Upload
lytruc
View
213
Download
1
Embed Size (px)
Citation preview
Application for Prevention of Significant Deterioration
Air Permit Greenhouse Gas Emissions
Enterprise Mont Belvieu Complex Propane Dehydrogenation Unit
Submitted by
Enterprise Products Operating LLC P.O. Box 4324
Houston, Texas 77210-4324
December 2012
I:\Projects\Enterprise\Texas\Mt Belvieu\PDH\GHG Permit\GHG Application.doc i
Table of Contents List of Sections
Section 1 Introduction ............................................................................................................ 1-1
Section 2 Administrative Information and PSD Applicability Forms ...................................... 2-1
Section 3 Area Map and Plot Plan ........................................................................................ 3-1
Section 4 Process Description .............................................................................................. 4-1
Section 5 Emission Rate Basis ............................................................................................. 5-1 5.1 Combustion Units ................................................................................................. 5-1
5.1.1 Reactor Charge Heater ............................................................................ 5-1 5.1.2 Waste Heat Boiler (WHB) ........................................................................ 5-2 5.1.2.1 Combustion Turbines ............................................................................... 5-2 5.1.2.2 Regeneration Air Heater .......................................................................... 5-2 5.1.2.3 WHB Duct Burner ..................................................................................... 5-3 5.1.2.4 Reactor Air Effluent and Ejector ............................................................... 5-3 5.1.2.5 Decoke ..................................................................................................... 5-3 5.1.3 Auxiliary Boilers ........................................................................................ 5-4 5.1.4 Combustion Unit Emissions Caps ............................................................ 5-4
5.2 Flare Emissions ..................................................................................................... 5-4 5.3 Process Fugitive Emissions .................................................................................. 5-5 5.4 Diesel Engines ...................................................................................................... 5-5
Section 6 Best Available Control Technology ....................................................................... 6-1 6.1 Reactor Charge Heater ......................................................................................... 6-2
6.1.1 Step 1 – Identification of Potential Control Technologies ......................... 6-2 6.1.2 Step 2 – Elimination of Technically Infeasible Alternatives ...................... 6-3 6.1.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness .. 6-3 6.1.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective .......................................................................................... 6-4 6.1.5 Step 5 – Selection of BACT ..................................................................... 6-8
6.2 Regeneration Air Heater ........................................................................................ 6-9 6.2.1 Step 1 – Identification of Potential Control Technologies ......................... 6-9 6.2.2 Step 2 – Elimination of Technically Infeasible Alternatives ...................... 6-9 6.2.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-10 6.2.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-10 6.2.5 Step 5 – Selection of BACT ................................................................... 6-11
6.3 Waste Heat Boiler .............................................................................................. 6-11 6.3.1 Step 1 – Identification of Potential Control Technologies ....................... 6-11 6.3.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-12 6.3.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-12 6.3.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-13 6.3.5 Step 5 – Selection of BACT ................................................................... 6-14
6.4 Auxiliary Boilers .................................................................................................. 6-14 6.4.1 Step 1 – Identification of Potential Control Technologies ....................... 6-14 6.4.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-15 6.4.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-15 6.4.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-16
I:\Projects\Enterprise\Texas\Mt Belvieu\PDH\GHG Permit\GHG Application.doc ii
6.4.5 Step 5 – Selection of BACT ................................................................... 6-17 6.5 Combustion Turbines ......................................................................................... 6-17
6.5.1 Step 1 – Identification of Potential Control Technologies ....................... 6-17 6.5.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-18 6.5.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-18 6.5.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-19 6.5.5 Step 5 – Selection of BACT ................................................................... 6-20
6.6 Flare .................................................................................................................... 6-20 6.6.1 Step 1 – Identification of Potential Control Technologies ....................... 6-20 6.6.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-21 6.6.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-21 6.6.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-21 6.6.5 Step 5 – Selection of BACT ................................................................... 6-21
6.7 Fugitives (EPNs FUG-PDH & FUG-NGAS) ......................................................... 6-22 6.7.1 Step 1 – Identification of Potential Control Technologies ....................... 6-22 6.7.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-22 6.7.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-22 6.7.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-22 6.7.5 Step 5 – Selection of BACT ................................................................... 6-23
6.8 Diesel Engines .................................................................................................... 6-23 6.8.1 Step 1 – Identification of Potential Control Technologies ....................... 6-23 6.8.2 Step 2 – Elimination of Technically Infeasible Alternatives .................... 6-23 6.8.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness 6-23 6.8.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to
Least Effective ........................................................................................ 6-24 6.8.5 Step 5 – Selection of BACT ................................................................... 6-24
List of Tables Table 1F Air Quality Application Supplement ....................................................................... 2-3 Table 2F Project Emissions Increase ................................................................................... 2-4 Table 3F Project Contemporaneous Changes ..................................................................... 2-5 Table 5-1 Proposed GHG Emission Limits ............................................................................ 5-6 Table 6-1 Approximate Cost for Construction and Operation of a Post-Combustion CCS
System for PDH Plant ......................................................................................... 6-25
List of Figures Figure 3-1 Area Map ............................................................................................................... 3-2 Figure 3-2 PDH Unit Plot Plan ................................................................................................ 3-3 Figure 4-1 Simplified Process Flow Diagram .......................................................................... 4-2
List of Appendices
Appendix A Emissions Calculations Appendix B RBLC Database Search Results
1-1
Section 1 Introduction
Enterprise Products Operating LLC (Enterprise) currently operates the Mont Belvieu Complex,
an oil and gas production facility in Chambers County. Enterprise proposes to construct a
Propane Dehydrogenation (PDH) Unit at the Complex with a design propylene production
capacity of 1.654 billion pound per year. A hydrogen byproduct will also be produced. Both the
propylene and hydrogen products will be sent offsite via pipeline. The new facilities in the PDH
Unit will include:
Ten parallel catalytic reactors that convert propane feed to propylene, One Reactor Charge Heater, One Regeneration Air Heater, One Waste Heat Boiler with duct firing capability, Two Auxiliary Boilers, Two Regeneration Air Compressors, Two Regeneration Air Combustion Turbines, Cooling tower, Hydrogen Recovery (PSA) Unit, Ancillary tanks, Emergency pump engines, Process flare, and Wastewater treatment facilities.
A New Source Review permit amendment application has also been submitted to TCEQ for this
project. The project triggers NNSR for VOC and PSD review for NOx, CO, PM/PM10/PM2.5, SO2,
and H2SO4, for which TCEQ has approved permitting programs and PSD for greenhouse gas
(GHG) emissions, for which TCEQ has not implemented a PSD permitting program. The
purpose of this permit application is to obtain a PSD permit for the GHG emissions associated
with the project.
This document constitutes Enterprise’s GHG PSD permit application for the modifications
described above. Because EPA has not developed application forms for GHG permitting,
TCEQ forms are used where deemed appropriate. The application is organized as follows:
Section 1 identifies the project for which authorization is requested and presents the application
document organization.
1-2
Section 2 contains administrative information and completed TCEQ Federal NSR applicability
Tables 1F, 2F, and 3F.
Section 3 contains an area map showing the facility location and a plot plan showing the
location of each emission points with respect to the plant property.
Section 4 contains more details about the proposed modifications and changes in operation and
a brief process description and simplified process flow diagram.
Section 5 describes the basis of the calculations for the project GHG emissions increases and
includes the proposed GHG emission limits.
Section 6 includes an analysis of best available control technology for the new and modified
sources of GHG emissions.
Appendix A contains GHG emissions calculations for the affected facilities.
Appendix B contains the results of an RBLC database search for GHG controls used on gas
fired heaters and boilers.
2-1
Section 2 Administrative Information and PSD Applicability Forms
This section contains the following forms:
Administrative Information
TCEQ Table 1F
TCEQ Table 2F
TCEQ Table 3F
Tables 1F, 2F and 3F are federal NSR applicability forms. Because this application covers only
GHG emissions, and PSD permitting of other pollutants is being conducted by TCEQ, these
forms only include GHG emissions. As shown in both the Table 1F and 2F, GHG emissions
from the project exceed 75,000 tpy of CO2e; therefore, a Table 3F, which includes the required
netting analysis, is also included. The net increase in GHG emissions exceeds 75,000 tpy of
CO2e; therefore, PSD review is required.
Permit No.: TBD
Project Name: PDH Unit
December A B
FIN EPN Facility Name
1 HR15.101 HR15.101 Combustion Unit Cap TBD - - 1,281,586 - 1,281,586 0 1,281,586
2 HR15.103 Waste Heat Boiler Burner TBD
3 HR15.102 Regeneration Air Heater TBD
4 GT26.101ARegen Air Comp. Gas
Turbine ATBD
5 GT26.101BRegen Air Comp. Gas
Turbine BTBD
6 BO10.103A Auxiliary Boiler A TBD
7 BO10.103B Auxiliary Boiler B TBD
8 SK25.801 SK25.801 Process Flare, Routine TBD - - 2,820.56 2,820.56 0.00 2,820.56
9 SK25.801 SK25.801 Process Flare, MSS TBD - - 4,439.30 4,439.30 0.00 4,439.30
10 FUG-PDH FUG-PDH Process Fugitives TBD - - 5.24 5.24 0.00 5.24
11 FUG-NGAS FUG-NGASNat. Gas Pipeline
FugitivesTBD - - 273.75 273.75 0.00 273.75
12 PM18.803 PM18.803 Fire Water Pump Engine TBD - - 16.14 16.14 0.00 16.14
13 PM18.850C PM18.850C Raw Water Pump Engine TBD - - 8.40 8.40 0.00 8.40
14
15
Page Subtotal9: 1,289,149
Project Total: 1,289,149
Difference
(B-A)6
(tons/yr)
Correction7
(tons/yr)
Project
Increase8
(tons/yr)
Affected or Modified Facilities2Permit
No.
Actual
Emissions3
(tons/yr)
Baseline
Emissions4
(tons/yr)
Proposed
Emissions5
(tons/yr)
Projected Actual Emissions(tons/yr)
DW37.101
Baseline Period: NA
TABLE 2FPROJECT EMISSION INCREASE
Pollutant1: GHG
12/18/2012
Table 3FProject Contemporaneous Changes
Company: Enterprise Products Operating LLCCriteria Pollutant: GHG
Permit Application No. TBDA B C
No. PROJECT DATEEMISSION UNIT AT WHICH
REDUCTION OCCUREDPERMIT
NUMBERPROJECT NAME OR
ACTIVITYPROPOSED EMISSIONS
BASELINE EMISSIONS
DIFFERENCE (A-B)
FIN EPN (tons / year) (tons / year) (tons / year)
1 July 1, 2015 HR15.101 HR15.101 TBD PDH Unit 1,281,586 0 1,281,586 1,281,5862 July 1, 2015 HR15.103 TBD PDH Unit3 July 1, 2015 HR15.102 TBD PDH Unit4 July 1, 2015 GT26.101A TBD PDH Unit5 July 1, 2015 GT26.101B TBD PDH Unit6 July 1, 2015 BO10.103A TBD PDH Unit7 July 1, 2015 BO10.103B TBD PDH Unit8 July 1, 2015 SK25.801 SK25.801 TBD PDH Unit 2,821 0 2,821 2,8219 July 1, 2015 SK25.801 SK25.801 TBD PDH Unit 4,439 0 4,439 4,439
10 July 1, 2015 FUG-PDH FUG-PDH TBD PDH Unit 5 0 5 5
11 July 1, 2015 FUG-NGAS FUG-NGAS TBD PDH Unit 274 0 274 274
12 0 0
13 0 0
14 0 0
15 0 0
16 0 0
17 0 0
18 0 0
19 0 0
20 0 0
PAGE SUBTOTAL: 1,289,125
Summary of Contemporaneous Changes TOTAL : 1,289,125
CREDITABLE DECREASE OR
INCREASE
(tons / year)
DW37.101
3 12/18/2012
3-1
Section 3 Area Map and Plot Plan
An Area Map showing the location of the Mont Belvieu Complex is presented in Figure 3-1. A
plot plan showing the location of the modified facilities is presented in Figure 3-2.
308000 308500 309000 309500 310000 310500 311000 311500 312000 312500 313000 313500 314000 314500 315000 315500 316000 316500 317000 317500 318000
UTM Easting (meters)
3302
000
3302
500
33030
00
33
035
00
33
040
00
330
450
0330
500
03305
500
3306
000
3306
500
33
070
00
33
075
00
33
0800
0330
850
0
UT
M N
ort
hin
g (
mete
rs)
FIGURE 3-1Area Map
411 North Sam Houston ParkwaySuite 400,Houston, Texas , 77060
Enterprise Products Operating LLCMont Belvieu Complex
Source: mytopo.com/Zone: 15Coordinate Datum: NAD 83
North
Property Line
3,000 ft
Scale
(feet)
3-2
Proposed PDH Unit
0 1000 2000 3000 4000 5000
Emission Points are out of Figure boundaries
411 North Sam Houston Parkway Suite 400, Houston, Texas , 77060.
Enterprise Products Operating LLC Mont Belvieu Complex
Figure 3-2 Proposed PDH Unit
4-1
Section 4 Process Description
A brief overview of the process is included below, and a simplified process flow diagram of the
PDH process is shown in Figure 4-1. A block flow diagram of the Waste Heat Boiler is shown in
Figure 4-2.
The proposed PDH Unit will convert propane to propylene over a catalyst. The unconverted
propane is recycled so that propylene is the only net product. A hydrogen byproduct is also
produced.
Operating conditions are selected to optimize the relationships among selectivity, conversion,
and energy consumption. Side reactions occurring simultaneously with the main reaction cause
the formation of some light and heavy hydrocarbons as well as the deposition of coke on the
catalyst.
The process takes place in fixed-bed reactors that operate on cyclic basis. In one complete
cycle, hydrocarbon vapors are dehydrogenated; the reactor is then purged with steam and
blown with air to reheat the catalyst and burn off the small amount of coke that is deposited on
the catalyst during the reaction cycle. These steps are followed by an evacuation and
reduction, and then another cycle is begun.
A key feature of the process is that the heat absorbed during the endothermic dehydrogenation
period is obtained by the adjustment of the air and hydrocarbon inlet temperatures and by the
oxidation of the coke.
The low temperature recovery area, product purification, and refrigeration systems have been
integrated to optimize energy efficiency. The design contains:
Cascade propylene and ethylene refrigeration system.
A high efficiency cold box design that minimizes equipment count and refrigerant compressor power demand.
A low pressure Deethanizer that eliminates the need for feed pumps.
A low pressure Product Splitter integrated with the propylene refrigeration system.
EPNRegen. Gas Return
HR15.101 (Charge Heater) Tail Gas
Cooled Offgas Deethanizer Vent
Propylene
Product
Fuel Gas (used internally)
Hydrogen Byproduct Feed
porization
um Botm
s
D il
Reactor Efluent
Recycle Propane
Reflux
Product Splitter ovhdPROPYLENE
REFRIGERATION SYSTEM
DW 37.101 (Waste Heat Boiler)
Import Fuel Gas
Import Fuel Gas
Reduction Gas
FEEDVAPORIZATION /
PREHEAT REACTORS PRODUCT PURIFICATION
REGENERATIONGAS SYSTEM
PSA UNIT
Fresh PropaneFeed
EPN
EPN
Regen Air
Fuel Gas (used internally)
EPN
GT26.101A/B Gas Turbine Bypass Stacks
Note: Import fuel gas may be either natural gas or ethane.
Propane Dehydrogenation Unit Mont Belvieu , TX
Figure 4‐1 Block Flow Diagram ‐ Overall Process
411 N. Sam Houston Parkway E. Suite 400,
Houston, Texas, 77060
SK25.801
Vap
Dru Deoiler
Overhead
SUPPORT FACILITIES
C4+ Products C4+ RECOVERY
Steam to Process
B010.103BB010.103A
Fuel Gas
Water Makeup/Return
AUXILIARY BOILERS
EPN EPN CT13.801
Water Return
Water to Exchangers
COOLING TOWER
EPN EPN
Misc. Vents from Process
PROCESS FLARE
Natural Gas
4‐2
Bypass Vents
Fuel Gas
Steam
Exhaust
Fuel Gas
Air
Air, VOC, CO
Fuel Gas
Air
GAS TURBINES GT26.101A GT26.101B
REGENERATION AIR HEATER HR15.102
REACTOR EVAC EJECTOR EXHAUST
REACTORS
DW37.101EPN
STEAMHEADER TO PROCESS
BFW TO Users
EPN
WASTE BOILER
Note: Fuel gas may be natural gas, ethane, or process offgas.
Propane Dehydrogenation Unit Mont Belvieu , TX
Figure 4‐2 Waste Heat Boiler Block Flow Diagram
411 N. Sam Houston Parkway E. Suite 400,
Houston, Texas, 77060
Boiler Feed Water(BFW)
Air, VOC
VOC REMOVAL BED No. 1 (Oxidation Catalyst)
Stack
WHB DUCT BURNER BO10.101
VOC REMOVAL BED No.2 (Oxidation Catalyst)
NH3
SCR CATALYST
CONDENSATE
4‐3
5-1
Section 5 Emission Rate Basis This section contains a description of the increases in GHG emissions from the proposed
facilities associated with the project. GHG emission calculations methods are also described,
and the resulting GHG emission rates are presented in Table 5-1 for each emission point.
Emissions calculations are included in Appendix A.
5.1 Combustion Units
The emissions calculations presented in Table A-1 of Appendix A identify all fuels that could
potentially be fired in each combustion unit. However, the emissions calculations are based on
firing the primary fuel for each unit, with all available Deethanizer Offgas and PSA Tail Gas
fired, and the balance of the fuel requirements made up by ethane and natural gas. Because
these fuels have different CO2 emission factors, the actual annual emission rate from each unit
will depend on the amount of each fuel fired. The maximum individual unit emission rates
shown in Table 5-1 are based on firing all available “worst case” fuel in each unit. As a result,
the sum of the individual unit emission limits exceeds the total emissions that are possible from
the plant as a whole. Thus, in addition to the individual emission limits, Enterprise is proposing
overall combustion unit caps for each GHG pollutant and total CO2e. This caps, calculated in
Table A-1, include all GHGs and CO2e from the Reactor Charge Heater, the WHB Stack (WHB
includes Gas Turbines, Regeneration Air Heater, Reactor VOC, Coke Burn, and WHB Duct
Burners), and the Auxiliary Boilers.
5.1.1 Reactor Charge Heater
The Reactor Charge Heater (HR15.101) will be fired primarily with Deethanizer Offgas. The
heater will also be capable of burning ethane and natural gas. Under normal conditions,
sufficient Deethanizer Offgas will be generated within the process to provide all required fuel for
the heater. Deethanizer Offgas and ethane result in higher CO2 emissions than natural gas;
therefore, the GHG emissions calculations for this unit are based on firing Deethanizer Offgas.
As can be seen from the emission factors presented in Table A-1 of Appendix A, Deethanizer
Offgas and ethane, have virtually identical GHG emission factors (lb/mmBtu basis). Annual
GHG emissions were calculated based on the maximum fuel firing rate of the heater occurring
continuously (8,760 hr/yr) all year. CO2 emissions were calculated based on the carbon content
of the Deethanizer Offgas using Equation C-5 in 40 CFR Part 98, Subpart C. Emissions of CH4
5-2
and N2O were calculated from emission factors from Table C-2 of Appendix A to 40 CFR Part
98, Subpart C.
5.1.2 Waste Heat Boiler (WHB)
Several facilities will contribute GHG emissions to the WHB. These include the Regeneration
Air Heater (HR15.102) combustion products, VOC from the Reactors that is converted to CO2
by oxidation catalyst beds, carbon from decoking of the reactor catalysts that is converted to
CO2 by the oxidation catalyst beds, Regeneration Air Gas Turbine (GT26.101A and GT26.101B)
combustion products, and WHB Duct Burners (HR15.103) combustion products. The
Regeneration Air Heater will primarily burn PSA Tail Gas and ethane or natural gas, but will also
be capable of burning Deethanizer Offgas. The Gas Turbines will be fired exclusively with
natural gas, and the WHB Duct Burners will be fired primarily with natural gas and ethane but
will be capable of firing Deethanizer Offgas and PSA Tail Gas. LTRU Offgas can be burned in
the Regeneration Air Heater and WHB Duct Burners; however, this only occurs when the PSA
Unit down, which is an upset condition. LTRU Offgas is primarily hydrogen, which results in
less emissions than other fuels. Under normal operating conditions, this stream is the feed to
the PSA Unit. For these reasons, none of the emission limits are based on combusting LTRU
Offgas. The calculations of the emissions from each facility that will exhaust through the WHB
Stack are described below.
5.1.2.1 Combustion Turbines
There will be two combustion turbines constructed for the project, (GT26.101A and GT26.101B).
The turbines will be used to compress the air used for reactor regenerations. Natural gas will be
the only fuel fired in the combustion turbines. Annual GHG emissions were calculated based on
the projected annual average fuel firing rate of each turbine. CO2 emissions were calculated
based on the carbon content of the natural gas using Equation C-5 in 40 CFR Part 98, Subpart
C. Emissions of CH4 and N2O were calculated from emission factors from Table C-2 of
Appendix A to 40 CFR Part 98, Subpart C.
5.1.2.2 Regeneration Air Heater
The Regeneration Air Heater (HR15.102) will normally be fired with all available PSA offgas with
the remainder of the heat input from either ethane or natural gas. Deethanizer Offgas may also
be fired in the heater. Annual GHG emissions were calculated based on the projected annual
5-3
average fuel firing rate of the heater. The emissions are base on burning all available PSA Tail
Gas and the balance of the fuel being Deethanizer Offgas and Ethane. CO2 emissions were
calculated based on the carbon content of each fuel using Equation C-5 in 40 CFR Part 98,
Subpart C. Emissions of CH4 and N2O were calculated from emission factors from Table C-2 of
Appendix A to 40 CFR Part 98, Subpart C.
5.1.2.3 WHB Duct Burner
The WHB will include a supplemenatally fired duct burner (HR15.103) that will be fired as
needed to provide for plant steam requirements. The duct burner will be fired primarily with
ethane or natural gas, but will also be capable of firing Deethanizer Offgas and PSA Tail Gas.
Maximum emissions occur from firing Deethanizer Offgas and/or ethane; therefore, the
emission limits were calculated based on firing Deethanizer Offgas. Annual GHG emissions
were calculated based on the projected annual average firing rate of the duct burner. CO2
emissions were calculated based on the carbon content of the fuels using Equation C-5 in 40
CFR Part 98, Subpart C. Emissions of CH4 and N2O were calculated from emission factors
from Table C-2 of Appendix A to 40 CFR Part 98, Subpart C.
5.1.2.4 Reactor Air Effluent and Ejector
VOC from the reactors is carried over in the Regeneration Air that enters the WHB. This VOC is
treated in a catalytic oxidation bed that converts the VOC to CO2. The catalytic oxidation bed
will be designed with a VOC destruction efficiency of at least 98.2%. CO2 emissions were
conservatively calculated assuming 100% destruction (conversion to CO2). Stoichiometrically,
production of CO2 from the oxidation of the VOC in the oxidation catalyst bed is identical to the
production of CO2 from combustion of carbon fuels. Therefore, CO2 emissions were calculated
based on the carbon content of the VOC using Equation C-5 in 40 CFR Part 98, Subpart C.
5.1.2.5 Decoke
CO2 emissions will be produced during periodic oxidation of the coke that builds up on the
catalyst. The emission rate is based on an estimate from the engineering design firm for the
project. These emissions are part of the Reactor Regeneration Effluent that is a contributor to
the combined WHB stack exhaust.
5-4
5.1.3 Auxiliary Boilers
The two Auxiliary Boilers (BO10.103A and BO10.103B) will normally operate at a very low
standby rate and will only be fully fired to provide steam when the primary units are down. The
Auxiliary Boilers will be fired primarily with ethane or natural gas, but will also be capable of
firing Deethanizer Offgas and PSA Tail Gas. Maximum emissions occur from firing Deethanizer
Offgas and/or ethane; therefore, the emission limits were calculated based on firing Deethanizer
Offgas. Annual GHG emissions were calculated based on firing the boilers at full load for 310
hour/yr each and at standby rates for the remainder of the year. CO2 emissions were calculated
based on the carbon content of the fuels using Equation C-5 in 40 CFR Part 98, Subpart C.
Emissions of CH4 and N2O were calculated from emission factors from Table C-2 of Appendix A
to 40 CFR Part 98, Subpart C.
5.1.4 Combustion Unit Emissions Caps
The combustion unit emissions caps which include all emissions from the facilities described
above were calculated based on the total combined annual heat input of all units. The
calculations of the caps are shown in Table A-1. The firing rates of each fuel used to provide
the total plant heat input were based on firing all produced Deethanizer Offgas and PSA Tail
Gas, firing natural gas in the combustion turbines, and the balance of the heat input being
provided by ethane. CO2 emissions were then calculated based on the carbon content of each
fuel using Equation C-5 in 40 CFR Part 98, Chapter C. Emissions of CH4 and N2O were
calculated from emission factors from Table C-2 of Appendix A to 40 CFR Part 98, Subpart C.
The CO2 from decoking and the oxidation of the Reactor VOC calculated as described in
Sections 5.1.2.4 and 5.1.2.5 were also added to the cap since this CO2 will be emitted through
the WHB Stack.
5.2 Flare Emissions
The new PDH Unit will have process vents that will be routed to a new flare (SK25.801) for
control. These process streams contain VOCs that when combusted by the flare produce CO2
emissions. Natural gas used as assist gas to maintain the minimum heating value required for
complete combustion also contains hydrocarbons, primarily methane, that also produce CO2
emissions when burned. Any unburned methane from the flare will also be emitted to the
atmosphere, and small quantities of N2O emissions can result from the combustion process.
Emissions of these pollutants were calculated based on the carbon content of the waste
streams sent to the flare and of the natural gas used for assist with the same equations and
5-5
emission factors from 40 CFR Part 98 that were used for the gas fired heaters. These
equations and factors were applied to the maximum projected annual waste gas and natural gas
flow rates to the flare. The calculations are shown in Table A-3.
5.3 Process Fugitive Emissions
Fugitive (equipment leak) emissions of methane will occur from the new natural gas and
process gas piping components (FUG-NGAS and FUG-PDH). The 28LAER leak detection and
repair (LDAR) program will be applied to the new VOC components associated with the PDH
Project. In addition, all flanges and connectors will be monitored quarterly using the same leak
detection level used for valves. All emissions calculations utilize current TCEQ factors and
methods in the TCEQ’s Air Permit Technical Guidance for Chemical Sources: Equipment Leak
Fugitives, October 2000. Each fugitive component was classified first by equipment type (valve,
pump, relief valve, etc.) and then by material type (gas/vapor, light liquid, heavy liquid).
Uncontrolled emission rates were obtained by multiplying the number of fugitive components of
a particular equipment/material type by the appropriate SOCMI emission factor. To obtain
controlled fugitive emission rates, the uncontrolled rates were multiplied by a control factor,
which was determined by the 28LAER LDAR program. The methane emissions were then
calculated by multiplying the total controlled emission rate by the weight percent of methane in
the natural gas and process gas. The calculations are shown in Table A-4.
5.4 Diesel Engines
There will be two diesel fired engines (PM18.803 and PM18.850C) used for emergency
purposes only. The engines will be used to drive fire water and raw water pumps. The
permitted emissions are based only on firing of the engines as required for scheduled testing to
insure operability, which will not exceed 52 hours per year each. Emissions were calculated
from emission factors for No. 2 distillate fuel in Tables C-1 and C-2 of Appendix A to 40 CFR
Part 98, Subpart C. The calculations are shown in Table A-5.
EPN
CO2
Emission Rate (tpy)
CH4
Emission Rate (tpy)
N2O Emission Rate (tpy)
CO2e Emission Rate (tpy)
HR15.101 Reactor Charge Heater 280,168 12.99 2.54 281,229
DW37.101 Waste Heat Boiler Burner 19,522 0.98 0.20 19,603
Regeneration Air Heater 650,704 23.89 4.25 652,523
Regen Air Comp. Gas Turbine A 124,897 2.32 0.23 125,018
Regen Air Comp. Gas Turbine B 124,897 2.32 0.23 125,018
VOC from Reactors 5,580 - - 5,580
Coke Burn 60,000 - - 60,000
BO10.103A Auxiliary Boiler A
BO10.103B Auxiliary Boiler B1,276,248 64.31 12.86 1,281,586
FUG-PDH Process Fugitives - 0.25 - 5
FUG-NGAS Nat. Gas Pipeline Fugitives - 13.04 - 274
SK25.801 Process Flare, Routine 2,818 0.04 0.01 2,821
Process Flare, MSS 4,426 0.16 0.03 4,439
PM18.803 Fire Water Pump Engine 16 0.0007 0.0001 16
PM18.850C Raw Water Pump Engine 8 0.0003 0.0001 8 1,283,517 77.79 12.90 1,289,149
Table 5-1 Proposed GHG Emission Limits
Description
Total GHG Emissions
16,389
Combustion Unit Cap
16,321 0.82 0.16
Individual Combustion Unit Limits
Other
5-6
6-1
Section 6 Best Available Control Technology
PSD regulations require that the best available control technology (BACT) be applied to each
new and modified facility that emits an air pollutant for which a significant net emissions
increase will occur from the source. The only PSD pollutant addressed in this permit application
is GHG. The new facilities associated with the project that emit GHGs include the following:
Reactor Charge Heater (HR15.101)
Regeneration Air Heater (HR15.102)
Waste Heat Boiler Duct Burner (HR15.103)
Two Combustion Turbines (GT26 101A and GT26 101A B),
Two Auxiliary Boilers (BO10.103A and BO10.103B)
Process Fugitives (FUG-PDH and FUG-NGAS)
Process Flare (SK25.801)
Two Emergency Use Diesel Engines (PM18.803 and PM18.850C).
BACT applies to each of these new sources of GHG emissions.
The U.S. EPA-preferred methodology for a BACT analysis for pollutants and facilities subject to
PSD review is described in a 1987 EPA memo (U.S. EPA, Office of Air and Radiation
Memorandum from J.C. Potter to the Regional Administrators, December 1, 1987). This
methodology is to determine, for the emission source in question, the most stringent control
available for a similar or identical source or source category. If it can be shown that this level of
control is technically or economically infeasible for the source in question, then the next most
stringent level of control is determined and similarly evaluated. This process continues until the
BACT level under consideration cannot be eliminated by any substantial or unique technical,
environmental, or economic objections. In addition, a control technology must be analyzed only
if the applicant opposes that level of control.
In an October 1990 draft guidance document (New Source Review Workshop Manual (Draft),
October 1990), EPA set out a 5-step process for conducting a top-down BACT review, as
follows:
1) Identification of available control technologies;
2) Technically infeasible alternatives are eliminated from consideration;
6-2
3) Remaining control technologies are ranked by control effectiveness;
4) Evaluation of control technologies for cost-effectiveness, energy impacts, and environmental effects in order of most effective control option to least effective; and
5) Selection of BACT.
In its PSD and Title V Permitting Guidance for Greenhouse Gases (March 2011), EPA
reiterates that this is also the recommended process for permitting of GHG emissions under the
PSD program. As such, this BACT analysis follows the top-down approach.
6.1 Reactor Charge Heater
6.1.1 Step 1 – Identification of Potential Control Technologies
To maximize thermal efficiency at the Mont Belvieu Complex, the proposed heaters will be
designed to achieve high thermal efficiencies, which minimize GHG emissions. The Reactor
Charge Heater will be designed to achieve a 90% thermal efficiency. These and other
potentially applicable technologies to minimize GHG emissions from the heater include the
following:
Periodic Tune-up – Periodically tune-up of the heater to maintain optimal thermal efficiency.
Heater Design – Good heater design to maximize thermal efficiency,
Heater Air/Fuel Control – Monitoring of oxygen concentration in the flue gas to be used to control excess air on a continuous basis for optimal efficiency.
Waste Heat Recovery – Use of heat recovery from the heater exhaust to preheat the heater combustion air or other streams.
Use of Low Carbon Fuels – Fuels vary in the amount of carbon per btu, which in turn affects the quantity of CO2 emissions generated per unit of heat input. Selecting low carbon fuels is a viable method of reducing GHG emissions.
CO2 Capture and Storage – Capture and compression, transport, and geologic storage of the CO2.
A RACT/BACT/LAER Clearinghouse (RBLC) search was also conducted in an attempt to
identify BACT options that have been implemented or proposed for other similar gas fired
combustion facilities. The results of this search are presented in Appendix B. No additional
technologies were identified. The control methods identified in the search were limited to the
first three options listed above (tune-ups, good design, and good combustion control and
operation). Information from Energy Efficiency Improvement and Cost Saving Opportunities for
the Petrochemical Industry: An ENERGY STAR Guide for Energy Plant Managers
6-3
(Environmental Energy Technologies Division, University of California, sponsored by USEPA,
June 2008) was also used in the preparation of this analysis.
6.1.2 Step 2 – Elimination of Technically Infeasible Alternatives
All options identified in Step 1 are considered technically feasible. Carbon capture and
sequestration (CCS) is not considered to be a viable alternative for controlling GHG emissions
from gas fired facilities. However, for completeness, this control option is included in the
remainder of this analysis, and the reasons that it is not considered viable are discussed in
Section 6.1.4.
6.1.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
The remaining technologies applicable to the proposed heater design in order of most effective
to least effective include:
Use of low carbon fuels (up to 100% for fuels containing no carbon),
CO2 capture and storage (up to 90%),
Heater Design (up to 10%),
Air and Fuel Control (5 - 25%),
Periodic tune-up (up to 10% for boilers; information not found for heaters), and
Waste heat recovery (variable).
Virtually all GHG emissions from fuel combustion result from the conversion of the carbon in the
fuel to CO2. Fuels used in industrial processes and power generation typically include coal, fuel
oil, natural gas, and process fuel gas. Of these, natural gas is typically the lowest carbon fuel
that can be burned, with a CO2 emission factor in lb/mmbtu about 55% of that of sub bituminous
coal. Process fuel gas is a byproduct of chemical process, which typically contains a higher
fraction of longer chain carbon compounds than natural gas and thus results in more CO2
emissions. Table C-2 in 40 CFR Part 98 Subpart C, which contains CO2 emission factors for a
variety of fuels, gives a CO2 factor of 59 kg/MMBtu for fuel gas compared to 53.02 kg/MMBtu for
natural gas. Of over 50 fuels identified in Table C-2, coke oven gas, with a CO2 factor of 46.85
kg/MMBtu, is the only fuel with a lower CO2 factor than natural gas, and is not viable fuel for the
proposed heaters, as the Mount Belvieu Complex does not contain coke ovens. Although Table
C-2 includes a typical CO2 factor of 59 kg/MMBtu for fuel gas, fuel gas composition is highly
dependent on the process from which the gas is produced. Some processes produce
significant quantities of hydrogen, which produces no CO2 emissions when burned. Thus, use
6-4
of a completely carbon-free fuel such as 100% hydrogen, has the potential of reducing CO2
emissions by 100%.
CO2 capture and storage is capable of achieving 90% reduction of produced CO2 emissions and
thus is considered to be the most effective control method.
Good heater design, air and fuel control, and periodic tune-ups are all considered effective and
have a range of efficiency improvements which cannot be directly quantified; therefore, the
above ranking is approximate only. The estimated efficiencies were obtained from Energy
Efficiency Improvement and Cost Saving Opportunities for the Petrochemical Industry: An
ENERGY STAR Guide for Energy Plant Managers (Environmental Energy Technologies
Division, University of California, sponsored by USEPA, June 2008). This report addressed
improvements to existing energy systems as well as new equipment; thus, the higher end of the
range of stated efficiency improvements that can be realized is assumed to apply to the existing
(older) facilities, with the lower end of the range being more applicable to new heater designs.
Heat recovery involves the use of heat exchangers to transfer the excess heat that may be
contained in one process or product stream to pre-heat another stream. Pre-heating of feed
streams in this manner reduces the heat requirement of the downstream process unit (e.g., a
distillation column) which reduces the heat required from process heaters. Where the product
streams require cooling, this practice also reduces the energy required to cool the product
stream. The Charge Heater will be designed for 90% thermal efficiency, and additional heat
recovery is not practical. However, heat exchange coils will be included in the convection
section to pre-heat Waste Heat Boiler feedwater.
6.1.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Carbon Capture and Sequestration. As stated in Section 6.1.2, carbon capture and sequestration
(CCS) is not considered to be a viable alternative for controlling GHG emissions from gas fired
facilities. This conclusion is supported by the BACT example for a natural gas fired boiler in Appendix
F of EPA’s PSD and Title V Permitting Guidance for Greenhouse Gases (March 2011). In the EPA
example, CCS is not even identified as an available control option for natural gas fired facilities. Also,
on pages 33 and 44 of the Guidance Document, it states:
“For the purposes of a BACT analysis for GHGs, EPA classifies CCS as an add-on pollution control
technology that is available for large CO2-emitting facilities including fossil fuel-fired power plants and
6-5
industrial facilities with high-purity CO2 streams (e.g., hydrogen production, ammonia production,
natural gas processing, ethanol production, ethylene oxide production, cement production, and iron
and steel manufacturing). For these types of facilities, CCS should be listed in Step 1 of a top-down
BACT analysis for GHGs.”
The CO2 streams included in this permit application are similar in nature to the gas-fired industrial
boiler in the EPA Guidance Appendix F example and are dilute streams, and thus are not among the
facility types for which the EPA guidance states CCS should be listed in Step 1. Although the
proposed facility is not one of the listed facility types for which CCS should be considered, it was
further evaluated for the project to ensure that the analysis was complete.
Enterprise has performed an order of magnitude cost analysis for CCS applied to the combustion
units addressed in this permit application. The results of the analysis, presented in Table 6-1, show
that the cost of CCS for the project would be approximately $104 per ton of CO2 controlled, which is
not considered to be cost effective for GHG control. This equates to a total cost of about
$119,000,000 per year all combustion units included at the proposed plant. The estimated total
capital cost of the PDH unit is $1,300,000,000. Based on a 7% interest rate, and 20 year equipment
life, this cost equates to an annualized cost of about $123,000,000. Thus, the annualized cost of
CCS would be about the same as the cost of the PDH plant alone; which far exceeds the threshold
that would make CCS economically viable for the project.
There are additional negative impacts associated with use of CCS for the facilities. The additional
process equipment required to separate, cool, and compress the CO2 would require a significant
additional power and energy expenditure. This equipment would include amine units, cryogenic units,
dehydration units, and compression facilities. The power and energy must be provided from
additional combustion units, including heaters, engines, and/or combustion turbines. Electric driven
compressors could be used to partially eliminate additional emissions from the Mont Belvieu
Complex, but significant additional GHG emissions, as well as additional criteria pollutant (NOx, CO,
VOC, PM, SO2) emissions, would occur from the associated power plant that produces the electricity.
The additional GHG emissions resulting from additional fuel combustion would either further increase
the cost of the CCS system if the emissions were also captured for sequestration or reduce the net
amount GHG emission reduction, making CCS even less cost effective than shown in Table 6-1.
6-6
Based on both the excessive cost effectiveness in $/ton of GHG emissions controlled and the inability
of the project to bear the high cost and the associated negative environmental and energy impacts,
CCS is rejected as a control option for the proposed project.
Heater Design. New heaters can be designed with efficient burners, more efficient heat transfer,
state-of-the-art refractory and insulation materials in the heater walls, floor, and other surfaces to
minimize heat loss and increase overall thermal efficiency. The function and near steady state
operation of the heater allows them to be designed to achieve “near best” thermal efficiency.
Air and Fuel Controls. Some amount of excess air is required to ensure complete fuel combustion,
minimize emissions, and for safety reasons. More excess air than needed to achieve these
objectives reduces overall heater efficiency. Manual or automated air fuel controls are used to
optimize these parameters and maximize the efficiency of the combustion process.
Periodic Heater Tune-ups. Periodic tune-ups of the heater include:
Preventive maintenance check of fuel gas flow meters annually,
Preventive maintenance check of excess oxygen analyzers quarterly,
Cleaning of burner tips on an as-needed basis, and
Cleaning of convection section tubes on an as-needed basis.
These activities insure maximum thermal efficiency is maintained; however, it is not possible to
quantify an efficiency improvement, although convection cleaning has shown improvements in
the 0.5 to 1.5% range.
Use of Low Carbon Fuel. Several low carbon fuels are potentially available for use in the PDH
plant combustion units. The discussion below applies to all combustion units within the
proposed PDH Unit.
Hydrogen. Hydrogen is a byproduct of the proposed PDH process. The PDH Unit will include
a PSA Unit that will purify the hydrogen byproduct. Enterprise’s business plan calls for selling
the hydrogen as a product; therefore, it is not available for use as a fuel at the plant. The most
common industrial use of hydrogen in the Gulf Coast area is for the desulfurization of crude oil
in petroleum refineries. Hydrogen for this use is typically produced at refineries in steam
methane reformers (SMR), which produce hydrogen from methane, producing a large CO2
stream that is exhausted to the atmosphere. Thus, the hydrogen product from the proposed
PDH Unit will displace an equivalent amount of hydrogen production from refinery SMRs,
6-7
eliminating the associated CO2 emissions. Thus, although using the hydrogen byproduct as fuel
within the PDH Unit would reduce CO2 emissions from the proposed plant, there would be a
corresponding increase in CO2 emissions from the production of hydrogen elsewhere, resulting
in no net “global” reduction of CO2 emissions. Unlike criteria pollutants, GHG emission impacts
are “global,” and there is no benefit in simply displacing the emissions to another location. For
this reason together with Enterprise’s business plan to produce hydrogen as a marketable
product, use of the hydrogen byproduct as a fuel at the PDH Unit is not considered to be a
viable option for reducing global CO2 emissions.
PSA Tail Gas. Tail Gas from the PSA Unit will contain a significant fraction (about 60% by
volume) of hydrogen. The CO2e emission factor for this Tail Gas will average about 96
lb/mmBtu, compared to about 118 lb/mmBtu for the natural gas that is available for use at the
plant. About 2,200,000 mmBtu/yr of PSA Tail gas will be produced at the PDH plant capacity.
This corresponds to a potential reduction in CO2e emissions of about 23,000 tpy compared to
firing an equivalent amount of natural gas.
Deethanizer Offgas. Deethanizer Offgas will also be produced in the PDH Unit. This process
gas, which is primarily ethane and ethylene, has a CO2e emission factor of about 131 lb/mmBtu,
which is only about 11% higher than natural gas. Thus this fuel is also considered a low carbon
fuel when compared to liquid and solid fuels. If this offgas is not burned as fuel at the PDH Unit,
the only other alternative means of disposal is destruction in a flare, which would result in the
same amount of CO2e emissions in addition to the CO2e emissions from the natural gas that
would replace it as a fuel. As such, use of the Deethanizer Offgas as fuel is an effective means
of reducing overall plant GHG emissions compared to the alternative of flaring the gas.
Ethane. Ethane is also an available fuel for the PDH Unit. There is currently an over-
abundance of ethane being produced from natural gas production facilities. Some of this
ethane can be used as feedstock to ethylene plants, but excess ethane still exists. The
alternatives for use or disposal of this excess ethane include flaring it, removing less of it from
natural gas, and using it as a fuel source at industrial facilities (such as the proposed PDH Unit).
All of these alternatives result in the same amount of CO2 emissions when the ethane is
ultimately burned. Flaring is the least desirable alternative as no heat benefit is gained, and
there would be additional CO2 emissions from combustion of the natural gas that it would
otherwise replace. Ethane has a CO2e emission factor of about 118 lb/mmBtu, which is about
the same as the Deethanizer Offgas that will be produced in the PDH Unit. Thus, using excess
6-8
ethane available on the market as fuel in place of natural gas results in only about 11% more
CO2e emissions from the plant compared to an equivalent amount of natural gas, and no net
increase in global CO2e emissions. Ethane is also a very clean burning fuel with respect to
criteria pollutants and thus has minimal environmental impact compared to other fuels.
Natural Gas. Other than PSA Tail Gas, natural gas is the lowest carbon fuel available for use
in the proposed heater. Natural gas is readily available at the Mont Belvieu Complex and is
currently considered a very cost effective fuel alternative. Natural gas is also a very clean
burning fuel with respect to criteria pollutants and thus has minimal environmental impact
compared to other fuels.
6.1.5 Step 5 – Selection of BACT
Air and fuel controls, efficient heater design, and tune-ups performed as needed are currently
utilized on existing heaters at the Mont Belvieu Complex to maximize efficiency and thus reduce
GHG emissions. These control practices are also included in the design of the Charge Heater
and are thus part of the selected BACT. These technologies and additional BACT practices
proposed for the Charge Heater are listed below:
Use of a combination of low carbon fuels. A combination of PSA Tail Gas, Deethanizer Offgas, ethane, and natural gas will be fired in the proposed PDH Unit combustion units. This will result in an overall CO2e emission rate of about 125 lb/mmBtu of fuel burned. This emission rate is comparable to burning 100% natural gas, and results in lower “global” CO2e emissions compared to burning 100% natural gas and disposing of the offgases by other methods.
Determine CO2e emissions from the Reactor Charge Heater based on metered fuel consumption and standard emission factors and/or fuel composition and mass balance.
Good heater design to maximize heat transfer efficiency to evenly heat the propane feed and reduce heat loss. Insulating material, such as ceramic fiber blankets of various thickness and density, will be used where feasible on all heater surfaces.
Demonstrate heater efficiencies by monitoring the exhaust temperature, fuel temperature, ambient temperature, and excess oxygen. Thermal efficiency will be calculated for each operating hour from these parameters using accepted API methods. Charge Heater efficiency of greater than 85% will be maintained on a 12-month rolling average basis, excluding malfunction and maintenance periods.
The heater will include heat exchange coils in the convection section to pre-heat the boiler feedwater used in the Waste Heat Boiler.
Install, utilize, and maintain an automated air and fuel control system to maximize combustion efficiency of the heater.
Clean heater burner tips and convection tubes as needed.
6-9
Calibrate and perform preventive maintenance on the fuel flow meter once per year and excess oxygen analyzer once per quarter.
6.2 Regeneration Air Heater
6.2.1 Step 1 – Identification of Potential Control Technologies
To maximize thermal efficiency at the Mont Belvieu Complex, the proposed heaters are
designed to achieve high thermal efficiencies, which minimize GHG emissions. The
Regeneration Air Heater will utilize duct burners, and the heater will be designed to maximize
thermal efficiency. These and other potentially applicable technologies to minimize GHG
emissions from the heater include the following:
Periodic Tune-up – Periodically tune-up of the heater to maintain optimal thermal efficiency.
Heater Design – Good heater design utilizing refractory to maximize thermal efficiency,
Waste Heat Recovery – Use of heat recovery from the heater exhaust and a waste heat boiler to produce steam for use at the site.
Use of Low Carbon Fuels – Use of low carbon fuels at the plant were addressed in Section 6.1 and are not addressed separately for the Regeneration Air Heater.
CO2 Capture and Storage – Capture and compression, transport, and geologic storage of the CO2 (This option is evaluated in detail in Section 6.1.4 for the plant as whole and was eliminated based on cost and is thus not addressed further in this section).
A RACT/BACT/LAER Clearinghouse (RBLC) search was also conducted in an attempt to
identify BACT options that have been implemented or proposed for other similar gas fired
combustion facilities. The results of this search are presented in Appendix B. No additional
technologies were identified. The control methods identified in the search were limited to the
first three options listed above (tune-ups, good design, and good combustion control and
operation). Information from Energy Efficiency Improvement and Cost Saving Opportunities for
the Petrochemical Industry: An ENERGY STAR Guide for Energy Plant Managers
(Environmental Energy Technologies Division, University of California, sponsored by USEPA,
June 2008) was also used in the preparation of this analysis.
6.2.2 Step 2 – Elimination of Technically Infeasible Alternatives
All options identified in Step 1 are considered technically feasible.
6-10
6.2.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
The remaining technologies applicable to the proposed heater design in order of most effective
to least effective include:
Waste heat recovery (variable),
Heater Design (up to 10%), and
Periodic tune-up (up to 10% for boilers; information not found for heaters).
Air is heated by the Regeneration Air Heater duct burners and used to regenerate the catalyst in
the reactors. The hot air from the reactors contains a large amount of usable heat energy, and
the proposed process is designed to recover and use this heat by routing the hot air through the
Waste Heat Boiler which provides the plant steam requirements. This is discussed in more
detail in Section 6.3.
Good heater design and periodic tune-ups are all considered effective and have a range of
efficiency improvements which cannot be directly quantified; therefore, the above ranking is
approximate only. The estimated efficiencies were obtained from Energy Efficiency
Improvement and Cost Saving Opportunities for the Petrochemical Industry: An ENERGY STAR
Guide for Energy Plant Managers (Environmental Energy Technologies Division, University of
California, sponsored by USEPA, June 2008). This report addressed improvements to existing
energy systems as well as new equipment; thus, the higher end of the range of stated efficiency
improvements that can be realized is assumed to apply to the existing (older) facilities, with the
lower end of the range being more applicable to new heater designs.
6.2.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Heater Design. New heaters can be designed with efficient burners, more efficient heat transfer,
state-of-the-art refractory and insulation materials in the heater walls, floor, and other surfaces to
minimize heat loss and increase overall thermal efficiency. The function and near steady state
operation of the heater allows it to be designed to achieve “near best” thermal efficiency.
Periodic Heater Tune-ups. Periodic tune-ups of the heater include:
Preventive maintenance check of fuel gas flow meters annually,
Preventive maintenance check of oxygen control analyzers quarterly,
Cleaning of burner tips on an as-needed basis, and
Cleaning of convection section tubes on an as-needed basis.
6-11
These activities insure maximum thermal efficiency is maintained; however, it is not possible to
quantify an efficiency improvement, although convection cleaning has shown improvements in
the 0.5 to 1.5% range.
6.2.5 Step 5 – Selection of BACT
Efficient heater design and tune-ups performed as needed are currently utilized on existing
heaters at the Mont Belvieu Complex to maximize efficiency and thus reduce GHG emissions.
These control practices are also included in the design of the Regeneration Air Heater and are
thus part of the selected BACT. These technologies and additional BACT practices proposed
for the heater are listed below:
Use of a combination of low carbon fuels. A combination of PSA Tail Gas, Deethanizer Offgas, ethane, and natural gas will be fired in the proposed PDH Unit combustion units, including the Regeneration Air Heater, to maintain a plantwide CO2e emission rate of about 125 lb/mmBtu.
Determine CO2e emissions from the Regeneration Air Heater based on metered fuel consumption and standard emission factors and/or fuel composition and mass balance.
Good heater design to maximize heat transfer efficiency and reduce heat loss. Insulating material, such as ceramic fiber blankets of various thickness and density, will be used where feasible on all heater surfaces.
Route hot spent regenerator air through Waste Heat Boiler to recover heat for steam production.
Install, utilize, and maintain an automated fuel control system to maximize combustion efficiency of the heater.
Clean heater burner tips as needed.
Calibrate and perform preventive maintenance on the fuel flow meter once per year.
6.3 Waste Heat Boiler
6.3.1 Step 1 – Identification of Potential Control Technologies
The Waste Heat Boiler (WHB) is the key heat energy efficiency feature of the proposed PDH
Unit design that will allow the plant to produce propylene with up to one-third less fuel
consumption than other production processes. The combustion products from the Regeneration
Air Heater and the Regeneration Air Compressor Combustion Turbines is routed through the
WHB to produce steam that is used internally in the PDH Unit. The WHB will include a gas-fired
duct burner that will be used for startup of the WHB and to provide supplemental heat as
6-12
needed to meet plant steam demand. These and other potentially applicable technologies to
minimize GHG emissions from the boilers include the following:
Good combustion practices via improved process controls.
Boiler Design – Good boiler design to maximize thermal efficiency,
Routine Boiler Maintenance - Periodically tune-up the boiler to maintain optimal thermal efficiency.
Waste Heat Recovery - The proposed boiler is a waste heat recovery unit that will obtain most of its required heat energy from waste heat.
Use of Low Carbon Fuels – Use of low carbon fuels at the plant were addressed in Section 6.1 and are not addressed separately for the WHB Duct Burners.
CO2 Capture and Storage – Capture and compression, transport, and geologic storage of the CO2 (This option is evaluated in detail in Section 6.1.4 for the plant as whole and was eliminated based on cost and is thus not addressed further in this section).
A RACT/BACT/LAER Clearinghouse (RBLC) search was also conducted in an attempt to
identify BACT options that have been implemented or proposed for other similar gas fired
combustion facilities. The results of this search are presented in Appendix B. No additional
technologies were identified. The control methods identified in the search were limited to the
first three options listed above (tune-ups, good design, and good combustion control and
operation). Information from Energy Efficiency Improvement and Cost Saving Opportunities for
the Petrochemical Industry: An ENERGY STAR Guide for Energy Plant Managers
(Environmental Energy Technologies Division, University of California, sponsored by USEPA,
June 2008) was also used in the preparation of this analysis.
6.3.2 Step 2 – Elimination of Technically Infeasible Alternatives
All options identified in Step 1 are considered technically feasible.
6.3.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
The remaining technologies applicable to the proposed boilers design in order of most effective
to least effective include:
Waste Heat Recovery has primary energy source (>90%),
Boiler Design (up to 26%), and
Routine planned maintenance tune-up (up to 10% ).
Hot exhaust from the regeneration of the reactors and from the Regeneration Air Compressor
Turbine exhaust contains sufficient waste heat to provide over 90% of the heat input normally
6-13
required for steam produced in the WHB and is thus considered the most effective means of
reducing GHG emissions by eliminating the combustion of fuel that would otherwise be
required.
Good boiler design and periodic tune-ups are all considered effective and have a range of
efficiency improvements which cannot be directly quantified; therefore, the above ranking is
approximate only. The estimated efficiencies were obtained from Energy Efficiency
Improvement and Cost Saving Opportunities for the Petrochemical Industry: An ENERGY STAR
Guide for Energy Plant Managers (Environmental Energy Technologies Division, University of
California, sponsored by USEPA, June 2008). This report addressed improvements to existing
energy systems as well as new equipment; thus, the higher end of the range of stated efficiency
improvements that can be realized is assumed to apply to the existing (older) facilities, with the
lower end of the range being more applicable to new boiler designs.
Heat recovery involves the use of economizers to transfer the excess heat from the boiler flue
gases to the boiler feed water streams. Pre-heating of boiler feed water stream in this manner
reduces the heat requirement of the boilers.
6.3.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Waste Heat Recovery. Rather than increasing boiler efficiency, this technology reduces potential
GHG emissions by reducing the required WHB duct burner firing rate, which can substantially reduce
overall plant energy requirements. Over 800 mmBtu/hr of waste heat energy from the Reactor
Regeneration Air Exhaust and Compressor Combustion Turbine Exhaust will be recovered in the
WHB and used to produce steam. On an annual average basis, the supplemental WHB duct burner
will only need to be fired at a rate of about 30 mmBtu/hr. Thus, over 95% of the heat energy required
for the PDH Unit steam demand will be provided from waste heat.
Boiler Design. New boilers can be designed with efficient burners, more efficient heat transfer,
state-of-the-art refractory and insulation materials in the boiler walls, floor, and other surfaces to
minimize heat loss and increase overall thermal efficiency. The function and near steady state
operation of the boilers allows them to be designed to achieve “near best” thermal efficiency.
Periodic Boiler Maintenance Tune-ups. Periodic tune-ups of the boilers include:
Preventive maintenance check of fuel gas flow meters annually,
6-14
Cleaning of burner tips on an as-needed basis, and
Cleaning of convection section tubes on an as-needed basis.
These activities insure maximum thermal efficiency is maintained; however, it is not possible to
quantify an efficiency improvement, although convection cleaning has shown improvements in
the 0.5 to 1.5% range.
6.3.5 Step 5 – Selection of BACT
Use of the proposed WHB itself is the primary GHG BACT feature of the PDH Unit. Air/fuel
controls, efficient boiler design, and tune-ups performed as needed will also be included to
maximize efficiency and thus reduce GHG emissions. These technologies and additional BACT
practices proposed for the boilers are listed below:
Use of waste heat to provide over 95% of the WHB heat energy requirements.
Use of low carbon fuel. A combination of PSA Tail Gas, Deethanizer Offgas, ethane, and natural gas will be fired in the proposed PDH Unit combustion units, including the WHB Duct Burner, to maintain a plantwide CO2e emission rate of about 125 lb/mmBtu.
Determine CO2e emissions from the Waste Heat Boiler based on metered fuel consumption and standard emission factors and/or fuel composition and mass balance.
Good boiler design to maximize heat transfer efficiency and to reduce heat loss.
Install, utilize, and maintain an automated fuel control system to maximize combustion efficiency on the boilers.
Clean heater burner tips and convection tubes as needed.
Calibrate and perform preventive maintenance on the fuel flow meter once per year.
Use of boiler feedwater pre-heated by the economizer in the Reactor Charge Heater.
6.4 Auxiliary Boilers
6.4.1 Step 1 – Identification of Potential Control Technologies
The Auxiliary Boilers will be designed to maximize thermal efficiency and will be designed to
operate in a very low (about 3% of full load firing rate) standby rate when not in use. These and
other potentially applicable technologies to minimize GHG emissions from the boilers include
the following:
Good combustion practices that include; improved process controls, reducing flue gas quantities, and reducing excess air.
Boiler Design – Good boiler design to maximize thermal efficiency,
6-15
Low standby operation,
Routine boiler maintenance - Periodically tune-up of the boilers to maintain optimal thermal efficiency.
Use of Low Carbon Fuels – Use of low carbon fuels at the plant were addressed in Section 6.1 and are not addressed separately for the Auxiliary Boilers.
CO2 Capture and Storage – Capture and compression, transport, and geologic storage of the CO2 (This option is evaluated in detail in Section 6.1.4 for the plant as whole and was eliminated based on cost and is thus not addressed further in this section).
A RACT/BACT/LAER Clearinghouse (RBLC) search was also conducted in an attempt to
identify BACT options that have been implemented or proposed for other similar gas fired
combustion facilities. The results of this search are presented in Appendix B. No additional
technologies were identified. The control methods identified in the search were limited to the
first three options listed above (tune-ups, good design, and good combustion control and
operation). Information from Energy Efficiency Improvement and Cost Saving Opportunities for
the Petrochemical Industry: An ENERGY STAR Guide for Energy Plant Managers
(Environmental Energy Technologies Division, University of California, sponsored by USEPA,
June 2008) was also used in the preparation of this analysis.
6.4.2 Step 2 – Elimination of Technically Infeasible Alternatives
All options identified in Step 1 are considered technically feasible.
The two auxiliary boilers, although of a size sufficient enough to consider use of a carbon
capture and sequestration (CCS) system, will only be in operation for short periods of time
during the year as backup boilers to the waste heat boiler. This makes the carbon capture and
sequestration process not technically feasible for the two auxiliary boilers. A cost analysis for
use of CCS at the proposed plant, included in Section 6.1, has also shown that CCS is not cost
effective.
6.4.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
The remaining technologies applicable to the proposed boilers design in order of most effective
to least effective include:
Low Standby Operating Rate,
Boiler Design (up to 26%),
Air and Fuel Control (1% improvement for each 15% less excess air),
Routine planned maintenance tune-up (up to 10%).
6-16
The Auxiliary Boilers are projected to be needed for full use less than 4% (310 hr/yr) of the time;
however, they must be kept in a hot standby condition to allow them to be brought on line
quickly when needed. As such, the potential exists for the majority of the fuel consumption and
resulting GHG emissions to occur from standby operation. As such, designing the boilers to
operate at a very low standby firing rate is considered the most effective means of reducing
GHG emissions.
Good boiler design, excess oxygen control, and periodic tune-ups are all considered effective
and have a range of efficiency improvements which cannot be directly quantified; therefore, the
above ranking is approximate only. Due to the very low expected usage rate, typical energy
efficiency features used in boiler designs have minimal benefit for the proposed boilers.
6.4.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Low Standby Operating Rate. Minimizing the standby firing rate to the maximum extent possible is
the most effective means of controlling GHG emissions as this operating mode will occur over 96% of
the time. There are no adverse environmental or economic impacts associated with this practice.
Boiler Design. New boilers can be designed with efficient burners, more efficient heat transfer,
state-of-the-art refractory and insulation materials in the boiler walls, floor, and other surfaces to
minimize heat loss and increase overall thermal efficiency. The function and near steady state
operation of the boilers allows them to be designed to achieve “near best” thermal efficiency.
Air and Fuel Controls. Some amount of excess air is required to ensure complete fuel combustion,
minimize emissions, and for safety reasons. More excess air than needed to achieve these
objectives reduces overall heater efficiency. Manual or automated air and fuel controls are used to
optimizes these parameters and maximize the efficiency of the combustion process.
Periodic Boiler Maintenance Tune-ups. Periodic tune-ups of the boilers include:
Preventive maintenance check of fuel gas flow meters annually,
Preventive maintenance check of excess oxygen analyzers quarterly,
Cleaning of burner tips on an as-needed basis, and
Cleaning of convection section tubes on an as-needed basis.
6-17
These activities insure maximum thermal efficiency is maintained; however, it is not possible to
quantify an efficiency improvement, although convection cleaning has shown improvements in
the 0.5 to 1.5% range.
6.4.5 Step 5 – Selection of BACT
Designing the burners to operate at a low standby firing rate is proposed as the primary GHG
BACT method for the Auxiliary Boilers. Air and uel controls and efficient boiler design, and
tune-ups performed as needed are currently utilized on the existing fired equipment at the Mont
Belvieu Complex to maximize efficiency and thus reduce GHG emissions. These control
practices are also included in the design of the new boilers and are thus part of the selected
BACT. These technologies and additional BACT practices proposed for the boilers are listed
below:
The boilers will be designed to be operated at a standby firing rate of 14 mmBtu/hr each, which is about 3.3% of the boiler capacities. Although standby operation will constitute over 96% of the operating hours, the low firing rate will result in total annual standby fuel usage and GHG emissions that are less than the total annual fuel usage and GHG emissions from full load operation.
Use of low carbon fuel. A combination of PSA Tail Gas, Deethanizer Offgas, ethane, and natural gas will be fired in the proposed PDH Unit combustion units, including the Auxiliary Boilers, to maintain a plantwide CO2e emission rate of about 125 lb/mmBtu.
Determine CO2e emissions from the Auxiliary Boilers based on metered fuel consumption and standard emission factors and/or fuel composition and mass balance.
Good boiler design to maximize heat transfer efficiency and to reduce heat loss.
Install, utilize, and maintain an automated airand fuel control system to maximize combustion efficiency on the boilers.
Clean heater burner tips and convection tubes as needed.
Calibrate and perform preventive maintenance on the fuel flow meter once per year and excess oxygen analyzers as needed.
6.5 Combustion Turbines
6.5.1 Step 1 – Identification of Potential Control Technologies
To maximize thermal efficiency at the Mont Belvieu Complex, the proposed natural gas fired
turbines are designed to achieve high thermal efficiencies, which minimize GHG emissions.
The proposed new gas turbines are designed to maximize thermal efficiency. In addition, as
described in Section 6.3, the turbines will exhaust into the WHB, where the heat in the exhaust
will be recovered to the maximum extent practical to produce steam. These and other
6-18
potentially applicable technologies to minimize GHG emissions from the gas turbines include
the following:
Good combustion practices via improved process controls and reducing excess air.
Turbine Design – Good design to maximize thermal efficiency,
Routine Maintenance - Periodically tune-up to maintain optimal combustion and thermal efficiency.
Waste Heat Recovery – Use of heat recovery from the turbine exhausts in the WHB to produce steam for use at the site.
Uses of low carbon fuels - Fuels vary in the amount of carbon per btu, which in turn affects the quantity of CO2 emissions generated per unit of heat input. Selecting low carbon fuels is a viable method of reducing GHG emissions.
CO2 Capture and Storage – Capture and compression, transport, and geologic storage of the CO2. (This option is evaluated in detail in Section 6.1.4 for the plant as whole and was eliminated based on cost and is thus not addressed further in this section).
A RACT/BACT/LAER Clearinghouse (RBLC) search was also conducted in an attempt to
identify BACT options that have been implemented or proposed for other similar gas fired
combustion facilities. The results of this search are presented in Appendix B. No additional
technologies were identified. The control methods identified in the search were limited to the
first three options listed above (tune-ups, good design, and good combustion control and
operation). Information from Energy Efficiency Improvement and Cost Saving Opportunities for
the Petrochemical Industry: An ENERGY STAR Guide for Energy Plant Managers
(Environmental Energy Technologies Division, University of California, sponsored by USEPA,
June 2008) was also used in the preparation of this analysis.
Waste heat recovery from the turbine exhaust is included in the process design and has been
addressed in Section 6.3 of the BACT analysis for the WHB and is not address further in this
section.
6.5.2 Step 2 – Elimination of Technically Infeasible Alternatives
All options identified in Step 1 are considered technically feasible.
6.5.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
The remaining technologies applicable to the proposed turbines in order of most effective to
least effective include:
Use of low carbon alternative fuels,
6-19
Turbine Design,
Good Combustion Practices,
Routine planned maintenance tune-up (up to 10%).
Natural gas is the lowest carbon fuel available for use in the proposed turbines. Use of other
gaseous fuels are not recommended by the turbine vendor.
Good turbine design, good combustion practices and periodic tune-ups are all considered
effective and have a range of efficiency improvements which cannot be directly quantified;
therefore, the above ranking is approximate only.
6.5.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Turbine Design. New turbines can be designed with efficient burners, more efficient heat transfer, to
increase overall thermal efficiency. The function and near steady state operation of the turbines
allows them to be designed to achieve “near best” thermal efficiency.
Good Combustion Practices. Some amount of excess air is required to ensure complete fuel
combustion, minimize emissions, and for safety reasons. More excess air than needed to achieve
these objectives reduces overall heater efficiency. Air to fuel ratios are tuned periodically to optimize
these parameters and maximize the efficiency of the combustion process.
Periodic Maintenance Tune-ups. Periodic tune-ups of the turbines include:
Preventive maintenance check of fuel gas flow meters annually,
Periodically tune the air flows, and
Cleaning of burner tips on an as-needed basis,
These activities insure maximum thermal efficiency is maintained; however, it is not possible to
quantify an efficiency improvement, although convection cleaning has shown improvements in
the 0.5 to 1.5% range.
Use of Low Carbon (Natural Gas) Fuel. Natural gas is the lowest carbon fuel available for use
in the proposed turbines. Natural gas is readily available at the Mont Belvieu Complex and is
currently considered a very cost effective fuel alternative. Natural gas is also a very clean
burning fuel with respect to criteria pollutants and thus has minimal environmental impact
compared to other fuels. Offgas and other fuels that will be used for the heaters and boilers are
6-20
not recommended by the turbine vendors, and turbine performance and criteria pollutant
emission limits cannot be guaranteed for fuels other than natural gas.
6.5.5 Step 5 – Selection of BACT
Good combustion practices, efficient boiler design, and tune-ups performed as needed are
currently utilized on the existing turbines at the Mont Belvieu Complex to maximize efficiency
and thus reduce GHG emissions. These control practices are also included in the design of the
new turbines and are thus part of the selected BACT. These technologies and additional BACT
practices proposed for the turbines are listed below:
Waste Heat Recovery. Recovering waste heat from the turbine exhaust to the maximum extent possible in the WHB to produce steam for use at the plant is a keep plant energy feature as described in Section 6.1
Use of low carbon fuel (natural gas). Natural gas will be the only fuel fired in the proposed turbines.
Determine CO2e emissions from the turbines based on metered fuel consumption and standard emission factors and/or fuel composition and mass balance.
Good turbine design to maximize heat transfer efficiency and to reduce heat loss.
Calibrate and perform preventive maintenance on the fuel flow meter once per year.
6.6 Flare
GHG emissions, primarily CO2, are generated from the combustion of waste gas streams from
the proposed units and assist natural gas used to maintain the required minimum heating value
to achieve adequate destruction.
6.6.1 Step 1 – Identification of Potential Control Technologies
The only viable control option for reducing GHG emissions from flaring is minimizing the
quantity of flared waste gas and natural gas to the extent possible. The technically viable
options for achieving this include:
Flaring minimization – minimize the duration and quantity of flaring to the extent possible through good engineering design of the process and good operating practice.
Proper operation of the flare – use of flow and composition monitors to accurately determine the optimum amount of natural gas required to maintain adequate VOC destruction in order to minimize natural gas combustion and the resulting CO2.
Use of a thermal oxidizer in lieu of a flare.
6-21
6.6.2 Step 2 – Elimination of Technically Infeasible Alternatives
Both flaring minimization and proper operation of the flare are considered technically feasible.
One of the primary reasons that a flare is considered for control of VOC in the process vent
streams is that it can also be used for emergency releases. Although every possible effort is
made to prevent such releases, they can occur, and the design must allow for them. A thermal
oxidizer is not capable of handling the sudden large volumes of vapor that could occur during an
upset release. A thermal oxidizer would also not result in a significant difference in GHG
emissions compared to a flare. Thus, although a thermal oxidizer may be a more effective
control alternative than a flare for VOC emissions, it does nothing to reduce GHG emissions.
For this reason, even if a thermal oxidizer was used for control of routine vent streams, the flare
would still be necessary and would require continuous burning of natural gas in the pilots, which
add additional CO2, NOx, and CO emissions.
For these reasons, use of either a thermal oxidizer is rejected as technically infeasible for the
proposed project.
6.6.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
Flare minimization and proper operation of the flare are potentially equally effective but have
case-by-case effectiveness that cannot be quantified to allow ranking.
6.6.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Use of an analyzer(s) to determine the heating value of the flare gas to allow continuous
determination of the amount of natural gas needed to maintain a minimum heating value of 300
Btu/scf to insure proper destruction of VOCs ensures that excess natural gas is not
unnecessarily flared. This added advantage of reducing fuel costs makes this control option
cost effective as both a criteria pollutant and GHG emission control option. There are no
negative environmental impacts associated with this option. Proper design of the process
equipment to minimize the quantity of waste gas sent to the flare also has no negative economic
or environmental impacts.
6.6.5 Step 5 – Selection of BACT
Enterprise proposes use of both identified control options to minimize GHG emissions from
flaring of process vents from the proposed facilities. Flare system analyzers will be used to
6-22
continuously monitor the combined waste gas stream sent to the flare from the proposed and
other existing facilities to determine the quantity of natural gas required to maintain a minimum
heating value of 300 Btu/scf and also to limit the quantity of natural gas use only what is needed
to maintain 300 Btu/scf. The efficient use of natural gas will avoid the production of both
unnecessary GHG emissions as well as criteria pollutants.
6.7 Fugitives (EPNs FUG-PDH & FUG-NGAS)
Hydrocarbon emissions from leaking piping components, (fugitives), in the process (EPN FUG-
PDH) and in the natural gas pipeline (EPN FUG-NGAS) associated with the proposed project
include methane, a GHG. The additional methane emissions from fugitives have been
conservatively estimated to be 5 tpy as CO2e from EPN FUG-PDH and 274 tpy as CO2e from
EPN FUG-NGAS as CO2e. This is a negligible contribution to the total GHG emissions;
however, for completeness, they are addressed in this BACT analysis.
6.7.1 Step 1 – Identification of Potential Control Technologies
The only identified control technology for a process fugitive emission of CO2e is use of a leak
detection and repair (LDAR) program. LDAR programs vary in stringency as needed for control
of VOC emissions; however, due to the negligible amount of GHG emissions from fugitives,
LDAR programs would not be considered for control of GHG emissions alone. As such,
evaluating the relative effectiveness of different LDAR programs is not warranted.
6.7.2 Step 2 – Elimination of Technically Infeasible Alternatives
LDAR programs are a technically feasible option for controlling process fugitive GHG emissions.
6.7.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
As stated in Step 1, this evaluation does not compare the effectiveness of different levels of
LDAR programs.
6.7.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Although technically feasible, use of an LDAR program to control the negligible amount of GHG
emissions that occur as process fugitives is clearly cost prohibitive. However, if an LDAR
program is being implemented for VOC control purposes, it will also result in effective control of
the small amount of GHG emissions from the same piping components. Enterprise uses
6-23
TCEQ’s 28LAER LDAR program at the Mont Belvieu Complex to minimize process fugitive VOC
emissions at the plant, and this program has also been proposed for the additional fugitive VOC
emissions associated with the project. 28LAER is TCEQ’s most stringent LDAR program,
developed to satisfy LAER requirements in ozone non-attainment areas.
6.7.5 Step 5 – Selection of BACT
Due to the negligible amount of GHG emissions from process fugitives, the only available
control, implementation of an LDAR program, is clearly not cost effective, and BACT is
determined to be no control. However, Enterprise will implement TCEQ’s 28LAER LDAR
program for VOC BACT/LAER purposes, which will also effectively minimize GHG emissions.
Therefore, the proposed VOC LDAR program more than satisfies GHG BACT requirements.
6.8 Diesel Engines
The diesel engines will be used for emergency purposes only, and the only non-emergency
operation will be for testing one hour per week each, or 52 weeks/yr.
6.8.1 Step 1 – Identification of Potential Control Technologies
The RBLC database did not include any control technologies for GHG emissions from
emergency use engines. The technologies that were considered for the engines included:
Low carbon fuel,
Good combustion practice and maintenance, and
Limited operation.
6.8.2 Step 2 – Elimination of Technically Infeasible Alternatives
Use of lower carbon fuel such as natural gas is not considered feasible for an emergency
engine. Natural gas supplies may be unavailable in emergency situations, and maintaining the
required fuel in an on-board tank associated with each engine is the only practical fuel option.
Good combustion practice and maintenance and limited operation are both applicable and
feasible.
6.8.3 Step 3 – Ranking of Remaining Technologies Based on Effectiveness
Limited operation and good combustion practices and maintenance are all effective in
minimizing emissions, but do not lend themselves to ranking by effectiveness.
6-24
6.8.4 Step 4 – Evaluation of Control Technologies in Order of Most Effective to Least Effective
Limited operation is directly applicable to the proposed engines since they are for emergency
use only, resulting in no emissions at most times. Operation for testing purposes is necessary
to ensure operability when needed. Properly designed and maintained engines constitutes
good operating practice for all maximizing efficiency of all fuel combustion equipment, including
emergency engines.
6.8.5 Step 5 – Selection of BACT
Enterprises proposes to use properly designed and maintained engines to minimize emissions.
Emergency use only inherently results in low annual emissions and normal operation will be
limited to 52 hours per year for scheduled testing only. This minimal use results in an
insignificant contribution to the total project GHG emissions making consideration of additional
controls unwarranted. These practices are proposed as BACT for GHG emissions from the
engines.
CCS System Component
Cost ($/ton of CO2
Controlled)1Tons of CO2
Controlled per Year2Total Annualized
Cost
CO2 Capture and Compression Facilities $103 1,153,427 $118,803,012
CO2 Transport Facilities3 Not Included Not Included Not Included
CO2 Storage Facilities $0.51 1,153,427 $588,248
Total CCS System Cost $104 1,153,427 $119,391,260
Proposed Plant Cost Total Capital Cost
Capital Recovery
Factor4Annualized Capital
Cost
Cost of PDH Unit without CCS $1,300,000,000 0.0944 $122,710,803
4. Capital recovery factor based on 7% interest rate and 20 year equipment life.
Interest Rate 7%Equipent Life (yrs) 20
Approximate Cost for Construction and Operation of a Post-Combustion CCS System for PDH Plant
1. Costs are from Report of the Interagency Task Force on Carbon Capture (August, 2010) . A range of costs was provided for transport and storage facilities; for conservatism, the low ends of these ranges were used in this analysis as they contribute little to the total cost. Reported costs in $/tonne were converted to $/ton.
2. Tons of CO2 controlled assumes 90% capture of all CO2 emissions from the proposed combustion units.
3. Pipeline costs are not included at this time. It is conservatively assumed that a suitable sequestration site is available in close proximaity to the proposed PDH Unit.
Table 6-1
6-25
Appendix A
Emissions Calculations
Table A-1 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitGHG Emissions - Individual Combustion Unit Limts
CO2 CH4 N2O CO2e
HR15.101 HR15.101 Reactor Charge Heater DeEth Offgas 3,758,478 2,503,713,725 0.765 26.66 246,846 12.43 2.49 247,877 Ethane 287,383,412 0.798 30.07 33,322 0.56 0.06 33,351 Natural Gas 494,432,362 0.723 17.46 30,139 0.56 0.06 30,168
Reactor Charge Heater Total/Max34,267,060 280,168 12.99 2.54 281,229
DW37.101 All of Below: Waste Heat Boiler:
HR15.103 Waste Heat Boiler Burner Ethane 297,241 167,961,130 0.798 30.07 19,475 0.33 0.03 19,492 DeEth Offgas 297,241 198,007,252 0.765 26.66 19,522 0.98 0.20 19,603
Natural Gas 297,241 288,970,814 0.723 17.46 17,615 0.33 0.03 17,632 PSA Tail Gas 297,241 599,900,478 0.443 11.14 14,315 0.33 0.03 14,332
LTRU Offgas4- - 0.270 4.03 - - - -
WHB Burner Total/Max5297,241 19,522 0.98 0.20 19,603
HR15.102 Regeneration Air Heater Ethane 4,789,100 2,706,164,815 0.798 30.07 313,779 5.28 0.53 314,053 DeEth Offgas 3,758,478 2,503,713,725 0.765 26.66 246,846 12.43 2.49 247,877 PSA Tail Gas 1,870,421 3,774,941,116 0.443 11.14 90,079 6.19 1.24 90,593 Natural Gas 4,789,100 4,655,854,889 0.723 17.46 283,807 15.84 3.17 285,121
LTRU Offgas4- - 0.270 4.03 - - - -
Regeneration Air Heater Total/Max610 417 999 650 704 23 89 4 25 652 523
508,582
Carbon Content
(CC)MW
(lb/lbmol)
Emission Rates (tpy)2Firing Rate
(scf/yr)EPN FIN Description Fuel1Firing Rate(mmBtu/yr)
Regeneration Air Heater Total/Max 10,417,999 650,704 23.89 4.25 652,523
GT26.101A Regen Air Comp. Gas Turbine A Natural Gas 2,107,571 2,048,933,053 0.723 17.46 124,897 2.32 0.23 125,018
GT26.101B Regen Air Comp. Gas Turbine B Natural Gas 2,107,571 2,048,933,053 0.723 17.46 124,897 2.32 0.23 125,018
BO10.103A BO10.103A Auxiliary Boiler A Ethane 248,500 140,419,280 0.798 30.07 16,282 0.27 0.03 16,296
BO10.103B BO10.103B Auxiliary Boiler B Natural Gas 248,500 241,586,096 0.723 17.46 14,726 0.82 0.16 14,795 PSA Tail Gas 248,500 501,530,283 0.443 11.14 11,968 0.82 0.16 12,036 DeEth Offgas 248,500 165,538,513 0.765 26.66 16,321 0.82 0.16 16,389
Auxiliary Boiler Total/Max7 248,500 16,321 0.82 0.16 16,389
1 Listed fuels are the fuels that may be burned in each facility. All available DeEth Offgas and PSA Tail Gas will be used, and balance of required fuel will be natural gas and/or ethane.
The fuel firing rates used for each facility are based on burning all available DeEth Offgas and PSA Tail Gas in the preferred facility, up to the required heat demand on that facility.
Any remaining off/tail gas will be used in other facilities as shown. As such, the individual fuel usage rates used in the calculations are not maximum annual rates for each facility.
2 Note all emission rates are in units of short tons. Eq. C-5 in 40 CFR Part 98 Chapter C yields emissions in metric tons.
Metric tons were converted to short tons by multiplying by 1.102311 short tons per metric ton.
3 All available DeEth Offgas will be burned in Reactor Charge Heater with balance of fuel being either natural gas or ethane. Total maximum emission rate is emissions
from DeEth Offgas plus maximum from ethane or natural gas.
4 LTRU Offgas will only be burned if the PSA Unit is down, which is an upset condition and thus not shown in the calculations.
5 PSA Tail Gas is primary fuel for WHB Burner. Natural gas and ethane are alternate fuels. Maximum emission rate shown is based on burning 100% ethane.
6 Regeneration Air Heater will burn any DeEth Offgas and PSA Tail Gas not consumed in the Charge Heater and WHB Burner. Total/Max emissions are based on burning PSA Tail
Gas not used in WHB Burner with balance of fuel from Ethane/DeEth Offgas. (Note that CO2 emission factor in lb/mmbtu for Ethane and DeEth Offgas are the same (see table below)).7 Auxiliary Boilers will be in hot standby under normal conditions and will be used interchangeably; thus, the firing rates shown are totals for the two together. They are capable of burning each of the fuels listed, and maximum emissions are based on burning all DeEth Offgas, which results in the highest CO2 emisions.
12/18/2012
Table A-1 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitGHG Emissions - Individual Combustion Unit Limts
Carbon Factor Calculations:
Component
Molecular Weight
(lb/lb-mol)
Number of Carbons per mole Natural Gas
DeEth Offgas (SOR)
PSA Tail Gas (SOR) LTRU Offgas
Import Ethane
MSS Flaring
Reactor VOC
Nitrogen 28.013 0 0.683 0.490 6.760 1.490 0.000 0.000 0.000Carbon Dioxide 44.010 1 1.797 2.200 0.520 0.120 0.000 0.000 0.000Carbon Monoxide 28.010 1 0.035 1.630 12.470 2.750 0.000 0.000 0.000Helium 4.003 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000Argon 39.95 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000Hydrogen 2.02 0 0.000 8.860 60.070 91.190 0.000 0.000 0.000Methane 16.04 1 93.361 7.680 13.960 3.080 0.000 0.000 0.000Ethane 30.07 2 3.043 71.330 3.470 0.770 100.000 0.000 1.530Propane 44.10 3 0.557 0.060 0.760 0.170 0.000 50.000 8.113Iso-Butane 58.12 4 0.191 0.000 0.000 0.000 0.000 0.000 0.000n-Butane 58.12 4 0.143 0.000 0.000 0.000 0.000 0.000 9.672Iso-Pentane 72.15 5 0.039 0.000 0.000 0.000 0.000 0.000 0.000n-Pentane 72.15 5 0.027 0.000 0.000 0.000 0.000 0.000 7.792n-Hexane 86.18 6 0.088 0.000 0.000 0.000 0.000 0.000 14.234n-Heptane 100.20 7 0.000 0.000 0.000 0.000 0.000 0.000 12.241C10+ 140.00 10 0.000 0.000 0.000 0.000 0.000 0.000 43.807Ethylene 28.05 2 0.000 7.170 0.970 0.210 0.000 0.000 0.182P l 42 08 3 0 000 0 310 1 010 0 220 0 000 50 000 2 429
Composition (mole %)
Propylene 42.08 3 0.000 0.310 1.010 0.220 0.000 50.000 2.429neo-Pentane 72.15 5 0.000 0.000 0.000 0.000 0.000 0.000 0.000Acetylene 26.04 2 0.000 0.220 0.010 0.000 0.000 0.000 0.000Hydrogen Sulfide 34.00 0 0.000 0.050 0.000 0.000 0.000 0.000 0.000Oxygen 32.00 0 0.037 0.000 0.000 0.000 0.000 0.000 0.000Water 18.02 0 0.000 0.000 0.000 0.000 0.000 0.000 0.000
MW (lb/lbmole): 17.46 26.66 11.14 4.03 30.07 43.09 102.22Carbon Content (kg C/kg Fuel): 0.723 0.765 0.443 0.270 0.798 0.835 0.847
Heating Value (btu/scf, HHV): 1028.6 1501.2 495.5 362.0 1769.7 NA NACO2 emission factor (lb/mmbtu,HHV): 118.55 131.39 96.35 29.10 131.04
Emission Factors:
Eq. C-5 from 40 CFR Part 98 Chapter CCO2e Equivalents:
kg CH4 /mmBtu kg N2O/mmBtu CO2 1.0Natural Gas 0.001 0.0001 CH4 21.0
CO2 = CO2 emissions, metric tons/yr Process Gas 0.003 0.0006 N2O 310.0Fuel = firing rate in mmscf/yr kg to lb conversion factor: 2.20462MVC = 836.6 (per Part 98)CC = as calculated aboveMW = as calculated above
CH4 and N2O Emission factors from Table C-2 of Appendix A to 40 CFR Part 98 Chapter C
12/18/2012
Table A-2 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitGHG Emissions - Combustion Unit Caps
HR15.101 HR15.101 Reactor Charge Heater 4,267,060
DW37.101 All of Below: Waste Heat Boiler:
HR15.103 Waste Heat Boiler Burner 297,241
HR15.102 Regeneration Air Heater 10,417,999
GT26.101A Regen Air Comp. Gas Turbine A 2,107,571
GT26.101B Regen Air Comp. Gas Turbine B 2,107,571
BO10.103A BO10.103A Auxiliary Boiler A
BO10.103B BO10.103B Auxiliary Boiler B
Total from Above Combustion Units 19,445,942
Available Fuels:
DeEth Offgas 3,758,478
PSA Tail Gas 2,167,662
Ethane 9,304,660
Natural Gas 4,215,142
Fuel Total 19,445,942
GHG Emission Calculation
CO2 CH4 N2O CO2e
EPN FIN DescriptionFiring Rate(mmBtu/yr)
Fuel1Firing Rate(mmBtu/yr)
248,500
Emission Rates (tpy)2
1. DeEth Offgas and PSA Tail Gas firing rates are all of these fuels that are projected to be produced annual in the process. All of these fuel gases will be burned in the PDH Unit combustion devices and the balance of the fuel requirements will be made up with either ethane or natural gas. Natural gas is the only fuel that will be fired in the Gas Turbines, and the natural gas firing rate shown is the fuel required for the two Gas Turbines. For the maximum annual GHG emissions calculations all remaining fuel requirements are assumed to be provided by ethane as ethane results in higher GHG emissions per btu than natural gas.
Firing Rate (scf/yr)
Carbon Content (CC)
MW (lb/lbmol)Fuel
Firing Rate(mmBtu/yr)
DeEth Offgas 3,758,478 2,503,713,725 0.765 26.66 246,846 12.43 2.49 247,877
PSA Tail Gas 2,167,662 4,374,841,594 0.443 11.14 104,394 7.17 1.43 104,989
Ethane 9,304,660 5,257,761,370 0.798 30.07 609,635 30.77 6.15 612,189
Natural Gas 4,215,142 4,097,866,106 0.723 17.46 249,794 13.94 2.79 250,950
Fuel Total 19,445,942 NA NA NA 1,210,669 64.31 12.86 1,216,006
VOC from Reactors NA 13,333,260 0.847 102.22 5,580 - - 5,580
Coke Burn3 NA NA NA NA 60,000 - - 60,000
Cap Total NA NA NA NA 1,276,248 64.31 12.86 1,281,586
3. CO2 from coke burn based on Lummus EOR estimate of 58,000 tpy, rounded to 60,000 tpy.
2. Note all emission rates are in units of short tons. Eq. C-5 in 40 CFR Part 98 Chapter C yields emissions in metric tons. Metric tons were converted to short tons by multiplying by 1.102311 short tons per metric ton.
12/18/2012
Table A-2 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitGHG Emissions - Combustion Unit Caps
Carbon Factor Calculations:
Component
Molecular Weight
(lb/lb-mol)
Number of Carbons per
mole Natural Gas
DeEth Offgas (SOR)
PSA Tail Gas (SOR)
Import Ethane
Reactor VOC
LTRU
Offgas4
Nitrogen 28.013 0 0.683 0.490 6.760 0.000 0.000 1.490Carbon Dioxide 44.010 1 1.797 2.200 0.520 0.000 0.000 0.120Carbon Monoxide 28.010 1 0.035 1.630 12.470 0.000 0.000 2.750Helium 4.003 0 0.000 0.000 0.000 0.000 0.000 0.000Argon 39.95 0 0.000 0.000 0.000 0.000 0.000 0.000Hydrogen 2.02 0 0.000 8.860 60.070 0.000 0.000 91.190Methane 16.04 1 93.361 7.680 13.960 0.000 0.000 3.080Ethane 30.07 2 3.043 71.330 3.470 100.000 1.530 0.770Propane 44.10 3 0.557 0.060 0.760 0.000 8.113 0.170Iso-Butane 58.12 4 0.191 0.000 0.000 0.000 0.000 0.000n-Butane 58.12 4 0.143 0.000 0.000 0.000 9.672 0.000Iso-Pentane 72.15 5 0.039 0.000 0.000 0.000 0.000 0.000n-Pentane 72.15 5 0.027 0.000 0.000 0.000 7.792 0.000n-Hexane 86.18 6 0.088 0.000 0.000 0.000 14.234 0.000n-Heptane 100.20 7 0.000 0.000 0.000 0.000 12.241 0.000C10+ 140.00 10 0.000 0.000 0.000 0.000 43.807 0.000Ethylene 28.05 2 0.000 7.170 0.970 0.000 0.182 0.210Propylene 42.08 3 0.000 0.310 1.010 0.000 2.429 0.220neo-Pentane 72.15 5 0.000 0.000 0.000 0.000 0.000 0.000Acetylene 26.04 2 0.000 0.220 0.010 0.000 0.000 0.000Hydrogen Sulfide 34.00 0 0.000 0.050 0.000 0.000 0.000 0.000Oxygen 32.00 0 0.037 0.000 0.000 0.000 0.000 0.000Water 18.02 0 0.000 0.000 0.000 0.000 0.000 0.000
MW (lb/lbmole): 17.46 26.66 11.14 30.07 102.22 4.03Carbon Content (kg C/kg Fuel): 0.723 0.765 0.443 0.798 0.847 0.270
Heating Value (btu/scf, HHV): 1028.6 1501.2 495.5 1769.7 NA 362.0
Composition (mole %)
Heating Value (btu/scf, HHV): 1028.6 1501.2 495.5 1769.7 NA 362.0CO2 emission factor (lb/mmbtu,HHV): 118.55 131.39 96.35 131.04 NA 29.10
4 LTRU Offgas will only be burned if the PSA Unit is down, which is an upset condition and thus not shown in the calculations.
Emission Factors:
Eq. C-5 from 40 CFR Part 98 Chapter Ckg CH4 /mmBtu kg N2O/mmBtu
Natural Gas 0.001 0.0001Process Gas 0.003 0.0006
CO2 = CO2 emissions, metric tons/yr kg to lb conversion factor: 2.20462Fuel = firing rate in mmscf/yrMVC = 836.6 (per Part 98) CO2e Equivalents:CC = as calculated above CO2 1.0MW = as calculated above CH4 21.0
N2O 310.0
CH4 and N2O Emission factors from Table C-2 of Appendix A to 40 CFR Part 98 Chapter C
12/18/2012
Table A-3 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitProcess Flare
CO2 CH4 N2O CO2e SK25.801 SK25.801 Process Flare, Routine
Pilots Natural Gas 9,011 8,760,000 0.723 17.46 534 0.0099 0.0010 534 Purge Natural Gas 16,399 15,943,200 0.723 17.46 972 0.0181 0.0018 973 Routine Steams Vent Gas 3,354 7,545,545 0.835 43.09 1,312 0.0111 0.0022 1,313 Routine Total 2,818 0.04 0.005 2,821
Process Flare, MSS Misc. MSS Vent Gas 2,061 8,613,636 0.835 43.09 1,498 0.0068 0.0014 1,499 Startup MSS Vent Gas 46,006 45,913,143 0.735 17.96 2,928 0.1521 0.0304 2,941 Shutdown MSS Vent Gas 6,944 8,613,636 0.832 43.29 1,498 0.0230 0.0046 1,500 MSS Total 4,426 0.16 0.03 4,439
1 Note all emission rates are in units of short tons. Eq. C-5 in 40 CFR Part 98 Chapter C yields emissions in metric tons.
Metric tons were converted to short tons by multiplying by 1.102311 short tons per metric ton.
Carbon Factor Calculations:
Component
Molecular Weight
(lb/lb-mol)
Number of Carbons per mole Natural Gas
Startup Flaring MSS Flaring
Shutdown Flaring
Nitrogen 28.013 0 0.683 0.000 0.000 0.000Carbon Dioxide 44.010 1 1.797 2.000 0.000 0.000Carbon Monoxide 28.010 1 0.035 0.000 0.000 0.000Helium 4.003 0 0.000 0.000 0.000 0.000Argon 39.95 0 0.000 0.000 0.000 0.000Hydrogen 2.02 0 0.000 0.000 0.000 0.000Methane 16.04 1 93.361 93.000 0.000 0.000Ethane 30.07 2 3.043 0.000 0.000 0.000Propane 44.10 3 0.557 3.000 50.000 60.000Iso-Butane 58.12 4 0.191 0.000 0.000 0.000n-Butane 58.12 4 0.143 0.000 0.000 0.000Iso-Pentane 72.15 5 0.039 0.000 0.000 0.000n-Pentane 72.15 5 0.027 0.000 0.000 0.000n-Hexane 86.18 6 0.088 0.000 0.000 0.000n-Heptane 100.20 7 0.000 0.000 0.000 0.000C10+ 140.00 10 0.000 0.000 0.000 0.000Ethylene 28.05 2 0.000 0.000 0.000 0.000P l 42 08 3 0 000 2 000 50 000 40 000
Emission Rates (tpy)1
Composition (mole %)
EPN FIN Description FuelFiring Rate(mmBtu/yr)
Firing Rate (scf/yr)
Carbon Content
(CC)MW
(lb/lbmol)
Propylene 42.08 3 0.000 2.000 50.000 40.000neo-Pentane 72.15 5 0.000 0.000 0.000 0.000Acetylene 26.04 2 0.000 0.000 0.000 0.000Hydrogen Sulfide 34.00 0 0.000 0.000 0.000 0.000Oxygen 32.00 0 0.037 0.000 0.000 0.000Water 18.02 0 0.000 0.000 0.000 0.000
MW (lb/lbmole): 17.46 17.96 43.09 43.29Carbon Content (kg C/kg Fuel): 0.723 0.735 0.835 0.832
Heating Value (btu/scf, HHV): 1028.6 1028.6 311.0 927.6CO2 emission factor (lb/mmbtu,HHV): 118.55
Emission Factors:
Eq. C-5 from 40 CFR Part 98 Chapter CCO2e Equivalents:
kg CH4 /mmBtu kg N2O/mmBtu CO2 1.0Natural Gas 0.001 0.0001 CH4 21.0
CO2 = CO2 emissions, metric tons/yr Process Gas 0.003 0.0006 N2O 310.0Fuel = firing rate in mmscf/yr kg to lb conversion factor: 2.20462MVC = 836.6 (per Part 98)CC = as calculated aboveMW = as calculated above
CH4 and N2O Emission factors from Table C-2 of Appendix A to 40 CFR Part 98 Chapter C
12/18/2012
Table A-4 Pipeline Fugitive GHG EmissionEnterprise Operating Products LLCMont Belvieu Complex - PDH Unit
EPN LDAR EPN LDARFUG-NGAS AVO FUG-PDH 28LAER
Annual AnnualComponent Stream Control Emissions Control Emissions
Type Type Eff. (tpy) Eff. (tpy)
Gas/Vapor 0.0089 140 30% 3.8202 1,119 97% 1.3086
Light Liquid 0.0035 0 0% 0.0000 1495 97% 0.6876
Heavy Liquid 0.0007 0 0% 0.0000 0 97% 0.0000
Light Liquid 0.0386 0 0% 0.0000 51 93% 0.6036
Heavy Liquid 0.0161 0 0% 0.0000 0 93% 0.0000
Gas/Vapor 0.0029 350 30% 3.1120 3,851 97% 1.4675
Light Liquid 0.0005 0 0% 0.0000 5263 97% 0.3458
Heavy Liquid 0.00007 0 0% 0.0000 0 97% 0.0000
Compressors Gas/Vapor 0.5027 0 0% 0.0000 4 95% 0.4404
Relief Valves Gas/Vapor 0.2293 10 30% 7.0303 45 100% 0.0000
Open Ends 0.004 0 0% 0.0000 0 97% 0.0000
Sample Con. 0.033 0 0% 0.0000 32 97% 0.1388
Gas/Vapor 0 0 0% 0.0000 0 97% 0.0000
Lt/Hvy Liquid 0 0 0% 0.0000 0 97% 0.0000Process Drains 0.07 0 0% 0.0000 0 97% 0.0000
TOTAL 500 Total Loss 13.96 11,860 Total Loss 4.99
Operating Hours: 8,760 % CH4 93% % CH4 5%Total CH4 13.04 Total CH4 0.25
GWP 21 GWP 21CO2e 273.75 CO2e 5.24
Flanges
Other
Number of Components
Number of Components
Emission Factor SOCMI without
Ethylene
Valves
Pumps
12/18/2012
Table A-5 GHG Emission CalculationsEnterprise Operating Products LLCMont Belvieu Complex - PDH UnitDiesel Engines
CO2 CH4 N2O CO2e PM18.803 PM18.803 Fire Water Pump Engine No. 2 Diesel 3.79 52 197 16.1 0.0007 0.0001 16.1
PM18.850C PM18.850C Raw Water Pump Engine No. 2 Diesel 1.97 52 103 8.4 0.0003 0.0001 8.4
Emission Factors:
CO2e Equivalents:Fuel kg CO2/mmBtu kg CH4 /mmBtu kg N2O/mmBtu CO2 1.0
No. 2 Distillate 73.96 0.003 0.0006 CH4 21.0N2O 310.0
kg to lb conversion factor: 2.20462
Firing Rate (mmbtu/hr)
Usage (hrs/yr)
Emission Rates (tpy)1
Emission factors from Tables C-1 & C-2 of Appendix A to 40 CFR Part 98 Chapter C
EPN FIN Description FuelFiring Rate(mmbtu/yr)
12/18/2012
Appendix B
RBLC Database Search Results
Appendix BRBLC Database Search Results for GHG Emissions from Boilers
RBLCID FACILITY_NAME COMPANY_NAME STATEPERMIT DATE PROCESS_NAME
PRIMARY FUEL THROUGHPUT POLLUTANT CONTROL_METHOD_DESCRIPTION EMISSION_LIMIT_1
AL‐0231 NUCOR DECATUR LLC NUCOR CORPORATION AL 06/12/2007 &
VACUUM DEGASSER
BOILER NATURAL GAS 95 MMBTU/H Carbon Dioxide 0.061 LB/MMBTU
*FL‐0330
PORT DOLPHIN ENERGY
LLC
PORT DOLPHIN ENERGY
LLC FL 12/01/2011 &Boilers (4 ) natural gas 278 MMBTU/H Carbon Dioxide
tuning, optimization,
instrumentation and controls,
insulation, and turbulent flow. 117 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Primary Reformer natural gas 1.13
million cubic
feet/hr Carbon Dioxide good combustion practices 117 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Primary Reformer natural gas 1.13
million cubic
feet/hr Methane good combustion practices 0.0023 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Primary Reformer natural gas 1.13
million cubic
feet/hr Methane good combustion practices 0.0023 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Primary Reformer natural gas 1.13
million cubic
feet/hr
Carbon Dioxide
Equivalent (CO2e) good combustion practices 596905 TONS/YR
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Auxiliary Boiler natural gas 472.4 MMBTU/hr Carbon Dioxide good combustion practices 117 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Auxiliary Boiler natural gas 472.4 MMBTU/hr Methane good combustion practices 0.0023 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Auxiliary Boiler natural gas 472.4 MMBTU/hr Nitrous Oxide (N2O) good combustion practices 0.0006 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Auxiliary Boiler natural gas 472.4 MMBTU/hr
Carbon Dioxide
Equivalent (CO2e) good combustion practices 51748 TONS/YR
IN‐0135
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION IN 11/10/2011 &
COAL BED METHANE
CBM DEHYDRATOR
UNITS (CBM‐FIRED
REBOILER AND FLASH
TANK)
COAL BED
METHANE 0.5 MMBTU/H Carbon Dioxide PROPER MAINTENANCE 59.36 LB/H
LA‐0248
DIRECT REDUCTION
IRON PLANT
CONSOLIDATED
ENVIRONMENTAL
MANAGEMENT INC ‐
NUCOR LA 01/27/2011 &
DRI‐108 ‐ DRI Unit #1
Reformer Main Flue
Stack
Iron Ore and
Natural Gas 12168 Billion Btu/yr Carbon Dioxide
good combustion practices, the
Acid gas separation system, and
Energy integration. 11.79
MMBTU/TON OF
DRI
LA‐0248
DIRECT REDUCTION
IRON PLANT
CONSOLIDATED
ENVIRONMENTAL
MANAGEMENT INC ‐
NUCOR LA 01/27/2011 &
DRI‐208 ‐ DRI Unit #2
Reformer Main Flue
Stack
Iron ore and
Natural Gas 12168 Billion Btu/yr Carbon Dioxide
good combustion practices, the
Acid gas separation system, and
Energy integration. 11.79
MMBTU/TON OF
DRI
LA‐0254
NINEMILE POINT
ELECTRIC GENERATING
PLANT ENTERGY LOUISIANA LLC LA 08/16/2011 &AUXILIARY BOILER (AUX‐NATURAL GAS 338 MMBTU/H Methane
PROPER OPERATION AND GOOD
COMBUSTION PRACTICES 0.0022 LB/MMBTU
LA‐0254
NINEMILE POINT
ELECTRIC GENERATING
PLANT ENTERGY LOUISIANA LLC LA 08/16/2011 &
AUXILIARY BOILER
(AUX‐1) NATURAL GAS 338 MMBTU/H Nitrous Oxide (N2O)
PROPER OPERATION AND GOOD
COMBUSTION PRACTICES 0.0002 LB/MMBTU
LA‐0254
NINEMILE POINT
ELECTRIC GENERATING
PLANT ENTERGY LOUISIANA LLC LA 08/16/2011 &
AUXILIARY BOILER
(AUX‐1) NATURAL GAS 338 MMBTU/H Carbon Dioxide
PROPER OPERATION AND GOOD
COMBUSTION PRACTICES 117 LB/MMBTU
*NE‐0054
CARGILL,
INCORPORATED CARGILL, INCORPORATED NE 03/01/2013 &Boiler K natural gas 300 mmbtu/h
Carbon Dioxide
Equivalent (CO2e) good combustion practices 0
RBLC Search of GHG BACT Database
12‐Nov
RBLC Database Search Results for GHG Emissions from Heaters
RBLCID FACILITY_NAME COMPANY_NAME STATEPERMIT DATE PROCESS_NAME
PRIMARY FUEL THROUGHPUT POLLUTANT CONTROL_METHOD_DESCRIPTION EMISSION_LIMIT_1
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Startup Heater Natural gas 110.12 MMBTU/hr Carbon Dioxide good combustion practices 117 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Startup Heater Natural gas 110.12 MMBTU/hr Methane good combustion practices 0.0023 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Startup Heater Natural gas 110.12 MMBTU/hr Nitrous Oxide (N2O) good combustion practices 0.0006 LB/MMBTU
*IA‐0105
IOWA FERTILIZER
COMPANY
IOWA FERTILIZER
COMPANY IA 10/26/2012 &Startup Heater Natural gas 110.12 MMBTU/hr
Carbon Dioxide
Equivalent (CO2e) good combustion practices 638 TONS/YR
*MN‐0085
ESSAR STEEL
MINNESOTA LLC
ESSAR STEEL MINNESOTA
LLC MN 05/10/2012 &INDURATING FURNACE NATURAL GAS 542 MMBTU/H Carbon Dioxide 710000 TON/YR
RBLC Database Search Results for GHG Emissions from Simple Cycle Turbines
RBLCID FACILITY_NAME COMPANY_NAME STATEPERMIT DATE PROCESS_NAME
PRIMARY FUEL THROUGHPUT POLLUTANT CONTROL_METHOD_DESCRIPTION EMISSION_LIMIT_1
LA‐0257
SABINE PASS LNG
TERMINAL
SABINE PASS LNG, LP &
SABINE PASS
LIQUEFACTION, LL LA 12/06/2011 &
Simple Cycle
Refrigeration
Compressor Turbines
(16) Natural Gas 286 MMBTU/H
Carbon Dioxide
Equivalent (CO2e)
Good combustion/operating
practices and fueled by natural gas ‐
use GE LM2500+G4 turbines 4872107 TONS/YR
LA‐0257
SABINE PASS LNG
TERMINAL
SABINE PASS LNG, LP &
SABINE PASS
LIQUEFACTION, LL LA 12/06/2011 &
Simple Cycle
Generation Turbines
(2) Natural Gas 286 MMBTU/H
Carbon Dioxide
Equivalent (CO2e)
Good combustion/operating
practices and fueled by natural gas ‐
use GE LM2500+G4 turbines 4872107 TONS/YR
RBLC Database Search Results for GHG Emissions from Flares
RBLCID FACILITY_NAME COMPANY_NAME STATEPERMIT DATE PROCESS_NAME
PRIMARY FUEL THROUGHPUT POLLUTANT CONTROL_METHOD_DESCRIPTION EMISSION_LIMIT_1
IN‐0135
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION IN 11/10/2011 &
COAL BED METHANE‐
FIRED STANDBY FLARE
W/PROPANE‐FIRED
PILOT
COAL BED
METHANE 25 MMBTU/H Carbon Dioxide
GOOD COMBUSTION PRACTICES
AND PROPER MAINTENANCE 3235 LB/MW‐H
IN‐0135
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION IN 11/10/2011 &
COAL BED METHANE‐
FIRED STANDBY FLARE
W/PROPANE‐FIRED
PILOT
COAL BED
METHANE 25 MMBTU/H Methane
GOOD COMBUSTION PRACTICES
AND PROPER MAINTENANCE 0.06 LB/MW‐H
IN‐0135
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION
HOOSIER ENERGY REC
INC. ‐ MEROM
GENERATING STATION IN 11/10/2011 &
COAL BED METHANE‐
FIRED STANDBY FLARE
W/PROPANE‐FIRED
PILOT
COAL BED
METHANE 25 MMBTU/H Nitrous Oxide (N2O)
GOOD COMBUSTION PRACTICES
AND PROPER MAINTENANCE 0.05 LB/MW‐H
RBLC Search of GHG BACT Database
12‐Nov