    Index

    1.Introduction of group with project title

    2.Primary investigation

    2.1 need of project - - - - - - - - - - - - - - - - - - - -

    - - 4

    2.2 project scope and disadvantages - - - - - - -

    - - - 6

    2.3 Profile of organization chart - - - - - - - - - -

    - - 8

    2.4 exiting system - - - - - - - - - - - - - - - - - - - -

    - - - 102.5 advantages and disadvantages of exiting -

    - - - 12

    System

    3

  • 8/6/2019 Ptoject of Hospital

    4/49

    2.6 organization chart - - - - - - - - - - - - - - - - -

    - - - 13

    2.7 Function decomposition chart - - - - - - - - -

    - - - 14

    2.8 Proposed system - - - - - - - - - - - - - - - - - -

    - - - 15

    2.9 Feasibility study - - - - - - - - - - - - - - - - - - -

    - - - - 17

    3.Building a project plane for scratch

    3.1 introduction(definition)

    3.2 Planning activity.

    3.3 Designing calendar

    4.System requirement specification - - - - - - - - - - - - - - - - - 18

    5.Data flow diagram of system - - - - - - - - - - - - - - - - -

    - - - - - 21

    5.1 context level - - - - - - - - - - - - - - - - - - - - - -

    - - - 21

    5.2 1st level - - - - - - - - - - - - - - - - - - - - - - - - - - -

    - - 23

    5.3 2nd level - - - - - - - - - - - - - - - - - - - - - - - - - - -

    - - 24

    4

  • 8/6/2019 Ptoject of Hospital

    5/49

    6.Entity relationship diagram - - - - - - - - - - - - - - - - - -

    - - - - - 26

    7.Data dictionary - - - - - - - - - - - - - - - - - - - - - - - - - -

    - - - - - 27

    8. Cost estimation, schedule and assigning resources

    (Phase-2)

    5

  • 8/6/2019 Ptoject of Hospital

    6/49

    Group introduction :-

    Group no :-B16No

    Rollno

    Name

    1 123 Parmar Bhavesh

    2 105 Dodha Ketan

    3 168 PathanShahnavaj4 162 Prajapati

    6

  • 8/6/2019 Ptoject of Hospital

    7/49

    Yogesh

    Need of system :-

    In hospital management patient management and its data is moreimportant. In this data arrange and store in proper way for long time. Its

    some needs are as under.

    This program is developed to make easy the routine work.

    Easy to find data or information.

    Save lot of manpower and time.

    7

  • 8/6/2019 Ptoject of Hospital

    8/49

    System covers large number of people and try minimize data

    redundancy.

    In this system process of summary report is main part, using the

    computerized system.

    This process is become simple and small; you can immediately

    getting the report for the query.

    This system provides interaction user friendliness and also less

    paper work.

    Project scope and limitation :-

    Project scope :-

    Patient management of general O.P.D. in the general hospital,

    Gandhinagar.

    In this you also stored patients report and you study on the

    specific disease.

    8

  • 8/6/2019 Ptoject of Hospital

    9/49

    We manage pharmacy department, general O.P.D. , and patient

    management system. Combine we will that three department

    through the server connection that use for without paperwork we

    done every process easily.

    Project limitation :-

    Data store 25 years only.

    In this system patient id is more impotent and without it cant

    manage this system.

    Note : patient data store for 25 years only.

    Profile :-

    Name : General hospital management,

    Gandhinagar.

    Address : sector 12,

    9

  • 8/6/2019 Ptoject of Hospital

    10/49

    Opp. Pathikashram,

    Pin-382016

    Phone number : 079-232221931-32

    2321913

    Fax : 079-23222733

    Email id : [email protected]

    Slogan : we accept high risk obstetric patient at this

    hospital.

    Logo :

    Mission : -

    We shall enhance the patient quality life through providing

    specialized medical treatment at free and affordable rates to the poor and

    the needy and preventive healthcare.

    10

  • 8/6/2019 Ptoject of Hospital

    11/49

    Vision : -

    To be the part of network of finest public healthcare institution in

    the state of Gujarat, providing quality medical care services with the state

    of art technology with easy accessibility, affordability and equity to the

    people of Gujarat and beyond.

    Exiting system :-

    The existing system is computerized system. It is not fully computerize

    system.

    11

  • 8/6/2019 Ptoject of Hospital

    12/49

    Most allies are done manually in Hospital Management system.

    All reports are done manually.

    Information about patient is recorded computerized but in that many

    problems.

    Data redundancy is more and data and information are not arranges

    in proper structure and way.

    All information is difficult to remember to doctor about patients.

    Manually reports or other document are not save long time.

    Work load is more.

    Report and data searching problems.

    In use more manpower and time.

    12

  • 8/6/2019 Ptoject of Hospital

    13/49

    Advantages of exiting system :-

    Error will be less.

    In the General O.P.D patient take treatment for every type of diseases

    It is comfortable with patient.

    Disadvantages of exiting system :-

    Work load is more.

    Waste time, money, manpower.

    Many problems in find proper data or information.

    In many chances lost information and reports.

    13

  • 8/6/2019 Ptoject of Hospital

    14/49

    Organization chart :-

    14

  • 8/6/2019 Ptoject of Hospital

    15/49

    G o v e r n m e n t o f

    G u j a r a t

    H e a l th a n d f a m i ly w e l fa r e

    d e p a r t m e n t

    M e d i ca l d e p a r t m e n tH e a lth d e p a r tm e n t E d u ca t io n d e p a r tm e n t

    C i v il hosp i t a l

    C i v il s u r g e o n R e s id e n t m e d i c a l o f f ic e r (R.M.O)

    C.H.C( com m un i ty

    h e a l t h c e n t e r )

    P.H.C ( p r im a r y

    h e l t h c e n t e r )

    M e d i c a l c o ll e g e

    D o c t o r s

    N u r s e& e m p l o y e e s O t h e r s t a f f

    Function decomposition chart :-

    15

  • 8/6/2019 Ptoject of Hospital

    16/49

    C I V I L G e n e r a l h o s p i ta l

    P a t ie n t m a n a g e m e n t

    G e n e r a l O.P.D.

    P h a r m a c y m a n a g e m e n tP a t i e n t r e g i s t r a ti o nm a n a g e m e n t

    L a b o t a r r y

    m a n a g e m e n tO.P.D. m a n a g e m e n tP h a r m a c y

    m a n a g e m e n t

    E m e rg e n c y

    p r e p a r e d n e s s

    C l i n i c a l r is k

    m a n a g e m e n t

    I n f e c ti o n c o n t r o l

    m a n a g e m e n t

    E q u i p m e n t s

    m a n a g e m e n t

    Proposed system :-

    16

  • 8/6/2019 Ptoject of Hospital

    17/49

  • 8/6/2019 Ptoject of Hospital

    18/49

    Feasibility study :

    There are four types of feasibility .operational feasibility, technical

    feasibility, economical feasibility, schedule feasibility. New system feasibility

    given below:

    1. operational feasibility:-

    The new system aim is save manpower with minimize data

    redundancy and data arrange in proper way. Proposed system is useful t

    searching data so, it is user friendly. System will not require any

    training. If you need any help related system then we will provided

    guidance and help only. The system will be comfortable for both user and

    patients.

    2. technical feasibility :-

    Patient data and information is important in any hospital. Hospitalis easy to purchase entire system requirements. The system will be

    operationally comfortable for the company.

    18

  • 8/6/2019 Ptoject of Hospital

    19/49

    3. economical feasibility :-

    The company is capable to requirement of proposed system. Its

    advantages is more and helpful in improve profit. The system will be

    economical feasible for the company.

    4. schedule feasibility :-

    .

    Time is the most effective factor while making a project or system. The

    project should be finished within the assigned time.

    So our proposed system in scheduling is feasible.

    19

  • 8/6/2019 Ptoject of Hospital

    20/49

    System requirement Specification :-

    Hardware :-

    Developers requirement :-

    RAM 1 GB,

    Processor Intel i3 core,

    Hard disk 160 GB,

    20

  • 8/6/2019 Ptoject of Hospital

    21/49

    User requirement :-

    Processor Intel i7 core,

    Hard disk 320 GB,

    RAM 3 GB,

    Software :-

    Operating system : windows XP professional version 2002,

    Service pack 2

    Ms Visualstudio.NET

    Data base : Microsoft ACCESS XP

    Data Flow Chart

    21

  • 8/6/2019 Ptoject of Hospital

    22/49

    Pharmacy management

    Registrationmanagement

    O.P.D. management

    Doctor

    Medicine & prescriptions

    information

    Patient data

    Prescription

    Patient

    information

    Data Flow Diagram

    22

  • 8/6/2019 Ptoject of Hospital

    23/49

    H o s p i t a l

    m a n a g e m e n t

    s y s t e m

    D o c t o r R e g i s te r c a s e

    P a t i e n tI n f o r m a t io n

    M e d i c in e s a n d

    s u g g e s t i o n P r e s c r i p t i o n s

    C o n t e x t l e v e l D F D f o r h o s p i ta l m a n a g e m e n t

    23

  • 8/6/2019 Ptoject of Hospital

    24/49

    0 level DFD

    24

    pat ient

    1

    Pat ient

    registrat ion

    system

    2

    Pa t ient repo rt

    Prescr ipt ions

    3

    Pharmacy

    management

    system

    Patient info

    Patient info

    Doctor Information

    Prescr ipt ion

    Medic ines, repo rt

    suggest ion

    Bi l l/ token

    0 leve l DF D for hospi ta l manageme nt sys tem

    Information

    payment

  • 8/6/2019 Ptoject of Hospital

    25/49

    1STLEVEL DFD

    Pat ient

    informat ion

    1.1

    Pat ient

    information

    system

    Pat ientIn fo rm a tion In fo rm a tion

    1.3

    information

    Searching

    system

    Patient detai ls

    information

    1.1

    prepare

    Bi l l\case

    information

    information

    Bi l l\ toke nBil l

    informat ionBil l id information

    Bil l ing information

    1st leve l D FD for pat ient reg is t ra t ions system

    Previous info

    25

  • 8/6/2019 Ptoject of Hospital

    26/49

    2ND LEVEL DFD

    Diagnosis

    informationDoctor

    2.1diagnosis

    Prescriptions Diagnosis

    Prescriptions

    2.2Doctor study

    2.3

    Doctor detailand work

    DoctordetailsDoctor details

    Prescriptions

    Prescriptions

    Diagnosisinformation

    Study information

    diagnosis details

    2nd level DFD for prepare prescriptions

    26

  • 8/6/2019 Ptoject of Hospital

    27/49

    3RD LEVEL DFD

    M e d i c i n e sd e t a i l s

    P a t i e n t 3.1

    P h a r m a c ym a n a g e m e n t

    s y s t e m

    G i ve de t a i l s abou t s t ocks

    F i n d o u t p h a r m a c y d e t a i l

    P a t ie n t s d i a g n o s i s

    P a t ie n t s d i a g n o s i s

    3.1m e d i c in e s y s te m

    d i a g n o s i s

    3r d l e v e l D F D fo r p h a rm a c y m a n a g e m e n t s y s te m

    Ph a rmacydepa r tmen tm a n a g e

    27

  • 8/6/2019 Ptoject of Hospital

    28/49

    28

  • 8/6/2019 Ptoject of Hospital

    29/49

    Doctorpatient Check up

    Pharmacy

    departmentPrescriptionMedicine

    Billing process

    registrationinformation

    Patient history

    Page 1

    ENTITY RELATIONSHIP DAIGRAM

    Information data

    Patient data

    Patient data

    Billtoken(case)

    Say about diagnosis All info

    Patient data

    Prescriptions & medicine

    medicinemedicine

    All prescription ,medicine, data

    Store all info

    Previous history of patients if they will be comeagain

    29

  • 8/6/2019 Ptoject of Hospital

    30/49

    Data dictionary :-

    A data dictionary is a central storehouse of information of about thsystems data. An analyst uses data dictionary to collect, document and

    organize specific fact about system, including the contents of data flow,

    data stores, entities and process.

    1) Diagnosis :-

    Filed name Type size Constraint Description

    D_name Text 20 Not null Disease name

    D_study Text 256 About that

    information

    D_work Text 256 Use for doctor

    2) Bill :-

    Filed name Type size Constraint Description

    B_no Number 10 Pk Bill noTotal Number 10 Not null Cost(bill)

    P_name Text 20 Not null Patient name

    P_id Number 10 Fk Patient id no

    30

  • 8/6/2019 Ptoject of Hospital

    31/49

    3) Patient case :-

    Filed name Type Size Constraint Description

    P_id Number 10 Primary key Patient key

    Case_no Number 10 Not null Case noDate Date and

    time

    - Not null Date

    P_name Text Not null Patient name

    P_add Text 50 Not null Patient address

    P_age Number 2 Not null Patient age

    Gender Yes\no - Not null Patient sex

    City Text 20 Not null Patient city

    Phone Number 10 Allow null Patient phone noMobile Number 10 Allow null Patient mobile no

    4) Patient history :-

    Filed name Type Size Constraint Description

    P_id Number 10 Foreign key Patient key

    Diseases Text 100 Not null Patient diseases

    Report Text 256 Not null Reports

    31

  • 8/6/2019 Ptoject of Hospital

    32/49

    Prescription Text 256 Not null Prescription

    5) Doctor details :-

    Filed name Type size Constraint Description

    D_ id Number 10 Primarykey

    Doctor id no

    D_name Text 20 Not null Doctor name

    Visit_date Date &

    time

    - Not null Doctor visit date

    Degree Text 15 Not null Degree

    D_address Text 56 Not null Address

    D_phone Number 10 Not null Doctor contact

    no

    6) Pharmacy :-

    Filed name Type size Constraint Description

    M_name Text 20 Not null Medicine name

    M_code Number 15 Pk Medicine code

    E_date Date Not null Expire date

    M_stock Number 20 Not null Stock

    M_price Number 10 Not null Price

    32

  • 8/6/2019 Ptoject of Hospital

    33/49

    Activity table:-

    33

  • 8/6/2019 Ptoject of Hospital

    34/49

    34

    Ac

    tiv

    ity

    Description Prec

    eden

    ce

    Dura

    tion

    Resourc

    es

    Opti

    misti

    c

    Most

    likel

    y

    Pessi

    misti

    c

    R

    e

    m

    a

    r

    k

    s

    A Select project - Project

    Manager

    B Define project

    scope

    - 1

    week

    Project

    manager

    1

    week

    1

    week

    1week

    C Existing

    System

    B 1

    Week

    Analyst,

    Project

    Leader

    1

    week

    1

    week

    1

    week

    D System

    planning

    C 1

    week

    Analyst,

    Project

    Leader

    1

    week

    1

    week

    1

    week

    E System

    analysis

    D 3

    week

    Analyst,

    Systems

    Booklet,

    Users

    3

    week

    3

    week

    4

    week

    F Information

    gathering

    3 day Analyst,

    Users

    G User

    requirements

    E 3 day Analyst,

    Users,

    Systems

    Booklet

    H Data and

    process

    modeling

    E 2

    days

    Data base

    designer

  • 8/6/2019 Ptoject of Hospital

    35/49

    Start date

    Project Project Information Set Project Start Date

    35

  • 8/6/2019 Ptoject of Hospital

    36/49

    Set priority

    Project Project information Set Project Priority

    36

  • 8/6/2019 Ptoject of Hospital

    37/49

    Change working times

    Tool Change Working Time

    37

  • 8/6/2019 Ptoject of Hospital

    38/49

    Set currency

    Tool Options View Currency Option Symbol

    38

  • 8/6/2019 Ptoject of Hospital

    39/49

    Critical path :

    39

  • 8/6/2019 Ptoject of Hospital

    40/49

    40

  • 8/6/2019 Ptoject of Hospital

    41/49

    41

  • 8/6/2019 Ptoject of Hospital

    42/49

    42

  • 8/6/2019 Ptoject of Hospital

    43/49

    Resources with their Costs and Overtime Costs:-

    PERT Analysis:-

    43

  • 8/6/2019 Ptoject of Hospital

    44/49

    Project Progress in a Bar Chart:-

    44

  • 8/6/2019 Ptoject of Hospital

    45/49

    I D

    1

    2

    34

    5

    6

    7

    8

    9

    1 0

    P r o j e c t M a n a g e r [ 8 6 % ]

    A n a l y s t , P r o j e c t L e a d e r

    A n a l y s t , S y s t e m ' s B o o k l e t

    P r o g r a m m e r , D e s i g n e r

    P r o g r a m m e r

    D e s i g n e r , P r o

    P r o g r

    1 8 2 12 42 7 3 0 2 5 8 1 1 1 41 7 2 02 32 6 2 9 2 5 8 1 1 1 41 7 2 02 32 6 2 9 1 4 7 1 01 3 1 61 9 2 22 5 2 8 1 4 7 1 01 3 1 61 9 2 22 5 2 83 1 3 6 9 1 2 1 51 8 2 12 4 2 73 0 2 5 8 1 11 4 1 72 02 3 2 62 9 2 5 8 1 1 1 41 7 2 0

    r c h 2 0 1 0 A p r i l 2 0 1 0 M a y 2 0 1 0 J u n e 2 0 1 0 J u l y 2 0 1 0 A u g u s t 2 0 1 0 S e p t e m b e r 2 0 1 0O c t o b e r 2 0

    Resource Table

    Available Unit/Days Cost

    Project

    Manager

    1 Days Rs300.00/hr

    Analyst 2 Days Rs200.00/hr

    Project Leader 1 Days Rs300.00/hr

    Systems

    Booklet

    4 Units Rs100.00/hr

    Users 2 Days Rs50.00/hr

    Database

    Designer

    1 Days Rs230.00/hr

    Designer 2 Days Rs350.00/hr

    MS Visio 1 Units Rs2,000.00/hr

    MS Word 1 Units Rs1,500.00/hr

    45

  • 8/6/2019 Ptoject of Hospital

    46/49

    ASP.NET 1 Units Rs9,000.00/hr

    Programmer 1 Days Rs300.00/hr

    MS Access 1 Units Rs1,500.00/hr

    Operating

    System

    1 Units Rs25,000.00/h

    46

  • 8/6/2019 Ptoject of Hospital

    47/49

    Resource :-

    ID Task Name Duration Start Finish Predecessors Resource Names

    1 Define project scope 1 wk Sat 4/10/10 Sat 4/17/10 Project Manager[86%]

    2 Existing System 2 wks Sun 4/18/10 Sat 5/1/10 1

    3 Systemplanning 2 wks Mon 5/3/10 Tue 5/18/10 2 Analyst,Project Leader

    4 Systemanalysis 3 wks Wed 5/19/10 Thu 6/10/10 3 Analyst,System's Booklet

    5 Proposed System 2 wks Fri 6/11/10 Fri 6/25/10 4

    6 Systemdesign 5 wks Sat 6/26/10 Thu 8/5/10 5 Programmer,Designer

    7 Coding and Testing 5 wks Fri 8/6/10 Wed 9/15/10 4,6 Programmer

    8 Implementation 1 wk Wed 9/15/10 Thu 9/23/10 7 Designer,Programmer,Database design

    9 Staff recruitment 2 wks Sat 6/26/10 Mon 7/12/10 5

    10 User training 1 wk Sat 10/2/10 Sat 10/9/10 9 Programmer,Project Leader

    Pert analysis :-

    47