Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 1
Proton PlanProton Plan
Booster Corrector UpgradeBooster Corrector Upgrade
Directors ReviewDirectors Review August 2006 August 2006
Presenter: Craig Drennan
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 2
AgendaAgenda
Progress Over The Last Year
The Plan For The Year Ahead
Management – Structure, Schedule and Cost
Project Risks and Managing Hazards
Conclusions
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 3
ProgressProgress
• Last Years Accomplishments Corrector Magnet Prototype: Many design and assembly
challenges were overcome to produce the first prototype.
Power Supplies / Amplifiers: Two varieties of magnet power supplies have been evaluated and found suitable for this project.
Controls: A new CAMAC power supply controller has been prototyped and software development has begun.
Prototype Testing: Testing for all these items is currently in progress.
Mechanical Designs: Initial measurements for new magnet stands were made during the Spring shut-down.
Cooling Water: The main header for the corrector magnet cooling water has been installed.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 4
Corrector Magnet DevelopmentCorrector Magnet Development
The first corrector package prototype has been
assembled and is being evaluated at MTF.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 5
Power SuppliesPower Supplies
• Power Supply Specifications
Current and voltage requirements are highlighted below.
Other power supply requirements are listed in the main
specifications document, Beams-doc-1881-v5 .
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 6
• Two Candidate Supplies To Drive Correctors
In-house design from AD/EES
• Advantages:
– Meets magnet field/current/voltage requirements
– Implements Fermi specified interlocks and diagnostics
– In house ability to service and repair
– Expected to be the lowest cost solution
• Weaknesses:
– Some chance that production will not meet the schedule
– Recent supply modifications have no history in the field
Power SuppliesPower Supplies
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 7
Power SuppliesPower Supplies
• Two Candidate Supplies To Drive Correctors (continued)
Vendor product from Copley Controls
• Advantages:
– Exceeds magnet field/current/voltage requirements
– Commercially proven quality (mainly used in MRI)
– Strongly deterministic delivery schedule.
• Weaknesses:
– More expensive
– No in-house repair ($300.00 flat repair fee)
– Needs additional hardware to support desired diagnostics
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 8
Power SuppliesPower Supplies
• Four Quadrant Switching Power Supplies
Design in AD/EE Support
• Magnet I_peak V_peak I_rms @ 50 degC
• Dipoles 40 A 150 V 40 A
• Sextupoles 40 A 150 V 40 A
• Norm. Quad. 65 A 150 V 65 A
• Skew Quad. 10 A 150 V 10 A
• Approx. Cost: < $3,000.00 each
• Magnet I_peak V_peak I_rms @ 50 degC
• Dipoles 40 A 150 V 40 A
• Sextupoles 40 A 150 V 40 A
• Norm. Quad. 65 A 150 V 65 A
• Skew Quad. 10 A 150 V 10 A
• Approx. Cost: < $3,000.00 each
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 9
Power SuppliesPower Supplies
• Model 231HC Power Amplifier from Copley Controls
One model used for all magnets except the skew quad.
• I_peak V_peak I_rms @ 35 degC
• 90 A 150 V 70 A
• Approx. Cost $4,000.00 each
• I_peak V_peak I_rms @ 35 degC
• 90 A 150 V 70 A
• Approx. Cost $4,000.00 each
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 10
ControlsControls
New Power Supply Ramp Controllers
• Will output ACNET programmable current reference curves for the power amplifiers and monitor amplifier tracking.
• Will provide digital Enable/Inhibit and monitor digital status.
• Controller specifications available, Beams-doc-1882-v3 .
• CAMAC C473 Users Manual available, Beams-doc-2361-v2
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 11
ControlsControls ACNET / Software work to support the new CAMAC
ramp controller has begun. Specification of more advanced applications will begin
soon.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 12
New Beam Position MonitorsNew Beam Position Monitors
New BPM's are being designed to fit into the aperture
of the new corrector package. • Reference Jim Crisp, “Proposed Booster BPM Geometry”,
Beams-doc-2221-v1
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 13
InstallationInstallation
• Corrector Upgrade involves two installations.
Summer 2007 Shutdown
• Booster long straight corrector system installation
• Upgrade of vertical beam control
Summer 2008 Shutdown
• Booster short straight corrector system installation
• Upgrade of horizontal beam control
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 14
InstallationInstallation
New Racks and Cables for the Corrector System • Rack space and cable penetrations have been
identified.• A booster floor plan has been marked up (Beams-doc-
1883, version 1) to show the possible location of the new corrector magnets, new racks, and cable routing.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 15
InstallationInstallation
• Estimate Rack Layout Using AD/EES Amplifiers
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 16
InstallationInstallation
• Estimate Rack Layout Using Copley Amplifiers
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 17
InstallationInstallation
• New Plumbing for Corrector Package Cooling
Water
• Total water flow -- 1/2 GPM at 60 PSI water pressure drop.
• Water temperature rise -- 20 C
• The current water system in the Booster is expected to be able to handle this additional load.
• The main header and shut-offs were installed in 2006.
• We are currently investigating water filtering schemes.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 18
InstallationInstallation
New Magnet Supports and Long and Short Straight Spool Piece Designs
• New cradle supports in the short straights will be designed for the Horizontal Corrector project.
• Initial measurements were taken during 2006 shutdown, and the design and drafting effort has begun.
• New Gamma-T Magnets will be included.
Booster Long Period 14
Booster Short Period 22
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 19
ES&H / QAES&H / QA
• ES&H Project Coordinator, Mike Andrews
• Design reviews to evaluate:
Equipment sizing – power cables, cooling capacity,
magnet stands and supports
Interlocks for equipment and personnel safety.
Electrical exposures in racks or in the enclosure ?
Can we ease trouble-shooting and maintenance in
light of NFPA70E requirements.
More -->
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 20
ES&H / QAES&H / QA
• Magnet and Power Supply Production & Testing
Will need considerations made for receiving and
handling of production units.
Will continue the commitment to designing safe test
stands and documenting procedures. (MTF works hard
at this) more -->
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 21
ES&H / QAES&H / QA
• Magnet Removal and Installation Hazard Analysis
Will work closely with the Task Managers, ES&H
Coordinator and other experts from Electrical and
Mechanical Support.
Job may require reviewed and approved lifting fixtures
Focus on avoiding strains, sprains, head injuries, cuts,
burns and electric shock.
Safety and Quality Monitored with Daily Walk
Throughs with Task Manager and ES&H Coord.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 23
Schedule (page 1 of 2)Schedule (page 1 of 2)
•
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 24
Schedule (page 2 of 2)Schedule (page 2 of 2)
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 25
Project RisksProject Risks
• Performance of Power Supplies, Controls, Interconnects and Interlocks (Quality Assurance).
Design reviews including ES&H issues. Production unit test stands will be required to exercise
all component functions and provide for burn-in. Interlock testing will be performed to ensure equipment
and personnel are protected from identified hazards.
• Maintaining Installation Schedules
Procurements will be made at the earliest opportunities
Tasks and task dependencies will be tracked and
continuously evaluated to ensure that tasks are
initiated and completed as early as possible.
Proton Plan Director's Review 8/15/06 – Booster Corrector Upgrade Drennan 26
Simple ConclusionsSimple Conclusions
• Good progress has been made in the various prototyping efforts .
• The current focus is on testing
• We are currently on track for a June 2007 installation.
• The corrector upgrade will greatly improve the throughput in the Booster.