Planning Act 2008 (as amended) EN020001 – Application by National Grid for an Order Granting Development Consent for the Hinkley Point C Connection Project Proposed route alignment accompanied site inspection itinerary 15 – 17 April 2015 The itinerary for the accompanied site inspection of the proposed route can be found below. In the tables below, references to the sites in the ‘Comments’ column are not exclusive but indicate what the Panel would like to see at this stage. Please note that the Panel’s inspection of sites is not an opportunity to provide any oral representations on the project or discuss evidence. It is an opportunity for the Panel to look at the physical features that can be seen on, or from the sites. Participants may be invited by the Panel to point out specific features or sites of interest. Clothing It will be necessary for all parties to wear appropriate sturdy footwear and weather-proof clothing. It is recommended that participants bring and wear high visibility jackets when walking on the public highway. Joining the site visit It is not possible to predict precisely how long each part of the visit will last. Parties wishing to join the visit should attend the advertised start point in good time. The Panel will not wait for parties who are not present at the start point at the notified time. Parties intending to join en route should notify the Planning Inspectorate, giving a contact telephone number. Maps of the route for sessions 1 and 2 and the meeting place for session 3 are at Annex A. Sites on private land Access onto private land is at all times by permission of the person controlling it; householders, occupiers and landowners may refuse to allow some persons accompanying the Panel onto their land. Under those circumstances, the Panel will decide whether or not to proceed with that part of the visit, and may ask those refused access to wait outside. A coach will transport participants around the port areas for session 3. It will not be possible to disembark from the coach during the inspection. Notifications To ensure the smooth running of the Panel’s inspection, any changes in attendance should be notified to the Case Officer, Siân Evans, by 5pm on Monday 13 April 2015 by telephone on 0303 444 5000 or email at
1
[email protected]. Please provide contact details for the day and ensure the Planning Inspectorate is made aware of any special access requirements for any participants. Cancellations Please note that in the unlikely event that these accompanied site inspections are cancelled due to unforeseen circumstances we shall endeavour to contact attendees beforehand but we would advise that you should regularly check the Planning Inspectorate’s website which can be viewed here: http://infrastructure.planningportal.gov.uk/projects/south-west/hinkley-point-c-connection/
2
Detailed itineraries Wednesday 15 April 2015: Proposed Route Alignment, Session 1 Site Meeting/stopping
point Approximate timings
Confirmed attendees Comments
Meet at Worle Railway Station car park
The new car park at Worle Railway Station, Diamond Batch, BS22 6WA located on the southbound side of the track.
9.30am – 9.45am
Jim Brown – National Grid Aileen Smith – National Grid Richard Gott – National Grid Doug Bamsey - Sedgemoor District Council (SDC) Paul Sobczyk - SDC Andrew Goodchild – West Somerset Council (WSC) Cllr Anne Fraser - SDC Eileen Corkish - Mark Parish Council (MPC) Alyn Jones – Somerset County Council (SCC) Tess Bond – SCC
Briefing at 9.30am, depart 9.45am prompt.
Travel time 9.45am – 10.15am
Travel between Worle and Horsey Levels.
Horsey Levels Scheduled Monument
Horsey Manor Farm, Horsey Lane, TA7 8QJ Private land.
10.15am – 11.00am
Jim Brown – National Grid Aileen Smith – National Grid Richard Gott – National Grid Doug Bamsey – SDC Paul Sobczyk - SDC Andrew Goodchild – WSC Cllr Anne Fraser - SDC Eileen Corkish - MPC
Private land. To view: Horsey levels scheduled
monument; deserted village Locations of the two proposed
cable sealing end compounds Extent of land proposed to be
used for mitigation planting
3
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
Alyn Jones – Somerset CC Tess Bond – Somerset CC Mel Barge – Historic England Alan Hudson
Location of the construction compound
Location of pylons VQ043R, VQ044R and ZGA1
Travel time 11.00am – 11.30am
Travel between Horsey Levels and East Huntspill.
East Huntspill, Factory Lane
Factory Lane, Bason Bridge, TA9 4RN
11.30am – 12.00 midday
Jim Brown – National Grid Aileen Smith – National Grid Richard Gott – National Grid Doug Bamsey - SDC Paul Sobczyk - SDC Andrew Goodchild – WSC Cllr Anne Fraser – SDC Eileen Corkish – MPC Alyn Jones – SCC Tess Bond – SCC Nigel Litton – East Huntspill Parish Council (EHPC) Claire Wright – EHPC Maurice Wall – EHPC Richard Wall
To view: Factory Lane and Hackmead
Lane junction. Jo Bird & Co Ltd’s premises.
Private land. To view: Riverview Farm, TA9 4RN.
Travel time 12.00 midday – 12.15pm
Travel between East Huntspill and Mark.
Mark Ashtrees, Mark Causeway, Mark, TA9 4QF Private land.
12.15pm– 1.15pm
Jim Brown – National Grid Aileen Smith – National Grid Richard Gott – National Grid Doug Bamsey – SDC Paul Sobczyk - SDC
Private land. To view: Location of proposed T-pylon
LD17 at Ashtrees. Area Joint Councils have
proposed for orchard planting
4
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
NB parking only available for 4 vehicles – already allocated to the Planning Inspectorate
Andrew Goodchild – WSC Cllr Anne Fraser - SDC Eileen Corkish - MPC Alyn Jones – SCC Tess Bond – SCC
at Ashtrees. Public land/highway on foot. To view: Locations of the new viewpoints
VPB31 and VPB32, Mark First School ES viewpoints VPB6, VPB29 and
VPB9. Travel time 1.15pm –
1.30pm Travel between Ashtrees and Mark
Village Hall. Lunch stop
Mark Village Hall Vole Road, Mark, TA9 4NY
1.30pm – 2.30pm
Seating and toilet facilities provided. Participants are required to bring their own lunch.
Travel time 2.30pm – 2.50pm
Travel between Mark Village Hall and Tarnock.
Tarnock Chapel Road, BS26 2TB
2.50pm – 3.50pm
Jim Brown – National Grid Aileen Smith – National Grid Richard Gott – National Grid Doug Bamsey - SDC Paul Sobczyk - SDC Andrew Goodchild – WSC Cllr Anne Fraser - SDC Eileen Corkish - MPC David Shepherd Catherine Fisher Sue Hayes – Badgworth Parish Council
Public land/highway on foot. To view: New viewpoint VPB30 ES viewpoints VPB22 and
VPB21 Acacia Farm Willows Farm Tarnock Garage Locations for haul road, bell
mouths and construction compounds.
5
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
Private land. The proposed location of T-
pylon LD32 Travel time 3.50pm –
4.30pm Travel between Tarnock and
Worle. Worle Railway Station
Return 4.30pm
6
Thursday 16 April 2015: Proposed Route Alignment, Session 2 Site Meeting/stopping
point Approximate timings
Confirmed attendees Comments
Meet at Worle Railway Station car park
The new car park at Worle Railway Station, Diamond Batch, BS22 6WA, located on the southbound side of the track.
9.30am – 9.45am
Jim Brown – National Grid Aileen Smith – National Grid Paul Cumpstone – National Grid Graham Quick – North Somerset Council (NSC) Helen Adams – Alliance Homes
Briefing at 9.30am, depart 9.45am prompt.
Travel time 9.45am – 10.15am
Travel from Worle to site of proposed Cable Sealing End (CSE) compound.
Site proposed for South of Mendips Cable Sealing End (CSE) Compound, Biddisham
Access via Hams Lane, off east/west unclassified road south of Loxton village. Private land. NB park either side of gate, not on field if ground conditions are wet.
10.15am – 11.15am
Jim Brown – National Grid Aileen Smith – National Grid Paul Cumpstone – National Grid Graham Quick – NSC Helen Adams – Alliance Homes Doug Bamsey – SDC Paul Sobczyk - SDC Mark Amesbury Julie Amesbury
Private land. To view: Pegged out footprint for
proposed CSE compound Location of proposed screen
planting (embedded mitigation).
Panel will wish to observe surrounding highpoints visible from the proposed CSE compound site.
Travel time 11.15am – 12.00 midday
Travel from Biddisham to proposed Sandford Substation site.
Sandford site
Droveway Farm, Nye Road,
12.00 midday – 1.00pm
Jim Brown – National Grid Aileen Smith – National Grid
Private land. To view: Locations for the new viewpoint
7
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
proposed for Substation
Sandford, BS25 5QF Private land.
Paul Cumpstone – National Grid Graham Quick – NSC Helen Adams – Alliance Homes Brian Keedwell
VPD31 and other agreed viewpoint on private land.
Pegged out footprint for the proposed Substation, goal-post T-pylons LD39A and LD39B, T-pylon 40, wooden post pylons
Proposed locations for construction compounds
Proposed haul road Alignment of footpath D1.F1 Panel will wish to observe
surrounding highpoints visible from the proposed substation site.
Travel time 1.00pm – 1.15pm
Travel from Sandford Substation to Cadbury Garden Centre.
Lunch stop Cadbury Wyevale Garden Centre Smallway, Congresbury BS49 5AA
1.15pm – 2.15pm
Lunch can be bought here.
Travel time 2.15pm – 2.30pm
Travel from Congresbury to Moorland Park.
Moorland Park
Moorland Park, Hewish, A370 BS24 6SQ Private land.
2.30pm – 3.00pm
Jim Brown – National Grid Aileen Smith – National Grid Paul Cumpstone – National Grid Graham Quick – NSC Helen Adams – Alliance Homes
Private land. To view: Location of properties at
Moorland Park Proposed haul road location
(pegged out)
8
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
Peter Penfold Liz Greaves – Congresbury Parish Council Cllr Tom Leimdorfer – NSC
T-pylon LD51 Bell mouth location Possible alternative amenity
field Applicant may be asked to
indicate locations of other nearby T-pylon locations in relation to existing lattice pylons.
Travel time 3.00pm – 3.30pm
Travel time from Moorland Park to Elm Tree Park.
Elm Tree Park
Elm Tree Park, off Sheepway, Portbury BS20 7WW Private land.
3.30pm – 4.00pm
Jim Brown – National Grid Aileen Smith – National Grid Paul Cumpstone – National Grid Graham Quick – NSC Helen Adams – Alliance Homes John Hall Mike Phipps – Portbury Parish Council
Private land. To view: Location of properties at Elm
Tree Park Location of the new viewpoint
VPF8.
Travel time 4.00pm - 4.30pm
Travel from Elm Tree Park to Worle Station.
Worle Railway Station
Return 4.30pm
9
Friday 17 April 2015: Proposed Route Alignment, Session 3
Site Meeting/stopping point
Approximate timings
Confirmed attendees Comments
Bristol Port Bristol Port Company (BPC)’s offices at St Andrew’s House, St Andrew’s Road, Avonmouth BS11 9DQ
10.00am – 12.30pm
Jim Brown – National Grid Aileen Smith – National Grid Tom Watson – Arup for Bristol City Council Gillian Ellis-King – South Gloucestershire Council
Briefing at 10am, depart 10.30am prompt. Note there is no opportunity to join this session en route. The entire visit will be undertaken by coach. The Panel would like to visit as close as possible to the location of ES viewpoint VPG8.
10
Tarnock
Horsey Levels Scheduled Monument
Mark, Ashtrees
East Huntspill –Factory Lane
Worle Railway Station
Return to WorleRailway Station via M5 Junction 22
Suggested driving route for Hinkley Route site visit – Day 1
Join M5 southbound at Junction 21
Exit M5 Junction 23
Start/finish – Worle Railway Station
Site visit location
Start/finish – Worle Railway Station
Site visit location
Lunch stop
Proposed driving route
Mark Village Hall
Annex A
Elm Tree Park
Proposed site for Sandford Substation
Moorland Park
Proposed site for Cable Sealing End Compound South of Mendips, Biddisham
WorleRailway Station
Cadbury Garden Centre, Yatton
Return to WorleRailway Station via M5 Junction 19
Start/finish – Worle Railway Station
Site visit location
Start/finish – Worle Railway Station
Site visit location
Lunch stop
Proposed driving route
Suggested driving route for Hinkley Route site visit – Day 2
Start/finish – Worle Railway Station
Site visit location
Start/finish – Bristol Port Company
Bristol Port Company, St Andrew's House, St Andrew's Road,
Avonmouth BS11 9DQ. Car parking is free.
Suggested driving route for Hinkley Route site visit – Day 3