JUMUCHA ENTERPRISES 24-08-15 PROPOSED PROGRAMME OF WORKS FOR THE CONSTRUCTION OF A 1x2 CRB Date: 24nd AUGUST , 2015 Contractor: JUMUCHA ENTERPRISES Construction Period: 20 WEEKS ACTIVITIES MON -1 1 2 3 4 5 6 Day -30 -15 15 30 15 30 15 30 15 30 15 30 15 30 MOBILIZATION SITE CLEARANCE AND SETTING OUT EXCAVATION AND EARTH WORKS CONCRETE WORK BLOCKWORK AND BRICKWORK ROOF COVERING METAL WORK CARPENTRY & JOINERY PLUMBING INSTALLATION ELECTRICAL INSTALLATION AIR CONDITIONING INSTALLATION FLOOR,WALL & CEILING FINISHINGS GLAZING PAINTING AND DECORATING EXTERNAL WORKS HANDING OVER PROPOSED LABOUR CHART

PROPOSED PROGRAMME OF WORKS FOR 1X 2 CRB.xls

Embed Size (px)

Citation preview

Page 1: PROPOSED PROGRAMME OF WORKS FOR 1X 2 CRB.xls

JUMUCHA ENTERPRISES 24-08-15

PROPOSED PROGRAMME OF WORKS FOR THE CONSTRUCTION OF A 1x2 CRB

Date: 24nd AUGUST , 2015 Contractor: JUMUCHA ENTERPRISES Construction Period: 20 WEEKS

ACTIVITIES MONTH -1 1 2 3 4 5 6

Day -30 -15 15 30 15 30 15 30 15 30 15 30 15 30

MOBILIZATION

SITE CLEARANCE AND SETTING OUT

EXCAVATION AND EARTH WORKS

CONCRETE WORK

BLOCKWORK AND BRICKWORK

ROOF COVERING

METAL WORK

CARPENTRY & JOINERY

PLUMBING INSTALLATION

ELECTRICAL INSTALLATION

AIR CONDITIONING INSTALLATION

FLOOR,WALL & CEILING FINISHINGS

GLAZING

PAINTING AND DECORATING

EXTERNAL WORKS

HANDING OVER

PROPOSED LABOUR CHART