Fund Contribution to Country Outcomes – Key Outputs

Education and Training:

Teachers trained to deliver road safety curriculum - 100

Students benefiting from revised road safety curriculum and informal learning programme – 2,000

Social and Economic Infrastructure:

Primary roads upgraded from 1 and 2-star safety levels to a minimum of 3-star for all road

users – 80 kilometres (km).

Beneficiaries of road project:

(a) Belize City to Hattieville: vehicle occupants travelling in an average of 8,000

vehicles/day.

(b) Hattieville to Belmopan: vehicle occupants travelling in an average of 2,000

vehicles/day.

Capacity Development:

Public sector employees trained in road safety management – 20

Public sector employees trained in traffic law enforcement – 35

1. STRATEGIC CONTEXT AND RATIONALE

LOAN REQUEST

1.1 By letter dated March 15, 2012, GOBZ requested that CDB assist in financing a multi-sectoral

road safety intervention that would include infrastructure improvements and capacity building for

agencies involved in road safety management.

SECTOR ANALYSIS

1.2 Belize’s road network is divided into 581 km of main roads (mainly consisting of the

Hummingbird, Southern, Northern and Western Highways); 711 km of secondary roads; and 1,980 km of

feeder roads. Approximately 20% of the total network is paved (90% of the main roads, 19% of the

secondary roads and 3% of the feeder roads). The current vehicle fleet is estimated to be 55,000 of

various types, with the majority of them being registered in the Belize and Cayo Districts. The fleet and

traffic volumes on the network have all grown at a steady 3 – 4% p.a.

1.3 Most of Belize’s main road network is in good structural condition, however, there are some

major safety deficiencies, in particular poor delineation and the lack of adequate shoulders and

appropriate road-side furniture. Speeds on the network are a major problem, as illustrated by a speed

survey conducted in November 2011, which indicated that more than 50% of vehicles exceeded the

posted limit. A comprehensive safety assessment of the main road network was initiated in August 2011.

This exercise determined the level of risk to each type of road user at 100 metre (m) intervals along the

network, which were then assigned safety ratings of between 0 to 5 stars, with 5 being the highest

and 3 stars being considered as the minimum acceptable standard. The results of this survey indicate

that 70%, 85%, 91% and 10% of the main road network is rated at between 0-2 stars for vehicle

occupants; motorcycle users; bicycle users; and pedestrians, respectively.

1.4 Road transport in Belize is administered under three Acts: the Public Roads Act (PRA), the Motor Vehicles and Road Traffic Act (MVRTA) and the Motor Vehicle Insurance (Third Party Risks) Act [MVIA]. PRA deals with the powers of the Minister and the Chief Engineer, Ministry of Works and Transport (MWT), in respect of public roads and their location, operation, and maintenance. MVRTA deals with traffic regulations and other matters regarding motor vehicle users and operators, as well as traffic control and licensing. MVIA regulates insurance of motor vehicles and enforces mandatory third

party liability. A recent study1

of these has determined that legislation at the national level is adequate to

support effective traffic law enforcement. However, a better definition of the roles and responsibilities is required for the municipalities and the fines and fees in the PRA require updating.

1.5 User knowledge of the risks associated with the use of the road is generally poor in Belize. Road

safety is not a formal part of the school curriculum. Dangerous behaviours, such as distracted driving and

riding in pick-up truck pans, are ubiquitous and have contributed to a significant proportion of the

fatalities. Drunken driving statistics are not available, but it is, at least anecdotally, perceived as a

widespread problem. Addressing such user behaviour is critical to improving safety on Belize’s road

network.

1.6 Road Traffic Injuries (RTI) are the fourth leading cause of death in Belize. In 2006, Belize

recorded 68 deaths and 652 non-fatal RTI 2. In 2009, fatalities rose to 70, equivalent to approximately 21

deaths per 100,000 inhabitants, the highest fatality rate of CDB’s Borrowing Member Countries (BMCs),

1 Legislative and Regulatory Analysis of Traffic Management in Belize, 2012.

2 World Health Organisation’s (WHO) Global Status Report on Road Safety, 2009.

- 2 -

which averages about 16, and higher than most of its Central American neighbours3. The highest death

rates have historically been in the Belize and Cayo Districts whose proportion of annual casualties averages about 60% and 11%, respectively. The Inter-American Development Bank (IDB) has recently

projected4

that, without action, the number of road-related fatalities in Latin America and the Caribbean will soar in the next 10 years from the current regional average of 17 to 31 deaths per 100,000 inhabitants. Appendix 1.1 provides additional details on road safety issues in Belize.

Organisation and Structure

1.7 Road safety is a cross-sectoral issue encompassing the following service providers in Belize: the

nine municipalities5, MWT, Ministry of Health (MOH), Police Department (PD), the National Fire Service

(NFS) and Belize Emergency Response Team (BERT). Over the past few years MOH6

and MWT7

have both developed strategies to address road safety. However, no action has been taken because: (a) road safety was not a GOBZ priority at the time; and (b) the roles and responsibilities of the various agencies were not well established. GOBZ proposes to establish a National Road Safety Committee (NRSC) to lead, manage, coordinate and evaluate efforts to improve road safety in the country.

1.8 Road safety statistics are not uniformly or consistently collected. Traffic and speed surveys are

not routinely performed by MWT due to lack of equipment. MOH has a Health Management Information

System (HMIS), which identifies deaths related to Road Traffic Accidents (RTA), and PD has a Crime

Information Management System for which a RTA database suite is expected to be rolled out shortly.

Belize City has a traffic enforcement database and one is currently under development for Belmopan.

Additional work is required to ensure dataset definitions in these databases and reporting is consistent,

timely and comparable, to inform effective M&E and ensure a results-based focus to a national road safety

strategy.

1.9 MWT, through its Department of Public Works (DPW), is responsible for the construction and

maintenance of the main roads in Belize, with the exception of those roads which fall within the limits of

the nine municipalities. CDB is satisfied that DPW has the capacity to effectively carry out its

responsibilities in the sector. However, under-investment in maintenance has led to the deterioration in

the road networks condition and its safety. Also, there is a need to better incorporate road safety

considerations into their maintenance planning and budgeting process.

1.10 MWT’s Department of Transport (DOT), shares responsibility with the nine municipalities for:

licensing and registration of motor vehicles; issuing of drivers’ permits; granting of bus permits; motor

vehicle inspections; driver testing; enforcing traffic regulations; and assisting PD with motor vehicle

accident investigations. With these 10 agencies responsible for licensing, standards for driver training

and vehicle inspection are not uniformly applied across the country; hence, there is a widespread lack of

understanding of the “rules of the road” and a growing fleet with a substantial proportion of poor quality

vehicles, both of which have adverse implications for road safety. There will never be sufficient

personnel to undertake all the enforcement required in Belize and a move towards a more automated

approach is ultimately essential. Along the inter-urban sections of the road network, enforcement is

particularly lacking. DOT has adequate personnel and systems in place to support enforcement

3 Which have rates of 20.7 (Mexico), 14.9 (Guatemala) and 13.5 (Honduras) per 100,000 inhabitants, whilst by

comparison the Organisation for Economic Cooperation and Development (OECD) countries average about 10.

Source: ibid. 4

Road Safety Initiative, IDB, 2011. 5

Belize City, Belmopan, Benque Viejo, Corazol, Dangriga, Orange Walk, Punta Gorda, San Ignacio and San Pedro. 6

National Five Year Strategic Plan to Reduce Road Traffic Accidents/Injuries in Belize 2007-2012. 7

Roads and Municipal Drainage Project, Institutional Strengthening – Volume II: National Road Safety Strategy

and Plan 2005-2010.

- 3 -

operations on these sections of the network, however, they are constrained by a lack of appropriate equipment. There is also a need to upgrade their enforcement skills to current best practices and techniques. The current institutional constraints faced by the municipalities are being addressed by a

separate ongoing World Bank (WB) intervention8.

1.11 Post-crash ambulatory service responsibility in Belize is shared between MOH and BERT. Only

BERT has ambulances equipped with the necessary medical equipment and staffed with qualified

emergency medical technicians to respond to RTA crash scenes where severe trauma is involved. BERT is

a well-established first responder in Belize and is an integral part of the country’s emergency medical

services. BERT has adequate personnel and systems in place to support their operations. The

organisation is, however, constrained by antiquated equipment which has resulted in increased operational

and maintenance costs. Appendix 1.2 provides further details on the operations of BERT.

Issues and Constraints

1.12 There are several key issues and constraints affecting road safety in Belize including:

(a)

(b) Education and awareness: School children are very vulnerable road users but there is

inadequate representation of road safety in the curriculum. What is referred to as “Traffic

Education” is minimally represented in the Social Studies curriculum, but the concepts

included provide for knowledge rather than application. Students therefore develop a

poor understanding of the risks associated with using roads. Additionally, the dangerous

behaviour of some road users has contributed significantly to the number of RTA.

(c) Traffic-law enforcement: The majority of RTA occur on inter-urban sections of the road

network where traffic law enforcement is not routinely applied. DOT has the personnel

and the mandate but requires appropriate vehicles and equipment to deter poor road user

behaviour through a high-visibility patrol and enforcement initiative on the main road

network. The municipalities concentrate on parking and vehicle condition enforcement

and are not equipped to deter speeding and drunk driving. All of the enforcement

agencies need an improved understanding of best practices in the various aspects of

traffic law enforcement.

(d) Post-crash care: Fundamental to a reduction of RTA fatalities, is the ability to provide

timely, efficient and effective on-scene emergency medical care. BERT, the main

emergency medical response service in the country, suffers from inadequate equipment

capacity to effectively respond to RTA.

(e) Institutional capacity and accountability: The present institutional arrangement has 15

agencies sharing responsibility for road safety. The lack of formalised inter-agency

coordination mechanisms is not conducive to improving road safety. A results-focused

strategy with a clear definition of roles and responsibilities, supported by improved cross-

sectoral capacity to manage road safety, is required. The effective M&E of this strategy is

also vital to ensure accountability. The NRSC needs to be formalised so that it can take

the lead in road safety management. GOBZ’s capacity will need to be strengthened to

effectively manage, monitor and evaluate road safety activities. In addition, due to the

absence of reliable data, there is little or no performance management to ensure service

providers focus on results.

8

Belize Municipal Development Project.

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

- 4 -

COUNTRY’S SECTOR STRATEGY

1.13 As noted previously, both MOH and MWT had developed road safety strategies that had not been

acted upon. Subsequently, Belize’s Medium Term Development Strategy 2010-13 and Horizon 2030 –

The Long Term Development Framework for Belize, both identified and recognised the need to support

the improvement of road safety as a high priority policy objective. To assist in operationalising GOBZ’s

strategy, as part of the Fourth Road Project (BD98/10), CDB provided grant resources for two Technical

Assistance (TA) interventions. The outputs of those two interventions included a Safer Roads

Infrastructure Investment Plan, a Road Safety Management Capacity Review and an Integrated Road

Safety Project Investment Plan. These have identified activities and objectives to be achieved over the

short-term (1-3 years), medium-term (3-5 years) and long-term (+6 years) to improve road safety. These

have informed the design of this Project.

SOCIAL AND MACROECONOMIC CONTEXT

Social Context 1.14 The proposed road safety intervention will focus on the Western Highway which straddles the

two most populous districts in Belize, Belize and Cayo, which contain the commercial and administrative

capitals, respectively. The former is dominated by the city of Belize which contains around 17% of the

country’s population. Belize City, with a population of approximately 53,000, is geographically small,

but vibrant and culturally rich. Also, in Belize District is the town of Hattieville and the sparsely

populated villages of La Democracia, Crooked Tree and Rockstone Pond, located along the Western

Highway. Hattieville, with a small population of about 1,300, is home to two primary schools and a

police station. Police and NFS stations are located in Belize City and Belmopan. The Western Highway

links Belize City and Belmopan, and is heavily trafficked by a wide cross section of the public who live in

Belize City and commute to work in Belmopan on a daily basis.

1.15 Two-thirds of the country’s Creole population lives in Cayo District, in which Belmopan as well

as the twin towns of Santa Elena/San Ignacio are located, and the large Mennonite enclave at Spanish

Lookout. Cayo District has been the fastest growing district with the population increasing by 39%

since 2000, followed by Belize District with a 34% increase. Belmopan, with a population of 13,654,

is recognised as one of the safest cities in Belize and, consequent upon a number of pull factors,

including the establishment of commercial banks, embassies and consulates, it has evolved into a thriving

city, as well as a place for retirees seeking easy and unencumbered access to essential services. The

population of Belmopan is expanding as Belizeans and immigrants inhabit the area and have built

several new suburbs such as Salvapan, San Martin and Las Flores. This has led to increased vehicular

and pedestrianised traffic within the municipality. Belmopan, as an expression of its local culture, offers a

local farmers’ market twice weekly, where a diverse demographic and cross-section of the society meet to

trade, socialise and strengthen social and economic relations around an eclectic variety of fresh

produce, and dry goods. (See Appendix 1.3 for the Macro Social Context).

1.16 There are eight primary and two secondary schools located along the Western Highway from

Belize City to Belmopan, catering to a population of 2,126 students ranging in age from 5-17 years. As a

result of the dispersed nature of the villages in relation to the location of schools, many students are

required to use the highway, either on foot, bicycles or by public transportation on a daily basis. In

addition, since many of the country’s secondary schools are located in the urban centres, many other

- 5 -

secondary students use public transportation along the highway to reach their schools located in either

Belize City or Belmopan. Therefore, significantly more than the number of students attending school

within the Corridor are impacted by safety issues along the highway.

Macroeconomic Context

1.17 Real Gross Domestic Product (GDP) growth at basic prices averaged 4.0% annually in Belize

between 2002 and 2009. This growth has generally been broad-based. Growth slowed during the latter

part of the period with a 1.7% annual increase between 2007 and 2009, compared to growth of 5.4%

annually over the previous years. Slower growth during the latter period was due to a decline in

agriculture and fishing, as well as to the impact of the global economic crisis which affected performance

in the tourism sector, particularly strongly. The weak economic environment which prevailed during

2009, as a result of the global economic crisis, continued to impact Belize in 2010-11, but there has

been some recovery. Real GDP grew by an estimated 1.7% during 2011, mainly due to strong

performance in manufacturing, wholesale and retail trade, and hotel and restaurant activity which grew

by 2.9%, 4.8% and 4.7%, respectively.

1.18 Since 2005, Belize has made significant efforts to correct unsustainable fiscal and external

imbalances. These imbalances had threatened to constrain economic growth and thereby adversely

impacting GOBZ’s ability to implement programmes aimed at reducing poverty. Under an adjustment

programme, GOBZ was successful in reducing the fiscal deficit to 1.9% of GDP by 2006, compared with

one of 6.8% of GDP during the previous year. Fiscal performance continued to improve and by 2008, an

overall surplus of 1.5% was registered. CDB’s support to Belize through a Policy-Based Loan of

USD25 mn was instrumental in the success that Belize has realised with its adjustment programme.

Given the impact of the global economic crisis, the fiscal position worsened to a deficit of $76.3 mn or

2.8% of GDP by 2009. However, due to a 6.7% ($50.2 mn) increase in revenue resulting from increased

intake from the petroleum industry and a higher yield on import duties, the overall deficit improved to

1.5% of GDP ($43.0 mn) in 2010 and to 0.2% of GDP ($7.2 mn) in 2011.

1.19 Belize is striving to maintain a stable fiscal outlook but the current global economic environment makes this more difficult. Further, there has been additional pressure on fiscal expenditure, given the

stepped-up interest rate to 8.0% in 2012 on the “super-bond”9, while the repayment of principal on the

super-bond is expected to commence in 2019. To maintain Central Government (CG) debt at about its current level (78.9% of GDP), and to prepare for the amortisation of the super-bond, Belize will need to

make significant additional effort to achieve fiscal balance. While Belize has fared better than many other Caribbean countries in coping with the global economic crisis, in the face of slow growth in fiscal revenue and consequently the country’s greater reliance on controlling expenditure to achieve targeted fiscal deficit levels, the country was not able to achieve the level of primary surpluses that would have made it much easier and less burdensome to service the stepped-up interest payments on the super-bond.

1.20 While GOBZ has attained the targeted levels of overall fiscal deficits and consequently has

succeeded in achieving a small reduction in debt relative to GDP since 2006 (when CG debt amounted

to 87.41% of GDP), this has been achieved at a cost to economic and social development. Worsened by

the impact of the global economic crisis, GOBZ has had to restrain spending in order to achieve the set

fiscal targets aimed at containing debt. Though it is desirable to eliminate unnecessary spending and

improve the efficiency of expenditure, Belize’s stage of development requires increasing the level of

expenditure if significant social and economic progress is to be achieved, given the low level of per-capita

income, extreme poverty, high crime rate and a long road ahead towards the achievement of the

9 A USD563.2 mn 22-year bond which was exchanged for pre-existing commercial debt in 2007. The

bond is payable semi-annually beginning in 2019, with interest rates payable semi-annually at 4.25% during 2007-09,

6% during 2010-11, and 8% for the remaining years of the bond.

- 6 -

Millennium Development Goals. Since 2007, Belize has had to restrain such desirable expenditure and

had not expended the level of resources needed to effectively maintain infrastructure and enhance its

safety. Consequently, the country’s infrastructure deteriorated to the point that in many instances

significant rehabilitation is required and failure to do so over the short to medium-term will compromise

the efficiency of many sectors, including tourism, agriculture and manufacturing, as well as continue to

compromise road safety. Given the social and economic impacts of RTI, Belize has prioritised

investments in road safety. In accordance with the priority given to this Project, it can be accommodated

within the country’s fiscal budget subject to its fiscal target (a deficit of no more than 2.5% of GDP).

GOBZ would have to determine the specific projects that can be accommodated in each fiscal year, given

its expenditure constraints. However, over the medium-term, Belize will be seeking to make appropriated

fiscal adjustments in order to be in a position to meet additional obligations related to the super-bond, as

well as other new obligations such as the re-imbursement of previous owners of nationalised assets. As

part of its strategy to undertake critical or highly desirable expenditure, while at the same time pursuing

sustainable fiscal operations, Belize is seeking support from its multilateral partners to provide loans on

the most concessional terms possible. Appendix 1.4 provides further details on Belize’s recent

macroeconomic performance.

LINKAGE OF PROJECT TO CDB’S STRATEGIC OBJECTIVE AND POVERTY GOALS

1.21 CDB’s Strategic Plan 2010-2014, recognises the positive relationship between infrastructure,

economic growth and poverty reduction. The proposed Project is consistent with CDB’s Strategic

Objectives of promoting broad-based economic growth and inclusive social development and promoting

good governance within its BMCs, and CDB’s Corporate Priorities of improving the quality and access to

education; promoting social protection measures; promoting social partnerships; strengthening human

resource capability and improving management practices; and strengthening and modernising social and

economic infrastructure. It is also consistent with the Special Development Fund 7 Operational Theme of

poverty reduction and human development. CDB, in its Country Strategy Paper for Belize (2011 to

2015), among the various strategies outlined, indicated that the Bank would support public sector

investments to improve road safety. The project objectives will support efforts to reduce the vulnerability

of road users to injuries and deaths, which have significant negative social and economic consequences.

RATIONALE FOR PROJECT

1.22 Belize recorded 70 road traffic deaths in 2009, equivalent to 21 traffic deaths per 100,000 inhabitants, giving it the highest fatality rate of CDB’s BMCs. The high death rate from RTI in Belize is not only disturbing from a public health point of view, but also translates into significant social and

economic impacts due to lost productivity and increased vulnerability to poverty. A MOH study10

estimated that the cost to Belize’s economy of RTI was equivalent to $31.97 mn in 2007. In order to

tackle this problem, a cross-sectoral approach is required11

which focuses on four strategic pillars:

• improving the safety of road infrastructure;

• enhancing the behaviour of road users;

• improving post-crash care; and

• building road safety management capacity.

10 Estimation of the Economic Impact of Road Traffic Injuries in Belize, August 2010.

11 United Nations Global Plan for the Decade of Action on Road Safety 2011-2020.

- 7 -

1.23 Responsibility for road safety lies within 15 agencies, and a wide variety of other public and private stakeholders are involved or have an interest in the issue. However, to effectively manage road safety, capacity requires strengthening and a lead agency is needed to drive and coordinate the process. Simple, low-cost engineering countermeasures must be implemented, as they have been proven to reduce

RTA injuries and fatalities by, on average, 25%12

. Improved post-crash care must also be provided as obtaining definitive medical treatment within 60 minutes of a serious trauma injury provides the greatest chance of victim survival. To curb the rising RTI rate, a targeted programme of law enforcement, public awareness and education intervention must be implemented to change road user behaviour. Finally, to ensure sustainability, funding resources must be mobilised to support improved safety over the long-term.

1.24 WB’s Guidelines13

recommend that, once agreement has been reached on the project concept,

arrangements should be made to “test” the effectiveness of the approach; illustrate the efficacy of the

investments; and to generate wider stakeholder support and demand. Accordingly, a Demonstration

Corridor has been selected to illustrate the impact of improved infrastructure; foster cooperation among

stakeholders; and to integrate enforcement, post-crash care and educational initiatives.

1.25 It is estimated that at least 20% of all RTA fatalities in Belize occur on the Western Highway

between Belize City and Belmopan. A detailed assessment of Belize’s entire main road network was

undertaken in 2011, and a series of infrastructure investment options were generated and the resultant

reductions in deaths and serious injuries were estimated. It was determined that this section of the road

network yielded the highest Cost Benefit Ratio. In addition, the Corridor accounts for the highest

inter-urban traffic volumes and serves as the only direct road link between the commercial and

administrative centres. Consequently, this was the highest priority choice for infrastructure upgrading

and to demonstrate a cross-sector, results-based approach to improving road safety.

2. PROJECT DESCRIPTION

PROJECT OBJECTIVE

2.1 The objective of the Project is to reduce deaths and serious injuries associated with road traffic

accidents. This will be achieved through improving the safety of road infrastructure along a

Demonstration Corridor; changing road user behaviour through increased awareness and understanding of

the issue; traffic law enforcement support; post-crash response support; and road safety management

capacity building.

PROJECT COMPONENTS

2.2 The Project is the first phase of what is expected to be a long-term GOBZ initiative to improve

road safety in Belize. The Project focuses on five objectives:

(a) safety of road infrastructure along the Demonstration Corridor improved;

(b) road user awareness of safety improved;

(c) driver behaviour and adherence to traffic laws improved;

12 A World Free of High Risk Roads, Rob McInerney [Chief Executive Officer, International Road Assessment

Programme (iRAP)] and Blair Turner (Principal Research Scientist, ARRB Group, formally the Australian Road

Research Board), 2011. 13

WB’s Global Road Safety Facility Country Guidelines for the Conduct of Road Safety Management Capacity

Reviews and the Specification of Lead Agency Reforms, Investment Strategies and Safe System Projects, 2009.

- 8 -

(d) post-crash care improved; and

(e) capacity to manage road safety improved.

2.3 The following project components respond to these objectives (further details of which are

presented in Appendix 2.1):

(a) Road Safety Infrastructure: this component will support improving the safety of road

infrastructure along an 80 km corridor of the Western Highway, between Belize City and

Belmopan. The proposed infrastructure works are located in Belize and Cayo Districts.

The Project Location Map and a diagram of the Demonstration Corridor are presented at

Figures 1 and 2, respectively.

(b) Road User Education and Awareness: this component will support increasing road user

awareness and improving behaviours. The sub-components are:

(i) Public Education and Awareness: consultancy services will be engaged to

conduct baseline and post-project Knowledge, Attitudes and Practices (KAP)

Surveys; to develop a comprehensive targeted communication strategy; and to

deliver five comprehensive biannual public awareness campaigns

(Communications Consultant).

(ii) Curriculum Development and Teacher Training: consultancy services will be

engaged to develop road safety curriculum for Primary and Secondary Schools,

produce relevant training materials and deliver training to 100 teachers at 10

schools within the Demonstration Corridor (Curriculum Consultant). This sub-

component will be supervised by the relevant Technical Working Group

(TWG) under the CDB financed Education Sector Reform Project being

implemented by Ministry of Education, Youth and Sports (MOEYS).

(c) Road Safety Enforcement: this component will support the improvement of traffic law

enforcement on the Demonstration Corridor and in the municipalities of Belize City and

Belmopan, through the provision of two highway patrol vehicles and enforcement

equipment to DOT. Additionally, consultancy services will be engaged to deliver a

training programme in traffic law enforcement (Enforcement Training Consultant) to 35

enforcement officers in DOT, PD, and the nine municipalities.

(d) Road Accident Emergency Services: this component will support the improvement of

post-crash trauma care through the provision of two ambulances to BERT, through MOH.

(e) Capacity Building: this component will support the improvement of GOBZ’s capacity to

manage road safety. The sub-components are:

(i) Road Safety Mentoring: consultancy services will be engaged to mentor, develop

and consolidate the capacity of the various agencies to manage road safety and

assist with the establishment of NRSC. The Consultant will assist GOBZ in the

development of the Medium-term National Road Safety Strategy and the M&E

Framework (Road Safety Consultant).

(ii) Road Safety Training: consultancy services will be engaged to deliver a training course on various aspects of road safety including road safety auditing (Road

Safety Training Consultant) to 20 staff members responsible for road safety in

MFED, MWT, PD and the nine municipalities.

- 9 -

(iii) M&E: this sub-component will support the establishment of clear targets for

road safety and the development of M&E framework. Equipment will be

provided to support MWT’s collection of speed and traffic data. Support will

also be provided to assist in establishing consistent indicators and entrenching

better data collection and sharing mechanisms between agencies. Following the

completion of the road safety infrastructure, consultancy services will be engaged

to re-survey and update the safety rating along the Demonstration Corridor (Road

Safety Assessment Consultant).

(f) Project Management: project management will be provided by a project team within

GOBZ line ministries led by a Road Safety Unit (RSU), for a period of 39 months.

Engineering consultancy services will be engaged to certify road safety infrastructure

works and assist MWT with a roundabout design (Design and Certification Consultant).

2.4 A Design and Monitoring Framework summarising the characteristics of the Project is presented

in Table 2.1. Draft Terms of Reference for the consultancies are set out at Appendices 2.2, 2.3, 2.4, 2.5,

2.6, 2.7 and 2.8.

- 10 -

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK

Design Summary

Performance Targets/Indicators Data Sources/Reporting

Mechanisms

Use of Information

Assumptions and Risks

Project Impact: Human, economic and financial

losses due to RTI reduced.

Direct and indirect losses associated with

RTI reduced from 1.26% to 1.0% of GDP by 2015.

1. MOH statistics.

2. Economic Cost of RTI report.

3. GOBZ, MFED, Supervisor of Insurance statistics.

1. 2. Safety investments are affective.

3. Behavioural changes materialise.

Project Outcome: Deaths and serious injuries associated with RTA reduced on the Demonstration Corridor.

1. Safety ratings of road infrastructure for

all users along the Demonstration Corridor improved from 1 or 2 stars to at

least 3 stars by September 1, 2014.

2. Killed and Seriously Injured (KSI) reduced by 20% by September 1, 2015.

1. International Road Assessment

Programme (iRAP) report. 2. MOH’s HMIS reports.

3. PD accident database reports.

To demonstrate project

effectiveness and viability for replication.

Assumptions: 1. Traffic levels increase as projected.

2. Public support remains strong.

Project Outputs: 1. Safety of road infrastructure

along the Demonstration

Corridor improved.

2. Demonstration Corridor road- user awareness of road

safety improved.

3. Driver behaviour and

adherence to traffic laws along the Demonstration

Corridor improved.

4. Post-crash care on the

Demonstration Corridor

improved.

1. Safety of road infrastructure improved

along 80 km of road by September 1, 2014.

2. KAP baseline surveys completed by

January 1, 2013.

3. Communication Strategy developed by March 1, 2013.

4. Five bi-annual road safety campaigns delivered by September 1, 2015.

5. Curriculum developed, training materials delivered and 100 teachers trained by January 1, 2014.

6. Curriculum delivered to 2,000 pupils by

January 1, 2016.

7. Post-project KAP delivered by September 2015.

8. Enforcement strategy developed by October 1, 2012.

9. Patrol vehicles and equipment delivered by April 1, 2013.

10. Enforcement training delivered by April 1, 2013.

11. Ambulances delivered by October 1,

2013.

1. Project Manager’s (PM) Reports.

2. Consultants’ Reports.

3. MWT design drawings. 4. CDB Supervision Reports.

5. Design and Certification Consultant’s Reports.

6. Consultants’ Project Completion

Reports (PCRs).

To track the progress of

project components.

1. Inter-agency cooperation is effective.

2. Inter-agency coordination is effective.

3. MOEYS approves and adopts

Curriculum.

4. Road safety campaign and school curriculum raises awareness.

5. MWT, Municipalities and Police establish and implement effective enforcement programmes.

6. DOT assigns enforcement officers to

patrol the highway. 7. BERT provide effective emergency

medical service response to RTA.

8. GOBZ agreement on NRSC composition.

Risks: 1. Inadequate maintenance; 2. Lack of legislative reform.

- 11 -

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK (Cont’d)

Design Summary

Performance Targets/Indicators Data Sources/Reporting

Mechanisms

Use of Information

Assumptions and Risks

5. GOBZ capacity to manage

road safety improved.

12. Project management vehicle and

equipment delivered by October 1, 2012.

13. Road safety training delivered by April 1, 2013.

14. Monitoring equipment delivered by

April 1, 2013. 15. M&E framework and performance

indicators established by December 1, 2012.

16. Road Safety Targets and Vision developed by July 2013.

17. Annual Action plans developed by October 1, 2013, 2014, 2015.

18. Results-based National Road Safety Strategy developed by October 1, 2015.

19. NRSC formalised by July 1, 2013. 20. Road Safety Assessment completed by

September 1, 2015.

Total Inputs (USD mn)

CDB: OCR – USD5.362 mn

SFR – USD1.886 mn

GOBZ: USD1.596 mn

1. Consultant’s Reports.

2. PM’s reports. 3. CDB site supervision visits.

4. Quarterly Reports on Investment Costs.

5. CDB disbursement records.

1. GOBZ counterpart contribution

available. 2. No major adverse weather conditions

to impact infrastructure.

- 12 -

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK (Cont’d)

Project Outcome Indicators

Baseline

2011

Year 1

Year 2

Year 3

Year 4

Report and

Frequency

Responsibility for

Data Collection

1. Safety of road infrastructure for all users along the Demonstration Corridor improved to at least 3 stars.

2. KSI reduced by 20% by September 1, 2015.

1 and 2 star

100

100

95

3 Star

90

80

Annual

Annual

MWT

PM/MWT/PD/MOH Project Output Indicators Targets achieved for:

0

40

40

1.5

Monthly

Progress Reports

Project Engineer

(PE)

1. Infrastructure improved Demonstration Corridor (km).

2. KAP baseline survey completed.

1 Monthly

Progress Reports

PM

3. Communication Strategy developed.

0

1 Communication Strategy

PM

4. Five bi-annual road safety campaigns delivered.

0

1.5

2 Monthly Progress Reports

PM

5. Curriculum developed, training materials delivered teachers trained.

and

0

100 Monthly

Progress Reports

PM/MOEYS

6. Curriculum delivered to pupils.

0

0

1,000

1,000 Monthly Progress Reports

PM/MOEYS

7. KAP post-project survey completed. 0 0 0 1 PCR PM

8. Enforcement strategy developed.

1 Enforcement Strategy

PM/DOT

9. Two patrol vehicles and equipment delivered.

0

2 Monthly

Progress Reports

PM/DOT

10. Enforcement training delivered to enforcement officers.

0

35 Monthly

Progress Reports

PM/DOT

11. Ambulances delivered.

0

2 Monthly

Progress Reports

PM/MOH/BERT

12. Project management vehicle and equipment delivered. 1

- 13 -

TABLE 2.1: DESIGN AND MONITORING FRAMEWORK (Cont’d)

Project Outcome Indicators

Baseline

2011

Year 1

Year 2

Year 3

Year 4

Report and

Frequency

Responsibility for

Data Collection

13.

Road Safety Training delivered.

0

20

1

1

Monthly Progress Reports

PM

14.

Monitoring equipment delivered.

1 Monthly

Progress Reports

PM

15. M&E framework established. 1 M&E framework PM

16.

Road Safety Vision adopted.

0

1

Road Safety

Vision

PM/Operational

Steering Committee

(OSC)

17. Annual Action Plans adopted. 0 1 Annually PM 18. National Road Safety Strategy adopted. 0 0 0 1 NRSC PM/OSC 19. NRSC formalised. 0 1 Cabinet Decision PM/OSC

20.

Road Safety Assessment completed.

0

0

0

1 Road Safety Assessment

PM/DOW

- 14 -

LESSONS LEARNT AND INCORPORATED INTO DESIGN

2.5 Lessons drawn from the experience of CDB, related to road infrastructure and education, which

are applicable to this Project and which have informed the Project design, include:

(a) appropriate designs, informed by adequate studies and investigations, are required to

achieve the expected design lives of infrastructure and minimise life-cycle costs. For

each 100 m section of road, countermeasure options proposed under the Project have

been tested for their potential to reduce death and injuries. They have also been assessed

against affordability and economic effectiveness criteria;

(b) an experienced project management team with personnel dedicated to the implementation

of the Project is critical in order to minimise cost and time overruns. The Project will

provide for PM and PE to support implementation and will be assisted by an experienced

Road Safety professional;

(c) good estimates of quantities and conservative cost estimates by engineering consultants

minimise the risk of incurring significant cost overruns. The countermeasure cost

estimates developed for the Project, are based on standard designs and recent tender rates

for similar works undertaken in Belize. Some additional geometric and hydraulic design

work will be required to finalise a roundabout design and adequate contingencies have

been considered for this particular feature; and

(d) fostering ownership is critical to successful implementation of new educational

programmes. Ensuring that stakeholders understand their roles and have opportunities

for input in the development of programmes and resources, and are able to provide

feedback on outputs contribute significantly to the success of activities. MOEYS,

through the relevant TWG and the teacher training institutions, will have a role in

working closely with the Curriculum Consultant and in supervising the development of

educational programmes and materials, and the training of teachers.

2.6 The Project supports specific interventions in four of the five Decade of Action pillars. The Project will implement interventions to improve the safety of infrastructure along the Demonstration Corridor; support traffic law enforcement; and improve post-crash response. These will be supported by a targeted approach to improve road user awareness and behaviours. The project design

also incorporates the recommendations of the World Report on RTI Prevention14

, which include:

(a) Identify a lead agency in government to guide the national road traffic safety effort:

GOBZ has identified a lead line ministry (MFED) through which the Project will be

implemented. OSC will also be provided to ensure coordination with the various project

participants and will be the main decision-making authority with respect to the Project.

The Project will also support the formalisation of a multi-stakeholder NRSC to provide

guidance, oversight, and accountability. Stakeholder support for the Project is very high

and road safety is a declared political priority for GOBZ.

(b) Assess the problem, policies and institutional settings relating to RTI and the capacity for

RTI prevention in each country. The design of the Project has been informed by a

Road Safety Management Capacity Review completed in accordance with WB’s Country

Guidelines.

14 WHO, 2004.

- 15 -

(c) Prepare a national road safety strategy and plan of action. The Project will develop a

cost-effective, long-term, performance-based national road safety strategy. Project

reviews will be held each year with all key stakeholders to develop Annual Action Plans

and to provide an opportunity to refocus efforts towards obtaining results.

(d) Allocate adequate financial and human resources to address the problem. GOBZ’s

public investment programmes compete for scarce resources. The Demonstration

Corridor has been designed to provide for results that will illustrate the effectiveness

of the investment before replicating it throughout Belize. Project results are also

expected to mobilise more sustainable long-term funding resources from non-government

stakeholders, in addition GOBZ’s new road maintenance strategy is expected to

include provision for a road maintenance fund.

(e) Implement specific actions to prevent road traffic crashes, minimise injuries and their

consequences and evaluate the impact of these actions. In addition to the specific

investments, M&E features have been incorporated into Project design.

(f) Support the development of national capacity. The Project provides for a significant

element of capacity building. The use of consultancies to support capacity has been

minimised in favour of a more learn-by-doing approach with case study and field

exercises. The project management will be supported by road safety expertise to mentor

and consolidate road safety management capacity in all participating agencies.

3. FINANCING STRUCTURE AND COSTS

FINANCING

3.1 The project cost is estimated at $17.7 mn (USD8.844 mn) which will be financed with resources

from CDB and GOBZ. The detailed cost estimates for the works were developed by independent

consultants procured by GOBZ. These estimates are based on unit rates derived from recent road works

contracts in Belize. Estimates for consultancy services associated with capacity building and training are

based on current rates for professional fees. Estimates for Education and Awareness campaign are based

on current unit production and airing rates for various media in Belize. CDB staff is satisfied that

adequate contingencies have been provided to ensure the completion of the proposed components.

A summary of the project cost is presented in Table 3.1. Further details are given the in Cost, Phasing

and Financing Plan, which is presented at Appendix 3.1.

3.2 The proposed loan to GOBZ will be for an amount not exceeding the equivalent of

USD7.248 mn, comprising USD5.362 mn from CDB’s OCR (the OCR portion), and USD1.886 mn from

CDB’s SFR. The OCR portion will be repayable over a period of 16 years inclusive of a grace period of four years, at variable interest rate current prevailing at 3.84%. The SFR portion will also be repayable

over a period of 16 years inclusive of a grace period of four years, at a fixed interest rate of 2.5%.

- 16 -

TABLE 3.1: SUMMARY OF PROJECT COSTS AND FINANCING

($’000)

Item

CDB

GOBZ Total OCR SFR Total 1. Road Safety Infrastructure 8,200 - 8,200 - 8,200 2. Road User Education & Awareness - 1,050 1,050 500 1,550 3. Road Safety Enforcement 280 150 430 - 430 4. Road Accident Emergency Services - 450 450 - 450

5. Capacity Building - 620 620 - 620

6. Project Management 840 840 2,245 3,085 Total Base Costs 8,480 3,110 11,590 2,745 14,335

7. Physical and Price Contingencies 1,703 489 2,192 446 2,637

Total Project Costs 10,183 3,599 13,782 3,191 16,972

8. Finance Charges 540 173 713 - 714

Total Finance Costs 10,723 3,772 14,495 3,191 17,686

USD Equivalent 5,362 1,886 7,248 1,596 8,844

Percentage 61% 21% 82% 18% 100%

4. PROJECT VIABILTY

TECHNICAL ANALYSIS

4.1 In recent years the predominant international approach to improving road safety has become known as the “Safe System Approach” (as illustrated in the figure

15 at right), which means reducing trauma impacts

through multiple measures involving the road user; the road system (including speed considerations); and the vehicle. The basic reasoning is that, even if not all collisions can be avoided, all severe injuries can, in principle, be avoided. Countermeasures must be implemented to reduce the likelihood of crashes and trauma impacts when they do occur. The system also encourages a better understanding of the interaction between the key elements of the road system. Project design supports the Decade of Action pillars that will assist in Belize moving towards having five-star road

15 Source: New Zealand Ministry of Transport.

This information is withheld in accordance with one or more of the exceptions

to disclosure under the Bank’s Information Disclosure Policy.

- 17 -

users (skilled, competent, wearing seat belts, sober and not distracted), driving in five-star vehicles, travelling on five-star roads at appropriate speeds, that match the road and its use.

4.2 Along the Demonstration Corridor, at 100 m intervals, 50 road attributes were assessed against

more than 70 engineering countermeasures to evaluate their ability to reduce RTA. An investment plan

was then derived through an economic analysis where the cost of implementing the countermeasures was

compared to benefits associated RTI prevented. The analysis revealed that the proposed countermeasures

are the most technically and economically feasible option for improving road safety on the Corridor.

4.3 The road safety infrastructure proposed presents no major technical issues. The works will

include shoulder widening, installation of safety barriers, delineation, provision of pedestrian crossings

and walkways, resealing, and construction of a roundabout. These low cost road safety countermeasures

are based on MWT’s standard designs which are informed by the standards of the American Association

of State Highway and Transportation Officials (AASHTO) and the New Zealand Transport Agency.

CDB considers that these are appropriate for application to the Project. MWT will require some additional

geometric and hydraulic design support to finalise their roundabout design at the junction of the

Western and Hummingbird Highways. The forecast volume of vehicular traffic used in the design, was

based on traffic surveys conducted in 2011. A lifecycle of 20 years was used. Certain sections of the

Demonstration Corridor are in good structural condition, but have poor skid resistance and corresponding

high accident rates, due to the limestone material employed in the surfacing. These sections will be

resurfaced utilising materials that will meet AASHTO’s skid resistance standards. Also, MWT’s

experience with the durability and luminosity of painted delineation markings on the Corridor has been

poor. Hence delineation markings will include the utilisation of high luminosity thermoplastic tape in

accordance with AASTHO standards, the lifecycle cost for which are lower than the materials currently

being used. A significant issue along the Corridor is the loss of shouldering material due to the movements

of transport buses. To reduce routine maintenance costs, rather than re-gravelling, sealed lay- bys will be

provided at known problem areas. Following project completion, the safety rating on all sections of the

Corridor is expected to be upgraded from its current 1 or 2 star rating (Appendix 4.1) to at least 3-stars for

all road users.

PROJECT IMPACTS

Macroeconomic Impact

4.4 The Project is likely to have a net positive macroeconomic impact on Belize. Over the short to

medium-term, employment will be provided through road safety improvement activity and the spill-over

effects. More importantly, the Project is expected to reduce the significant negative economic impact

that RTI have had on Belize. A study of the economic impact of RTI in Belize estimated that, during 2007,

the economic cost of RTI amounted to $31.97 mn (1.26% of GDP). The great majority of the cost was

for fatal injuries, specifically on indirect cost attributed to premature death. Direct cost was estimated at

$491,549, of which 2.1% was spent on fatalities, 61.6% on the severely injured and 36.3% on slightly

injured. The Project is also expected to have a positive impact on poverty, as fewer families will have to

suffer economic lost from RTI. While the fiscal positions of the country will be adversely impacted

through higher debt service payments, this impact is likely to be counterbalanced in the long run by the

efficiency gains in the economy.

Economic Impact

4.5 The objective of the Project is to reduce road traffic deaths and serious injuries in Belize, by

applying an integrated, cross-sectoral set of interventions to a high risk Demonstration Corridor. RTA

fatalities on this Corridor have averaged 14 p.a., over the last 10 years, and account for 20% of all

fatalities nationwide. Although the chart below suggests a general declining trend in fatality rates, the

- 18 -

Dea

th R

ate

per

100,0

00 in

ha

bita

nts

overall cost of RTA to the economy of Belize remains significant, accounting for 1.26% of GDP in 2007,

and 4.03% of the total government budget for the same year.

BELIZE RTA FATALITY RATE TRENDS

*Estimated

Year

Table 4.1 highlights the results of a MOH study aimed at quantifying the economic impact of RTI in

Belize, and provides compelling evidence for a systematic and national response to the problem.

TABLE 4.1: ECONOMIC IMPACT OF RTI IN BELIZE IN 2007

($)

Severity Direct Cost Indirect Cost Total Fatal 10,267 30,348,870 30,359,137 Non-Fatal severe injury 302,847 1,105,930 1,408,777 Non-Fatal minor injury 178,435 19,696 198,131 Total 491,549 31,474,496 31,966,045 Source: Estimation of Economic Impact of Road Traffic Injuries in Belize, August 2010.

4.6 The proposed investment is expected to reduce road user costs and costs to society, by reducing

the number and severity of accidents, injuries and fatalities that result from road crashes. Project

beneficiaries include road users, roadside communities and businesses in the Demonstration Corridor and, to a lesser extent, those outside the corridor who will subsequently benefit from improved management of

the sector. The main direct economic benefits of the Project come from the expected reductions in social

cost, resulting from reduced numbers and severity of fatalities and injuries caused by RTA. These

benefits include:

(a) reduction in the incidence and severity of road accident injury and death, and the

associated cost to individuals and the economy of Belize;

(b) cost savings from greater effectiveness of road safety interventions, as a result of

enhanced institutional capacity to monitor, evaluate and manage road safety at both the

national and municipal levels;

(c) reduction in the public resources absorbed by road accidents, including temporary or

permanent loss and diversion of human resources, consumption of medical resources and

damage or destruction to property; and

(d) improved efficiency of road transport due to reduced economic inefficiencies resulting

from RTA.

- 19 -

4.7 The main criteria applied for the quantification of the Project’s economic benefits have been the

number of lives saved, prevented disabilities and public health system savings due to lower illness levels

associated with trauma caused by RTA, as a consequence of actions implemented on the Demonstration

Corridor, and a vigorous public awareness and education campaign. A model has been developed for

road safety on the Demonstration Corridor that takes into account the current and predicted accident rates,

current and predicted traffic volumes, speeds, road design elements, and estimates of the effect of project

interventions. RTA fatalities and injuries are modelled for the Demonstration Corridor, with and without

the Project. The economic evaluation compares the incremental costs and benefits of these two

alternatives.

4.8 The results of the incremental analysis are shown in Appendix 4.2. It indicates that 470 fatalities

and serious injuries could be avoided over the 20-year analysis period, for the level of investment

proposed. This is equivalent to a reduction of 20% in the number of injuries and fatalities over the

20-year period.

4.9 The economic benefit from the fatalities and injuries avoided is calculated using the methodology developed by McMahon and Dahdah in 2008, and is applied by iRAP, globally. The approach estimates the economic value of a statistical life at 70 times GDP per capita at current prices and the economic value of a serious injury at 25% of the value of a fatality. The ratio of serious injuries to fatalities is

estimated to be 10:116

. Details of the methodology used to predict injury and fatalities, and associated economic cost, for various categories of road users are provided in Appendix 4.3.

4.10 Based on the assumptions in Appendix 4.2, the estimated Net Present Value (NPV) of the Project,

using very conservative accident cost values17

, is $13.2 mn and the Economic Rate of Return (ERR) is 28.8%. ERR is well above CDB’s cut-off rate of 12.0%, which highlights the significant economic benefits that can be had from road safety investments. Such high rates of return are typical for road safety projects in which small investments can significantly reduce loss of life, for which the economic value is substantial. Details of the calculations of the ERR are shown are shown in Appendix 4.4.

4.11 The economic analysis focused on the quantifiable costs and benefits related to the safety infrastructure improvements on the Demonstration Corridor, as these can be estimated with greater

reliability and robustness. However, the institutional strengthening and capacity building components are

also expected to have a significant impact on road safety throughout the country. Tangible benefits are

also expected in terms of reductions in RTI and fatalities due to changes in behaviour of road users, as a

result of the proposed road education, awareness and communication activities contemplated by the

Project. In addition, the strengthening of Belize’s road safety management capacity will contribute to

saving lives and improving the overall safety of Belize’s road net work. There will be some time savings to

road users from more timely availability of medical services, which will alleviate blockage and traffic

build-up on the road. However, these benefits have not been included in the analysis.

16

The True Cost of Road Crashes: Valuing Life and the Cost of Serious Injury was written by Kate MacMahon

(previously head of the Road Safety Strategy Division in the Great Britain Department for Transport) and Said

Dahdah (Road Safety Engineer at WB’s Global Road Safety Facility). 17

A study entitled Health, Wealth and Welfare by David E Bloom, David Canning and Dean T Jamison, Finance

and Development, March 2004, suggest that a reasonable range for a country’s value of a statistical life is 100 to 200 times GDP per capita. The Project assumes a value of 70 times GDP per capita which underscores the conservative nature of the estimates made in Appendix 4.3.

- 20 -

Sensitivity Analysis 4.12 The critical item driving the NPV and ERR are the estimated savings in fatalities and injuries.

Accordingly, a sensitivity analysis was carried out to analyse the effect on the NPV and ERR, if the

estimated reduction in the number of KSI did not materialise. Two scenarios have been investigated: a

10% and a 20% reduction in the number of KSI prevented. The results are shown in the table below:

TABLE 4.2: SENSITIVITY ANALYSIS

Sensitivity Variables

NPV

($ mn) ERR (%)

Base Case 13.2 28.8 1. 10% reduction KSI prevented 10.4 26.7 2. 20% reduction in KSI prevented 7.9 23.5

4.13 The sensitivity analysis demonstrates that even with a lower effectiveness rate in the proposed

measures, the Project still provides an acceptable overall economic return.

ENVIRONMENTAL, SOCIAL AND GENDER ANALYSIS, RISKS AND SAFEGUARDS

Environmental Assessment 4.14 These are small-scale works that will for the most part take place in within the existing right-of-

way, except for the proposed construction of the roundabout. Potential negative impacts are negligible,

easily identifiable, spatially restricted, likely to be short-term and can be easily prevented or controlled

with simple mitigation techniques known to the construction industry. Impacts expected will consist

mainly of noise; vibration; dust; traffic management; and improper handling, storage and disposal of

construction waste materials. DPW has ample experience with respect to the environmental performance

requirements for the design and implementation of road works, including the handling of likely

environmental considerations that could arise with respect to the design and construction of the

roundabout.

4.15 The contract documents will require that the Contractor submit an Environmental Management

Plan (EMP) to DPW’s PE for approval, prior to commencement of the road works component. The

environmental requirements of the construction specifications should be costed and specifically cover

items such as: work staff health and safety; use of personal protective equipment; signage; traffic

management and controls; and communication of works-schedule to the public; management and disposal

of construction materials and waste; and the assigned internal contractual responsibilities for

environmental monitoring and reporting. GOBZ is required to provide necessary approved licenses and

permits for borrow material, as well as any other required environmental clearances. The Design and

Certification consultants will monitor the Contractor’s compliance with the approved EMP and report on

environmental performance as part of their routine project management reporting to CDB.

Social Assessment

4.16 The Project is classified as category “B” under the Bank’s Environmental and Social Review

Procedures. Significant social risks are not anticipated and tremendous positive social impacts are

expected for beneficiaries (all categories of road users along the Western Highway). The anticipated

positive impacts to be derived from this Project will lead to improved driving and safe road use practices

through behavioural change; development of a road safety culture in Belize; reduction in the number of

road deaths and seriously injured through RTA; significant reduction in the direct and indirect human and

social costs associated with road accidents; and reduction in inordinate traumatic and emotional burden

- 21 -

placed on families due to family members’ loss of life and/or their recovery (short or long-term) from

RTI. The cumulative benefits of the Project are expected to contribute to the development of Belize’s

social and human capital and poverty reduction.

4.17 Statistics from the National Health Information Surveillance Unit of MOH indicated that in 2005,

death as a result of RTI were identified as the fourth leading cause of death in general, regardless of age

and sex18

. RTA rank as the fourth leading cause of death in Belize and are identified as a significant contributor to the overall mortality and morbidity levels in the country. Through educational programmes

targeted at primary and secondary school children, to be delivered in a manner that complements current institutional efforts of DOT, PD and the traffic department in the municipalities of Belize City and

Belmopan, the Project will target risk factors for road users (such as speeding, seat belt wearing, and

drink-driving) and vehicles, as part of an integrated Safe System Approach to achieve project objectives and deliver positive social impacts. It will employ a differentiated, methodological approach to

disseminating information to reach different target audiences through promotions and educational campaigns in order to inculcate a culture and practice of safety. In that regard, various culturally-relevant

educational materials will be developed in English, Spanish and local dialects to reach the school population along the Corridor. Language-appropriate materials will also be developed to target a diverse

adult demographic, including ethnic communities (through Community Education Programmes) living in the project area. Furthermore, the Project will utilise an incremental instructional approach since long-

term behavioural change must be based on infusion, which is focused on maximisation of repetition which is highly likely to lead to automaticity. In addition, given that the enhanced educational

programmes must provide adequate opportunity for practical application of the principles introduced, authentic, real life situations, under adult supervision, must be incorporated and teachers must be

adequately trained to inculcate the appropriate road safety principles and their seamless practicability in the youth.

4.18 The education component will have significant potential for long-term social impact since:

(a) children assimilate and transfer knowledge and skills learnt, therefore there is not only

the likelihood that their long-term behaviour will be influenced, but also that they will

influence the behaviours of the adults around them;

(b) the teacher training modules and materials which will be developed can be used and

replicated across the entire system and therefore there are likely to be systemic benefits;

and

(c) culturally-relevant materials will address issues specific to Belize.

4.19 Special attention will be placed on targeting male drivers, including youth, given their over-

representation in the fatality and seriously injured statistics. Moreover, since RTI continue to affect the

young population in its most productive years, the Project is designed to assist in protecting Belize’s

social and human capital base by minimising human costs that have negatively impacted the country over

time. In addition, given that the death of the male or female household head/bread-winner can increase

that family’s vulnerability and in some cases be the trigger that plunges them into poverty, targeted

interventions at this level are intended to reduce negative social impacts on households, including the

burden of care for either head (male/female) resulting from RTA.

18 Road Safety is No Accident: National Five Year Strategic Plan to Reduce Road Traffic Accidents/Injuries in

Belize 2007-2012. Technical support for the Plan was provided by Pan American Health Organisation (PAHO)

(2007).

- 22 -

4.20 No major social risks are expected. However, one anticipated risk relates to the possibility of the

slow pace of behavioural change as a result of long existing practices, attitudes and knowledge (or

lack of) of road safety leading to delayed project benefits to the target population. This risk to road

safety will be addressed by implementing programmes that integrate elements of enforcement,

reinforcement and education of the public along the Corridor and the identification and mobilising of

private sector resources to sustain a long term educational programme.

RELEVANT POLICY, LEGAL AND REGULATORY ISSUES

4.21 The Project will operate within the existing policy framework, which currently provides adequate

legislation and regulations to support traffic-law enforcement efforts on the Demonstration Corridor.

Shortcomings pertaining to the levels of fines imposed will require further review and analysis, which has

been provided for in the Project. Relevant reform requirements identified by that review will be

incorporated into the design of a second phase project.

5. THE BORROWER

5.1 GOBZ may, pursuant to Section 3(1) of the Loans (Caribbean Development Bank) Act,

Chapter 59 of the laws of Belize [the Loans (CDB) Act], in such manner and on such terms as may be

agreed between GOBZ and CDB, borrow from time to time such sums as may be required by GOBZ.

Any agreement between GOBZ and CDB in respect of sums borrowed under this power must be made in

the name of the Minister responsible for Finance (the Finance Minister) for and on behalf of GOBZ and

may be signed by the Finance Minister for or on behalf of GOBZ. No such agreement shall be executed

unless the conditions thereof have been first approved by resolution of the House of Representatives to

that effect.

5.2 CDB has so far approved loans totalling USD217.79 mn to GOBZ and Statutory Authorities

established in Belize. Of this amount, USD168.03 mn has been disbursed and USD115.95 mn was

outstanding at April 25, 2012. The loans by CDB to the Statutory Authorities have been made under the

guarantee of GOBZ pursuant to Section 8(1) of the Loans (CDB) Act. CDB has also approved a loan of

USD4.896 mn to the University of the West Indies of which an amount of USD301,874 has been

guaranteed by GOBZ.

5.3 All amounts required for the payment of any sums borrowed by GOBZ from CDB and all interest

and other charges on any such sums are charged on and payable out of the Consolidated Revenue Fund

(CRF) and assets of GOBZ. Where any sum becomes payable by GOBZ under a guarantee given by

GOBZ, that sum is charged to CRF and the Finance Minister must direct payment to be issued out of that

Fund accordingly. GOBZ is current with its loan payments to CDB.

IMPLEMENTING AGENCY

5.4 The Road Safety Management Capacity Review financed by CDB as part of the Fourth Road

Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10) examined the institutional capacity of the

various government agencies involved in road safety. The conclusion of that Study was that the lead

agency for road safety should be MFED. MFED manages several donor projects and programmes and is

the central coordinating body for all external donor development assistance to Belize. MFED has several

key champions driving the project forward and has the necessary authority and broad perspective to

coordinate cross-sector initiatives such as this.

- 23 -

PROJECT MANAGEMENT AND ENGINEERING SERVICES

5.5 The proposed management structure is presented in Appendix 5.1. Prior to the disbursement of

the Loan, GOBZ will be required to take measures necessary to facilitate the management of the Project.

These measures include the following:

(a) assigning the administration and management of the Project to RSU within MFED, which

will be responsible for leading the initiative and managing project tasks assigned to line

ministries;

(b) designating task leaders from MWT - DPW and DOT, and MOH, who will be

responsible for coordinating, managing and reporting to RSU on the Road Safety

Infrastructure, Road Safety Enforcement, and Road Accident Emergency Services

components, respectively;

(c) establishing OSC which shall be chaired by the Chief Executive Officer, MFED, and will

be a decision-making forum to direct project activities, monitor the progress of project

components and resolve implementation obstacles;

(d) engaging PM;

(e) establishing RSU; and

(f) providing suitable accommodation for RSU, and providing RSU with adequate

accounting and clerical support.

The TOR for PM, PE, Task Leader (TL) and OSC are set out at Appendix 5.2.

5.6 In addition to the above, GOBZ will be required:

(a) prior to the disbursement of the Road Safety Infrastructure Works component:

(i) to engage consultants to provide the engineering services specified in

Appendix 2.8. The cost of these services will be financed by the Loan; and

(ii) to engage a PE who will report to TL, Road Safety Infrastructure, and manage all

aspects of the implementation of that component.

(b) prior to disbursement of the Road User Education and Awareness component, to engage

consultants to provide the services specified in Appendix 2.2. The cost of these services

will be financed by the Loan; and

(c) prior to disbursement of the Road Accident Emergency Component, to submit to CDB a

Memorandum of Understanding (MOU) between GOBZ and BERT with respect to the

use by BERT, of the emergency equipment procured under the Project.

GOBZ will also be required to establish the NRSC which will function as a high-level, multi-

stakeholder guidance and advisory body on road safety. A draft of the proposed NRSC composition has

been developed, but there is a need to incorporate wider representation and to better define its role. Also, further planning is required for transitioning RSU from MFED to DOT, by the end of the Project to

ensure capacity built therein is retained.

- 24 -

IMPLEMENTATION SCHEDULE

5.7 The Project will be implemented over a 39-month period, commencing September 2012 and

ending December 2015. The proposed Project Implementation Schedule is presented in Appendix 5.3.

PARTICIPATION OF BENEFICIARIES AND STAKEHOLDERS

5.8 The preparation and appraisal of this Project involved consultation with a wide range of

stakeholders. Meetings were held with different categories of various Government officials, including

inter alia, MFED, Education, Health, Works and Transport, Bureau of Women’s Affairs, PD,

representatives of BERT, PAHO, and local insurance industry representatives. In addition, key

stakeholders participated in a workshop that was coordinated by GOBZ and CDB, and conducted on

January 31, 2012, to deliberate on project design. This workshop, in addition to other in-country meetings

with key stakeholders that were conducted during project preparation and appraisal, provided

opportunities for their insights, opinions and concerns to be expressed and considered in the design of the

Project. This principle of stakeholder participation, while already central to the approach, will be

reinforced and strengthened during the implementation and post-implementation stages of the Project.

Project stakeholders will be invited to participate in a Project Launch, formative evaluation of the Project,

and establishment of action plans through the Annual Review of project activities along the Corridor.

During implementation, efforts will be made to include community participation in the placement of

footpaths and pedestrian crossings, and in traffic law enforcement. The Communication Strategy and its

Biannual Awareness Campaigns are expected include events and activities in the communities and schools

along the Corridor, and incorporate feedback mechanisms to inform campaign designs. Multi-modal

strategies will be used to communicate interim project results nationally and a mechanism will be

established to encourage timely feedback.

PROCUREMENT

5.9 Procurement of consultancy services shall be in accordance with CDB's Procedures for the

Selection and Engagement of Consultants by Recipients of CDB Financing. Contracts for capital works

and equipment to be financed by the CDB Loan, will be procured in accordance with CDB’s Guidelines

for Procurement. A waiver of CDB’s Guidelines for Procurement is requested to permit procurement of

new vehicles (a project management vehicle, two patrol vehicles and two ambulances), with no restriction

on country eligibility. The waiver will facilitate full participation of local suppliers and vehicle

dealerships and improve access to spare parts and maintenance services. The total value of the waiver is

estimated at USD385,000. The Procurement Plan is provided at Appendix 5.4.

DISBURSEMENT

5.10 Disbursement of the CDB loan will be made in accordance with CDB’s Guidelines for the

Withdrawal of Loan Proceeds. It is expected that the first disbursement from the Loan will be made by

September 2012. The Loan is expected to be fully disbursed by December 2015. The Disbursement Schedule is provided at Appendix 5.5.

MONITORING AND REPORTING

5.11 PM and TLs will be responsible for providing relevant reporting and establish mechanisms for

monitoring indicator data collection for their respective components. It will be a condition of the Loan

that PM shall furnish, or cause to be furnished, to CDB the reports listed in Appendix 5.6 to this Report,

in such form or forms as CDB may require, not later than the times specified therein for so doing.

- 25 -

MAINTENANCE

5.12 It will be a condition of the Loan that GOBZ adequately maintain the infrastructure, vehicles and

equipment financed under the Project. As a further condition of the Loan, GOBZ will undertake a

condition assessment of the project infrastructure upon the receipt of such a request from CDB. Further,

GOBZ will submit to CDB its annual road maintenance budget.

PERFORMANCE EVALUATION RATING

TABLE 5.1: PROJECT PERFORMANCE EVALUATION

Criteria Score Justification Strategic Relevance 7.0 The need for improving road safety was identified in GOBZ’s Medium

Term Development Strategy and in Horizon 2030 – Long Term

National Development Framework for Belize and is accorded a high

priority by GOBZ and wide group of cross-sector stakeholders. Poverty Relevance 7.0 The Project is expected to make a significant contribution to poverty

reduction. Recent statistics report that wage earners accounted for 65%

of RTI deaths in Belize. A total of 2,501 Years of Potential Life were lost in Belize during 2007, due to RTI, which translated into a social loss of $28,812.67 attributed to indirect cost due to productivity loss.

By improving road safety knowledge, attitudes and practices, the

Project will contribute to increasing Belize’s human capital base and

reducing poverty. Efficacy 5.0 As the Project is a pilot, some shortcomings are expected as new

approaches are tested on the Demonstration Corridor. The Project will

have annual reviews and stakeholder consultations, which will afford

the opportunity to adjust project design, as necessary, to improve the

likelihood of achieving the anticipated results.

Cost Efficiency 8.5 The estimated NPV for the Project is $13.2 mn and ERR is 28.8%. Such high returns are typical for road safety investments.

Institutional

Development

Impact

6.0 The Project is expected to make a significant contribution towards

improving the enforcement of traffic laws and the effectiveness of post-

crash response on the Demonstration Corridor. GOBZ’s ability to

manage road safety is expected to be significantly improved. Sustainability 6.0 There is strong political and cross-sector stakeholder support for the

Project. Private sector stakeholders have indicated that they would

likely contribute financially towards public awareness efforts, which is

expected to contribute significantly to financial resilience. The

Demonstration Corridor, on a high volume highway with a high

accident rate, is expected to generate stakeholder demand for the

Project’s wider replication on the national road network. Composite Score 6.25 Highly Satisfactory

SUSTAINABILITY

5.13 The principal risk during implementation is the lack of counterpart funding resources. The

majority of GOBZ’s contributions are in-kind. The main cash contribution is associated with supporting

the public awareness campaigns. It is anticipated that GOBZ will be able to mobilise private sector

resources to aid in supporting this project component.

- 26 -

5.14 The risks during implementation and operation include:

(a) Ineffective enforcement: TA will be provided to support improved enforcement

strategies. Public awareness and the sharing of Demonstration Corridor results, will build

public support.

(b) Poor inter-agency coordination: The Project has a high level of political and stakeholder

support. Project management team participants recognise that potential benefits for the

country are significant and are committed to achieving the project objectives. OSC will

be established to assist with coordination and to clarify accountability which will be

formalised with inter-agency MOU.

(c) Lack of public support: Changing attitudes and road user behaviour will require long-

term commitment. It is expected that private sector financial and in-kind stakeholder resources will be mobilised in support of continued public awareness and education.

(d) Inadequate maintenance of infrastructure, vehicles and equipment: The relatively low

monetary level and high profile of the investment in the Demonstration Corridor

activities is expected to illustrate its effectiveness to all stakeholders and generate

demand for wider replication on the national road network. Project activities will include

the planning and the identification of financing resources for a second phase.

(e) Lack of legislative reform: The Project will work within the existing policy, legislative

and regulatory framework and identify a second phase potential shortcomings and a

reform action plan.

6. TERMS AND CONDITIONS

6.1 It is recommended that CDB lend to GOBZ an amount not exceeding the equivalent of

seven million two hundred and forty-eight thousand United States dollars (USD7,248,000) (the Loan)

consisting of an amount from CDB's SFR not exceeding the equivalent of one million eight hundred and

eighty-six thousand United States dollars (USD1,886,000) (the SFR Portion), and an amount from CDB's

OCR not exceeding the equivalent of five million three hundred and sixty-two thousand United States

dollars (USD5,362,000) (the OCR Portion) to assist GOBZ in financing the establishment of a project

to increase the level of road safety in Belize through the establishment of a Demonstration Corridor

along the Western Highway of Belize, training and other activities, on CDB's standard terms and

conditions and on the following terms and conditions:

(1) Repayment:

SFR Portion: In forty-eight (48) equal or approximately equal and consecutive quarterly

instalments commencing four (4) years after the date of the Loan Agreement.

OCR Portion: In forty-eight (48) equal or approximately equal and consecutive quarterly

instalments commencing four (4) years after the date of the Loan Agreement.

- 27 -

(2) Interest: Payable quarterly:

(a) at the rate of two decimal five percent (2.5%) p.a. on the amount of the

SFR Portion withdrawn and outstanding from time to time; and

(b) at the rate of three decimal eight four percent (3.84%) p.a. (variable) on the

amount of the OCR Portion withdrawn and outstanding from time to time.

(3) Commitment Charge: Payable at the rate of one percent (1%) p.a. on the amount of the

OCR Portion unwithdrawn from time to time. Such charge shall accrue from the sixtieth

(60th) day after the date of the Loan Agreement and shall be payable quarterly.

(4) Disbursement:

(a) The first disbursement of the Loan shall be made by September 30, 2012, and the

Loan shall be fully disbursed by December 31, 2015, or such later dates as CDB

may specify in writing.

(b) Except as CDB may otherwise agree:

(i) the Loan shall be used to finance the components of the Project allocated

for financing by CDB as shown in the Financing Plan for the Project up

to the respective limits specified therein; and

(ii) total disbursements shall not exceed the aggregate eighty-two percent

(82%) of the cost of the Project.

(c) The Loan shall not be used to meet any part of the cost of the Project which

consists of identifiable taxes and duties.

(5) Procurement:

(a) Except as set out in sub-paragraph (b) below, procurement shall be in

accordance with the procedures set out and/or referred to in the Loan

Agreement or such other procedures as CDB may from time to time specify

in writing. The Procurement Plan approved by CDB is set out at Appendix

5.4 of this Report. Any revisions to this Plan shall require CDB’s prior approval

in writing.

(b) Purchase of vehicles costing up to three hundred and eighty-five thousand

United States dollars (USD385,000) comprising one project management vehicle,

two patrol vehicles and two ambulances may be procured by national competitive

bidding without restriction to eligible countries.

(6) Conditions Precedent to First Disbursement:

GOBZ shall:

(a) establish and assign the administration and management of the Project to RSU;

(b) designate Task Leader as required under sub-paragraph (10)(a)(iv);

(c) establish OSC in accordance with sub-paragraph (10)(a)(ii);

- 28 -

(d) engage PM in accordance with sub-paragraph (10)(b)(i); and

(e) provide evidence acceptable to CDB that suitable accommodation and adequate

accounting and clerical support have been provided for RSU.

(7) Conditions Precedent to Disbursement with respect to Road User Education and

Awareness Component

GOBZ shall have engaged the consultants to provide the services set out in the TOR at

Appendix 2.2.

(8) Conditions Precedent to Disbursement with respect to Road Safety Infrastructure

Component

GOBZ shall have engaged:

(a) consultants to provide the engineering services set out in Appendix 2.8; and

(b) PE to provide the services set out in Appendix 5.2.

(9) Conditions Precedent to Disbursement with respect to Road Accident Emergency

Component

GOBZ shall have submitted to CDB, the MOU referred to in sub-paragraph (10)(c).

(10) Other Conditions:

(a) GOBZ shall:

(i) implement the Project through MFED;

(ii) establish OSC which shall be the main decision-making body for the

Project and shall provide managerial oversight, advice, guidance

and direction to the implementation of the Project. OSC shall have the

composition and additional functions set out in Appendix 5.2;

(iii) establish RSU which shall have the composition and functions set out in

Appendix 5.2;

(iv) designate persons with qualifications and experience acceptable to CDB

as Task Leader to coordinate and lead activities in relation to the

Road Safety Infrastructure, Road Safety Enforcement and Road Accident

Emergency Services components, including the activities set out in

Appendix 5.2;

(v) carry out the Project at all times with due diligence and efficiency, with

management personnel whose qualifications and experience are

acceptable to CDB, and in accordance with sound technical,

environmental, financial and managerial standards and practices;

(vi) institute and maintain organisational, administrative, accounting and

auditing arrangements for the Project acceptable to CDB; and

- 29 -

(vii) contribute to the Project an amount of not less than the equivalent of

one million five hundred and ninety-six thousand United States dollars

(USD1,596,000) which shall be expended in a timely manner, on the

components of the Project designated for financing by GOBZ, as shown

in the Financing Plan for the Project, unless CDB shall otherwise specify

in writing.

(b) GOBZ shall in accordance with the procurement procedures applicable to the

Loan, select and engage:

(i) as PM, a competent and experienced person who shall report to the CEO,

MFED, and will be responsible for coordinating and monitoring all

aspects of the implementation of the Project including the duties set out

in Appendix 5.2;

(ii) as PE, a competent and experienced person who shall report to the

Task Leader, MWT, and, with the support of RSU, manage all aspects of

the implementation of the Road Safety Infrastructure Works Component,

including the duties set out in Appendix 5.2; and

(iii) competent and experienced consultants to provide the services set out in

the TORs at Appendices 2.2, 2.3, 2.4, 2.5, 2.6, 2.7 and 2.8.

(c) GOBZ shall conclude with BERT an MOU, in form and substance acceptable to

CDB, with respect to the conditions under which the equipment procured from

the proceeds of the Loan will be used and operated by BERT.

(d) GOBZ shall by July 1, 2013, establish NSRC with composition acceptable to

CDB, to act as a permanent advisory body to GOBZ for improvement of road

safety in Belize.

(e) GOBZ shall keep the road, infrastructure, vehicles and equipment financed under

the Project, or cause the same to be kept, in good repair and condition.

(f) GOBZ shall:

(i) upon the request of CDB conduct a condition survey of the infrastructure

and vehicles financed by the Loan; and

(ii) commencing in the financial year after practical completion of the road

safety infrastructure works, submit its annual road maintenance budget to

CDB by January 31 in each year to facilitate discussion between CDB

and GOBZ on the adequacy of the allocation for road maintenance.

(g) Except as CDB may otherwise agree, GOBZ shall furnish, or cause to be

furnished, to CDB the reports listed in Appendix 5.6 in the forms specified or in such form or forms as CDB may require, not later than the times stated therein

for so doing.

I STITUTIONAL FRAMEWORK Lead agency

Funded in national budget National Road Safety Committee

No

National road safety strategy

Measurable targets

Funded

Yes

Yes

No

DATA Reported road traffic fatalities (2006)

68' (75% males, 25% females) Reported non-fatal road traffic injuries (2006)

652' Costing study available

No

NATIONAL LEGISLATION Speed limits set nationally Yes

Local authorities can set lower limits No

Maximum limit urban roads 40 km/h Enforcement" 101 (!)2 3 5 6 7 8 s WJ

Drink-driving law Yes

BAC limit- general population 0.08 g/dl

BAC limit- young or novice drivers 0.08 g/dl

Random breath testing and/or police checkpoints Yes

Road traffic deaths involving alcohol - Enforcement• 101 ll 2 @-t 56 U' 8 9 00

Motorcycle helmet law Yes

Applies to all riders Yesb

Helmet standards mandated Yes

Helmet wearing rate - Enforcement" 101 ll 2 @ 5 6789 00

Seat-belt law Yes

Applies to all occupants No

Seat-belt wearing rate - Enforcement• IDi ll 2 3 @s 6 18 9 oo

Child restraints law No

Enforcement• n/a

VEHICLE STANDARDS No car manufacturers ROAD SAFETY AUDITS Formal audits required for major new road construction projects Yes Regular audits of existing road infrastructure Yes PROMOTING ALTERNATIVE TRANSPORT National polic ies to promote walking or cycling No

National policies to promote public transportation No

i

APPENDIX 1.1

SUMMARY OF BELIZE ROAD SAFETY STATISTICS

BELIZE

Population: 287 699

Income group: Middle

Gross national income per capita: $3 800

N

' Health data, defined as died within 1year of the crash. Palca data reported 47 duths In 2006.

' Belize Institute of Statlstlcs.

DEATHS BY ROAD USER CATEGORY

Drivers (13%)

SoulU, BttiztlnstituteafSt atistics

' Enforcement score represents consensus basad on professional opinion of respondents ,on a scala of 0 to 10 where o Is not effective and 1DIs hllfdY affectiYa .

' Soma exceptions .

TRENDS IN ROAD TRAFFIC DEATHS

100

w 90 =

80

70 60

..., 50

'E 40

j 30 § 20 z:

10

0

2001 2002 2003 2004 2005 2006 2007

Year

Soun:e, Ministry of Health , Epidemi DIJ Un

POST-CRASH CARE

Formal, publicly available pre-hospital care system

National universal access number

- Data not available. nla Data not required/not applicable .

Yes

Yes

REGISTERED VEHICLES

54 225 total (2007)

Registered vehicle types: data not available

Data cleared by the M inistry of Health.

APPENDIX 1.2

BELIZE EMERGENCY RESPONSE TEAM 1. BERT is a non-profit, non-governmental organisation

which specializes in pre-hospital care in the form of emergency

response and transportation. The organisation was founded by

the Wagner Foundation of Wisconsin, United States of America,

along with the Rotary Club of Belize. Its mission is to serve the

emergency medical needs of the Belizean people through active

volunteerism, education and by providing the material necessities

to assure swift, professional, life-saving measures in medical

emergency situations. BERT offers:

(a) Emergency Response Service 24 hours per day

to road traffic accidents, injuries and medical emergencies;

(b) Ambulance transfer services between medical facilities, airports, homes, etc;

(c) Air ambulance emergency and transfer services, within country and to neighboring

Mexico, Guatemala and Honduras; and

(d) Training to Emergency Medical Technicians (EMT) country-wide.

2. BERT currently provides land ambulatory emergency services only to the Belize and

Cayo Districts. In addition, they also provide air services nationwide. The Belize City based operations

has two teams readily available 75% of the time with a third team on call. Approximately 25% of the

time, there is one team readily available with a second on call within 10 minutes. BERT also has a

semi-volunteer satellite unit in the community of Spanish Lookout. The Spanish Lookout based crews

are always on-call. They do respond to all incidents along the Western Highway when requested. Their

dispatch center is open 24 hours per day, seven days per week and can be accessed directly through their

telephone number. BERT’s aircraft will fly to any location with a usable airstrip (weather allowing) and

generally operates from first light until just at dark. Their flights include a qualified EMT with equipment

and supplies to sustain life during flight. One family member/friend is allowed to accompany the flight.

3. The organisation works in close collaboration with GOBZ, through MOH, which provides

financial support to it through an annual subvention to assist with the operational cost. Education is a

major factor in BERT’s endeavor to deliver quality emergency medical care to Belize and, since 1996, the

organisation has trained over 200 EMTs across the country.

4. BERT employs a full-time staff of 15 persons and 10 additional part-time employees, all of whom

are qualified EMTs. Its operations are overseen by a Board of Directors, which includes members from

civil society, MOH and the Rotary Club of Belize. The organisation has a fleet of seven ambulances, all

of which were donated, in addition to one fixed-wing aircraft. At any given time no more than four of the

ambulances are operational, due to maintenance issues and the aging nature of its fleet. The average age

of the fleet is 15 years and several of the vehicles are well past their useful lives. As a consequence,

annual maintenance expenditures are high, averaging $120,000 p.a., which represents approximately 20%

of its annual operating cost. This has limited BERT’s ability to expand its services. Its annual operating

budget is in the range of $600,000 to $700,000, of which $300,000 is financed by GOBZ.

APPENDIX 1.2

Page 2

5. BERT is a well-established organisation and forms an integral part of Belize’s emergency medical

care services. It provides services to the two major urban centers. However, there is still much to be

done in order to get its operations up to the standard of international good practice. In addition to financing and capacity constraints, the organisation’s ability to effectively carry out its mandate is

constrained by antiquated equipment, which has drained its resources due to high maintenance cost. The

proposal to provide new ambulances will allow BERT the opportunity to retire some of its aging fleet and

thereby help reduce operating and maintenance costs.

APPENDIX 1.3

MACRO SOCIAL CONTEXT

1. Similarly to Belize’s annual growth rate, the population rate has been increasing from 2% during

the 70s, around 2.5% in the 80s and 90s, to 3.7% over the past decade. Growth has not, however, been evenly spread across the country. Corozal, on the border with Mexico, continues to show the slowest rate of growth, with an average of 1.5% per year, while the fastest growing districts were Cayo District, which includes Belmopan, the administrative capital and location of universities, and Belize District, which contains Belize City, the country’s largest city and commercial centre. These were the only districts to

have growth rates above the national average over the past decade. As a result, these two districts now

account for over half the population in the country. Population density is about 15 persons per km2

which makes it one of the least densely populated countries among CDB’s BMCs. Belize’s population is youthful, ethnically diverse and is evenly distributed between males and females.

2. Administratively, Belize is split into six districts, which, from north to south, are Corozal, Orange Walk, Belize, Cayo, Stann Creek and Toledo, and comprises two Municipal Councils and 194 Village Councils. The northernmost district, Corozal, has a common border with Mexico and is

predominantly Spanish-speaking Mestizo1. The main economic activities are the cultivation of sugar cane

and the Corozal Free Zone, on the border with Mexico. Orange Walk, immediately to the south, is based around the town of the same name. Its economy is also dominated by sugar cane, although small scale agriculture prevails in the western areas and potatoes, onions and soya beans are grown for sale. It contains several Mayan cultural sites. Like Corozal, it is predominantly Mestizo and Spanish-speaking.

3. The 2009 Country Poverty Assessment determined that poverty levels are relatively high in the

Cayo District, having increased from 27% of the population living below the poverty line in 2002, to

41%. This situation mirrors that of the country as a whole, which recorded an increase in poverty levels

from 34% in 2002 to 41% in 2009. The statistics showed 16% of the population to be indigent. At 12%

indigent level, Cayo was close to that of the total population. This situation may be attributed largely to

the lingering effects of the global recession, which has precipitated a circumstance of severe economic

and social constraints faced by the country in the last five years. As expected, this would have led to a

decline in the quality of life for a large proportion of the population, particularly those living in rural areas

where poverty levels were higher than the national average.

4. Faced with the continuing challenge to improve poverty reduction effectiveness, GOBZ has

adopted several approaches to enhance living conditions in both urban and rural sections of the country.

These efforts, contained in the National Poverty Elimination Strategy and Action Plan (NPESAP) are

articulated around strategic priorities consistent with the objectives of the country’s national Millennium

Development Goals and have been the main vehicle for poverty reduction interventions in the last few

years. Among others, NPESAP includes strategies such as the provision of key economic

infrastructure to remove obstacles to poverty elimination and foster sustainable economic growth and

development.

1 Mestizo is the term commonly used in Belize to describe the Hispanic population.

APPENDIX 1.4

RECENT MACROECONOMIC PERFORMANCE

OVERVIEW

1. The weak economic environment which prevailed during 2009, as a result of the global economic

crisis, continued to impact Belize in 2010-11, but there has been some recovery. Real GDP grew by an

estimated 1.7% during 2011. Contributing to the growth in 2011, manufacturing activity increased by

2.9% and was led by higher output of sugar and citrus juices. Wholesale and retail activity registered a

significant boost by 4.8% which was largely due to increased trade with Mexico through the Commercial

Free Zone (CFZ). Moderate growth was recorded with respect to hotel and restaurant activity, as well as

transport and communications services, largely reflecting a 3.5% increase in stay-over arrivals. An

overall deficit of $7.2 mn (0.2% of GDP) was recorded on CG operations during 2011, compared with

$43.0 mn (1.5% of GDP) attained during 2010 and $76.3 mn (2.8% of GDP) recorded in 2009. This

performance was largely influenced by a 6.7% ($50.2 mn) increase in revenue resulting from increased

intake from the petroleum industry and a higher yield on import duties. The weak economic environment

has also been manifested in the banking system through slow expansion of domestic credit and excess

liquidity held by commercial banks. A $52.8 mn rise in the net foreign assets held by CBB, indicated an

overall surplus on the external Balance of Payment (BOP). Underlying this, the external current account

deficit narrowed, while Foreign Direct Investment (FDI) continued to fall and commercial banks held

more assets abroad.

Output and Prices

2. Real GDP grew by an estimated 1.7% during 2011. By comparison, output growth amounted

to 2.3% in 2010. Contributing to the growth in 2011, manufacturing activity increased by 2.9% and was

led by higher output of sugar and citrus juices. However, petroleum production, which is reflected within

manufacturing activity and which has contributed significantly to growth in manufacturing since 2006,

fell as production from the larger of two commercial oil fields declined, given that the field is in its

declining cycle and higher production from the other field was not sufficient to compensate. Wholesale

and retail activity registered a significant boost by 4.8%, which was largely due to increased trade with

Mexico through CFZ. Moderate growth was recorded with respect to hotel and restaurant activity (4.7%),

as well as transport and communications services (4.0%), largely reflecting a 3.5% increase in stay-over

arrivals. This increase follows a 2.5% increase registered in 2010, and shows the continued recovery of

the tourism industry following the adverse impact of the global economic crisis. Declines in stay-over

visitors of 5.2 and 2.6% were registered during 2009 and 2008, respectively. However, Belize continued

to feel the repercussions of the global economic crisis, the weak global recovery from the crisis, and

depressed investor confidence stemming from continued risks in the global financial system. Reflecting

this, construction activity has continued to decline (4.1% during of 2011) and was partly related to

continued decline in FDI. Along with the decline in construction activity, agriculture output which fell

by 3.4%, moderated output growth. The decline in agriculture output reflected several influences

including weather-related factors. However, with respect to sugar cane and citrus, higher “sucrose

content” and higher “pound solid per box” contributed to higher sugar and citrus juice production during

the period.

3. The Consumer Price Index rose by 1.6% during the three quarters up to August 2011, compared

with no growth during the corresponding period leading up to August 2010. Inflation in 2011, was driven

largely by higher international commodity prices. Reflecting this, the sub-index for Food, Beverages and

Tobacco rose by 3.6%, while that for “Transportation and Communications” and that for “Rent, Fuel and

Power” rose by 3.8 and 1.2%, respectively.

APPENDIX 1.4 Page 2

Fiscal Operations and Debt 4. An overall deficit of $7.2 mn (0.2% of GDP) was recorded on CG operations during 2011,

compared with $43.0 mn (1.5% of GDP) attained during 2010, and $76.3 mn (2.8% of GDP) recorded in

2009. The primary surplus for 2011, rose by 43.5% to $96.3 mn (3.3% of GDP) from $52.8mn (1.9% of

GDP) in 2010. The performance during 2011, was largely influenced by a 6.7% ($50.2 mn) increase in

revenue. Revenue expanded due largely to higher intake from the petroleum industry and a higher yield

on import duties. Higher international crude oil prices boosted government’s receipts from the production

and export of crude oil by $20.4 mn, to $97.7 mn, including a windfall petroleum tax of $11.2 mn.

Import duties rose by 13.8% ($17.4 mn), reflecting an expansion in imports, as well as the removal of

General Sales Tax (GST) on fuel and its replacement with a fixed tax on fuel imports. Partly reflecting

the removal of GST on fuel, the overall intake on GST declined by 2.6% to $177.5 mn. GST (similar to

value added tax) is the largest single revenue source. Grant receipts during the period under review,

declined by 7.5% to $9.4 mn. Total expenditure during the period under review increased at a much

slower rate – 1.7%, than the increase in revenue. Underlying this, recurrent expenditure rose 5.6%

($37.8 mn) but was largely negated by a 19.1% ($24.1 mn) reduction in capital expenditure and net

lending. The rise in recurrent expenditure reflected increases across all categories, but major influences

included the employment of new staff and the prepayment of electricity services. The latter had been

done in an attempt to provide financing to the electricity distribution company, which was subsequently

purchased by the Government. Further, interest payment grew by 8.1% ($7.8 mn) mostly reflecting an

increase in foreign interest payments. Overall, CG debt stood at $2,427.7 mn (78.9% of GDP) at the

end of 2011.

Financial Sector

5. The broad money supply grew by 5.6% to $2,201.2 mn during 2011, in contrast to a decline of

0.1% for 2010. During 2009, the money supply declined by 6.4%, but grew much quicker (at an average

of 13.9% annually) during the three years prior to 2009. The slower growth in the money supply over the

last three years (2009-11), partly reflected the decline in economic activity in 2009, and the subsequent

slower pace of activity. The weak economic environment which prevailed during 2009, as a result of the

global economic crisis, continued in 2010-11, albeit with some recovery. The rise in broad money supply in

2011, partly reflected the growth in GDP at current prices. The impact of the global economic crisis was

also manifested in the banking system through slow expansion of domestic credit which is dominated by

credit to the private sector. Following a 2.3% decline in 2010, credit to the private sector contracted

marginally (0.3%) in 2011. Credit to the private sector grew by an average of 12.9% annually, during the

three years prior to 2009. In 2009, credit to the private sector grew by 4.1%. Weak demand for credit

resulted in a decline in interest rates and, reflecting this, the weighted-average lending rates across all

commercial banks declined to 13.1% at the end of 2011, compared with 13.8% and 14.1% at the end of

2010 and 2009, respectively.

6. Further, as a consequence of the weak growth in commercial bank credit, excess liquidity within

commercial banks increased and, reflecting this, the excess holding of statutory liquid assets by

commercial banks grew to $221.1 mn at the end of 2011, compared with $160.1 mn and $105.0 mn at the

end of 2010 and 2009, respectively.

7. Net foreign assets within the banking system increased by 19.9% during the 2011, and stood at

$752.5 mn at the end of the year. Reserve assets held by CBB rose from $445.7 mn at the end of 2010, to

$498.5 mn at the end 2011. This level of reserves held by CBB, amounted to more than four months of

imports of goods and services, exceeding the international benchmark of three months.

APPENDIX 1.4 Page 3

External Sector 8. A smaller deficit of $73.7mn (2.5% of GDP) was estimated on the external current account of

BOP, compared with a deficit of $80.1 mn (2.9% of GDP) for 2010. The external current account deficit

amounted to 6.2% of GDP in 2009, and averaged 5.6% of GDP annually during the prior three years. The

narrowing of the current account deficit in 2011, was due in part to smaller income outflows (down

$26.3 mn due mainly to lower profit outflows) which outweighed a $15.6 mn fall in current transfers, along with a small increase ($3.6 mn) in the merchandise trade deficit and a negligible

contraction in the surplus on the services account. Notably, merchandise exports climbed by 26.1% to

$1,206.6 mn partly as a result of higher earnings from the export of crude oil given the rise in the

international price, far outweighing the impact of the decline in export volumes. Growth in cross-border

trade with Mexico, as reflected in increased sales at CFZ, also contributed significantly to the growth in

exports. However, the higher exports were slightly outweighed by a 19.6% rise in imports which

amounted to $1,548.0 mn. Higher acquisition cost for fuel, as well as increased imports into CFZ were

the major factors contributing to the rise in imports. CBB estimated a surplus on the Capital and

Financial Account of $81.8 mn (2.8% of GDP) during 2011, up from $69.1 mn for 2010. Of note, FDI

declined by $5.8 mn to reach $186.4 mn, continuing the downward trend since 2009. In 2008, FDI

amounted to $333.8 mn.

OUTLOOK

9. Given current macroeconomic policies, output growth is projected to continue to average

between 1.5 and 2.5% over the medium-term. However, prospects are uncertain with significant downside risks. A weakened international investment climate and the associated weak consumer confidence, is likely to continue to constrain FDI into Belize, while growth of the tourism industry may continue to be bedevilled by slow and jobless recovery in the United States of America. Further, external gross financing needs will remain high over the medium-term and increased efforts by GOBZ to meet the expected rise in interest costs on external debt in 2012, to make allowance for the commencement of the

amortisation of the “super-bond”1

in 2019, and to repay for assets which were nationalised in 2011, will

constrict other government spending. However, upside risks include possible new oil discoveries and improvement in agricultural output.

1

A USD563.2 mn 22-year bond which was exchanged for pre-existing commercial debt in 2007. The bond is

payable semi-annually beginning in 2019, with interest rates payable semi-annually at 4.25% during 2007-09, 6%

during 2010-11, and 8% for the remaining years of the bond.

APPENDIX 2.1

DETAILS OF THE PROJECT

ROAD SAFETY INFRASTRUCTURE

1. This component includes investments to improve the safety of road infrastructure along a

Demonstration Corridor. The Corridor includes the Western Highway, between its junction with

Central American Boulevard in Belize City to its junction with the Hummingbird Highway in

Belmopan; the Hummingbird Highway, from its junction with the Western Highway to its junction

with Constitution Drive in Belmopan; and Constitution Drive and the Belmopan Ring Road.

Detailed designs are based on MWT’s standard designs for road works, furniture and delineation.

Total estimated base cost

ROAD USER EDUCATION AND AWARENESS

2. This component will support increasing road user awareness and improving behaviours. This

component consists of two elements:

(a) Public Education and Awareness: consultancy services will be engaged to conduct

baseline and post-project KAP Surveys; to develop a comprehensive targeted

communication strategy; and to deliver five comprehensive biannual public awareness

campaigns (Communications Consultant).

(b) Curriculum Development: consultancy services will be engaged to develop road safety

curriculum for Primary and Secondary Schools; produce relevant training materials; and

deliver training to 100 teachers at 10 schools within the Demonstration Corridor

(Curriculum Consultant).

Total estimated base cost

ROAD SAFETY ENFORCEMENT

3. This component will support the improvement of traffic law enforcement on the

Demonstration Corridor and in the municipalities of Belize City and Belmopan through the provision of

two highway patrol vehicles and enforcement equipment to support MWT, Transport Department and PD

to effectively patrol and enforce traffic laws along the Demonstration Corridor. Two patrol vehicles will

be provided with high visibility livery, light bars and sirens. Equipment is expected to include mobile

alcohol screening devices, hand-held radar guns, Global Positioning System devices, computers, traffic

control signs, Light Emitting Diode road flares, and high visibility clothing. Additionally, consultancy

services will be engaged to deliver a training programme in traffic law enforcement and crash scene

investigation (Enforcement Training) to 35 enforcement officers in DOT, PD and the 9 municipalities;

Total estimated base cost

APPENDIX 2.1 Page 2

ROAD ACCIDENT EMERGENCY SERVICES

4. This component includes the provision of two ambulances to support improved emergency

medical services and RTA crash scene response capacity along the Demonstration Corridor.

Total estimated base cost

CAPACITY BUILDING

5. This component supports the strengthening of road safety management capacity of the Ministries

of Health; Works and Transport; PD and the nine Municipalities. The sub-components are:

(a) Road Safety Mentoring: consultancy services will be engaged to mentor, develop and

consolidate the capacity of the various agencies to manage road safety and assist with the

establishment of NRSC. The Consultant will assist GOBZ in the development of the

Medium-term National Road Safety Strategy; and M&E Framework (Road Safety

Consultant).

(b) Road Safety Training: consultancy services will be engaged to deliver a training course

on various aspects of road safety including road safety auditing (Road Safety Training)

to 20 staff responsible for road safety in MFED, MWT, PD and the 9 municipalities.

(c) M&E: this sub-component will support the establishment of a road safety vision with

clear targets and the development of M&E framework. Equipment will be provided to

support MWT’s collection of speed and traffic data. Support will also be provided to

assist in establishing consistent indicators and entrenching better data collection and

sharing mechanisms between agencies. Following the completion of the road safety

infrastructure, consultancy services will be engaged to re-survey and update the safety

rating along the Demonstration Corridor (Road Safety Assessment).

Total estimated base cost

PROJECT MANAGEMENT

6. MFED, RSU and other line staff of participating government ministries and departments are

costed as part of GOBZ’s contribution, along with transportation and communications. PM, RSU and PE,

MWT, will be funded by CDB. This component also makes provision of a vehicle for use by PM, office

equipment and supplies, as well as office space for accommodation of PM within MFED, and RSU and

PE within MWT. Engineering consulting services will be provided to assist MWT in certain design

activities and to certify the road safety infrastructure works, including periodic inspection of the works,

certification of payments and the preparation of a PCR.

Total estimated base cost

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.2

DRAFT TERMS OF REFERENCE

COMMUNICATIONS CONSULTANT

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10), a

Consultant undertook a survey of approximately 600 kilometres of Belize’s main road network and

prepared a prioritised infrastructure investment programme for improving the safety of road infrastructure.

In addition, another consultant undertook a Management Capacity Review of Road Safety within Belize

and prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

1.3 Road Traffic Injuries have significant negative impacts on Belize, at all levels, as they place

significant emotional, psychological and financial burden on families of accident victims, elevate the

number of healthy life-years lost and contribute to the overall mortality and morbidity levels in the

country. Road death and injury are not inevitable. Road trauma is a preventable public health challenge.

Road systems can be developed that reduce the likelihood of a crash occurring and minimise the severity,

if a crash does occur. This can be achieved with road users understanding the risks they impose on

themselves and other road users, safe vehicles and safe roads, together with appropriate enforcement.

2. OBJECTIVE

2.1 The objective of the consultancy is to undertake a baseline and post-project Knowledge, Attitudes

and Practices (KAP) Survey and develop a Communications Strategy to be implemented with the oversight

of the Project Manager (PM) and other stakeholders.

3. DURATION

3.1 The services of the Consultant(s) will be required periodically and intermittently, over a 36-

month period. The level of effort during initial project start-up is expected to be high particularly

during the first KAP survey; preparation of the communications strategy; and the initial biannual

campaign design, with a gradual decrease in services as the biannual campaigns roll out.

4. SCOPE OF WORKS

4.1 The Consultant(s) shall report to, and coordinate activities with, other participating agencies

through PM, Road Safety Unit. The scope of work shall include, but not be limited to, the following

activities:

KAP Surveys:

(a) review the norms, values, beliefs and community practices in relation to road safety;

APPENDIX 2.2

Page 2

(b) compile and review available statistics on road safety, morbidity and mortality in Belize;

(c) define study population, which should include communities and schools along the

Demonstration Corridor and, utilising accepted statistical sampling techniques, identify

required sample size;

(d) prepare survey protocol, data collection tools, pre-testing and translation of

questionnaires, and train enumerators;

(e) based on composition of the survey areas and linguistic, cultural and gender

considerations, develop appropriate questionnaires;

(f) data for this survey should be collected through desk review, questionnaires, face-to-face

interviews and focus group discussions. To minimise any observer-bias, interviewers

should adopt the same approach in explaining the survey, phrasing particular questions,

and recording the responses;

(g) process data and undertake statistical analysis of the results; and

(h) recommend the most effective ways of promoting road safety in Belize.

Communications Strategy:

(a) compile experiences of similar road safety campaigns in Caribbean Development Bank’s

(CDB) Borrowing Member Countries or other relevant sources, including examples of

promotional materials, lessons learnt and results achieved;

(b) develop a sound, evidence-based communication strategy for changing road-user

behaviour;

(c) include national and Demonstration Corridor-specific communications focused on

improving awareness;

(d) utilise high visibility, high impact and cost-effective measures for message delivery

including, but not limited to, print and broadcast media; electronic social media; and less

informal mechanisms, such as school and community-based activities and events;

(e) special attention should be given to mechanisms for targeting and changing the

behaviours of males aged 15-59;

(f) design mechanisms to measure the effectiveness of, and for obtaining stakeholder

feedback on, biannual campaigns; and

(g) define a role for private sector participation in biannual awareness campaigns.

Biannual Awareness Campaign:

(a) develop, design, produce and procure all relevant media material for the proposed

campaign for both national efforts and specific activities with communities and schools

within the Demonstration Corridor; and

APPENDIX 2.2

Page 3

(b) based on stakeholder feedback and effectiveness of preceding campaign(s), prepare

following biannual campaigns. 5. INPUTS

5.1 The Consultant(s) will provide the equipment and software required to carry out the assignment

and be responsible for obtaining all additional information for the execution of the services necessary for

the Project.

6. REPORTING REQUIREMENTS

6.1 The Consultant(s) will submit the following reports:

(a) Inception Report describing the approach proposed to be taken to deliver the scope of

works outlined, within two weeks of the start of the consultancy.

(b) Baseline KAP Survey Report presenting the data and results of the survey and proposed

recommendations for incorporation into the Communication’s Strategy.

(c) Communication’s Strategy Report outlining proposed approach options, measuring tools

and budgetary requirements.

(d) Biannual Campaign Report presenting results and feedback from previous campaigns,

proposed activities and corresponding budget.

(e) Post-project KAP Survey Report, presenting the data and results of the survey and

proposed recommendations for incorporation into the Project Completion Report.

6.2 GOBZ and CDB will provide comments on reports within two weeks of receipt of the report and

the consultants will adjust the ongoing work according to the comments received. Reports should be

submitted in three hard copies and electronically.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.3

DRAFT TERMS OF REFERENCE

CURRICULUM CONSULTANT

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10), a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

1.3 The challenges facing road safety in Belize require a multi-faceted response which seeks to improve road conditions, enact an appropriate legislative framework, improve the administration and monitoring of road use, as well as enhance the capacity of all road users to utilise this resource optimally and safely. However, a particular focus must be placed on children and youth as statistics indicate that on average, 20% of all people killed in traffic accidents in developing countries are under age 15. This is

twice as high as in the developed world1. Since human error plays a significant role in road accidents,

teaching safety skills to children can provide lifelong benefits to society for two reasons:

(a) children become adults who use the road for multiple reasons, including the operation of

vehicles; and

(b) children transfer knowledge learnt in school to the home, often subliminally influencing

the adults around them.

Road safety education can therefore provide the necessary structure for the acquisition of safety

knowledge and skills and, if provided from an early age, will have a positive impact on the society in the

long-term.

1.4 Roads in developing countries tend, very often, to be more unsafe than roads in industrial

countries, so traffic safety problems faced by children in these countries will often be greater than those

faced in the developed world. Absence of traffic education can therefore leave them exposed to significant

risks. However, pervasive and effective traffic education is more likely if it is within the formal

curricula, is culturally relevant and delivered by competent teachers utilising appropriate materials and

pedagogy.

1.5 The inclusion of traffic education in the curriculum ensures that it is part of the instructional

programme of schools and complements other curricula goals associated with preparing children for a

productive life within the society. However, since the traffic circumstances and issues faced by children

in the developing world are sometimes radically different from those faced by their counterparts in

1 Road Safety Education of Children, Asian Development Bank. http://www.adb.org.

APPENDIX 2.3

Page 2

developed countries, it is inappropriate and very often ineffective to simply transfer materials created for

use in the developed world to educate these children about road safety. The development of culturally

relevant materials is therefore absolutely necessary, if road safety programmes are to have the desired

effect. Such materials may be based on a number of generic principles which do not change from

country-to-country, but must reflect the special circumstances which affect the particular country, if they

are to be effective. Further, an incremental approach is required. Such programmes are ineffective when

they rely on one-off campaigns. Long-term behaviour change must be based on infusion, which is

focused on maximisation of the repetition which leads to automaticity. In addition, educational

programmes must not only embrace the theoretical, but must provide adequate opportunity for practical

application of the principles introduced. Authentic, real life situations, under adult supervision, must

therefore be incorporated on a regular basis as well.

1.6 Developers of road safety programmes should also not assume that teachers will have the

knowledge and skills, and will automatically be able to integrate road safety education into their

programmes. It is therefore necessary for modules to be incorporated into initial teacher training, as well

as in continuing professional development programmes, so that all teachers can be equipped with

standardised knowledge and skills for classroom delivery. The provision of teacher support materials will

also facilitate the process of incorporation, since teachers are less likely to omit road safety principles if

they are provided with the necessary references which spell out what is to be taught.

1.7 As part of a wider public education programme to improve road safety in Belize, the Ministry of

Education, Youth and Sports (MOEYS) is seeking technical assistance to strengthen traffic education

within the education sector. This is consistent with the newly ratified Education Sector Strategy which

articulates as a key priority, the enhancement of relevance of the curricula for improving student

outcomes. Traffic education in Belize is given minimal attention in the curricula and is limited to generic

safety concepts in subjects such as Social Studies, where the focus is on traffic rules and laws. In

addition, teachers need upgrading of skills and appropriate pedagogical resources are required to support

the acquisition of perspectives, knowledge, competencies and attitudes in children as responsible and safe

users of roads in Belize.

2. OBJECTIVE

2.1 The objective of this consultancy is to assist MOEYS in strengthening the focus of road safety in

the curricula in early childhood education, basic education and teacher education and developing

appropriate pedagogical resources to support effective delivery of the programme in schools.

3. METHODOLOGY

3.1 The Consultant will perform all investigative work and analyses to realise the objective stated

above. They will use participatory and consultative methodologies in working closely with MOEYS and

other critical stakeholders in the sector. These will include, but are not limited to, the University of

Belize, the Traffic Department, public and private sector stakeholders, principals, teachers, students,

parents and community leaders.

3.2 The Consultant will work closely with the relevant Technical Working Group (TWG), established

under the Belize Education Sector Reform Project. The relevant technical officer shall be assigned by

MOEYS to act as counterpart and coordinate the work of the Consultant. In consultation with MOEYS

and the TWG, the Consultant will organise a consultation with critical stakeholders at Draft Report stage

to share and discuss the draft curricula, training programmes, materials and major recommendations

emanating from the consultancy.

APPENDIX 2.3

Page 3 3.3 The Consultant will also examine options for development and delivery of traffic education in

other jurisdictions to be guided by best practice and lessons learned.

4. SCOPE OF SERVICE

4.1 The consultancy will involve desk and fieldwork and consultations across the sector, as well as

across other related sectors. The Consultant will be expected to undertake the following activities:

(a) review the existing curricula for Early Childhood, primary, and secondary education and

recommend revisions on traffic education to the curricula for each grade as appropriate;

(b) review the teacher education programmes and recommend revisions relative to the

professional development of teachers for effective traffic education instruction, as

appropriate;

(c) evaluate the quality of pedagogical resources available and utilised in the classroom,

including teaching guides and teacher manuals;

(d) identify and/or develop culturally relevant materials to support the implementation of the

curriculum on traffic education;

(e) prepare teachers guides and training materials to support effective instructional delivery

of traffic education;

(f) conduct a consultation with representatives of key stakeholders to discuss and obtain

feedback on the recommendations proposed; and

(g) conduct five-day training workshops, number, type and schedule to be agreed with

MOEYS, to train teachers nationally in effective traffic education instruction.

5. TIMING AND QUALIFICATIONS

5.1 It is anticipated that the consultancy will require a maximum of 50 person-days over a period of

one year. The consultancy team should have post-graduate expertise in, but not be limited to, the

following areas:

(a) curriculum and instruction with emphasis on curriculum development, design and

implementation; teacher education and Social Studies or a related discipline. Expertise in

Road Safety would be an asset; and

(b) demonstrated capacity for strategic thinking as well as excellent communication and

analytical skills. Knowledge of the education sector in Belize, as well as those in the

Region, would also be an asset.

6. REPORTING

6.1 The Consultant will submit the following reports:

(a) an Inception Report within seven days of commencement of the assignment;

APPENDIX 2.3

Page 4

(b) an Interim Report on the review of the curriculum on traffic education, teacher education

programmes, teaching approaches and effective approaches and programmes within

eight weeks of commencement of the assignment;

(c) a Draft Report, including the following key outputs, within five months of commencement

of the assignment:

(i) proposed revisions to the curriculum on traffic education;

(ii) proposed revisions to the teacher education programmes on traffic education;

(iii) draft teachers’ guides/manuals and training materials to support instruction;

(iv) proposed recommendations of culturally relevant materials to be developed; and

(v) draft training programme for teachers and schedule for delivery of training;

(d) report on training of teachers within two weeks of completion of the training; and

(e) Final Report and finalised outputs within four weeks of receiving feedback from

stakeholder consultation, MOEYS and the Caribbean Development Bank (CDB).

6.2 GOBZ and CDB will provide comments on reports within two weeks of receipt of the report and

the consultants will adjust the ongoing work according to the comments received. Reports should be

submitted in three hard copies and electronically.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.4

DRAFT TERMS OF REFERENCE

ENFORCEMENT TRAINING

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10), a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize now intends to undertake a

series of investments to improve road safety along a Demonstration Corridor. The Corridor includes the

Western Highway, between its junction with Central American Boulevard in Belize City to its junction

with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction with the

Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and the

Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

2. OBJECTIVE

2.1 The objective of the assignment is to improve the traffic law enforcement capacity of staff of the

Ministry of Works and Transport, Department of Transport; Police Department; and the Traffic

Departments of Belize’s nine municipalities. This will be delivered through a series of Enforcement

Training Courses.

3. DURATION

3.1 It is expected that a series of five courses will be delivered to approximately 35 participants

intermittently over a one-year period.

4. SCOPE OF WORKS

4.1 The Consultant(s) shall report to, and coordinate activities with, other participating agencies

through the Project Manager, Road Safety Unit. The enforcement training courses should include the

following elements and considerations:

(a) defensive driving, personal security and general patrol duties;

(b) traffic management and general traffic law enforcement;

(c) speed enforcement in urban and highway environments;

(d) impaired driving enforcement;

(e) dangerous driving enforcement;

(f) overloading and mechanical failure enforcement; and

(g) road crash scene management, investigation, reconstruction and analysis.

Course work should include case study exercises and field trips with participants, to facilitate their

practical application of concepts learnt during the formal classroom sessions.

APPENDIX 2.4

Page 2

5. INPUTS

5.1 The services of the Consultant(s) will be required periodically over a one-year period to

undertake the various activities outlined at Section 4 of the Terms of Reference (TOR). The

Consultant(s) will provide the education materials, presentations and supplies to carry out the assignment.

6. REPORTING REQUIREMENTS

6.1 The Consultant(s) will consolidate the course material and presentations associated with the

training and prepare a training manual. The manual should be submitted in 12 bound and one electronic

copy within one month following the completion of the final training course.

7. QUALIFICATIONS AND EXPERIENCE

7.1 The Consultant(s) should have the necessary skills including, but not limited to, high-level

expertise and experience in policing, traffic-law enforcement and training.

8. COMMENTS BY THE CONSULTANT(S)

8.1 The Consultant(s) are invited to make any comments on, and suggestions for, improvements to

the TOR. The financial implications, if any, of the said suggestions/recommendations should be clearly

indicated in the Financial Proposal.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.5

DRAFT TERMS OF REFERENCE

ROAD SAFETY CONSULTANCY SERVICES

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10) a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

2. OBJECTIVE

2.1 The objective of the assignment is to rapidly develop and consolidate the capacity of the

Road Safety Unit (RSU) and other participating agencies to effectively manage road safety.

3. DURATION

3.1 It is expected that the consultancy will be completed, periodically and intermittently, over

a 6-month period. The level of effort during initial project start is expected to be high, with a gradual

decrease in services as participating agencies gain increased competency.

4. SCOPE OF WORKS

4.1 The Consultant shall report to, and coordinate activities with, other participating agencies through

the Project Manager (PM), RSU. The scope of work shall include, but not be limited to, the following

activities:

(a) assist the Operational Steering Committee (OSC) and provide inputs to inform and guide

their decision-making;

(b) assist OSC and PM, RSU, to establish a road safety vision for Belize;

(c) assist OSC and PM with the formalisation of the National Road Safety Committee;

(d) assist PM and relevant stakeholders to analyse road traffic accidents data and make

practical recommendations to ensure dataset definition commonality in the Ministry of

Health’s Health Management Information System, Police Department’s (PD) Crime

Information Management System road traffic accidents database suite, and Belize City’s

and Belmopan’s traffic enforcement database. Assist stakeholders to establish

comparable, consistent, and timely generation of database reports to inform effective

APPENDIX 2.5

Page 2

monitoring and evaluation (M&E) and ensure a results-based focus to a national road

safety strategy;

(e) assist in the establishment of collision reduction targets;

(f) assist PM in calculating the cost of collisions on the Demonstration Corridor;

(g) review the report on Legislative and Regulatory Analysis of Traffic Management in

Belize and assist PM to identify and legislative and regulatory changes to improve

enforcement effectiveness;

(h) review vehicle registration and driver licensing practices and testing standards and

materials of the Department of Transport (DOT) and Belize City and Belmopan

Municipalities. Make recommendations on a uniform approach for improving the quality

of vehicles and drivers entering the system;

(i) review the new and used vehicle-importing industry and associated regulations, and make

recommendations on vehicle age limits and quality standards;

(j) assist the Ministry of Works and Transport (MWT), DOT, and Ministry of Security, PD,

in the development of biannual enforcement strategies;

(k) review and provide comments and recommendations on the Road User Education and

Awareness Communication Strategy and biannual campaigns;

(l) assist PM in stakeholder consultations to mobilise funding resources. Make

recommendations for the establishment of sustainable road safety funding mechanisms;

(m) assist PM in identifying capacity constraints within participating agencies. Make

recommendations for institutional strengthening activities;

(n) assist PM in developing M&E framework, including the development of appropriate

performance indicators;

(o) participate in project launch and annual project reviews. Assist in the development and

implementation of Annual Action Plans based on the deliberations and outcomes of these

proceedings;

(p) assist PM in planning transitioning of Road Safety Unit from the Ministry of Finance and

Economic Development to MWT, DOT;

(q) assist PM in integrating cross-sector needs and developing a results-focused, medium

term national road safety strategy, identifying goals and objectives along with specific

activities, initiatives, capacity building measures required and a financing plan.

5. INPUTS

5.1 The services of the Consultant will be required over a 36-month period to undertake the

various activities outlined at Section 4 of the Terms of Reference. The Consultant will provide the

equipment and software required to carry out the assignment and be responsible for obtaining all

additional information for the execution of the services necessary for the Project.

APPENDIX 2.5 Page 3

6. REPORTING REQUIREMENTS

6.1 The Consultant will be required to submit the following number of reports to the

Government of Belize (GOBZ) and the Caribbean Development Bank (CDB), respectively,

within the time periods indicated:

(a) Inception Report: within two weeks of the completion of the Project Launch,

submit an Inception Report describing the approaches proposed to be taken to

prepare and deliver the scope of works outlined and a biannual work plan.

(b) Monthly Progress Reports: preparation of monthly reports on the progress of the

consultancy.

(c) Annual Project Review: preparation of a report summarising proceedings and the

proposed action plan for the coming year, within two weeks of the Annual

Review consultations.

(d) Periodic Ad Hoc Reports: preparation of Ad Hoc Reports, as and when

required, to provide guidance to RSU and PM on particular issues; and

(e) Project Completion Report: preparation of a Completion Report within three months

after the completion of the services.

6.2 GOBZ and CDB will provide comments on reports within two weeks of receipt of the report

and the consultants will adjust the ongoing work according to the comments received. Reports

should be submitted in three hard copies and electronically.

7. QUALIFICATIONS AND EXPERIENCE

7.1 The Consultant should have the necessary skills, including but not limited to, high-level

expertise and experience in road safety management, advocacy, and strategy development.

Experience with the design, implementation and management of results-focused national road

safety strategies, at senior agency and ministerial levels, is required. The Consultant should have

significant experience in skills and knowledge transfer and mentoring.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.6

DRAFT TERMS OF REFERENCE

ROAD SAFETY TRAINING

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10) a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

2. OBJECTIVE

2.1 The objective of the assignment is establishment of a road safety audit system complete with

procedures and guidelines, and the delivery of a Road Safety Training Course for GOBZ staff and other

stakeholders.

3. DURATION

3.1 It is expected that the consultancy will be delivered over a one-month period.

4. SCOPE OF WORKS

4.1 The Consultant(s) shall report to, and coordinate training course delivery activities with the

Project Manager, Road Safety Unit. The specific activities required are:

(a) develop a road safety audit system and manual for Belize based on

adaptation/modification of international best practices and similar safety audit guidelines

from other countries;

(b) carry out demonstration Safety Audits on selected roads, to improve safety of the audited

roads and to create examples of safety audit reports;

(c) assist local safety auditors to develop and implement the system; and

(d) deliver a Road Safety Training Course, which should include the following elements and

considerations:

(i) road user behaviour;

(ii) vulnerable road users;

(iii) engineering aspects of roadside safety;

APPENDIX 2.6 Page 2

(iv) black spot analysis and solutions;

(v) road safety auditing; and

(vi) case study exercises.

Course work should include a field trip with participants to facilitate their practical application of

concepts learnt during the formal classroom sessions.

4.2 The course should be based on internationally recognised standards for roadside safety design and

the conduct of audits and black spot analysis.

5. INPUTS

5.1 The services of the Consultant(s) will be required over a one-month period to undertake the

various activities outlined at Section 4 of the Terms of Reference. The Consultant(s) will provide the

education materials, presentations and supplies to carry out the assignment.

6. REPORTING REQUIREMENTS

6.1 The Consultant(s) will submit the course material and presentations associated with the training.

7. QUALIFICATIONS AND EXPERIENCE

7.1 The Consultant(s) should have the necessary skills including, but not limited to, high-level

expertise and experience in road safety engineering, auditing, and black spot analysis and training will be

required to undertake the assignment.

8. COMMENTS BY THE CONSULTANTS

8.1 The Consultant(s) are invited to make any comments on, and suggestions for, improvements to

TOR. The financial implications, if any, of the said suggestions/recommendations should be clearly

indicated in the Financial Proposal.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.7

DRAFT TERMS OF REFERENCE

ROAD SAFETY ASSESSMENT

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10) a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to overcome revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; enforcement and emergency services

support.

2. OBJECTIVE

2.1 The objective of the consultancy is to update the previous International Road Assessment

Programme (iRAP) 2011 survey of the Demonstration Corridor, using established iRAP protocols to

determine post-implementation star ratings.

3. DURATION

3.1 It is expected that the consultancy will be completed over a one-month period.

4. SCOPE OF WORKS

4.1 The Consultant(s) shall report to and coordinate activities with the Ministry of Works and

Transport through the Project Manager, Road Safety Unit. The study will include the following tasks:

(a) Meetings with key agency staff to determine the availability of key data needed for the

iRAP assessment.

(b) Updating of background data: this data should include traffic and speed data,

countermeasure costs and crash data.

(c) Mobilisation of iRAP’s RAPID survey equipment: the survey equipment will be fitted to

a GOBZ-supplied vehicle, and technology to be used for the Project will be provided by

an existing iRAP accredited company or equal. The characteristics of this equipment will

be determined based upon availability, cost and effectiveness for the field work.

(d) Survey inspection: the Demonstration Corridor will be surveyed according to iRAP

current survey inspection protocols.

(e) Rating of data: the Project will involve the assessment of approximately 40 attributes of

the road environment that influence road safety outcomes using criteria presented in the

APPENDIX 2.7 Page 2

iRAP inspection manual. iRAP will carry out this work remotely by a highly

experienced data rating team.

(f) Analysis of data and updating of star ratings: iRAP will conduct an analysis of data. As

part of this analysis, iRAP will thoroughly review the rating data, perform post-

processing to prepare the data for analysis, load the data into iRAP analysis software,

develop calibration factors for Belize conditions and conduct the required analyses.

(g) Preparation of draft and final reports.

5. INPUTS

5.1 The services of the Consultant(s) will be required over a one-month period to undertake the

various activities outlined at Section 4 of the Terms of Reference (TOR). GOBZ will endeavour to make

available to the Consultant(s), relevant reports and statistics for Belize. GOBZ will also assist the

Consultant(s) in identifying the key stakeholders, scheduling meetings and obtaining data from

Government Departments and other sources that might be necessary for the execution of the work required

under the TOR. The Consultant(s) will provide the equipment and software required to carry out the

assignment and be responsible for obtaining all additional information, the execution of the study and

other services necessary for the Project.

6. REPORTING REQUIREMENTS

6.1 The Consultant(s) will submit the following reports:

(a) Draft Final Report: to be submitted 60 days after completion of the survey.

(b) Final Report: within 14-days of receipt of comments from GOBZ/Caribbean

Development Bank (CDB) on the Draft Final Report.

6.2 GOBZ/CDB will endeavour to provide comments within 14 days of receipt of each report.

Electronic and three bound copies of each report are required, two copies to GOBZ and one copy to CDB.

7. QUALIFICATIONS AND EXPERIENCE

7.1 The consultancy team should have the necessary skills including, but not limited to, high-level

expertise and experience in iRAP road safety assessments required to undertake the study.

8. COMMENTS BY THE CONSULTANTS

8.1 The Consultant(s) are invited to make any comments on and suggestions for improvements to

TOR. The financial implications, if any, of the said suggestions/recommendations should be clearly

indicated in the Financial Proposal.

APPENDIX 2.7 Page 3

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 2.8

DRAFT TERMS OF REFERENCE

CONSULTANCY SERVICES FOR THE DESIGN AND CERTIFICATION

OF ROAD SAFETY INFRASTRUCTURE WORKS

1. BACKGROUND

1.1 In 2011, as part of the Fourth Road Project (Santa Elena/San Ignacio Bypass) (Paper BD 98/10) a

Consultant undertook a survey of approximately 600 km of Belize’s main road network and prepared a

prioritised infrastructure investment programme for improving the safety of road infrastructure. In

addition, another consultant undertook a Management Capacity Review of Road Safety within Belize and

prepared an investment strategy to address revealed capacity weaknesses.

1.2 Based on the outcomes of that assignment, the Government of Belize (GOBZ) now intends to

undertake a series of investments to improve road safety along a Demonstration Corridor. The Corridor

includes the Western Highway, between its junction with Central American Boulevard in Belize City to

its junction with the Hummingbird Highway in Belmopan; the Hummingbird Highway, from its junction

with the Western Highway to its junction with Constitution Drive in Belmopan; Constitution Drive; and

the Belmopan Ring Road. Investments will include: road safety infrastructure; capacity building and

implementation support; road user education and awareness; and enforcement and emergency services

support.

1.3 GOBZ is also proposing the construction of a new roundabout located at the junction of the

Western and Hummingbird Highways. The design for this structure is to be based on the Ministry of

Works and Transport’s (MWT) standard roundabout design. However, this location’s poor geometric

alignment and its propensity to periodic flooding must be considered in developing a solution for the

junction.

2. OBJECTIVE

2.1 The objective of the assignment is to provide independent inspection and certification of the road

safety infrastructure works being funded under the Loan. In addition, design services are required for a

new roundabout to be located at the junction of the Western and Hummingbird Highways.

3. DURATION

3.1 It is expected that the consultancy will be completed, intermittently, over an 18-month period.

4. SCOPE OF WORKS

4.1 The Consultant(s) shall report to the Project Engineer, MWT. The scope of work shall include,

but not be limited to, the following activities:

Certification Services:

(a) periodic technical inspection of the works;

(b) review contractors’ Environmental Management Plans;

(c) environmental monitoring of contracts;

APPENDIX 2.8 Page 2

(d) review and approve traffic control plans prepared by the contractors and ensure

compliance with all applicable road safety standards, guidelines and regulations, before

commencement of road works;

(e) review and revise designs, as appropriate, to deal with unforeseen circumstances;

(f) certify work done by the contractor for purposes of payment;

(g) prepare monthly reports on the progress of the works indicating any engineering

difficulties affecting their efficient and timely execution, commencing one month after

the start date defined in the construction contract;

(h) consult and advise MWT during construction;

(i) issue certificates of practical completion to contractors on completion of construction

contracts; and

(j) prepare a Completion Report on the Project, including as-built drawings where

appropriate.

Design Services:

(a) collect and analyse existing topographic, land use, hydrological, meteorological,

geological, aerial imagery, and hazard event data and studies to characterise the current

site conditions at the junction of the Western and Hummingbird Highways. Site

characterisation should include the identification of critical infrastructure and key land

use in the vicinity of the site;

(b) consider and factor available historic precipitation data, climate model forecasts,

catchment surface area, slope, soil conditions, and geometry of the Belize River adjacent

to the site, develop and/or apply relevant hydraulic models to characterise day-to-day,

storm event river channel flow, and predicted water levels (1-in-10, 50, 100 and 150-year

events) in developing hydraulic design options for flood mitigation in the vicinity of the

site;

(c) based on hydraulic modelling, and in consultation with MWT, recommend optimal

design flood;

(d) develop and present design options, identifying preferred flood mitigation, and geometric

design solutions;

(e) prepare cost and quantity estimates: where necessary, land ownership and land values

should be given due consideration;

(f) prepare detailed designs for these works; and

(g) provide recommendations for the geometry for the future replacement of the

Roaring Creek Bridge, just to the west of the junction.

APPENDIX 2.8

Page 3

5. INPUTS

5.1 The services of the Consultant(s) will be required over an 18-month period to undertake the

various activities outlined at Section 4 of the Terms of Reference. The Consultant(s) will provide the

equipment and software required to carry out the assignment and be responsible for obtaining all additional

information for the execution of the services necessary for the Project.

6. REPORTING REQUIREMENTS

6.1 The Consultant(s) will submit the following reports:

(a) completed payment certificates for works executed by contractors to support requests for

disbursement/reimbursement from the Caribbean Development Bank (CDB);

(b) three copies each of monthly reports on the progress of the works;

(c) certificates of practical completion to be issued to each contractor upon completion of

each contract;

(d) electronic and four hard copies each of a Project Completion Report on each construction

contract within four weeks of issuing the certificates of completion;

(e) detailed design report; and

(f) as-built drawings where appropriate, on completion of the contracts.

6.2 GOBZ and CDB will provide comments on reports within two weeks of receipt of the report and

the consultants will adjust the ongoing work according to the comments received. Reports should be

submitted in three hard copies and electronically.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 3.1

PROJECT COST, PHASING AND FINANCING PLAN

(BZ $'000)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

AP

PE

ND

IX 4

.1

DEMONSTRATION CORRIDOR 2012 STAR RATINGS

Star Rating Vehicle Occupants Motorcyclists Bicyclists Pedestrians

Length (km) % Length (km) % Length (km) % Length (km) %

0 0 0 0 0 0 1 1

4 5 4 5 4 5 1 1

0 0 0 0 0 0 72 94

44 57 0 0 44 57 0 0

29 38 73 95 29 38 0 0

N/A 0 0 0 0 0 0 3 4

TOTAL 77 100% 77 100% 77 100% 77 100%

Note: Star Rating for Vehicle Occupants illustrated

APPENDIX 5.2

DRAFT TERMS OF REFERENCE

PROJECT MANAGER

1. The Project Manager (PM) will be located in the Road Safety Unit (RSU) and will report to the

Chief Executive Officer, Ministry of Finance and Economic Development. He/she will be responsible for

coordinating and monitoring all aspects of the implementation of the Project. PM shall be assigned

exclusively to the Project and will be supported by an administrative staff within the RSU. The PM’s

duties will include, but not be limited to:

(a) maintaining records and carrying out the day-to-day coordination and supervision of the

Project, including the preparation of regular progress reports;

(b) monitoring and controlling of project cost, preparing/reviewing withdrawal applications,

supervising preparation of financial reporting and submit to Operational Steering

Committee (OSC) and the Caribbean Development Bank (CDB). Preparing and

submitting to CDB, a Quarterly Report on the Investment Cost of the Project, in the form

specified by CDB, within two weeks after the end of each calendar quarter, commencing

with the quarter following the commencement of the assignment;

(c) compiling baseline data for all performance targets and indicators as early as possible,

but no later than one quarter after mobilisation, and develop and implement an

overall monitoring plan for the Project;

(d) organising indicator data from project participants, measure and report to OSC and CDB

progress of achieving the performance targets at the annual project reviews and

completion stages;

(e) developing a consolidated schedule, showing the critical path of the overall project

implementation;

(f) managing the selection and engagement of consultancy services and supervising these

consultancies;

(g) evaluating bids and recommending the awards for the consultants, goods and construction

contracts;

(h) keeping OSC and CDB timely informed of implementation problems that could

jeopardise the project objectives and recommending how those objectives can be

safeguarded;

(i) liaising with CDB on all technical and administrative aspects of the Project;

(j) submiting to CDB, within two weeks after the end of each month, the reports prepared by

the Consultant(s) and the Task Leaders;

(k) developing key partnerships with stakeholders and liaising with them to inform about the

Project and its implementation status;

(l) organising meetings in collaboration with stakeholders at strategic times to discuss all

aspects of project implementation, including any current and/or potential obstacles to

timely implementation;

APPENDIX 5.2 Page 2

(m) attending and preparing minutes of PSC meetings;

(n) preparing supporting information for the formalisation of the National Road Safety

Committee;

(o) assisting in the preparation of inter-agency Memorandum of Understanding to formalise

roles and responsibilities;

(p) establishing overall targets for collision reduction along the Demonstration Corridor;

(q) assisting, with the support of the Road Safety Consultant stakeholders to integrate

databases and collision reporting statistics;

(r) identifying legislative and regulatory requirements to support improved road safety;

(s) identifying and mobilising private sector funding resources to support the public

education and awareness campaigns;

(t) developing, with the support of the Road Safety Consultant, medium-term national road

safety strategy identifying goals and objectives, along with specific activities, initiatives,

capacity building measures required and a financing plan; and

(u) preparing and submitting to CDB, a Project Completion Report within three months after

completion of the works and services.

2. Prospective candidates should have a minimum of the following qualifications: a Masters Degree

or equivalent in Public Administration, Project Management or other related field with a minimum of

eight years’ experience in the management and implementation of multi-sectoral projects. Proposed

personnel with strong communication, supervisory and monitoring skills and good relations with local

stakeholders are desirable.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 5.2 Page 3

DRAFT TERMS OF REFERENCE

PROJECT ENGINEER

3. The Project Engineer (PE) will be located in the Ministry of Works and Transport (MWT),

Department of Public Works (DPW) and will report to the Task Leader, Roads Safety Infrastructure,

DPW. He/she will be responsible for coordinating and monitoring all aspects of the implementation of

the road safety infrastructure. PE shall be assigned exclusively to the Project and will be supported by

administrative staff within DPW. PE’s duties will include, but not be limited to:

(a) supervision of the design and certification consultants, including review of the monthly

reports prepared by the consultants and transmittal to the Project Manager, Road Safety

Unit;

(b) management and administration of the construction contracts; and

(c) integration of road safety investments into annual maintenance programmes.

4. Prospective candidates must be civil engineers, with a minimum of a Bachelors Degree in civil

engineering and five years’ of suitable experience in engineering design and supervision, including road

works or project implementation.

BUDGET

(USD)

This information is withheld in accordance with one or more of the exceptions to

disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 5.2 Page 4

DRAFT TERMS OF REFERENCE

TASK LEADER

1. The Task Leader (TL) will be assigned from line ministries to coordinate and lead activities

within the following components:

(a) Road Safety Infrastructure;

(b) Road User Education and Awareness;

(c) Road Safety Enforcement; and

(d) Road Accident Emergency Services.

2. TL will be responsible for coordinating, monitoring and reporting on all aspects of the respective

component they are assigned. TL shall be supported by an administrative staff and technical within their

respective line ministries. TL’s duties will include, but not be limited to:

(a) maintaining records and carrying out the day-to-day coordination and supervision of the

assigned Project Component, including the preparation of regular progress reports for

transmission to Project Manager (PM);

(b) monitoring and controlling of component costs. Preparing and submitting to PM,

Road Safety Unit (RSU), a Quarterly Report on the Investment Cost of the Project, in the

form specified by the Caribbean Development Bank, within two weeks after the end of each calendar quarter, commencing with the quarter following the commencement of the

assignment;

(c) compiling component baseline data for all performance targets and indicators;

(d) developing a schedule for component activities;

(e) participating in the procurement of consultancy services, goods and/or works;

(f) keeping PM, RSU, timely informed of implementation problems that could jeopardise the

project objectives and recommending how those objectives can be safeguarded;

(g) preparing supporting information for the formalisation of the National Road Safety

Committee;

(h) assisting in the preparation of inter-agency Memorandum of Understanding, to formalise

roles and responsibilities;

(i) assisting with the development of the medium-term national road safety strategy; and

(j) preparing and submitting to PM, RSU, a Completion Report.

APPENDIX 5.2 Page 5

DRAFT TERMS OF REFERENCE OPERATIONAL STEERING COMMITTEE

1. The implementation of this Project will influence, and be influenced by, the activities of various

stakeholders including government departments and agencies, Non-Governmental Organisations and

development partners. The Operational Steering Committee (OSC) will be the main decision-making

body for the Project. In addition, OSC will be established to provide managerial oversight, advice,

guidance and direction on project implementation. OSC will comprise:

(a) Chief Executive Officer, Ministry of Finance and Economic Development - Chairperson

(or designate).

(b) Project Manager

(c) Representative from the Ministry of Works and Transport.

(d) Representative from the Ministry of Health.

(e) Representative from the Ministry of Education.

(f) Representative from the Police Department.

2. OSC will be responsible for facilitating the seamless implementation of the Project by promoting

information-sharing and inter-agency cooperation among government departments and agencies,

development partners and other stakeholders, reviewing project status and progress, and addressing issues

that may arise. The establishment of OSC will be a condition precedent to first disbursement of the Loan.

The members of OSC shall be persons whose qualifications and experience are acceptable to the

Caribbean Development Bank.

APPENDIX 5.4

PROCUREMENT PLAN

This information is withheld in accordance with one or more of the

exceptions to disclosure under the Bank’s Information Disclosure Policy.

APPENDIX 5.5

ESTIMATED QUARTERLY LOAN DISBURSEMENT SCHEDULE

($'000)

Year

Quarter No.

Disbursement IDC &

OCR SFR Commitment Fees

Total

2012 4 - 124 26 150

Sub-total 0 124 26 150

2013

1

-

405

27

432

2 1,643 405 43 2,091

3 1,643 405 57 2,105

4 1,643 405 75 2,123

Sub-total 4,930 1,620 202 6,752

2014

1

1,313

242

83

1,638

2 1,313 242 95 1,652

3 1,313 243 106 1,662

4 1,314 243 118 1,675

Sub-total 5,253 970 402 6,625

2015

1

-

221

19

240

2 - 221 20 241

3 - 221 22 243

4 - 222 23 245

Sub-total 0 885 84 969

TOTAL 10,183 3,599 714 14,496

APPENDIX 5.6

REPORTING REQUIREMENTS

Reports Frequency Deadline for Submission

Implementation

1. Progress Report on project

implementation prepared by PM.

Monthly

Within one month after the end of

each calendar month until project

implementation is completed,

commencing one month after the

Project Launch. 2. Evaluation Reports on shortlists and

proposals for the consultancies

prepared by PM.

- Within two weeks of the submission

deadlines.

3. Evaluation Reports on

prequalification and tenders for

works prepared by PM.

- Within two weeks of the submission

deadlines.

4. Evaluation Reports on requests for

quotations for goods prepared by

PM.

- Within two weeks of the submission

deadlines.

5. Reports on the Investment Costs of

the Project prepared by PM.

(Sample guidelines presented in

Annex 1).

Quarterly Two weeks after the end of each

quarter until project implementation

is completed, commencing with the

quarter following the appointment

of PM. 6. Report on the progress of the works

prepared by PE. Monthly Within one month after the end of

each calendar month until project

implementation is completed. 7. Consultants’ Reports. - Within one month of acceptance of

the reports. 8. Enforcement Strategy prepared by

DOT. Biannually Two weeks after the end of each

half-year until project

implementation is completed.

commencing with the month

following the appointment of PM. 9. Summary of Quarterly Monitoring

Indicators prepared by PM. Quarterly Two weeks after the end of each

quarter until project implementation

is completed, commencing with the

quarter following the appointment

of PM. 10. Summary of Annual Review

Proceedings prepared by PM. Annually Two weeks after the end of each

Annual Review Workshop until

project implementation is

completed. 11. Project Implementation Completion

Report prepared by PM. - Within three months of completion

of the Project.

Operation

12. Reports on Monitoring Indicators.

Annually

By October 1, commencing in 2016.

13. Maintenance Plan for the road

infrastructure, including reports of

condition assessments of road

infrastructure.

Annually By October 1, commencing in 2014.

AN

NE

X T

O A

PP

EN

DIX

5.6

QUARTERLY REPORT ON INVESTMENT COST OF PROJECT

($'000)

Elements of Project

Expenditure

for this

Quarter

Cumulative

Expenditure

to date

Projected Expenditure

for the Quarter

Estimated

Expenditure

to Complete

Project

Latest

Estimate of

Expenditure

Project

Estimate

as per

Appraisal

Report

Variance

Favourable/

(Adverse)

Comments/

Reasons for Adverse

Variance and

Financing Proposal to

Meet Cost Overrun

Ending

Ending

Ending

(1)

(2)

(3)

(4)1

(4)2

(4)3

(5)

(6)

(7)

(8)

(9)

1. Road Safety Infrastructure

2. Road User Education and Awareness

3. Road Safety Enforcement

4. Road Accident Emergency Services

5. Capacity Building

6. Project Management

8,200

1,550

430

450

620

3,085

Base Cost 14,335

7. Physical and Price Contingencies

2,637

Total Project Cost 16,972

8. Finance Charges 714

Total Finance Costs 17,686

Financing:

CDB: - OCR

CDB: - SFR

GOBZ

10,723

3,772

3,191

ANNEX TO APPENDIX 5.6

Page 2

GUIDELINES FOR COMPLETION OF REPORT ON PROGRESS

OF INVESTMENT COST

1. Elements of Project - The elements of the Project as outlined in the Appraisal Report must

be recorded in this column. If it becomes necessary to further sub-divide the

main elements of the project, then the sub-elements should be grouped to facilitate

the determination of the expenditure related to the main elements identified in the

Appraisal Report.

2. Expenditure for this Quarter - The expenditure incurred in the quarter to which the report

relates in respect of each element of the project must be recorded in this column.

3. Cumulative Expenditure to Date - The expenditure incurred in respect of each element of

the project from the commencement of the project to the end of the quarter to which the

report relates must be recorded in this column.

4. Projected Expenditure for Quarter - An estimate of the expenditure to be incurred in each

of the next three quarters must be recorded in the columns 41, 42, and 43.

5. Estimate of Expenditure to complete Project - This column should be completed only in

respect of those elements of the project, construction/installation of which stretches beyond

three quarters from the end of the quarter to which the report relates. Where a project

extends over more than one year - four quarters - an estimate of the expenditure to be

incurred in the period subsequent to the year must be recorded in this column.

6. Latest Estimate of Expenditure - The amounts to be recorded in this column should be

derived by adding columns 3, 4123, and 5. The amounts recorded in this column should be

the best estimate of expenditure to be incurred in respect of each element of the project.

These amounts may be less or greater than the appraised expenditure.

7. Project Estimates as per Appraisal Report - The estimate of expenditure to be incurred in

respect of each element of the project, as outlined in the Appraisal Report, must be

recorded in this column.

8. Variance - The difference between columns 6 and 7 must be recorded in this column.

Where the amount in column 6 is less than that in column 7, a favourable variance results.

An adverse variance results where the amount in column 6 is greater than that in column 7.

9. Comments - An explanation should be given for each variance which is more than 10% of

the project estimates as per Appraisal Report.

FIGURE 1: PROJECT LOCATION MAP

FIGURE 2: DEMONSTRATION CORRIDOR