48
i i i I I I 1 I I I I I I 1 I I I I i PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT WATER MANAGEMENT BRANCH CONTRACT NO. 75 Drilling, Construction and Testing of Observation Wells a t Coombs and Hornby Island, B.C. Observation Well No.'s 287 and 288 M. Wei Geol ogical Engineer Groundwater Section Water Management Branch Victoria, B.C. February, 1985

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

  • Upload
    others

  • View
    2

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

i

i

i

I I

I

1 I I I I I I 1 I I

I I

i

PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT WATER MANAGEMENT BRANCH

CONTRACT NO. 75

D r i l l i n g , Construction and Test ing o f Observation Wells a t

Coombs and Hornby Is land, B.C.

Observation Well No . 's 287 and 288

M. Wei Geol ogical Engineer Groundwater Section

Water Management Branch

V i c t o r i a , B.C. February, 1985

Page 2: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

i I I I I I I 1 I I I I I I I I I I 1

- i -

TABLE OF CONTENTS

Page

TABLE OF CONTENTS ................................................. i LIST OF FIGURES ....................................................... i LIST OF TABLES ...................................................... ii LIST OF PICTURES .................................................... ii LIST OF APPENDICES ................................................ ii

1. INTRODUCTION ...................................................... 1

2. WELL DRILLING ..................................................... 1 2.1 Observation Well No. 287 ................................... 2 2.2 Observation Well No. 288 ................................... 3

3. WATER CHEMISTRY ................................................... 4

4. DISCUSSION .................................................... 5

5. CONCLUSIONS AND RECOMMENDATIONS ................................... 6

6. .REFERENCES ........................................................ 6

7. APPENDICES . ...................................................... 27

LIST OF FIGURES

Figure 1

Figure 2

F igure 3

F igure 4

F igure 5

F igure 6

F igure 7

F igure 8

Location Map ............................................. 8

Location o f Observation Well No. 287, Coombs, B.C. ....... 9

S i t e Plan, Observation Well No. 287, Coombs, B.C. ........ 10

Geologic Descr ip t ion and Well Completion, Observation Well No. 287, Coombs, B.C. ................... 11

Location o f Observation Well No. 288, Hornby Island, B.C.. 12

S i t e Plan, Observation Well No. 288, Hornby Island, B.C... 13

Geologic Descr ip t ion and Well Completion, Observation Well No. 288, Hornby Island, B.C. ............ 14

General Water Chemistry Presented on Schoel ler Diagram ... 15

Page 3: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

1 I I I I I I I I I I 1 I I I I I I

Table 1

Table 2

. ii .

Page

LIST OF TABLES

Well D r i l l i n g Summary .................................... 16

Water Chemistry Summary .................................. 17

LIST OF PICTURES

P i c t u r e 1 ................................................ P i c t u r e 2 ................................................ P i c t u r e 3 ................................................ P i c t u r e 4 ................................................ P i c t u r e 5 ................................................ P i c t u r e 6 ................................................ P i c t u r e 7 ................................................ P i c t u r e 8 ................................................ P i c t u r e 9 ................................................ P i c t u r e 10 ............................................... P i c t u r e 11 ............................................... P i c t u r e 12 ............................................... P i c t u r e 13 ............................................... P i c t u r e 14 ............................................... P i c t u r e 15 ............................................... P i c t u r e 16 ............................................... P i c t u r e 17 ...............................................

18 19 19 20 20 2 1 2 1 22 22 23 23 24 24 25 25 26 26

LIST OF APPENDICES

Appendix A Well Logs F i l e s .......................................... 27

Appendix B Contract Costs ........................................... 30

Appendix C Water Chemistry Reports .................................. 32

Appendix D Water Level Recorder I n s t a l l a t i o n Spec i f ica t ions ......... 37

Page 4: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I I I I I I I

- 1 -

D r i l l i n g , Cons t ruc t ion and Tes t ing o f Observation Wells a t

Coombs and Hornby I s l and , B. C. Observation We1 1 No. ' s 287 and 288

CONTRACT NO. 75

1. INTRODUCTION

Establ ishment of observa t ion wells a t Coombs and Hornby Is land was

recommended by Zubel (1982) and \lei (1983). Coombs and Hornby Is land l i e along t h e east coast of Vancouver I s l a n d between Courtenay and Nanaimo ( F i g u r e 1). Both a r e a s depend on groundwater as the m a i n source of water supply and have a high concen t r a t ion of wells. Many wells are open holes d r i l l e d i n t o bedrock intercepting water-bearing zones. Water quan t i ty and q u a l i t y a r e repor ted problems. Observation wells i n these a r e a s would al low c o l l e c t i o n of groundwater da t a f o r a s ses s ing a q u i f e r behaviour to loca l pumping, na tura l recharge and p o l l u t i o n over a period of time. A f i e l d survey by D. Kalyn, groundwater t echn ic i an , i n the winter of 1983 t o l o c a t e sui t a b l e abandoned we1 1 s f o r use a s observa t ion we1 1s was unsuccessful. Consequently, d r i l l i ng was required t o e s t a b l i s h these observa t ion we1 1 s.

2. WELL DRILLING

Well d r i l l i n g was c a r r i e d o u t by Island Well D r i l l i n g Ltd. of Ladysmith. In t o t a l , Wo observa t ion wells (152 mm 0) were established, one each a t Coombs and Hornby Is land (Appendix A ) .

The wells were dr i l led by the air r o t a r y method w i t h a Shram R o t a d r i l l r i g . Cont rac t c o s t t o t a l l e d $7,996.17 (Appendix B).

Page 5: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

,I 1 I I I 1 I 1 I I I I 1 1 I I I I 1

~

7

0.0 m t o 3.0 m ( 10 ' ) 3.0 m t o 8.2 m ( 27 ' ) 8.2 m to 92.4 m (303')

- 2 -

~ ~ -~

Brown till Grey sandy till So f t black shale

2.1 Observation Well No. 287

. Work began on March 5, 1984, a t Coombs along the Burgoyne Road r i g h t - of-way (F igures 2 and 3). An i n i t i a l hole, Testhole #1, was d r i l l e d i n

the wrong l o c a t i o n due to mis loca t ing a survey pin, t o a depth o f 8.8 m (29 f e e t ) and was subsequently b a c k f i l l e d and abandoned.

The r i g was moved 12.1 m (39.7 f e e t ) west o f Testhole #1 and a second

ho le was d r i l l e d f o r completion as an observat ion well (P i c tu re 1). Surface casing 254 mm (10 inches) i n diameter was f i r s t i n s t a l l e d to 8.8 m (29 fee t ) . Bedrock was encountered a t 8.2 m (27 fee t ) . A 152 mm (6-inch)

diameter overlap casing was placed ins ide the surface casing and d r i l l i n g

was then continued w i t h a 152 mm (6-inch) open hole to a depth o f 92.4 m (303 f e e t ) . Geologic samples co l l ec ted a t regu la r i n t e r v a l s showed

d r i 11 i ng encountered the fo l low ing :

1 Depth I Mater ia l I

Water was f i r s t d e t e c t e d ' a t about 24 m (80 f e e t ) f low ing i n t o the we l l a t a r a t e o f roughly 3(10-2) L/s (1/2 gpm). No other water-bearing zones were detected below t h i s depth. The s t a t i c water l e v e l upon

completion was 2.74 m (9.0 feet ) below the t o p of the 152 mm casing. A f t e r d r i l l i n g , the we l l was developed by f l ush ing w i t h a i r . A surface

seal was then constructed by f i l l i n g the annular space between the 254 mm and 152 mm casings w i t h cement and cut t ings, and p u l l i n g out the 254 mm

Page 6: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I 1 I I I I I I I 1 I I I I I

Depth

0.0 m t o 0.8 m (2.5') 0.8 m t o 1.8 m ( 6 ' ) 1.8 m t o 48.8 m (160')

48.8 m t o 67.1 m (220')

- 3 -

~ ~~ ~~ ~~

Materi a1

Topsoil Conglomerate Grey sandstone w i t h some

l i g h t grey sandstone Black shale

casing. A we l l l i d was attached t o the wel l head t o complete the we l l (F igure 4 and P ic tu res 2, 3, 4, 5, 6 and 7). A pump t e s t was not

performed because o f the low y i e l d .

2.2 Observation Well No. 288

Work on Hornby Is land began March 7, 1984, along the Central Road

r ight-of-way w i t h Testhole #1 a t S i t e #1 (Figure 5 and P i c t u r e 8 ) . This

152 mm diameter hole was d r i l l e d to 67.1 m (220 f e e t ) and encountered the fo l l ow ing geologic mater ia ls :

The hole was dry and subsequently b a c k f i l l e d and abandoned (Pic tures 9 and 10).

Another ho le (Observation Well No. 288) was d r i l l e d a t S i t e #2 275 m (900 f e e t ) south of Testhole #1 (Figures 5 and 6 and P i c t u r e 11). A 254 mm surface casing was i n s t a l l e d t o 6.1 m (20 f e e t ) . A 152 mm over lap

casing was then placed i n s i d e the surface hole and d r i l l i n g continued with a 152 mm open hole to 77.1 m (253 fee t ) . Geologic samples co l l ec ted

showed d r i 11 i ng encountered the f o l l owi ng:

Page 7: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I 1 I I 1 I I I I I I I I 1 I I I I I

Depth

0.0 m to 3.0 m (10 ' ) 3.1 m t o 4.6 m (15 ' ) 4.6 m to 5.2 m (17 ' ) 5.2 m t o 16.8 m ( 5 5 ' )

16.8 m t o 38.1 m (125 ' ) 38.1 m to 39.6 m (130') 39.6 m t o 42.7 m (140') 42.7 m to 45.7 m (150') 45.7 m t o 51.8 m (170 ' ) 51.8 m to 62.5 m (205') 62.5 m t o 77.1 m (253')

- 4 -

Mate r i a1

Conglomerate So f t b lack shale L i g h t grey sandstone Greenish grey sandstonel

conglomerate Black shale Grey sandstone Black shale L i g h t grey sandstone Black shale L i g h t grey sandstone B1 ack s i 1 ts tone gradi ng

down to black shale

( 17

Some water was f i r s t detected between 4.6 m (15 f e e t ) and 5.2 rn f e e t ) . No major water-bearing zones were encountered below that,

however, small quan t i t i es o f water were being cont r ibu ted to the wel l a t

depth. Upon completion the t o t a l y i e l d was estimated a t 6(10-3) L/s (5 gph) and the s t a t i c water l e v e l was 15.03 m (49.3 f e e t ) below the top o f the 152 mm casing. The we l l was developed by f l ush ing w i t h a i r . A surface seal was constructed by f i l l i n g the annular space between the

254 mm and 152 mm casings w i t h cement and cut t ings, and p u l l i n g out the

254 mm casing. A wel l l i d was attached to the wel l head to complete the

w e l l (F igure 7 and P ic tu res 12, 13, 14 and 15). A pump t e s t was not performed because o f the low y i e l d . A summary o f the wel l d r i l l i n g i s

presented i n Table 1.

3. WATER CHEMISTRY

Water chemistry was tested i n the f i e l d w i t h a conduc t i v i t y meter and

Hach K i t from a i r f lushed samples. Fol lowing d r i l l i n g bu t before recorder

i n s t a l l a t i o n , a sample was co l l ec ted from each we l l w i t h a tube sampler, and

Page 8: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I 1 I I I I I

I I I I I I I I I

m

- 5 -

sent to the Environmental Laboratory i n Vancouver f o r chemical analysis.

Chemistry resu1,ts are shown i n F igure 8, Table 2 and Appendix C.

Water q u a l i t y from both observation we l ls i s very s o f t and r e l a t i v e l y

h igh i n pH, d isso lved minera l i za t ion , f luor ide , boron and aluminum. PH, TDS and f luor ide exceed those l i m i t s se t i n B.C. Dr ink ing Q u a l i t y Standards,

1982. I n addi t ion, water from Observation Well No. 287 appears to conta in

excessively high amounts of i r o n (Fe diss. = 0.57 mg/L). The waters can be character ized as Na-HC03 type water w i th corroding tendency (moderately h igh

Ryznar Index) and no t idea l fo r i r r i g a t i o n (h igh SAR index).

4. DISCUSSION

The Coombs Observation Well No. 287 appears t o be completed i n t o shales o f the Haslam Formation. The Hornby Is land Observation Well No. 288 appears t o be completed i n t o conglomerates, sandstones and shales o f the Geoffrey

Formation. Both formations belong to the Nanaimo Group, a sequence o f sedi-

mentary rocks formed dur ing the Mesozoic Era. Most we l ls i n both areas are completed i n t o bedrock. However, overburden i n both areas, comprising most- l y till up to several metres th ick , ove r l i es bedrock and some we l ls i n

Coombs are dug i n t o t h i s overburden to tap shal low groundwater. No high

capaci ty we l ls are known to e x i s t i n e i t h e r area - the bedrock aqui fers

appear to have very l i m i t e d y ie ld . Although Observation Well No. 288 penetrated several bedding plane f ractures, none proved productive. The

water chemistry suggests some s a l t y and/or brackish water may be seeping

i n t o the lower p o r t i o n o f both observat ion wel ls .

Water q u a l i t y from both observat ion wel'ls i s s i m i l a r even though the

we1 1 s are compl eted i n t o d i f f e r e n t fl ow systems. Hydro1 ogica l ly , Hornby

I s l a n d can be regarded as a freshwater mound atop a seawater basement w i t h

the mound con t inua l l y being recharged by p r e c i p i t a t i o n and discharging t o the sea, and i s separate from the f low systems o f Vancouver Is land. The

Page 9: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I

I 'I 'I I I I 1 I I I I I I I I 1

~I I - 6 -

r e l a t i v e l y high concentrat ions o f boron and f l o u r i d e may r e f l e c t the presence of some brackish groundwater seeping i n t o the wells. The aluminum

content may be n a t u r a l l y occurr ing o r may be from contamination during

sampl i n g - t h i s i s not c lear .

A more complete assessment o f the hydrogeology can be made through

continued monitor ing o f the bedrock aqui fers i n both these areas.

5. CONCLUSIONS AND RECOMMENDATIONS

Two 152 mm diameter observation wel ls were established: one each a t

Coombs and Hornby Island. Observation Well No. 287 a t Coombs was completed to 92 m i n s o f t black shales. Observation Well No. 288 a t

Hornby I s land was completed to 77 m i n i n te r l aye red conglomerates,

sandstonesand shales. Both wel ls have very low capaci t ies. The wel ls

are adequate however t o monitor water l e v e l response.

Cost f o r the d r i l l i n g con t rac t t o t a l l e d $7,996.17.

Water q u a l i t y from both wel ls i s s im i l a r : very s o f t and r e l a t i v e l y

h igh i n pH, dissolved minera l izat ion, f luor ide, boron and aluminum.

The waters can be character ized as Na-HC03 type water.

Water samples should be co l l ec ted a t l e a s t twice a year.

Water l e v e l should be monitored w i t h an automatic recorder f o r a minimum o f 10 years (P ic tures 16 and 17 and Appendix 0) .

6. REFERENCES

Wei , M. 1983. Groundwater Observation We1 1 Network Expansion Program

Proposal , 1983-84 F i scal Year. M i n i s t r y o f Environment, Groundwater

Section, V ic tor ia , B.C., F i l e 0183613-6.

Page 10: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

- 7 -

Zubel , M. 1982. Groundwater Observation We1 1 Network Expansion Program

Proposal, 1982-83 F isca l Year. M i n i s t r y o f Environment, Groundwater

. Section, V i c t o r i a , B.C., F i l e 0183613-8. I

M. Wei Geological Engineer Groundwater Section Water Management Branch

MW/dma

Page 11: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures
Page 12: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures
Page 13: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

k

~ovimcit'tkitbh~dumbia Ministry of Environment WATER MANAGEMENT BRANCH

L O T

s w E P-, OSSERWWON LJEU ~ o . ~ e + ,

COOM6S, 6 - C .

L-

N

L O 7 7 443

Page 14: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

- I I -

I I I I I I I I I I I I I I 1 I I I I'

' . I

- c c - c

c

L

c -

Rovince of British Columbia Ministry of Environment WATER MANAGEMENT BRANCH

Page 15: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures
Page 16: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I I I I I I I

N 169 . . I ... ._

1 Ir

137

2 6 m - NO. 208

23

. . . .. I . , . . . . ',-> ' . .. ; ,

Rovince of British Columbia Ministry of Environment WATER MANAGEMENT BRANCH

Page 17: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

- 14 -

hvince of British Columbia Ministry of Environment WATER MANAGEMENT BRANCH

I I I I I I I I I I I I I I I I I I I

. - G€DWbIC PB-L f&-OL,

06!SEF?dA77Od dELL 288 p

WW6y S L A d D , e*c*

I?.// at#

Page 18: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I B B I I I I I I I I I I I I I I I I

- 15 -

‘;.. -:i?.;.

.i*.

,> . , . ~. *.- .. I i : .,

,$

0 - 005. WELL No. 28+

. .* . .

Ministry of Environment WATER MANAGEMENT BRANCH PFZ~ESUJTED oh) SWOEUSR OUGRAH.

Page 19: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

yIll Location

Testhole #1

Obs. Well No. 287

Testhole #1

Obs. Well No. 288

Coombs

Coombs

Hornby Is1 and

Hornby Is land

2 54

152

152

152

TABLE 1

We1 1 Drll 1 f ng Summary

-

Depth (m)

8.84 -

92.35

67.06

77.11

7

[stimated del l Head 3 evat ion

( m )

-

103

-

42

E s t i mated Y i e l d (L/s) Status

~~

back f i 1 1 ed & abandoned

i n use

b a c k f i l l e d & abandoned

i n use

Estimated Je l l Bottom Elevat ion

( m )

11

-3 5

Estimated Sate r Level E levat ion

( m )

-

100

-

27

I

m I

4

Page 20: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I 1 I 1 1 I I 1 1 I I I I I I 1 1 I I

Lhemi c a1 Parameters

Temperature ("C) Spec. Conductance

PH TDS Hardness Ca+2 Mgt2 Na+ + K+

( mhos/cm)

c1-

HCO3- Fe Mn F > B Ryznar Index SAR Index

so4-2

- 17 -

TABLE 2

Water Chmi stry Sumnary

COOMBS

Observation Well No. 287

V e l d Analysis

9.5 7 10

10

42.8

6 1

>5.0

Lab Analysi!

970

9.2 584

9.78 2.83 0.66

228 + 1.1 33.7

1.2 465.8

0.57 0.02 1.65 0.79 7.7

32

HORNBY ISLAND

Observation Well No. 288 ~~

'i e l d Anal ys i s

10 1,600

10

576

3.5

.ab Analysis

1,210

710 9.1

7.27 2.22 0.42

268 + 1.4 164

1.6 375.0

0.16 0.01 1.93 1.46 8.3

43

*All parameters are i n mg/L except Temperature, Spec i f ic Conductance, pH, Ryznar Index and SAR index.

Page 21: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

P i c t u r e 1. Looking nor th a t s i t e #1 (abandoned TH # 1 ) and 2 (Obs. Well no. 287) w i t h respect t o A l l a n S t r e e t r ight-of-way

Page 22: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

-I -

I I I I I I I I I I I I I

._ . ..

- 19 -

Picture 2. Drilling Obs. Well no. 287 at s i te #2, Coombs

P i c t u r e 3. Estimating y i e l d

Page 23: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I - 20 -

I I I I I I I I I I I I I I I I I

Picture 4. Grouting the surface seal

Picture 5. Pulling out the 254 mm (10") 0 surface casing

Page 24: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

. . ,_. . ._ . . ., . ._ -. . .. . _w - .

I I I I I I I I I I I I I m I I I I

- 21 -

Picture 6. Constructing the well lid

Picture 7. The completed Obs. Well no. 287

Page 25: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I_u -. .

I - 22 -

I ..

I I I I I I I I

Picture 8. Looking south at site #1, Hornby Island

Picture 9. Drilling testhole #1 at site #1

Page 26: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I I I I I I I

- 23 -

Picture 10. Pulling out 152 mm (6") 0 surface casing and abandoning testhole #1

Picture 11. Looking south at site #2, Hornby Island

Page 27: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I 1 I I I I I

:- 24 -

Picture 12. Drilling Obs. Well no. 288 at site #2, Hornhy Island

Picture 13. Mixing ceme for grouting surface sear

Page 28: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

__

I I I I I I I I I I I I I 1 I I I I I

- 25 -

- Picture 14. Grouting surface seal

Picture 15. Constructing the well lid

Page 29: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

- 26 -

I I

I I I I I I I I I I I I I I

P i c t u r e 16. Obs. Well no. 287, Coombs

Picture 17. Obs. Well no. 288, Hornby Island

Page 30: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

- 27 -

I I I 1 I 1 I I I I I I I I I I 1 I

Appendix A

Well Log F i l e s

Page 31: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

WELL = = NO. 1- WATER W E L L RECORD

DEPT. OF ENVIRONMENT, WATER RESOURCES SERVICE, WATER INVESTIGATIONS BRANCH VICTORIA, BRITISH COLUMBIA aesvx--r

L E G A L D E s C R ~ P T ~ O N . L O T rq SEC. TP. - R. - D.L. ___ LAND DISTRICTAWGQSE P L A N

' E L €VAT I 0 N U E S T I M A T E O 0 SURVEYED C A S I N G D 1 A M . L L E N G T H z?'

METHOD OF CONSTRUCTION &QrARy CASING D I A M LENGTH - SCREEN LOCATION SCREEN 0 S I Z E LENGTH TYPE S A N I T A R Y SEAL Y E S 0 N O 0 S C R E E N O S I Z E L E N G T H T Y P E

PERFORATED CASING 0 LENGTH- PERFORATIONS FROM TO

GRAVEL PACK 0 LENGTH, DIAM SIZE CRAVEL.ETC.

FROM-L U M E A ~ U R E O ELEVATION ARTESIAN PRESSURE -- DISTANCE TO WATER 9 0 ESTIMATED WATER L E V E L

D A T E OF wATEP L E V E L MEASUREMENTJIALJL~H WATER USE 08 SER4A-r IOQ M P L L , (*287\

C H E M I S T R Y

T E S T B Y & W ~ A ? f ~ NrAL l a m A 7 o h V - d c o J v €.A D A T E

TOTAL D I S S O L V E D SOLIDS mgA TEMPERATURE - -c pH S I L I C A ('SlOz) mg/ I

CONDUCTANCE AT 25.C TOTAL IRON (Fe) mg/l T O T A L HARDNESS (COCO,) m g/I

TOTAL A L K A L I N I T Y (COCO,) mg/I P H E N A L K A L I N I T Y (Co COS) mq/1 MANGANESE(Mn1 mg/I

COLOUR O D O U R T U R B I D I T Y

pmhosfcm

A N I O N S mg/l pm . moll p m CAT I O N S

C A R B O N A T E (COS) C A L C I U M ( C d

MAGNESIUM (Ma)

S O D I U M I N o ) P O f A S S I U M I K )

I RON (DI SSOLVED) 33 ElCA R BON A T E (HCO,)

S U L P H A T E (SO,) C H L O R I D E t C l )

NO) NO) (NITROGEN!

0 TKN. (NITROGEN)

PHOSPHORUS ( P I

rn TKN T O T A L KJELDAHL'NITROGEN C H E M I S T R Y S I T E NO.

NO) N I T R I T E NOS m NITRATE

C H E M I S T R Y F I E L D T E S T S

T E S T B Y D A T E EOUIPMENT U S E D I I

-- -- CONTENTS OF FO-R

O D R l L L LOG 0 PUMP TEST DATA O C H E M I C A L ANALYSIS OSIEVE ANALYSIS 0 GEOPHYSICAL LOGS 0 REPORT

OTHER - .

PRO~UCTION TEST SUMMARY

lEST BY- 3AIL T E S T 0 PUMP T E S T 0

DRAWDOWN ?ATE ~

MATER L E V E L AT COMPLETION OF TEST PVAILABLE DRAWDOWN SPECIFIC CAPACITY 'ERME AB1 Ll TY STORAGE COEFF. rRANSMlSS lV lTY

DURATION OF TEST

SECOMMENDED PUMPING RATE RECOMMENDED PUMP SETTING

FROM I TO 1 D E S C R I P T I O N

I I

I I

I I

~

I

Page 32: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

WATER W E L L RECORD VICTORIA, BRITISH COLUMBIA DEPT OF ENVIRONMEN r, WATER RESOURCES SERVICE, WATER INVESTIGATIONS BRANCH

U a a c c J r To 0 P L A N L E G A L D E S C R I P T I O N LOT.>- SEC 1 TP. - R - D L ___ L A N D DISTRICT-I f l

OESC RI P T I v E LOC A T I o N CE~JVU L - ~ P ,-R /WL=-JWW W . . . - - X S L A N I ? ~ LICENCE NO -DATE-

8 ELEVATION O E S T I M A T E D DEPTH- OF- 0 SURVEYED C A S I N G OIAM. 6' L E N G T H =lo' M E T H O O OF CONSTRUCTION A ~ ~ ' Q Z H K Y CASING OIAM - LENGTH

SCREEN LOCATION SCREEN 0 S I Z E LENGTH T Y P E S A N I T A R Y SEAL Y E S 0 N O D S C R E E N O S I Z E - L E N G T H T Y P E

PERFORATED CASING 0 1-ENGTH PERFORATIONS F R O M - TO

GRAVEL PACK 0 L E N G T H - DIAM SIZE GRAVEL, ETC.

DISTANCE TO WATER 15.03 Id O E S T I M A T E D WATER L E V E L

F R O M ~ L c O M E A S U R E D E L E V A T I O N ___ ARTESIAN PRESSURE -- D A T E OF WATER L E V E L M E A S U R E M E N T WATER USE S R V A T I O M w u 0.B

1-1 WELL NO. [T KuZLru -

2 X Y NO.

C H E M I S T R Y

T E S T B Y E d V m TAL b b A m v - D A T E ,&w% T O T A L D I S S O L V E D SOLIDS mgA TEMPERATURE - .C pH S I L I C A (SlOr) mg/ I

CONDUCTANCE AT 2s.c TOTAL IRON ( fc) mg/l T O T A L HARDNESS (COCO,) m p/l

T O T A L A L K A L I N I T Y (COCOS) mQ/I PHEN. A L K A L I N I T Y (Co COS) mq/\ MANGANESE(Mn) mg/l

COLOUR O D O U R T U R B l D l T Y

Brnhoskrn

A N I O N S mg/1 egm CATIONS mg/I * p m

C A R B O N A T E (CO,) C A L C I U M (Co)

MAGNESIUM (Mg)

S O D I U M ( N a ) P O T A S S I U M (K)

IRON(DISSOLVE0)

B ICARBONATE (HCO,)

S U L P H A T E (SO,) C H L O R I D E ( C I 1 NO8 NO3 (NITROGEN)

TKN. (NITROGEN)

PHOSPHORUS ( P I

e TKN T O T A L KJELDAHL N I T R O G E N

NO8 N I T R I T E NOS NITRATE

C H E M I S T R Y F I E L D T E S T S

TEST B Y D A T E EOUIPMENT U S E D

CONTENTS OF FOLDEJ

U O R l L L LOG O P U M P TEST DATA l3 CHEMICAL ANALYSIS O S I E V E ANALYSIS 0 GEOPHYSICAL LOGS 0 REPORT

n T u r o

FROM I TO

0 I 1 0 ,

ATE -thQ2.%L8 4-- EST BY -AIR: ebtPa9- IAIL T E S T O PUMP T E S T O IATE rJ 5 6.p. H- DRAWDOWN UATER L E V E L AT COMPLETION OF TEST IVAILABLE DRAWDOWN S P E C I F IC C APACl TY 'E R M E AB I LI T Y STORAGE COEFF.

DURATION OF TZT-

RANSMISS~V~TY

IECOMMENDED PUMPING RATE IECOMMENOED PUMP SETTING

D E S C R I P T I O N

coDJ&bc&mmY

I I -

Page 33: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I I I I I 1 I

- 30 -

Appendix B

Contract Costs

Page 34: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

/' i

,,mephone: 245-2078 - 31 -

ISLAND WELL DRILLING Water M7cll Drilling Contractor '-1

W. J. W I L L I A M S , OWNER-OPERATOR - G R O U H E L ROAD, R.R. 1, L A D Y S M I T H , B.C. I I I I

Erovince of B.C., Nater Banagernent branch, 1,:inistry of Enviroment , Parl iament Bui ld ings , V i c t o r i a , B.C. V 8 V 1x5

3etCont rac t No. 75

tiarch 14, 1984

F i l e 92, F/B 1 0

Unit P r i c e Quani ty I t e m s

3 I A. ILob .& bemob. $200.00

2.

3 . I 1 4.

13 I 6.

b;ove Etwn s i t e s a t Coorr.bs Ilove Coombs t o

- - Hornby Is.

10" Cased a r i l l i n g 3O.Qo/ft.

10" re fund cas ing l'5.00/ft.

80.00/hr

6" Overlap e a s i n g 7. oo/f t.

1

1

1 82 '

82

57 5' 723 ' 3.5hrs.

15. 6" Aefundcasing S.OO/ft. 7 .5f t .

17. Standby 50. co/hr . 1.1 hr.

I 16. 6" Cap 6: F i t t i n g s 2O.OO/cap 2 ,I I

lu 5bags Cement €. OG/bag 5

F R E E ESTIMATES

c o s t

$ 200.00 J

- 2460.00 J

-1230.00 J

/ 402.50 j784.00 J

ir n-

I

$ 9261.50 57,2 C- 3.63. T o t a l of Items 1,4,6,7,12,16,17 &Cement --------- :.inus T o t a l of Items 1 3 tc 15 .................... &),2 67 e s@ 1268.50

11 Amount Due $ 7993- 00 4 3 1 q76.13

WATER MANAGEMENT BRANCH P* GOODS/SERVICES RECEIVED - - -

ON /??&& 9, /92+ L L

-. 4

3 2 - 48- Zlf -OS43/-zCY)/ 1

CHARGE TO 1 * - Y

I' ' ./ SIGNATURE r/Jd LA2 * - . I - 1 " - ,

DATE /it?acc/, 2 7 , /9$+ - I

I --- . -. ,

Page 35: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I 1 1 I I I I I I I I I I I I I I I

- 32 -

Appendix C

Water Chemistry Reports

Page 36: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

r I'

i

t

. --

2;8S 3550214 M G / L

CHROHf UM TOTAL

. _ _ _

Page 37: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I

I I:

L 0.1 2S90211 M A G N E S I U M WG/L- - TOTAL-

2601413 Y A N C A Y E S E @ I S S C L v E D

OD36 2h60214 COBALT V G / L - ?OTAL

.............. . . . . . . . . . . . . . . . . . . . . . . . . . . . . ... .. . .... I - .- ._ .-

Page 38: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I

Page 39: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I c - . I ., .

I I I f I I

r H E A P P R O X I M A T E COST OF THE A B W E TESTS 13 S 187.20 -_ -

..- - -

Page 40: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I 1 I I I I I 1 I I I I

- 37 -

Appendix D

Water Level Recorder Installation Specifications

Page 41: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

W.S. tiodge

Groundwater Section Water Management Branch

T' Senior Technician

Re: Establishment of Observation Well #287, Coornbs

I n t r o d u c t i o n

April 1 2 , 1984 Date:

File: 0183613-8-287

On Monday, March 12 , 1984 an automatic water level recorder was ins ta l led on the recently dr i l led observation well i n Coornbs. This well along with another observation well on Hornby Island was dr i l led under Governnent Contract No. 75 - "Dril l ing, Construction and Testing of Groundwater Observation Wells a t Coombs a n d Hornby Island, B.C."

The purpose of establishing th i s observat ion well was t o monitor long- term water level f luctuations i n the aquifer. Most dr i l led wells i n t h i s area report low well yields and poor water quality (mainly hydrogen sulphide problems). Coombs area residents rely solely on groundwater for the i r water requirements.

We1 1 Location

T h e well i s located w i t h i n the Burgoyne Road right-of-way adjacent to Lot 1 4 , Block 5 , Plan 1939 (Figures 1 and 2 ) . Attached to this memorandum i s a copy of "Permission t o Construct Works Within Crown Lands" which has been approved by the Ministry of Transportation and Hi ghways.

Well Dri l l ina a n d Testinc Details

Date Drilled llarch 5-6, 1984 DeDth of Well 92.3 metres (303 f e e t ) Di aneter of We1 1 152 m (6-inch) Aquifer Material S h a l e Stat ic Water Level 2.77 m (March 12 , 1984) Yell Yield Approx. 1 /2 gpm Dril l ing Cont rac tor Island Well Dril l ing - Red Williams

Equipment on S i t e

1 steel recorder housing 1 152 mm diameter steel casing extension (1.2 rn length) 1 101 mm diameter weight drive p ipe 1 wood recorder s t a n d w i t h painter 1 8 k g lead clock dr ive weight 1 127 mn diameter f loa t 1 1 2 metre graduated f loa t tape

Page 42: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I 1

I I I I I I I I I I I I I I

lI I

- 39 -

W.3, Hodae Anr i l 12. 1984

1 met r i c Stevens water l e v e l recorder (RG 30) w i t h Chelsea c lock (C6

1 6 ounce counterweight 2 c l i p s 1 V i r 0 lock

'59) w i t h 2 : l gage scale

The recorder housing and standpipes were painted dark preen and a M i n i s t r y o f Environnent i d e n t i f i c a t i o n l abe l and number (287) was attached t o the housing.

Ground Level Datum Eeasurenents

S t a t i c w a t e r l e v e l t o p o i n t e r .................. 4.279 metres Ground l e v e l (concrete pad) t o p o i n t e r ......... 1.510 metres Tape reading ................................... 1.956 metres

The c o r r e c t i o n f a c t o r t o be app l ied t o the tape reading i s t he re fo re t0.813 netres.

Ob server

Frs. Sharon Etty Highways f l a i ntenance Yard Box 249 P a r k s v i l l e , B.C. VOR ?SO Telephone: 248-6212

r lrs. Et ty w o r k s f o r the K i n i s t r y o f TransDortat ion and Highways i n P a r k s v i l l e and has aareed t o change the recorder char ts nonth ly and send then d i r e c t l y t o the M i n i s t r y o f Environnent rea ional o f f i c e i n Idanairno. There w i l l be - 110 charge f o r t h i s service.

D3ve Kalyn Techni c i an Grou ndwa t e r Sect i on Water Planagement Branch 387-1 115

DK / dma

Page 43: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

i ............. ._ ._ -- -. - .... .... __ I

DAIE SCALE: WM.. ... .I..: 50 ,000 . . . . . . .

70 ACCOMPANY REPORT ON

+tea? .............................................. I !larch9 .J 984.., Province of British Columbia Ministry of Environment

Coombs Observation Well No. 287 ........................... . . . . . . . . . . . . . . . . . . . . . . Y t \lei. .. ENGINEER

WATER M A N A G E M E N T BRANCH FILE No. 0153613-~-!?7 owc. No. . . I . . . . . . . . . .

I

P 0 I

Page 44: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

N

1

Province of British Columbia Ministry of the Environment ENVIRONMENTAL AND ENGINEERING SERVICE

WATER INVESTIGATIONS BRANCH

. -___.

DATE S C A I E VERI h2'/r3 7 0 ACCOMPANY REPORT ON

CoanBS - 005€R~AT\oN MJELL MOR 50' /rma9/84 NO* 207 fi!, WE/ ENGINEER

FILE No 32F d DWG N~ FGL'PE 2

I

I

4

b . j

/35. 7 ' V 4

56' b

Page 45: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I C

I 1 I I I I I I I I I I I

!'-->. S. Hodge TG- 'Senior Technician

Groundwater Sect ion Water Management Branch

Apr i l 12, 1984 Date: File: 0183613-B-288

Re: Establishment of Observation Well #288, Hornby Island

Introduction

On Tuesday, March 13, 1984 an automatic water level recorder was instal led on the recently dr i l led observation well on Hornby Island. T h i s well along with another observation well i n Coombs was dr i l led under Government Contract No. 75 - "Dril l ing, Construction and Testing o f Groundwater Observation Wells a t Coombs and Hornby Island, B.C."

The purpose of establishing t h i s observation well i s to mnitor lona- term water level f luctuations i n the aquifer. Many of the nearby dr i l led wells i n this area (T- y ) report poor water qual i ty and low well yields. Some well owners have also reported s a l t water i n t he i r wells. Well density i s very h i g h i n t h i s area and residents are very concerned a b o u t the q u a l i t y and quantity o f groundwater, as i t i s the i r sole source of water.

Well Location

Observation we1 1 6288 i s located w i t h i n the Central Road right-of-way adjacent t o L o t 2 , Section 1, P l a n 26598, Hornby Island (Figures 1 and 2 ) . Attached to th i s memorandum i s a copy of "Permission to Construct Works GIithin Crown Lands" which has been approved by the Ministry o f Transportation a n d Highways.

Well Dril l inq a n d Testinq Details

Date Drilled March 8-9, 1984 Depth o f We1 1 Di aneter of We1 1 152 m (6-inch) Aqui f e r Materi a1 'I Shal e Stat ic Water Level 15.031 m (March 13, 1984) \Jell Yield Approx. 5 gallons per hour Dril l ing Contractor Island Well Dril l ing - Red Williams

77.1 metres (253 f ee t )

Eauipmont on S i t e

1 steel recorder housing 1 152 mrn diameter steel casing extension (1.2 m length) 1 101 mm diameter weight drive pipe 1 wood recorder s t a n d w i t h pointer 1 8 k g lead clock drive weight 1 127 mm diameter f l o a t 1 1 2 metre graduated f l o a t tape

Page 46: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I

1 I I I 1 I i I I I I I I I I I I

F** - 43 -

April 1 2 , 1984 t9 W . .,: Hodge

1 metric Stevens water level recorder ( R G 38) w i t h Chelsea clock (CG

1 .6 ounce counterweight 2 c l ip s 1 Vir0 lock

4 3 ) w i t h 2 : l gage scale

T h e recorder housing and standpipes were painted dark green and a Flinistry of Environment ident i f icat ion label and number ( 2 8 8 ) was attached to the h o u s i n g .

Ground Level D a t u m Measurements

Stat ic water level t o pointer .................. 16.681 metres Ground level* to pointer ....................... 1 .650 metres Tape r e a d i n g ................................... 3 .229 metres

*Ground level i s 0.300 rn below bottom of s l i p - o n sleeve.

The correction factor to be applied to the tape reading is therefore +ll.R02 metres.

Observer

Mr. Gordon Batement Highways Kaintenance Yard General Delivery Hornby Island, B.C. VOR 1ZO Telephone: 335-2722 (Yard)

335-0227 (Home)

t4r. Bateman works f o r the Ministry of Transportation and Highways on Hornby Island and has agreed to change the recorder charts on the Denman Island observation \!e11 ( g 2 6 8 ) . These charts will be nailed direct ly to the Hinistry o f Environment regional off ice in Nanaimo a n d there will be - 110 charge f o r th i s service.

Dave Kalyn Technician Groundwater Section k' a t e r :,la n a gem e n t B r a n c h 387- 1115

Dt:/dma

Page 47: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I

. -. ..

...... __- .....

. . . . . . . ....... , . . .

i

Province of British Columbia Ministry of Environment WATER M A N A G E M E N T BRANCH '. .

-1 - ' '

! i

i i i ' !

!

. ... .- ........... , .

I

I

................................ -. -. ...

I 1 L I

...... .........

!

- I I

! i I j ........

j

!

! . - .... .....

1.. ...... ...j ...... i i

i 1 I i

I

P P

I

Page 48: PROVINCE OF BRITISH COLUMBIA MINISTRY OF ENVIRONMENT …a100.gov.bc.ca/appsdata/acat/documents/r6467/1163... · The hole was dry and subsequently backfilled and abandoned (Pictures

I I I I I I I I I I I I I I I I

I

3

2

3 S A h l D P I P & R R D.