Upload
duongkiet
View
216
Download
1
Embed Size (px)
Citation preview
GEOTECHNICAL REPORT
PROPOSED BOWLDER CREEK
CULVERT REPLACEMENT, HIGHWAY 97
23 KM WEST OF CHETWYND, B.C.
Prepared for
B.C. MINISTRY OF TRANSPORTATION AND INFRASTRUCTURE
NORTHERN REGION
Prepared by
GEONORTH ENGINEERING LTD.
3975 18th AVENUE
PRINCE GEORGE, B.C., V2N 1B2
Phone: 250-564-4304 Fax: 250-564-9323
PROJECT No. K-4544
March 21, 2018
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
TABLE OF CONTENTS
Page No.
1.0 INTRODUCTION 1
2.0 GEOLOGICAL BACKGROUND 1
3.0 SITE INVESTIGATION
AND SUBSURFACE CONDITIONS 2
4.0 DISCUSSION AND RECOMMENDATIONS 4
4.1 Pile Foundations 5
4.2 Seismic Design Considerations 7
4.3 Earth Embankment Fills and
Barrier Flare Embankment Widening 7
4.4 Retaining Walls 9
4.5 Bridge End Fill 10
4.6 Pavement Structure 11
4.7 Spread Footing Foundations 11
4.8 Trench Crossings 12
4.9 Aggregates and Fill 13
5.0 CONSTRUCTION REVIEW 13
6.0 CLOSURE 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
APPENDICES
APPENDIX A
Site Location Plan Drawing 4544-A1
Site Plan Showing Drill Hole Locations Drawing 4544-A2
Profile Along Existing Road Centreline Drawing 4544-A3
APPENDIX B
Drill Hole Summary Logs 11 pages
Materials Classification Legend 1 page
APPENDIX C
Laboratory Test Results Plates 4544-C1 to C7
APPENDIX D
Typical Embankment Widening Detail Drawing 4544-D1
Lock Block Retaining Wall Drawing 4544-D2
Typical Lateral Earth Pressures Drawing 4544-D3
Transition Detail: Existing to New Road Structure Drawing 4544-D4
Details of Trench for Culvert Installation Drawing 4544-D5
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
1.0 INTRODUCTION
B.C. Ministry of Transportation and Infrastructure (BCMoTI) is replacing an existing
culvert at Bowlder Creek on Highway 97 and commissioned GeoNorth Engineering Ltd.
(GeoNorth) to carry out a geotechnical investigation at the crossing. The work was carried out
under “As and When” Contract Number 860C5933. The crossing is about 100 m west of the
intersection with Hasler Road and about 23 km west of Chetwynd, B.C., at BCMoTI Landmark
Kilometre Inventory segment 1161, Okanagan-Cariboo-Alaska, kilometre 123.16. Bowlder
Creek is a tributary of Pine River. The confluence with Pine River is about 0.5 km south of the
highway crossing. The site location is shown on Drawing 4544-A1, in Appendix A.
The existing crossing is an approximately 4.5 m high soil embankment with a 2.4 m
diameter corrugated steel culvert. The new crossing will be a 31.5 m long steel girder and
concrete deck bridge. The bridge will be supported at the west and east abutments by single
rows of four 762 mm diameter by 12 mm wall thickness steel closed-end pipe piles. Project
stationing, geometric details and test hole locations are shown on Drawing 4544-A2, in
Appendix A.
A previous report dated February 22, 2017 presented the results of the site investigation,
described existing subsurface stratigraphy and presented preliminary geotechnical
recommendations for design and construction of spread footings, driven pile foundations and the
highway embankment. This report presents finalized geotechnical recommendations for the
project.
2.0 GEOLOGICAL BACKGROUND
The surficial soil deposits at the site are the result of the last glaciation, which ended with
melting of the glacial ice between about 10,000 and 12,000 years before present. Geological
Page 1 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
Survey of Canada Bulletin 3311 describes the chronology and landforms that were created in
Pine Valley during de-glaciation. The Bulletin indicates that early in the de-glaciation process,
Pine River Valley was inundated by a glacial lake that existed while major stream channels
further east were still covered by glacial ice, preventing drainage of the area. Pine River Valley
had been scoured and deepened by the glacial ice and was subsequently filled with sediment
carried into the glacial lake from the adjacent valley streams. As the ice further east melted, the
lake drained and the resulting stream flow cut into the valley sediments, creating the present
drainage patterns.
Fan deposits, such as those from Bowlder Creek were later deposited over the valley
floor. Fan deposits typically vary horizontally and vertically as a result of random relocation of
stream flow across the fan. Abandoned channels are sometimes filled with loose soil deposits
and peat. Sand and gravel deposited throughout active fan areas is subject to high stream flow
and typically has finer grained materials selectively removed.
Bedrock outcrops are visible along the upslope side of Highway 97 approximately 250 m
to the west. British Columbia Geological Survey maps2 maintained by the B.C. Ministry of
Energy and Mines and Responsible for Core Review show that bedrock in the area is fine grained
sedimentary rocks, shale and siltstone, of the Fort St. John Group, Hasler Formation.
3.0 SITE INVESTIGATION AND SUBSURFACE CONDITIONS
Between November 15 and 17, 2016, GeoNorth personnel observed soil and groundwater
conditions in six drill holes, designated DH16-1, 2, 3, 3A, 4 and 4A. Drilling was carried out
by Westech Drilling Corp. of Prince George. Drill holes DH16-1 and 2 were carried out to 3 m
depth, DH16-3A and 4A to 1.5 m depth, DH16-3 to 24.7 m depth and DH16-4 to 30.8 m depth.
1Mathews, W. H., 1980. Retreat of the Last Ice Sheets in Northeastern British Columbia and Adjacent
Alberta, Geological Survey of Canada Bulletin 331.
2http://www.empr.gov.bc.ca/Mining/Geoscience/MapPlace/Pages/default.aspx
Page 2 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
DH16-1, 2, 3A and 4A were drilled through the asphalt surface of the highway using solid-stem
augers and DH16-3 and 4 were through the gravel shoulder adjacent to the westbound and
eastbound lanes, respectively, using cased, air-rotary methods. The drill hole locations are
shown on Drawing 4544-A2. A section along the road centreline is shown on Drawing 4544-A3,
in Appendix A. All drill holes were filled with the drill cuttings and bentonite chips after they
were completed.
Samples were taken from the auger flights while drilling DH16-1, 2, 3A and 4A, for soil
identification and laboratory testing.
Standard penetration tests (SPTs) (ASTM D1586) were carried out in DH16-3 and 4 at
0.75 m intervals above 6 m depth, then at 1.5 m intervals to 15 m depth, and at 3 m intervals to
the bottom of the drill holes. SPT N values provide an indication of the relative density of a soil
deposit, and are used to calculate foundation bearing capacity and settlement. The SPT allows
a soil sample to be collected. Our field personnel logged soil conditions based on the samples
recovered from the SPT, supplemented with information provided from the drill cuttings.
Drill hole logs describing subsurface conditions are in Appendix B, and are followed by
an explanation of terms and symbols used on the logs. Laboratory test results are shown on the
logs and on Plates 4544-C1 to C7, in Appendix C.
We determined the locations of the drill holes by measuring from site landmarks and
using a hand-held GPS device. We estimated the ground surface elevations of the drill holes
from survey information shown on drawings provided by BCMoTI.
DH16-1, 2, 3A and 4A, drilled through the asphalt surface of the highway, encountered
between 100 mm and 200 mm of asphalt, over dense gravel and sand with some fines to between
0.3 and 0.4 m depth, over loose to compact sand with a variable fines and gravel content to the
bottom of DH16-2, 3A and 4A, over silty gravel and sand below 2.4 m depth and to the bottom
of DH16-1.
Page 3 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
DH16-3, located at the west bridge abutment adjacent to the westbound lane, encountered
compact sandy gravel fill to 0.3 m depth, over loose to compact silty, gravelly sand to 3.4 m
depth, over compact sandy gravel with a variable fines content to the bottom of the drill hole.
DH16-4, located at the east bridge abutment adjacent to the eastbound lane, encountered
compact sandy gravel fill to 0.3 m depth, over compact sandy gravel with a variable fines content
to the bottom of the drill hole.
We interpret the compact sand and gravel with a variable fines content to be alluvial fan
deposits.
SPT N values in the sandy gravel fan deposits were between 8 and 33 and averaged 16
indicating generally compact conditions.
Seepage was observed below 19.0 m depth in DH16-3 and 28.0 m depth in DH16-4,
about geodetic elevations 617.0 m and 607.2 m, respectively. Bedrock was not encountered.
4.0 DISCUSSION AND RECOMMENDATIONS
Natural soil conditions at the site generally consist of compact sandy gravel with a
variable fines content that will provide satisfactory support for spread footing and steel pipe pile
foundations. The sandy gravel has moderate shear strength, a low to moderate susceptibility to
settlement, and a moderate to high susceptibility to the formation of frost lenses and heave. We
understand that steel pipe pile foundations are preferred and recommendations for this option
follow. We can provide recommendations for other foundation options as requested.
The following recommendations are based on the necessary assumption that soil
conditions encountered in the drill holes are representative of conditions elsewhere on the site.
Please contact our office for additional recommendations if conditions encountered during
construction differ in any way from those described in this report.
Page 4 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
4.1 Pile Foundations
Ultimate limit states design loads provided by WSP, structural engineers for the project,
are 1,555 kN in compression and 212 kN in shear for each pile.
We carried out pile capacity analyses using several procedures, including Driven version
1.2 (2001), as well as the effective stress method and Standard Penetration Test method by
Decourt (1995), as described in the Canadian Foundation Engineering Manual, Fourth
Edition (2006). We recommend closed-end steel pipe piles with a steel plate at least 50 mm
thick welded to the pile tip to support the proposed bridge. Axial pile capacity and the maximum
and anticipated pile tip elevations are summarized in Table 1, below.
Table 1 - Pile Capacity, Maximum and Anticipated Pile Tip Elevation
762 mm Diameter Closed-End Pipe Piles
Unfactored
Geotechnical
Resistance
Factored
Geotechnical
Resistance (ULS)
Anticipated Pile Tip
Elevation
Maximum Pile Tip
Elevation
4,443 kN 1,555 kN 609 m* 615 m*
* Pile tip elevations assumes the maximum scour depth is elevation 627.9 m at bridge centre line.
As outlined in Section 6.5 of the Canadian Highway Bridge Design Code
CAN/CSA S6-14, 2014 (CHBDC) Consequence and Site Understanding Classification our
analysis is based on a typical consequence level and low degree of understanding, resulting in
a consequence factor Ø of 1.0 and a geotechnical resistance factor of 0.35, as shown in
Tables 6.1 and 6.2, respectively.
Pile capacity will depend on shaft and end-bearing resistance, as well as the pile stiffness
(wall thickness and length), the energy of the pile driving equipment, and the penetration
resistance at end-of-driving. We analysed the estimated embedment depth and driveability of
Page 5 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
a 762 mm diameter closed-end steel pipe pile with a 12 mm wall thickness using the computer
program GRL WEAP by GRL Engineers Inc. (2005). Our analysis indicates the shaft would
contribute about 60% of the total pile resistance. A summary of the analysis is shown in
Table 2, below.
Table 2 - Pile Driving Analysis
Pile
Diameter
Wall
Thickness
Ultimate
Capacity
Driving
Energy
End-of-Driving
Penetration Resistance
Maximum Pile
Stress
762 mm 12 mm 4,443 kN 207 kJ 45 blows per 250 mm 252 MPa
Based on the estimated maximum pile stress we recommend using piles manufactured
with Grade 3 steel (ASTM A252).
Pile settlement occurs due to elastic shortening of the pile and transfer of stress to the soil
along the pile shaft and at the pile tip. Settlement will occur as loads are applied to the piles and
a small portion of the initial settlement will occur as plastic creep over time. We estimated the
settlement of the soil around and below the pile using the computer program TZPILE by
Ensoft Inc. (Ensoft). Using a load of 1,555 kN per pile the estimated settlement is less than
0.5 cm. Differential settlement between each abutment could be as high as the total settlement.
Most of the anticipated settlement is likely to occur within one year of construction.
We used the program Group by Ensoft Inc. (2016) to estimate the bending moment and
lateral deflection under the design lateral load. Inputs to the program included the soil conditions
encountered during the investigation, the design horizontal load of 212 kN applied longitudinally
to the top of a single row of four 762 mm diameter by 12 mm wall thickness pipe piles and
assuming the pile head is not free to rotate. The results of the analysis indicate less than 1 cm
of deflection and a maximum bending moment of about 600 kNm. We can carry out additional
analysis as requested.
Page 6 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
4.2 Seismic Design Considerations
The 2014 CHBDC defines the “Site Classification for Seismic Site Response” in Table
4.1, which is based on properties of the soil at the site in the top 30 m. Based on the results of
the drill holes the Site Classification for Seismic Site Response is Site Class “D”, as defined in
Table 4.1.
A seismic hazard calculation obtained from the National Resources Canada website
indicates the peak horizontal ground acceleration (PGA) with a 2% probability of exceedance
in 50 years is 0.082 g. This value is based on Site Class “C”. The CHBDC specifies adjusting
the PGA for sites classified as Site Class “D” and “E” using a scaling factor from Table 4.8. For
Site Class “D”, Table 4.8 indicates a scaling factor of 1.3 resulting in an adjusted PGA of 0.107.
The factor of safety against liquefaction is defined as the ratio of Cyclic Resistance Ratio
(CRR) to Cyclic Stress Ratio (CSR). A factor of safety (FoS) of at least 1.2 against liquefaction
is required. To assess the potential for liquefaction, we calculated the cyclic stress ratio based
on a peak surface acceleration of 0.107 g and a design earthquake of magnitude 7.5. The results
indicate a low likelihood of liquefaction at the site, with a FoS against liquefaction greater
than 1.5.
4.3 Earth Embankment Fills and Barrier Flare Embankment Widening
Construct earth embankment fills and barrier flare embankment widening following the
BCMoTI Standard Specifications, Section 201. Use temporary excavation slopes no steeper
than 1 horizontal to 1 vertical (1H:1V).
The CHBDC specifies a global geotechnical resistance factor against sliding of 0.65 for
permanent embankments slopes. Based on the results of our drilling investigation and published
correlations that relate soil index properties to shear strength we recommend constructing
embankment slopes below the ballast wall and above Bowlder Creek channel no steeper than
Page 7 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
2H:1V. Place a geotextile separator between the embankment fill and riprap to prevent sand and
silt in the embankment from migrating into the riprap.
We recommend constructing embankments for highway widening using mineral soil free
of organic and deleterious material and containing less than 15% by volume of rock larger than
150 mm. Granular material excavated from the existing embankment that meets these
requirements may be reused as embankment fill provided it can be compacted to the specified
density. We recommend using finished embankment fill slopes no steeper than 2H:1V for
granular fill with a fines content less than 15% and 2.5H:1V for fill with greater than 15% fines.
In some areas the surface of the existing embankment will be covered with winter road
sand, grass, and brush. We recommend stripping the surface of the embankment to expose
compact mineral soil. Key new fill into the existing embankment using benches. Cut the
benches into the existing embankment using a minimum bench width of 1.5 m and a maximum
height of 1.2 m. If suitable, the material from the bench can be incorporated into the new
embankment. Slope the bench surface at a gradient of 2% towards the outside slope face. A
conceptual cross section showing this detail is on Drawing 4544-D1, in Appendix D.
Place the embankment fill in thin, uniform layers and compact each layer to at least 95%
Standard Proctor Density (SPD) (ASTD D698), and to at least 100% SPD within 300 mm of
the top of subgrade, at a moisture content within 2% of optimum. The maximum layer thickness
will depend on several factors, including compactor type, size and energy, and the soil type and
moisture content, but do not use a layer thickness more than 150 mm. Add water and dry the fill
as necessary to attain the specified density and moisture content.
Protect embankments from erosion up to the 200 year design flood elevation. Place a
geotextile separator between the embankment fill and riprap to prevent sand and silt in the
embankment from migrating into the riprap. Use a nonwoven geotextile that has a puncture
strength (ASTM D6241) of at least 1.8 kN at 50% elongation, and an apparent opening size
Page 8 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
(ASTM D4751) no larger than 0.25 mm (average maximum roll value). Place suitably sized
riprap over the geotextile in uniform layers no more than 1 m thick and work the rock into place
using an excavator bucket.
4.4 Retaining Walls
Retaining walls are required at each end of the west and east ballast walls to retain bridge
end fill. Design drawings show the walls will be 2.25 m long by 3 m high and will be
constructed using interlocking concrete blocks. The concrete blocks have dimensions of 0.75 m
high by 1.5 m long by 0.75 m deep. Bridge End Fill (BEF) is shown spilling around the walls,
burying all but parts of the top two rows of blocks.
The natural, compact sandy gravel will provide adequate support for the proposed
retaining wall. It has moderate bearing capacity, moderate susceptibility to settlement when
subjected to the weight of the retaining wall fill and low to moderate susceptibility to frost heave.
Existing fill that does not meet the gradation and placement specifications for BEF is not suitable
for support of the retaining wall.
We designed the wall using principles found in Report No. FHWA-NH1-00-043, dated
March 2001 (published by the National Highway Institute, US Department of Transportation)
and the Canadian Foundation Engineering Manual, 4th Edition. The wall design details are
shown on Drawing 4544-D2, in Appendix D. We checked the design for bearing capacity,
sliding and overturning. We determined that adequate factors of safety were achieved using the
block configuration shown on Drawing 4544-D2 and the following construction procedures:
1. Design the elevation of the bottom of the wall to allow at least 0.6 m soil cover over
the front of the blocks.
2. Excavate all existing fill that does not meet the gradation and placement
specifications for BEF or expose natural, undisturbed, compact sandy gravel as
Page 9 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
encountered during the investigation. Bring the excavation to within 150 mm of
design grade using material meeting the gradation specifications for BEF placed in
uniform layers no more than 150 mm thick and compacted to 100% Standard Proctor
Density (SPD) (ASTM D698).
3. Below the first row of blocks, place a levelling course of 25 mm Well Graded Base
(WGB), at least 150 mm thick. Extend the WGB out a horizontal distance to allow
a 1H:1V distribution of stress through the WGB onto bridge end fill or natural sandy
gravel. Place the WGB in maximum 150 mm thick layers and compact to at least
100% SPD. Slope the levelling surface so the blocks will be battered back at 1H:6V.
4. Place the blocks on the levelling course with the bottom row oriented with their long
axis into the slope. Configure subsequent rows to be interlocking.
5. Behind the blocks place BEF in uniform layers no thicker than 150 mm and
compact each layer to at least 100% SPD. Within 1 m of the back of the blocks,
use hand-operated vibratory compaction equipment weighing less than 450 kg
(1,000 lbs).
4.5 Bridge End Fill
Construct bridge end fill following the BCMoTI Standard Specifications, Section 202.
Use clean granular soil that meets the gradation specifications for BEF. Place the fill in thin
uniform layers and compact each layer to at least 100% SPD. Add water or dry the fill as
required to achieve the specified density. The layer thickness will depend on the size of
compaction equipment, moisture conditions and other variables, but do not exceed 150 mm.
Design the abutments to withstand lateral pressures caused by soil, compaction, seismic
loads, and any surcharges. Drawing 4544-D3, in Appendix D, shows typical lateral earth
pressures that can develop against a restrained wall. It assumes that the wall is unyielding and
Page 10 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
that the fill is free-draining. The at-rest (Ko) and seismic loads will apply for all restrained walls.
Use an at-rest coefficient of lateral earth pressure, Ko, of 0.38 and a soil density of 22 kN/m3.
Add the pressures from compaction and vehicle loading where they are appropriate.
4.6 Pavement Structure
We recommend the following pavement structure:
• 125 mm of Asphalt Pavement (Class 1), over
• 300 mm of 25 mm WGB or 25 mm Intermediate Graded Base (IGB), over
• 600 mm of Select Granular Subbase (SGSB), over
• A prepared subgrade.
Construct all components of the new pavement structure with at least a 2% crossfall to
the outside. Where the new structure ties into the existing structure we recommend using a saw
cut between 20� and 30� from perpendicular to the road centreline. At the face of the saw cut,
leave an undisturbed width of existing crushed base 500 mm wide, then begin excavation of a
transition slope of 8H:1V to accommodate the new pavement structure thickness. A conceptual
transition detail is shown on Drawing 4544-D4, in Appendix D.
4.7 Spread Footing Foundations
If spread footing foundations are used to support a temporary detour bridge or
open-bottomed culvert, we recommend they be supported either directly on the natural, compact
sandy gravel, or on compacted bridge end fill, rip rap, or lean concrete placed on the natural
sandy gravel. Existing fill is not suitable for support of spread footing foundations. Design the
footings using a factored bearing resistance of 375 kPa (limit states design), and an allowable
bearing pressure (working stress design) of 250 kPa. The allowable bearing pressure may be
increased by one-third for transient loads from wind or seismic events. Use a minimum footing
Page 11 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
width of 1.2 m. Provide at least 0.6 m of cover over foundations and at least 0.6 m setback
between the foundation and the crest of the slope. We can carry out additional analysis to suit
site conditions upon request.
We estimate that footings less than about 2.5 m wide, subjected to the design loading and
bearing on the natural, undisturbed, compact sandy gravel, or BEF, rip rap or on lean concrete
placed on the natural soil will settle less than 1.5 cm. Differential settlement could be as high
as the total settlement. Please contact our office if detailed settlement assessments are required
for specific foundation configurations.
To prepare foundation areas, remove organic material, fill, disturbed soil and heavily
rooted soil from below and out a horizontal distance equal to the depth of fill below the proposed
foundation footprint. Excavate to the natural, compact sandy gravel using an excavator equipped
with a smooth-edge bucket to minimize disturbance to the underlying soil. Compact the exposed
soil in the excavation with several passes of a vibratory plate compactor weighing at least
200 kg.
Bring foundation areas to grade using granular fill that meets the specifications for BEF,
angular rock or lean concrete with a compressive strength of at least 10 MPa at 28 days. If using
lean concrete, place the lean concrete out past the edges of the footing by at least 200 mm on
each side. If seepage is encountered or if the base of the excavation is wet, slope the excavation
to a temporary sump, as needed, to keep the excavation dry. If using BEF, place the fill in
uniform layers no more than 150 mm thick and compact each layer to at least 100% SPD. Place
the BEF or rock fill out laterally from the edges of the footing to a 1 horizontal to 1 vertical
(1H:1V) slope down to the natural ground.
4.8 Trench Crossings
To reduce the potential for unevenness in the driving surface where culverts will cross
below driving surfaces we recommend a transition zone on each side of the trench. Excavate up
Page 12 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
at a minimum 8H:1V slope from the edge of the trench where it meets the top of the subgrade
to the underside of asphalt and sawcut the asphalt back 0.3 m from the top of the slope. Skew
the cut at no less than 30� measured from a perpendicular line drawn across the width of the
road. A conceptual detail is shown on Drawing 4544-D5, in Appendix D.
4.9 Aggregates and Fill
Four material types are specified for construction of the pavement structure and bridge
embankment noted above:
• 25 mm Well Graded Base (WGB),
• 25 mm Intermediate Graded Base (IGB),
• Select Granular Subbase (SGSB),
• Bridge End Fill (BEF).
Use material that meets BCMoTI’s specifications noted in Section 202 of the 2012
Standard Specifications for Highway Construction.
5.0 CONSTRUCTION REVIEW
We recommend that we review final design drawings to confirm that the intent of our
recommendations have been applied, that the recommendations in this report are appropriate and
that sufficient geotechnical investigation has been carried out.
We recommend that an experienced geotechnical engineer, or their designate, review
critical aspects of the project to confirm that soil conditions are as expected and that construction
materials, their placement and their level of compaction are as specified. If soil conditions or
construction materials are different than expected, we can provide additional recommendations
to address the actual conditions. We consider the following geotechnical aspects of the work as
being critical to the project:
Page 13 of 14
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
A P P E N D I X A
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
A P P E N D I X B
0.22m
0.36m
2.4m
3.0m
AC
GP-GM
SM4
GM1
1
2
3
4
ASPHALT.
GRAVEL, and sand, some silt, very dense,brown, dry (FILL).SAND, and silt, gravelly, dense, brown,damp.
GRAVEL, and sand, silty, very dense,brown, damp.
End of drill hole at 3.0m.No seepage observed.
{G:50 S:42 F:8}
{G:20 S:40 F:40}
{G:35 S:35 F:30}
{G:45 S:40 F:15}
L#-Lab Sample W-Wash(mud return)
Elevation: 634.6 m
634
633
632
631
630
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: Standard Auger
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-1
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 1
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
5
0
Northing/Easting: 6163390 , 565288
Final Depth of Hole: 3.0 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
3.1
7
6.2
4.9
0.14m
0.3m
0.76m
2.3m
3.0m
AC
GP-GM
SM2
SM4
SM2
1
2
3
4
ASPHALT.
GRAVEL, and sand, some silt, dense,brown, dry (FILL).SAND, silty, gravelly, dense, brown, damp.
SAND, and silt, some gravel, dense,brown, damp.
SAND, silty, gravelly, very dense, brown,damp.
End of drill hole at 3.0m.No seepage observed.
{G:50 S:42 F:8}
Sieve (Sa#2)G:35% S:41% F:24%
{G:10 S:50 F:40}
{G:35 S:40 F:25}
L#-Lab Sample W-Wash(mud return)
Elevation: 636.7 m
636
635
634
633
632
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: Standard Auger
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-2
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 1
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
5
0
Northing/Easting: 6163410 , 565199
Final Depth of Hole: 3.0 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
3.6
4
7.3
5
0.3m
3.4m
5.6m
9.7m
GP-GM
SM2
GP-GM
GM1
1A1
1B
2
3
4
5
6
7
87
62
25
75
75
67
54
GRAVEL, and sand, trace fines, compact,brown, dry (FILL).SAND, silty, gravelly, compact to loose,brown-grey, damp.
GRAVEL, sandy, some silt, compact,brown, damp.
GRAVEL, and sand, silty to some silt,dense to compact, grey and brown, damp.
{G:52 S:45 F:3}
{G:30 S:35 F:35}
Sieve (Sa#2)G:29% S:42% F:29%
{G:35 S:40 F:25}
{G:32 S:60 F:8}
{G:40 S:40 F:20}
Sieve (Sa#6)G:53% S:33% F:14%
{G:50 S:40 F:10}
L#-Lab Sample W-Wash(mud return)
Elevation: 636.0 m
635
634
633
632
631
630
629
628
627
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
5
6
7
8
9
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
5
6
7
8
9
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-3
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 3
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
10
0
Northing/Easting: 6163410 , 565226
Final Depth of Hole: 24.7 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
18
11
9
15
16
18
13
4.9
7.4
7.9
5.6
4.6
6.3
5.6
6.9
12.3m
13.0m
19.0m
GP
SP-SM
GP-GM
8
9
10
11
12
46
50
67
67
GRAVEL, and sand, trace fines, verydense, brown, some small boulders,damp. (continued)
SAND, gravelly, trace fines, loose, brown,damp.
GRAVEL, and sand, some fines, dense tocompact, brown, damp.
GRAVEL, and sand, some to trace fines,dense to compact, brown, wet.
{G:50 S:45 F:5}
{G:30 S:65 F:5}
Sieve (Sa#10)G:50% S:37% F:13%
{G:50 S:45 F:5}
{G:50 S:45 F:5}
L#-Lab Sample W-Wash(mud return)
Elevation: 636.0 m
625
624
623
622
621
620
619
618
617
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
11
12
13
14
15
16
17
18
19
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
11
12
13
14
15
16
17
18
19
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-3
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
1010
Page 2 of 3
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
20
10
Northing/Easting: 6163410 , 565226
Final Depth of Hole: 24.7 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
33
8
21
23
13
9.8
11.2
8.3
8.6
13.3
24.7m
GP/SP
13
14
50
67
GRAVEL, and sand, some to trace fines,dense to compact, brown, wet. (continued)
End of drill hole at 24.7m.No seepage observed.
{G:45 S:45 F:10}
{G:46 S:46 F:8}
L#-Lab Sample W-Wash(mud return)
Elevation: 636.0 m
615
614
613
612
611
610
609
608
607
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
21
22
23
24
25
26
27
28
29
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
21
22
23
24
25
26
27
28
29
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-3
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
2020
Page 3 of 3
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
30
20
Northing/Easting: 6163410 , 565226
Final Depth of Hole: 24.7 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
19
14
11.7
11.8
0.15m
0.3m
1.5m
AC
GP-GM
SM4
1
2
ASPHALT.
GRAVEL, and sand, some silt, dense,brown, dry (FILL).SAND, and silt, gravelly, dense to verydense, brown, damp.
End of drill hole at 1.5m.No seepage observed.
{G:50 S:42 F:8}
{G:20 S:40 F:40}
L#-Lab Sample W-Wash(mud return)
Elevation: 636.0 m
635
634
633
632
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: Standard Auger
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-3A
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 1
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
5
0
Northing/Easting: 6163408 , 565227
Final Depth of Hole: 1.5 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
3.4
6.8
0.25m
4.3m
8.8m
GP
SM2
GM2
GP-GM
1A1
1B
2
3
4
5
6
7
62
75
54
38
54
75
58
GRAVEL, sandy, trace fines, compact,brown, damp.SAND, gravelly, silty, compact, grey,damp.
GRAVEL, sandy, silty, compact, grey,damp.
GRAVEL, sandy, trace fines, compact,brown, saturated.
{G:50 S:45 F:5}
{G:25 S:50 F:25}
Sieve (Sa#2)G:25% S:47% F:28%
{G:35 S:35 F:30}
{G:40 S:30 F:30}
{G:45 S:35 F:20}
Sieve (Sa#6)G:41% S:41% F:18%
{G:60 S:30 F:10}
L#-Lab Sample W-Wash(mud return)
Elevation: 635.2 m
635
634
633
632
631
630
629
628
627
626
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
5
6
7
8
9
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
5
6
7
8
9
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/16
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-4
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 4
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
10
0
Northing/Easting: 6163393 , 565253
Final Depth of Hole: 30.8 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
11
10
8
12
21
14
16
6.3
8.1
8.5
9.4
3.8
6.5
9
10.3
GP-GM
8
9
10
11
12
58
54
58
58
58
GRAVEL, sandy, trace fines, compact,brown, saturated. (continued)
{G:50 S:40 F:10}
{G:60 S:30 F:10}
{G:50 S:40 F:10}
{G:50 S:40 F:10}
Sieve (Sa#12)G:50% S:37% F:13%
L#-Lab Sample W-Wash(mud return)
Elevation: 635.2 m
625
624
623
622
621
620
619
618
617
616
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
11
12
13
14
15
16
17
18
19
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
11
12
13
14
15
16
17
18
19
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/16
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-4
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
1010
Page 2 of 4
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
20
10
Northing/Easting: 6163393 , 565253
Final Depth of Hole: 30.8 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
10
17
13
18
19
12.6
6.8
11.5
8
10.8
GP-GM
13
14
15
58
58
54
GRAVEL, sandy, trace fines, compact,brown, saturated. (continued)
{G:60 S:30 F:10}
{G:45 S:45 F:10}
{G:45 S:45 F:10}
L#-Lab Sample W-Wash(mud return)
Elevation: 635.2 m
615
614
613
612
611
610
609
608
607
606
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
21
22
23
24
25
26
27
28
29
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
21
22
23
24
25
26
27
28
29
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/16
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-4
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
2020
Page 3 of 4
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
30
20
Northing/Easting: 6163393 , 565253
Final Depth of Hole: 30.8 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
26
17
12
11.7
10.6
10.4
30.8m
GP-GM16
GRAVEL, sandy, trace fines, compact,brown, saturated. (continued)
End of drill hole at 30.8m.No seepage observed.
{G:50 S:45 F:5}
L#-Lab Sample W-Wash(mud return)
Elevation: 635.2 m
605
604
603
602
601
600
599
598
597
596
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
31
32
33
34
35
36
37
38
39
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
31
32
33
34
35
36
37
38
39
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/16
Drilling Method: ODEX
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-4
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
3030
Page 4 of 4
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
40
30
Northing/Easting: 6163393 , 565253
Final Depth of Hole: 30.8 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
128.5
0.12m
0.35m
0.96m
1.5m
AC
GP-GM
SM2
SM3
1
2
3
ASPHALT.
GRAVEL, and sand, some silt, compact,brown, dry.
SAND, silty, gravelly, compact, brown, dry.
SAND, and silt, gravelly, compact, brown,dry.
End of drill hole at 1.5m.No seepage observed.
{G:50 S:42 F:8}
{G:25 S:55 F:20}
{G:25 S:40 F:35}
L#-Lab Sample W-Wash(mud return)
Elevation: 635.3 m
635
634
633
632
631
GeoNorth Engineering LtdPrepared by:
ELE
VA
TIO
N (m
)
1
2
3
4
LegendSample Type:
S-SplitSpoon
O-Odex(air rotary)
T-ShelbyTube
C-CoreA-Auger G-Grab V-Vane
1
2
3
4
Driller: DaveDrill Make/Model: Mobile B54
CLAS
SIFI
CATI
ON
Location: Highway 97Date(s) Drilled: 2016/11/15
Drilling Method: Standard Auger
Project: Bowlder Creek Culvert Replacement
Logged by: DN Reviewed by:
SO
IL S
YM
BO
L
Drill Hole #: DH16-4A
RE
CO
VE
RY
(%)
SA
MPL
E N
O
SA
MPL
E T
YP
E
SOILDESCRIPTION
00
Page 1 of 1
DE
PTH
(m)
DR
ILLI
NG
DE
TAIL
SAlignment:
5
0
Northing/Easting: 6163395 , 565258
Final Depth of Hole: 1.5 mDepth to Top of Rock:
Station/Offset:
COMMENTSTESTING
Drillers Estimate{G % S % F %}
Drilling Company: Westech DrillingK-4544
SUMMARY LOG
Datum: 10U
MO
T-S
OIL
-RE
V2 4
544-
GIN
T-M
OT-
DH
LO
GS.
GP
J M
OT-
DR
AFT-
RE
V2.G
DT
18/
03/2
1
DYNAMIC CONE (BLOWS/300 mm)
W % LW %20 40 60 80
P W% SPT "N" (BLOWS/300 mm)
Natural Vane (KPa) Remold Vane (KPa)
100 200 300 400 Pocket Penetrometer Shear Strength (kPa)
3.2
6.1
5.9
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
A P P E N D I X C
GEONORTH ENGINEERING LTD.
B.C. Ministry of Transportation and Infrastructure - Northern Region March 21, 2018
Geotechnical Report, Proposed Bowlder Creek Culvert Replacement,
Highway 97, 23 km West Of Chetwynd, B.C. File No. K-4544
A P P E N D I X D