1. Onshore Pipeline Installation 2. Shore Approach Construction 3. Offshore Pipelaying 4. Riser Installation 5. Post-lay Trenching Proposed Methodology (Preliminary)

Proposed Methodology Shore Approach

Embed Size (px)

Citation preview

Page 1: Proposed Methodology  Shore Approach

1. Onshore Pipeline Installation

2. Shore Approach Construction

3. Offshore Pipelaying

4. Riser Installation

5. Post-lay Trenching

Proposed Methodology (Preliminary)

Page 2: Proposed Methodology  Shore Approach

TA B L E O F C O N T E N T S

1) BRIEF INTRODUCTION TO COMPANY’S KEY PERSONNEL

2) FIELD MAP AND PIPELINE ROUTE

3) SCOPE OF WORKS

4) PIPELINE CONSTRUCTION AND INSTALLATION OVERVIEW

5) PROJECT SCHEDULE AND DURATIONS

6) PROPOSED PROJECT MANAGEMENT TEAM (PMT)

7) PIPELAY BARGE ‘OMBAK BIRU SATU’

1) PIPELAY BARGE ‘OMBAK BIRU SATU’ SPECIFICATIONS AND BARGE LAYOUT

2) BARGE WELDING STATIONS AND BARGE ROLLER ARRANGEMENT

3) STINGER DETAILS

4) PIPELAY BARGE PHOTOS

8) ONSHORE PIPELINE INSTALLATION FROM LANDFALL POINT TO LANDFALL STATION (APPROXIMATELY 5.3KM)

9) SHORE APPROACH & BEACHPULL METHODOLOGY AT LANDFALL POINT

10) SUBSEA PIPELAYING BY PIPELAY BARGE ‘OMBAK BIRU SATU 1 (APPROXIMATELY 12 KM)

1) ENGINEERING ANALYSIS

11) RISER INSTALLATION AT TBDP-A PLATFORM

12) PRE-COMMISSIONING METHODOLOGY

13) PRE AND POST TRENCHING WORKS SCOPE AND METHODOLOGY

14) SUMMARY OF MARINE SPREAD & MAJOR EQUIPMENT

15) PROJECT RELATED PHOTOS

Thai Binh-Ham Rong Gas Pipeline

Page 3: Proposed Methodology  Shore Approach

LINEAR WINCH AT LANDFALL

POINT

PRE-TRENCH PRIOR TO PIPE PULLING FROM KP11.0 TO KP13.03

SUBSEA PIPELINE= 13.03 km = 1,056 jointsKP0.00

KP13.03

LAYING DIRECTION

300 Linear Winch

LAY BARGE

LINEAR WINCHSUBSEA

SPOOL TIE-IN

LAUNCHER AT TBDP-A

KP0.00

LAYING DIRECTIONPulling Direction

KP5.283

LAND PIPE = 5.283 km = 428 joints

SUBSEA PIPELINELANDFALL STATION (KP5.283)

LANDFALL POINT

TBDP-A

EXCAVATION USING

AMPHIBIOUS EXCAVATOR

RECEIVER AT LANDFALL STATION

Page 4: Proposed Methodology  Shore Approach

NO. DESIGNATION NO.OF PERSON

1 PROJECT MANAGER 1

2 CONSTRUCTION MANAGER (OCS) 1

3 OPERATION MANAGER 1

4 HEAD OF PLANNING AND COST CONTROL 1

5 HEAD OF PROCUREMENT AND SUB-CONTRACTING 1

6 HEAD OF MARINE AND LOGISTIC 1

7 LOGISTIC COORDINATOR 1

8 ENGINEERING MANAGER 1

9 FIELD ENGINEER 4

10 QA/QC COORDINATOR 1

11 SAFETY COORDINATOR 1

12 DRAUGHTMAN 1

13 DOCUMENT CONTROLLER 1

TOTAL OF PMT 16 PERSONS

Page 5: Proposed Methodology  Shore Approach

ENGINEERING ANAYLSIS - SHORE APPROACH - BEACH PULL CALCULATION - SHORE APPROACH – COFFERDAM DESIGN ANALYSIS

- PIPELAY ANALYSIS ( START-UP, LAYING,LAYDOWN )- RISER ANALYSIS- MISCELLANEOUS CALCULATION ( ANCHOR CATENARY, LINEAR WINCH HOLD-BACK

TIE-IN DOWN DESIGN, PULLING HEAD DESIGN , ETC.)

OPERATION / INSTALLATION PROCEDURES - PRE-LAY SURVEY ( HYDROGRAPHIC PROCEDURE )- WELDING PROCEDURE SPECIFICATION ( WPS )- PROJECT QUALITY PLAN ( PQP )- SAFETY MANAGEMENT MANUAL- ONSHORE PIPELINE PROCEDURE- SUBSEA PIPELINE INSTALLATION PROCEDURE - SHORE APPROACH - BEACH PULL PIPELINE PROCEDURE- RISER INSTALLATION PROCEDURE- SUBSEA SPOOL INSTALLATION PROCEDURE- PRE-TRENCHING PROCEDURE- PRE-COMMISSIONING PROCEDURE (PIGGING, HYDROTESTING, DEWATERING, AIR-DRYING &

NITROGEN PACKING)

- POST-TRENCHING PROCEDURE- PROJECT CLOSED-OUT REPORT

Page 6: Proposed Methodology  Shore Approach

Pipelay Barge Ombak Biru Satu

Page 7: Proposed Methodology  Shore Approach

Barge Particulars :

- Length: 242ft ( 73.74m)

- Breadth : 80 ft (24.38m)

- Moulded Draft : 16ft (4.88m)

- Light Draft : 1.8m

- Operating Draft : 2.0m

- Accommodation : 52 pax

Mooring System :

- 8 point mooring winches with delta flipper anchor

- 800m Anchor Wire

- Anchor buoy : 12 nos

Pipe Laying Facilities :

- Pipe Conveyor

- Pipe Alignment System

- Tensioner : 60MT

- A&R Winch : 120MT

- Main Compressor : 900cfm

- Air Tugger : 10 MT

- Stinger Length – 25 m length

Pipelay Station :

- Cleaning and Bevelling

- Alignment/ Fit-up and Welding Station #1 ( Root & Hot Pass )

- Welding Station #2 ( Filling )

- Welding Station #3 ( Filling & Capping )

- Tensioner

- X-Ray and Repair Station

- Field Joint Coating ( Wrapping and In-Fill Coating )

Page 8: Proposed Methodology  Shore Approach

General Layout of Pipelay Barge

Page 9: Proposed Methodology  Shore Approach
Page 10: Proposed Methodology  Shore Approach
Page 11: Proposed Methodology  Shore Approach
Page 12: Proposed Methodology  Shore Approach
Page 13: Proposed Methodology  Shore Approach
Page 14: Proposed Methodology  Shore Approach

Typical Beachpull

Page 15: Proposed Methodology  Shore Approach

General Beach-pull Arrangement

Page 16: Proposed Methodology  Shore Approach

Methodology:

Page 17: Proposed Methodology  Shore Approach

Methodology:

Page 18: Proposed Methodology  Shore Approach

Methodology:

Page 19: Proposed Methodology  Shore Approach
Page 20: Proposed Methodology  Shore Approach
Page 21: Proposed Methodology  Shore Approach

9

14

125

102

Page 22: Proposed Methodology  Shore Approach

-

PREPARATION WORKS :

- RIG-UP 300MT LINEAR WINCH AT SHORE APPROACH LOCATION

- RIG-UP LONG-ARMED EXCAVATOR ONBOARD PONTOON BARGE

SHORE APPROACH METHODOLOGY :

- SET-UP PIPELAY BARGE ( W.D = 5m at ACD )

- PASS PULLING CABLE TO BARGE ( MESSENGER LINE ) BY SPEED BOAT

- PIPELAY BARGE TO HEAVE UP PULLING CABLE

- PIPELAY BARGE TO CONNECT PULLING CABLE TO PULLING HEAD

( PULLING HEAD cum UNDERWATER RECEIVER FOR GAUGING )

- COMMENCE PULLING PIPE STRING WITH BUOYANCY TANKS

( OFF-BOTTOM PULL )

- MAXIMUM 150 MT CALCULATED TO PULL 2,500M (203 JTS)

Page 23: Proposed Methodology  Shore Approach

Pre-Lay Survey & Post-Lay Survey Works- Survey Boat

Shore Approach & Subsea Pipeline Installation Works- Pipelay Barge – Ombak Biru Satu- Anchor HandlingTug- Crew Boat

Tow & Tie-in Pipe Strings at Mud Flat- 2 x Flat-bottomed boats

Riser and Spool Installation Work at TBDP-A- Pipelay Barge – Ombak Biru Satu- Anchor HandlingTug- Crew Boat

Pre- and Post-lay Trenching Works- Long-armed Excavators onboard Steel Barge- Jet-sled Trencher

Equipment & Vessels

Page 24: Proposed Methodology  Shore Approach

Shore Approach at Con Vanh & Subsea Pipeline Installation

- Air Diving System

- 150MT crawler crane ( onboard pipelay barge )

- NDT Equipment & Spread

- Survey Equipment

- Field Joint Coating Equipment

- 300 MT Linear Winch

- Long Arm Excavator

Page 25: Proposed Methodology  Shore Approach

Thai Binh-Ham Rong Gas Pipeline

Page 26: Proposed Methodology  Shore Approach
Page 27: Proposed Methodology  Shore Approach

POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM

Page 28: Proposed Methodology  Shore Approach

TRENCHER

Water for ballasting

Air for deballasting

Previous contain material been

push out

POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM

Page 29: Proposed Methodology  Shore Approach

POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM

Page 30: Proposed Methodology  Shore Approach

APPROACHING COFFERDAM /STARTUP POINT

Thai Binh-Ham Rong Gas PipelinePOST-TRENCHING WORKS AT MUD-FLAT AREA USING

JET-SLED TRENCHING SYSTEM

Page 31: Proposed Methodology  Shore Approach

INITIAL POSITIONING OF TRENCHER BY DIVER

POST-TRENCHING WORKS AT MUD-FLAT AREA USING JET-SLED TRENCHING SYSTEM

Page 32: Proposed Methodology  Shore Approach

Our Experience : Beach Pull Operation 1

Page 33: Proposed Methodology  Shore Approach

Our Experience: Typical Mid Point Tie-in Operation 1

Page 34: Proposed Methodology  Shore Approach

Our Experience : Mid Point Tie-in Operation 2

Page 35: Proposed Methodology  Shore Approach

Our Experience: Beach Pull Operation 2

Page 36: Proposed Methodology  Shore Approach

Our Experience: Laying Through Sand Bank Area

Page 37: Proposed Methodology  Shore Approach

Our Experience: Typical Water Master During Excavation Operation

Page 38: Proposed Methodology  Shore Approach

Our Experience:Typical Linear Winch For Beach Pull Operation

Page 39: Proposed Methodology  Shore Approach

Our Experience:Barge with Excavator for Pre-Trenching

Page 40: Proposed Methodology  Shore Approach

1. Onshore Pipeline Installation

2. Shore Approach Construction

3. Offshore Pipelaying

4. Riser Installation

5. Post-lay Trenching

Proposed Methodology (Preliminary)