Projects Solutions Pfa

Embed Size (px)

Citation preview

  • 7/31/2019 Projects Solutions Pfa

    1/89

    Chapter 4

    MARKET AND DEMAND ANALYSIS

    1. We have to estimate the parameters a and b in the linear relationshipYt= a + bT

    Using the least squares method.According to the least squares method the parameters are:

    T Yn T Yb =

    T2 n T2

    a = YbTThe parameters are calculated below:

    Calculation in the Least Squares Method

    T Y TY T 2

    1 2,000 2,000 12 2,200 4,400 43 2,100 6,300 94 2,300 9,200 165 2,500 12,500 256 3,200 19,200 367 3,600 25,200 498 4,000 32,000 649 3,900 35,100 8110 4,000 40,000 100

    11 4,200 46,200 12112 4,300 51,600 14413 4,900 63,700 16914 5,300 74,200 196

    T = 105 Y = 48,500 TY = 421,600 T2 = 1,015

    T= 7.5 Y= 3,464

    T Yn T Y 421,600 14 x 7.5 x 3,464

    b = = T2 n T2 1,015 14 x 7.5 x 7.5

    57,880= = 254

    227.5a = YbT

    = 3,464 254 (7.5)

    = 1,559

  • 7/31/2019 Projects Solutions Pfa

    2/89

    Thus linear regression isY= 1,559 + 254 T

    2. In general, in exponential smoothing the forecast fort+ 1 isFt+ 1 =Ft+ et

    WhereFt+ 1 = forecast for year ) = smoothing parameteret = error in the forecast for yeart= St =Ft

    F1is given to be 2100 and is given to be 0.3

    The forecasts for periods 2 to 14 are calculated below:

    Period t Data (St) Forecast

    (Ft)

    Error

    (et St=Ft)

    Forecast for t + 1

    (Ft + 1 = Ft + et)

    1 2,000 2100.0 -100 F2 = 2100 + 0.3 (-100) = 2070

    2 2,200 2070 130 F3 = 2070 + 0.3(130) = 2109

    3 2,100 2109.0 -9 F4 = 2109 + 0.3 (-9) = 2111.7

    4 2,300 2111.7 188.3 F5 = 2111.7 + 0.3(188.3) = 2168.19

    5 2,500 2168.19 331.81 F6 = 2168.19 + 0.3(331.81) = 2267.7

    6 3,200 2267.7 932.3 F7 = 2267.7 + 0.3(9332.3) = 2547.4

    7 3,600 2547.4 1052.6 F8 = 2547.4 + 0.3(1052.6) = 2863.28 4,000 2863.2 1136.8 F9 = 2863.2 + 0.3(1136.8) = 3204.24

    9 3,900 3204.24 695.76 F10 = 33204.24 + 0.3(695.76) = 3413.0

    10 4,000 3413 587.0 F11 = 3413.0 + 0.3(587) = 3589.1

    11 4,200 3589.1 610.9 F12 = 3589.1 + 0.3(610.9) = 3773.4

    12 4,300 3772.4 527.6 F13 = 3772.4 + 0.3(527.6) = 3930.7

    13 4,900 3930.7 969.3 F14 = 3930.7 + 0.3(969.3) = 4221.5

    3. According to the moving average methodSt+ St 1++ St n +1

    Ft+ 1 = n

    whereFt+ 1 = forecast for the next periodSt = sales for the current periodn = period over which averaging is done

    Given n = 3, the forecasts for the period 4 to 14 are given below:

  • 7/31/2019 Projects Solutions Pfa

    3/89

    Period t Data (St) Forecast

    (Ft)

    Forecast for t + 1

    Ft + 1 = (St+ St 1+

    St 2)/ 3

    1 2,000

    2 2,200

    3 2,100 F4 = (2000 + 2200 + 2100)/3 = 2100

    4 2,300 2100 F5 =(2200 + 2100 + 2300)/3= 2200

    5 2,500 2200 F6 = (2100 + 2300 + 2500)/3 = 2300

    6 3,200 2300 F7 = (2300 + 2500 + 3200)/3= 2667

    7 3,600 2667 F8 = (2500 + 3200 + 3600)/3 = 31008 4,000 3100 F9 = (3200 + 3600 + 4000)/3 = 3600

    9 3,900 3600 F10 = (3600 + 4000 + 3900)/3 = 3833

    10 4,000 3833 F11 = (4000 + 3900 + 4000)/3 =3967

    11 4,200 3967 F12 =(3900 + 4000 + 4200)/3 = 4033

    12 4,300 4033 F13 = (4000 + 4200 + 4300)/3 = 4167

    13 4,900 4167 F14 = (4200 + 4300 + 4900) = 4467

    14 5,300 4467

    4.Q1 = 60

    Q2 = 70I1 = 1000I2 = 1200

    Q1Q2 I1 +I2

    Income Elasticity of DemandE1 = xI2 - I1 Q2Q1 E1 = Income Elasticity of Demand

    Q1 = Quantity demanded in the base yearQ2 = Quantity demanded in the following yearI1 = Income level in base yearI2 = Income level in the following year

    70 60 1000 + 1200E1 = x1200 1000 70 + 60

    22000E1 = = 0.846

    26000

  • 7/31/2019 Projects Solutions Pfa

    4/89

    5.P1 = Rs.40

    P2 = Rs.50Q1 = 1,00,000Q2 = 95,000

    Q2Q1 P1 +P2Price Elasticity of Demand = Ep = x

    P2P1Q2 + Q1 P1 , Q1 = Price per unit and quantity demanded in the base year

    P2, Q2 = Price per unit and quantity demanded in the following yearEp= Price Elasticity of Demand

    95000 - 100000 40 + 50Ep= x

    50 - 40 95000 + 100000

    - 45Ep= = - 0.0231

    1950

  • 7/31/2019 Projects Solutions Pfa

    5/89

    Chapter 6

    FINANCIAL ESTIMATES AND PROJECTIONS

    1. Projected Cash Flow Statement (Rs. in million)

    Sources of Funds

    Profit before interest and tax 4.5Depreciation provision for the year 1.5Secured term loan 1.0

    Total (A) 7.0

    Disposition of Funds

    Capital expenditure 1.50

    Increase in working capital

    0.35Repayment of term loan 0.50Interest 1.20Tax 1.80Dividends 1.00

    Total (B) 6.35

    Opening cash balance 1.00Net surplus (deficit) (A B) 0.65Closing cash balance 1.65

    Projected Balance Sheet

    (Rs. in million)

    Liabilities Assets

    Share capital 5.00 Fixed assets 11.00Reserves & surplus 4.50 Investments .50Secured loans 4.50 Current assets 12.85Unsecured loans 3.00 * Cash 1.65Current liabilities 6.30 * Receivables 4.20

    & provisions 1.05 * Inventories 7.0024.35 24.35

    2. Projected Income Statement for the 1st Operating Year

    Working capital here is defined as :(Current assets other than cash) (Current liabilities other than bank borrowings)In this case inventories increase by 0.5 million, receivables increase by 0.2 million and current

    liabilities and provisions increase by 0.35 million. So working capital increases by 0.35 million

  • 7/31/2019 Projects Solutions Pfa

    6/89

    Rs.Sales 4,500

    Cost of sales 3,000Depreciation 319Interest 1,044Write off of Preliminary expenses 15Net profit 122

    Projected Cash Flow Statements

    Construction period 1stOperating yearSources

    Share capital 1800 -Term loan 3000 600Short-term bank borrowing 1800Profit before interest and tax 1166Depreciation 319Write off preliminary expenses 15

    4800 3900Uses

    Capital expenditure 3900 -Current assets (other than cash) - 2400Interest - 1044Preliminary expenses 150 -Pre-operative expenses 600 -

    4650 3444Opening cash balance 0 150Net surplus / deficit 150 456

    Closing balance 150 606Projected Balance Sheet

    Liabilities 31/3/n+1 31/3/n+2 Assets 31/3/n+1 31/3/n+2

    Share capital 1800 1800 Fixed assets (net) 4500 4181

    Reserves & surplus - 122

    Secured loans : Current assets

    - Term loan 3000 3600 - Cash 150 606

    - Short-term bank

    borrowing

    1800 Other current assets 2400

    Unsecured loans - - Miscellaneousexpenditures & losses

    Current liabilities andprovisions

    - Preliminaryexpenses

    150 135

    4800 7322 4800 7322

    Notes :

  • 7/31/2019 Projects Solutions Pfa

    7/89

    i. Allocation of Pre-operative Expenses : Rs.

    Type Costs beforeallocation Allocation Costs afterallocation

    Land 120 19 139

    Building 630 97 727

    Plant & machinery 2700 415 3115

    Miscellaneous fixed assets 450 69 519

    3900 600 4500

    ii. Depreciation Schedule :

    Lan

    d

    Building Plant & machinery M.Fixed

    assets

    Total (Rs.)

    Opening balance 139 727 3115 519 4500

    Depreciation - 25 252 42 319

    Closing balance 139 702 2863 477 4181

    iii. Interest Schedule :Interest on term loan of Rs.3600 @20% = Rs.720Interest on short term bank borrowings of Rs,1800 @ 18% = Rs.324

    = Rs.1044

    Chapter 7

  • 7/31/2019 Projects Solutions Pfa

    8/89

    THE TIME VALUE OF MONEY

    1. Value five years hence of a deposit of Rs.1,000 at various interest rates is asfollows:

    r = 8% FV5 = 1000 x FVIF (8%, 5 years)= 1000 x 1.469 = Rs.1469

    r = 10% FV5 = 1000 x FVIF (10%, 5 years)= 1000 x 1.611 = Rs.1611

    r = 12% FV5 = 1000 x FVIF (12%, 5 years)= 1000 x 1.762 = Rs.1762

    r = 15% FV5 = 1000 x FVIF (15%, 5 years)= 1000 x 2.011 = Rs.2011

    2. Rs.160,000 / Rs. 5,000 = 32 = 25

    According to the Rule of 72 at 12 percent interest rate doubling takes placeapproximately in 72 / 12 = 6 years

    So Rs.5000 will grow to Rs.160,000 in approximately 5 x 6 years = 30 years

    3. In 12 years Rs.1000 grows to Rs.8000 or 8 times. This is 23 times the initialdeposit. Hence doubling takes place in 12 / 3 = 4 years.

    According to the Rule of 69, the doubling period is:

    0.35 + 69 / Interest rate

    Equating this to 4 and solving for interest rate, we get

    Interest rate = 18.9%.

    4. Saving Rs.2000 a year for 5 years and Rs.3000 a year for 10 years thereafter isequivalent to saving Rs.2000 a year for 15 years and Rs.1000 a year for the years6 through 15.

    Hence the savings will cumulate to:

    2000 x FVIFA (10%, 15 years) + 1000 x FVIFA (10%, 10 years)= 2000 x 31.772 + 1000 x 15.937 = Rs.79481.

  • 7/31/2019 Projects Solutions Pfa

    9/89

    5. LetA be the annual savings.

    A x FVIFA (12%, 10 years) = 1,000,000A x 17.549 = 1,000,000

    So A = 1,000,000 / 17.549 = Rs.56,983.

    6. 1,000 x FVIFA (r, 6 years) = 10,000

    FVIFA (r, 6 years) = 10,000 / 1000 = 10

    From the tables we find that

    FVIFA (20%, 6 years) = 9.930FVIFA (24%, 6 years) = 10.980

    Using linear interpolation in the interval, we get:

    20% + (10.000 9.930)

    r= x 4% = 20.3%(10.980 9.930)

    7. 1,000 x FVIF (r, 10 years) = 5,000FVIF (r,10 years) = 5,000 / 1000 = 5

    From the tables we find thatFVIF (16%, 10 years) = 4.411

    FVIF (18%, 10 years) = 5.234

    Using linear interpolation in the interval, we get:

    (5.000 4.411) x 2% r= 16% + = 17.4%

    (5.234 4.411)

    8. The present value of Rs.10,000 receivable after 8 years for various discount rates(r) are:r= 10% PV = 10,000 x PVIF(r= 10%, 8 years)

    = 10,000 x 0.467 = Rs.4,670

    r= 12% PV = 10,000 x PVIF (r= 12%, 8 years)= 10,000 x 0.404 = Rs.4,040

    r= 15% PV = 10,000 x PVIF (r= 15%, 8 years)

  • 7/31/2019 Projects Solutions Pfa

    10/89

    = 10,000 x 0.327 = Rs.3,2709. Assuming that it is an ordinary annuity, the present value is:

    2,000 x PVIFA (10%, 5years)= 2,000 x 3.791 = Rs.7,582

    10. The present value of an annual pension of Rs.10,000 for 15 years when r= 15%is:

    10,000 x PVIFA (15%, 15 years)= 10,000 x 5.847 = Rs.58,470

    The alternative is to receive a lumpsum of Rs.50,000.

    Obviously, Mr. Jingo will be better off with the annual pension amount ofRs.10,000.

    11. The amount that can be withdrawn annually is:100,000 100,000

    A = ------------------ ------------ = ----------- = Rs.10,608PVIFA (10%, 30 years) 9.427

    12. The present value of the income stream is:

    1,000 x PVIF (12%, 1 year) + 2,500 x PVIF (12%, 2 years)+ 5,000 x PVIFA (12%, 8 years) x PVIF(12%, 2 years)

    = 1,000 x 0.893 + 2,500 x 0.797 + 5,000 x 4.968 x 0.797 = Rs.22,683.

    13. The present value of the income stream is:

    2,000 x PVIFA (10%, 5 years) + 3000/0.10 x PVIF (10%, 5 years)= 2,000 x 3.791 + 3000/0.10 x 0.621= Rs.26,212

    14. To earn an annual income of Rs.5,000 beginning from the end of 15 years fromnow, if the deposit earns 10% per year a sum of

    Rs.5,000 / 0.10 = Rs.50,000

    is required at the end of 14 years. The amount that must be deposited to get thissum is:

    Rs.50,000 / PVIF (10%, 14 years) = Rs.50,000 / 3.797 = Rs.13,165

  • 7/31/2019 Projects Solutions Pfa

    11/89

    15. Rs.20,000 =- Rs.4,000 x PVIFA (r, 10 years)PVIFA (r,10 years) = Rs.20,000 / Rs.4,000 = 5.00

    From the tables we find that:

    PVIFA (15%, 10 years) = 5.019PVIFA (18%, 10 years) = 4.494

    Using linear interpolation we get:

    5.019 5.00r= 15% + ---------------- x 3%

    5.019 4.494= 15.1%

    16. PV (StreamA) = Rs.100 x PVIF (12%, 1 year) + Rs.200 xPVIF (12%, 2 years) + Rs.300 x PVIF(12%, 3 years) + Rs.400 xPVIF (12%, 4 years) + Rs.500 x PVIF (12%, 5 years) +Rs.600 x PVIF (12%, 6 years) + Rs.700 x PVIF (12%, 7 years) +

    Rs.800 x PVIF (12%, 8 years) + Rs.900 x PVIF (12%, 9 years) +Rs.1,000 x PVIF (12%, 10 years)

    = Rs.100 x 0.893 + Rs.200 x 0.797 + Rs.300 x 0.712+ Rs.400 x 0.636 + Rs.500 x 0.567 + Rs.600 x 0.507+ Rs.700 x 0.452 + Rs.800 x 0.404 + Rs.900 x 0.361+ Rs.1,000 x 0.322

    = Rs.2590.9

    Similarly,PV (StreamB) = Rs.3,625.2PV (Stream C) = Rs.2,851.1

    17. FV5 = Rs.10,000 [1 + (0.16 / 4)]5x4

    = Rs.10,000 (1.04)20

    = Rs.10,000 x 2.191= Rs.21,910

    18. FV5 = Rs.5,000 [1+( 0.12/4)]5x4

    = Rs.5,000 (1.03)20

    = Rs.5,000 x 1.806= Rs.9,030

    19. A B C

  • 7/31/2019 Projects Solutions Pfa

    12/89

    Stated rate (%) 12 24 24Frequency of compounding 6 times 4 times 12 timesEffective rate (%) (1 + 0.12/6)6- 1 (1+0.24/4)4 1 (1 + 0.24/12)12-1

    = 12.6 = 26.2 = 26.8Difference between theeffective rate and statedrate (%) 0.6 2.2 2.8

    20. Investment required at the end of 8th year to yield an income of Rs.12,000 peryear from the end of 9th year (beginning of 10th year) for ever:

    Rs.12,000 x PVIFA(12%, )= Rs.12,000 / 0.12 = Rs.100,000

    To have a sum of Rs.100,000 at the end of 8th year , the amount to be depositednow is:

    Rs.100,000 Rs.100,000

    = = Rs.40,388PVIF(12%, 8 years) 2.476

    21. The interest rate implicit in the offer of Rs.20,000 after 10 years in lieu ofRs.5,000 now is:

    Rs.5,000 x FVIF (r,10 years) = Rs.20,000

    Rs.20,000FVIF (r,10 years) = = 4.000

    Rs.5,000

    From the tables we find thatFVIF (15%, 10 years) = 4.046

    This means that the implied interest rate is nearly 15%.I would choose Rs.20,000 for 10 years from now because I find a return of 15%

    quite acceptable.

    22. FV10 = Rs.10,000 [1 + (0.10 / 2)]10x2

    = Rs.10,000 (1.05)20

    = Rs.10,000 x 2.653= Rs.26,530

    If the inflation rate is 8% per year, the value of Rs.26,530 10 years from now, in

    terms of the current rupees is:

  • 7/31/2019 Projects Solutions Pfa

    13/89

    Rs.26,530 x PVIF (8%,10 years)= Rs.26,530 x 0.463 = Rs.12,283

    23. A constant deposit at the beginning of each year represents an annuity due.

    PVIFA of an annuity due is equal to : PVIFA of an ordinary annuity x (1 + r)

    To provide a sum of Rs.50,000 at the end of 10 years the annual deposit should be

    Rs.50,000A = FVIFA(12%, 10 years) x (1.12)

    Rs.50,000= = Rs.2544

    17.549 x 1.12

    24. The discounted value of Rs.20,000 receivable at the beginning of each year from2005 to 2009, evaluated as at the beginning of 2004 (or end of 2003) is:

    Rs.20,000 x PVIFA (12%, 5 years)= Rs.20,000 x 3.605 = Rs.72,100.

    The discounted value of Rs.72,100 evaluated at the end of 2000 is

    Rs.72,100 x PVIF (12%, 3 years)= Rs.72,100 x 0.712 = Rs.51,335

    IfA is the amount deposited at the end of each year from 1995 to 2000 thenA x FVIFA (12%, 6 years) = Rs.51,335A x 8.115 = Rs.51,335A = Rs.51,335 / 8.115 = Rs.6326

    25. The discounted value of the annuity of Rs.2000 receivable for 30 years, evaluatedas at the end of 9th year is:

    Rs.2,000 x PVIFA (10%, 30 years) = Rs.2,000 x 9.427 = Rs.18,854

    The present value of Rs.18,854 is:Rs.18,854 x PVIF (10%, 9 years)

    = Rs.18,854 x 0.424= Rs.7,994

    26. 30 percent of the pension amount is0.30 x Rs.600 = Rs.180

    Assuming that the monthly interest rate corresponding to an annual interest rate of12% is 1%, the discounted value of an annuity of Rs.180 receivable at the end of

    each month for 180 months (15 years) is:

  • 7/31/2019 Projects Solutions Pfa

    14/89

    Rs.180 x PVIFA (1%, 180)

    (1.01)180 - 1Rs.180 x ---------------- = Rs.14,998

    .01 (1.01)180

    If Mr. Ramesh borrows Rs.Ptoday on which the monthly interest rate is 1%

    P x (1.01)60 = Rs.14,998P x 1.817 = Rs.14,998

    Rs.14,998P = ------------ = Rs.8254

    1.817

    27. Rs.300 x PVIFA(r, 24 months) = Rs.6,000

    PVIFA (4%,24) = Rs.6000 / Rs.300 = 20

    From the tables we find that:

    PVIFA(1%,24) = 21.244PVIFA (2%, 24) = 18.914

    Using a linear interpolation

    21.244 20.000r = 1% + ---------------------- x 1%

    21.244 18,914

    = 1.53%Thus, the bank charges an interest rate of 1.53% per month.The corresponding effective rate of interest per annum is

    [ (1.0153)12 1 ] x 100 = 20%

    28. The discounted value of the debentures to be redeemed between 8 to 10 yearsevaluated at the end of the 5th year is:

    Rs.10 million x PVIF (8%, 3 years)+ Rs.10 million x PVIF (8%, 4 years)+ Rs.10 million x PVIF (8%, 5 years)= Rs.10 million (0.794 + 0.735 + 0.681)= Rs.2.21 million

    IfA is the annual deposit to be made in the sinking fund for the years 1 to 5, thenA x FVIFA (8%, 5 years) = Rs.2.21 millionA x 5.867 = Rs.2.21 million

    A = 5.867 = Rs.2.21 million

  • 7/31/2019 Projects Solutions Pfa

    15/89

    A = Rs.2.21 million / 5.867 = Rs.0.377 million

    29. Let n be the number of years for which a sum of Rs.20,000 can be withdrawnannually.

    Rs.20,000 x PVIFA (10%, n) = Rs.100,000PVIFA (15%, n) = Rs.100,000 / Rs.20,000 = 5.000

    From the tables we find thatPVIFA (10%, 7 years) = 4.868PVIFA (10%, 8 years) = 5.335

    Thus n is between 7 and 8. Using a linear interpolation we get

    5.000 4.868n = 7 + ----------------- x 1 = 7.3 years

    5.335 4.868

    30. Equated annual installment = 500000 / PVIFA(14%,4)= 500000 / 2.914= Rs.171,585

    Loan Amortisation Schedule

    Beginning Annual Principal Remaining

    Year amountinstallment Interestrepaid balance

    1 50000017158570000 1015853984152 39841517158555778 1158072826083 28260817158539565 1320201505884 15058817158521082 150503 85*

    (*) rounding off error

    31. Define n as the maturity period of the loan. The value of n can be obtained fromthe equation.

    200,000 x PVIFA(13%, n) = 1,500,000PVIFA (13%, n) = 7.500

    From the tables or otherwise it can be verified that PVIFA(13,30) = 7.500

    Hence the maturity period of the loan is 30 years.

    32. Expected value of iron ore mined during year 1 = Rs.300 millionExpected present value of the iron ore that can be mined over the next 15 yearsassuming a price escalation of 6% per annum in the price per tonne of iron

    1 (1 +g)n / (1 + i)n

    = Rs.300 million x ------------------------

    i -g

  • 7/31/2019 Projects Solutions Pfa

    16/89

    = Rs.300 million x 1 (1.06)15 / (1.16)150.16 0.06

    = Rs.300 million x (0.74135 / 0.10)= Rs.2224 million

    Chapter 8

    INVESTMENT CRITERIA

    1.(a) NPV of the project at a discount rate of 14%.

    100,000 200,000

  • 7/31/2019 Projects Solutions Pfa

    17/89

    = - 1,000,000 + ---------- + ------------(1.14) (1.14)2

    300,000 600,000 300,000+ ----------- + ---------- + ----------

    (1.14)3 (1.14)4 (1.14)5

    = - 44837

    (b) NPV of the project at time varying discount rates

    = - 1,000,000

    100,000+

    (1.12)

    200,000+

    (1.12) (1.13)

    300,000+

    (1.12) (1.13) (1.14)

    600,000+

    (1.12) (1.13) (1.14) (1.15)

    300,000+

    (1.12) (1.13) (1.14)(1.15)(1.16)

    = - 1,000,000 + 89286 + 158028 + 207931 + 361620 + 155871= - 27264

    2. InvestmentA

    a) Payback period = 5 yearsb) NPV = 40000 x PVIFA (12%,10) 200 000

    = 26000c) IRR (r) can be obtained by solving the equation:

    40000 x PVIFA (r, 10) = 200000

  • 7/31/2019 Projects Solutions Pfa

    18/89

    i.e., PVIFA (r, 10) = 5.000

    From the PVIFA tables we find that

    PVIFA (15%,10) = 5.019PVIFA (16%,10) = 4.883

    Linear interporation in this range yields

    r = 15 + 1 x (0.019 / 0.136)= 15.14%

    d) BCR = Benefit Cost Ratio= PVB / I= 226,000 / 200,000 = 1.13

    Investment B

    a) Payback period = 9 years

    b) NP V = 40,000 x PVIFA (12%,5)+ 30,000 x PVIFA (12%,2) x PVIF (12%,5)+ 20,000 x PVIFA (12%,3) x PVIF (12%,7)

    - 300,000

    = (40,000 x 3.605) + (30,000 x 1.690 x 0.567)+ (20,000 x 2.402 x 0.452) 300,000

    = - 105339

    c) IRR (r) can be obtained by solving the equation40,000 x PVIFA (r, 5) + 30,000 x PVIFA (r, 2) x PVIF (r,5) +20,000 x PVIFA (r, 3) x PVIF (r, 7) = 300,000

    Through the process of trial and error we find thatr= 1.37%

    d) BCR = PVB /I= 194,661 / 300,000 = 0.65

    Investment C

    a) Payback period lies between 2 years and 3 years. Linear interpolation inthis range provides an approximate payback period of 2.88 years.

  • 7/31/2019 Projects Solutions Pfa

    19/89

    b) NPV = 80.000 x PVIF (12%,1) + 60,000 x PVIF (12%,2)+ 80,000 x PVIF (12%,3) + 60,000 x PVIF (12%,4)

    + 80,000 x PVIF (12%,5) + 60,000 x PVIF (12%,6)+ 40,000 x PVIFA (12%,4) x PVIF (12%,6)- 210,000

    = 111,371

    c) IRR (r) is obtained by solving the equation80,000 x PVIF (r,1) + 60,000 x PVIF (r,2) + 80,000 x PVIF (r,3)+ 60,000 x PVIF (r,4) + 80,000 x PVIF (r,5) + 60,000 x PVIF (r,6)

    + 40000 x PVIFA (r,4) x PVIF (r,6) = 210000

    Through the process of trial and error we getr= 29.29%

    d) BCR = PVB /I = 321,371 / 210,000 = 1.53

    Investment D

    a) Payback period lies between 8 years and 9 years. A linear interpolation inthis range provides an approximate payback period of 8.5 years.8 + (1 x 100,000 / 200,000)

    b) NPV = 200,000 x PVIF (12%,1)+ 20,000 x PVIF (12%,2) + 200,000 x PVIF (12%,9)+ 50,000 x PVIF (12%,10)

    - 320,000= - 37,160

    c) IRR (r) can be obtained by solving the equation200,000 x PVIF (r,1) + 200,000 x PVIF (r,2)+ 200,000 x PVIF (r,9) + 50,000 x PVIF (r,10)

    = 320000Through the process of trial and error we get r= 8.45%

    d) BCR = PVB / I= 282,840 / 320,000 = 0.88Comparative Table

    Investment A B C D

    a) Payback period(in years) 5 9 2.88 8.5

  • 7/31/2019 Projects Solutions Pfa

    20/89

    b) NPV @ 12% 26000 -105339 111371 -37160

    c) IRR (%) 15.14 1.37 29.29 8.45

    d) BCR 1.13 0.65 1.53 0.88

    Among the four alternative investments, the investment to be chosen is Cbecause it has the a. Lowest payback period

    b. Highest NPVc. Highest IRRd. Highest BCR

    3. IRR (r) can be calculated by solving the following equations for the value of r.60000 x PVIFA (r,7) = 300,000i.e., PVIFA (r,7) = 5.000

    Through a process of trial and error it can be verified that r= 9.20% p.a.

    4. The IRR (r) for the given cashflow stream can be obtained by solving the

    following equation for the value of r.-3000 + 9000 / (1+r) 3000 / (1+r) = 0

    Simplifying the above equation we getr = 1.61, -0.61; (or) 161%, (-)61%

    Note : Given two changes in the signs of cashflow, we get two values for theIRR of the cashflow stream. In such cases, the IRR rule breaks down.

    5. Define NCF as the minimum constant annual net cashflow that justifies thepurchase of the given equipment. The value of NCF can be obtained from theequation

    NCF x PVIFA (10%,8) = 500000NCF = 500000 / 5.335

    = 93271

    6. DefineIas the initial investment that is justified in relation to a net annual cash

    inflow of 25000 for 10 years at a discount rate of 12% per annum. The valueofIcan be obtained from the following equation

    25000 x PVIFA (12%,10) = Ii.e.,I = 141256

    7. PV of benefits (PVB) = 25000 x PVIF (15%,1)+ 40000 x PVIF (15%,2)+ 50000 x PVIF (15%,3)

    + 40000 x PVIF (15%,4)

  • 7/31/2019 Projects Solutions Pfa

    21/89

    + 30000 x PVIF (15%,5)= 122646 (A)

    Investment = 100,000 (B)Benefit cost ratio = 1.23 [= (A) / (B)]

    8. The NPVs of the three projects are as follows:

    Project

    P Q RDiscount rate

    0% 400 500 600

    5% 223 251 31210% 69 40 7015% - 66 - 142 - 13525% - 291 - 435 - 46130% - 386 - 555 - 591

    9. NPV profiles for ProjectsPand Q for selected discount rates are as follows:(a)

    ProjectP Q

    Discount rate (%)

    0 2950 5005 1876 20810 1075 - 2815 471 - 22220 11 - 382

    b) (i) The IRR (r) of projectPcan be obtained by solving the followingequation for `r.

    -1000 -1200 x PVIF (r,1) 600 x PVIF (r,2) 250 x PVIF (r,3)+ 2000 x PVIF (r,4) + 4000 x PVIF (r,5) = 0

    Through a process of trial and error we find that r= 20.13%

    (ii) The IRR (r') of project Q can be obtained by solving the following

    equation forr'

    -1600 + 200 x PVIF (r',1) + 400 x PVIF (r',2) + 600 x PVIF (r',3)

    + 800 x PVIF (r',4) + 100 x PVIF (r',5) = 0

    Through a process of trial and error we find that r' = 9.34%.

    c) From (a) we find that at a cost of capital of 10%

  • 7/31/2019 Projects Solutions Pfa

    22/89

    NPV (P) = 1075NPV (Q) = - 28

    Given that NPV (P), NPV (Q) and NPV (P) > 0, I would choose projectP.From (a) we find that at a cost of capital of 20%

    NPV (P) = 11NPV (Q) = - 382

    Again NPV (P) > NPV (Q); and NPV (P) > 0. I would choose projectP.

    d) Project PPV of investment-related costs

    = 1000 x PVIF (12%,0)

    + 1200 x PVIF (12%,1) + 600 x PVIF (12%,2)+ 250 x PVIF (12%,3)

    = 2728TV of cash inflows = 2000 x (1.12) + 4000 = 6240The MIRR of the projectPis given by the equation:

    2728 = 6240 x PVIF (MIRR,5)(1 + MIRR)5 = 2.2874MIRR = 18%

    (c) ProjectQPV of investment-related costs = 1600TV of cash inflows @ 15% p.a. = 2772The MIRR of project Q is given by the equation:

    16000 (1 + MIRR)5 = 2772MIRR = 11.62%

    10.

    (a) ProjectANPV at a cost of capital of 12%

    = - 100 + 25 x PVIFA (12%,6)= Rs.2.79 million

    IRR (r) can be obtained by solving the following equation for r.25 x PVIFA (r,6) = 100i.e., r= 12,98%

    Project B

    NPV at a cost of capital of 12%= - 50 + 13 x PVIFA (12%,6)= Rs.3.45 million

    IRR (r') can be obtained by solving the equation

    13 x PVIFA (r',6) = 50

    i.e., r' = 14.40% [determined through a process of trial and error]

  • 7/31/2019 Projects Solutions Pfa

    23/89

    (b) Difference in capital outlays between projectsA andB is Rs.50 millionDifference in net annual cash flow between projectsA andB is Rs.12 million.NPV of the differential project at 12%

    = -50 + 12 x PVIFA (12%,6)= Rs.3.15 million

    IRR (r'') of the differential project can be obtained from the equation

    12 x PVIFA (r'', 6) = 50

    i.e., r'' = 11.53%

    11.(a) ProjectM

    The pay back period of the project lies between 2 and 3 years. Interpolating inthis range we get an approximate pay back period of 2.63 years.

    Project N

    The pay back period lies between 1 and 2 years. Interpolating in this range weget an approximate pay back period of 1.55 years.

    (b) ProjectMCost of capital = 12% p.aPV of cash flows up to the end of year 2 = 24.97PV of cash flows up to the end of year 3 = 47.75PV of cash flows up to the end of year 4 = 71.26

    Discounted pay back period (DPB) lies between 3 and 4 years. Interpolating in

    this range we get an approximate DPB of 3.1 years.

    Project N

    Cost of capital = 12% per annumPV of cash flows up to the end of year 1 = 33.93PV of cash flows up to the end of year 2 = 51.47

    DPB lies between 1 and 2 years. Interpolating in this range we get an

    approximate DPB of 1.92 years.(c) ProjectM

    Cost of capital = 12% per annumNPV = - 50 + 11 x PVIFA (12%,1)

    + 19 x PVIF (12%,2) + 32 x PVIF (12%,3)+ 37 x PVIF (12%,4)

    = Rs.21.26 millionProject N

    Cost of capital = 12% per annum

  • 7/31/2019 Projects Solutions Pfa

    24/89

    NPV = Rs.20.63 million

    Since the two projects are independent and the NPV of each project is (+) ve,both the projects can be accepted. This assumes that there is no capitalconstraint.

    (d) ProjectMCost of capital = 10% per annumNPV = Rs.25.02 million

    Project N

    Cost of capital = 10% per annumNPV = Rs.23.08 million

    Since the two projects are mutually exclusive, we need to choose the projectwith the higher NPV i.e., choose projectM.

    Note : The MIRR can also be used as a criterion of merit for choosing betweenthe two projects because their initial outlays are equal.

    (e) Project MCost of capital = 15% per annumNPV = 16.13 million

    Project N

    Cost of capital:15% per annumNPV = Rs.17.23 million

    Again the two projects are mutually exclusive. So we choose the project with thehigher NPV, i.e., choose projectN.

    (f) ProjectMTerminal value of the cash inflows: 114.47MIRR of the project is given by the equation

    50 (1 + MIRR)4 = 114.47

    i.e., MIRR = 23.01%Project N

    Terminal value of the cash inflows: 115.41MIRR of the project is given by the equation

    50 ( 1+ MIRR)4 = 115.41i.e., MIRR = 23.26%

    12. The internal rate of return is the value ofrin the equation

  • 7/31/2019 Projects Solutions Pfa

    25/89

    2,000 1,000 10,000 2,0008000 = - + +

    (1+r) (1+r)2 (1+r)3 (1+r)4

    At r= 18%, the right hand side is equal to 8099At r= 20%, the right hand side is equal to 7726Thus the solving value ofris :

    8,099 8,00018% + x 2% = 18.5%

    8,099 7,726

    Unrecovered Investment Balance

    Year Unrecovered investment balance at

    the beginning Ft-1

    Interest for theyear Ft-1 (1+r)

    Cash flow at theend of the year CFt

    Unrecoveredinvestment balance at

    the end of the year Ft-1(1+r) + CFt

    1 -8000 -1480 2000 -7480

    2 -7480 -1383.8 -1000 -9863.8

    3 -9863.8 -1824.80 10000 -1688.60

    4 -1688.60 -312.39 2000 0

    13. Rs. in lakhsYear 1 2 3 4 5 6 7 8 Sum Average

    Investment 24.0 21.0 18.0 15.0 12.0 9.0 6.0 3.0 108 13.500

    Depreciation 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 24.0 3.000

    Income beforeinterest and tax

    6.0 6.5 7.0 7.0 7.0 6.5 6.0 5.0 51.0 6.375

    Interest 2.5 2.5 2.5 2.5 2.5 2.5 2.5 2.5 20.0 2.500

    Income before tax 3.5 4.0 4.5 4.5 4.5 4.0 3.5 2.5 31.0 3.875

    Tax - 1.0 2.5 2.5 2.5 2.2 1.9 1.4 14.0 1.750Income after tax 3.5 3.0 2.0 2.0 2.0 1.8 1.6 1.1 17.0 2.125

    Measures of Accounting Rate of Return

    A. Average income after tax 2.125= = 8.9%

    Initial investment 24

    B. Average income after tax 2.125= = 15.7%

    Average investment 13.5

    C. Average income after tax but before interest 2.125 + 2.5= = 19.3%

    Initial investment 24

  • 7/31/2019 Projects Solutions Pfa

    26/89

    D. Average income after tax but before interest 2.125 + 2.5= = 34.3%

    Average investment 13.5

    E. Average income before interest and taxes 6.375= = 26.6%

    Initial investment 24

    F. Average income before interest and taxes 6.375= = 47.2%

    Average investment 13.5

    G. Total income after tax but beforeDepreciation Initial investment 17.0 + 24.0 24.0

    =(Initial investment / 2) x Years (24 / 2) x 8

    = 17.0 / 96.0 = 17.7%

    Chapter 9

    PROJECT CASH FLOWS

    1.(a) Project Cash Flows (Rs. in million)

    Year 0 1 2 3 4 5 6 7

  • 7/31/2019 Projects Solutions Pfa

    27/89

    1. Plant & machinery (150)

    2. Working capital (50)

    3. Revenues 250 250 250 250 250 250 250

    4. Costs (excluding de-preciation & interest) 100 100 100 100 100 100 100

    5. Depreciation 37.5 28.13 21.09 15.82 11.87 8.90 6.67

    6. Profit before tax 112.5 121.87 128.91 134.18 138.13 141.1 143.33

    7. Tax 33.75 36.56 38.67 40.25 41.44 42.33 43.0

    8. Profit after tax 78.75 85.31 90.24 93.93 96.69 98.77 100.33

    9. Net salvage value of

    plant & machinery 48

    10. Recovery of working 50capital

    11. Initial outlay (=1+2) (200)

    12. Operating CF (= 8 + 5) 116.25 113.44 111.33 109.75 108.56 107.67

    107.00

    13. Terminal CF ( = 9 +10) 98

    14. NCF (200) 116.25 113.44 111.33 109.75 108.56 107.67 205

    (c) IRR (r) of the project can be obtained by solving the following equation for r

    -200 + 116.25 x PVIF (r,1) + 113.44 x PVIF (r,2)+ 111.33 x PVIF (r,3) + 109.75 x PVIF (r,4) + 108.56 x PVIF (r,5)+107.67 x PVIF (r,6) + 205 x PVIF (r,7) = 0

    Through a process of trial and error, we get r = 55.17%. The IRR of the projectis 55.17%.

    2. Post-taxIncremental Cash Flows (Rs. in million)

  • 7/31/2019 Projects Solutions Pfa

    28/89

    Year 0 1 2 3 4 5 6 7

    1. Capital equipment (120)2. Level of working capital 20 30 40 50 40 30 20

    (ending)3. Revenues 80 120 160 200 160 120 804. Raw material cost 24 36 48 60 48 36 245. Variable mfg cost. 8 12 16 20 16 12 86. Fixed operating & maint. 10 10 10 10 10 10 10

    cost

    7. Variable selling expenses 8 12 16 20 16 12 88. Incremental overheads 4 6 8 10 8 6 49. Loss of contribution 10 10 10 10 10 10 1010.Bad debt loss 411. Depreciation 30 22.5 16.88 12.66 9.49 7.12 5.3412. Profit before tax -14 11.5 35.12 57.34 42.51 26.88 6.6613. Tax - 4.2 3.45 10.54 17.20 12.75 8.06 2.0014. Profit after tax - 9.8 8.05 24.58 40.14 29.76 18.82 4.66

    15. Net salvage value ofcapital equipments 25

    16. Recovery of working 16capital

    17. Initial investment (120)18. Operating cash flow 20.2 30.55 41.46 52.80 39.25 25.94 14.00

    (14 + 10+ 11)

    19. Working capital 20 10 10 10 (10) (10) (10)

    20. Terminal cash flow 41

    21. Net cash flow (140) 10.20 20.55 31.46 62.80 49.25 35.94 55.00(17+18-19+20)

    (b) NPV of the net cash flow stream @ 15% per discount rate

    = -140 + 10.20 x PVIF(15%,1) + 20.55 x PVIF (15%,2)+ 31.46 x PVIF (15%,3) + 62.80 x PVIF (15%,4) + 49.25 x PVIF(15%,5)+ 35.94 x PVIF (15%,6) + 55 x PVIF (15%,7)

    = Rs.1.70 million

    3.

  • 7/31/2019 Projects Solutions Pfa

    29/89

    (a) A. Initial outlay (Time 0)

    i. Cost of new machine Rs. 3,000,000

    ii. Salvage value of old machine 900,000iii Incremental working capital requirement 500,000iv. Total net investment (=i ii + iii) 2,600,000

    B. Operating cash flow (years 1 through 5)

    Year 1 2 3 4 5

    i. Post-tax savings inmanufacturing costs 455,000 455,000 455,000 455,000 455,000

    ii. Incrementaldepreciation 550,000 412,500 309,375 232,031 174,023

    iii. Tax shield onincremental dep. 165,000 123,750 92,813 69,609 52,207

    iv. Operating cashflow ( i + iii) 620,000 578,750 547,813 524,609 507,207

    C. Terminal cash flow (year 5)

    i. Salvage value of new machine Rs. 1,500,000

    ii. Salvage value of old machine 200,000iii. Recovery of incremental working capital 500,000iv. Terminal cash flow ( i ii + iii) 1,800,000

    D. Net cash flows associated with the replacement project (in Rs)

    Year 0 1 2 3 4 5

    NCF (2,600,000) 620000578750547813524609 307207

    (b) NPV of the replacement project

    = - 2600000 + 620000 x PVIF (14%,1)+ 578750 x PVIF (14%,2)+ 547813 x PVIF (14%,3)+ 524609 x PVIF (14%,4)+ 2307207 x PVIF (14%,5)

  • 7/31/2019 Projects Solutions Pfa

    30/89

    = Rs.267849

    4. Tax shield (savings) on depreciation (in Rs)

    Depreciation Tax shield PV of tax shield

    Year charge (DC) =0.4 x DC @ 15% p.a.

    1 25000 10000 8696

    2 18750 7500 5671

    3 14063 5625 3699

    4 10547 4219 2412

    5 7910 3164 1573--------22051--------

    Present value of the tax savings on account of depreciation = Rs.22051

    5. A. Initial outlay (at time 0)

    i. Cost of new machine Rs. 400,000ii. Salvage value of the old machine 90,000iii. Net investment 310,000

    B. Operating cash flow (years 1 through 5)

    Year 1 2 3 4 5

    i. Depreciationof old machine 18000 14400 11520 9216 7373

    ii. Depreciationof new machine 100000 75000 56250 42188 31641

  • 7/31/2019 Projects Solutions Pfa

    31/89

  • 7/31/2019 Projects Solutions Pfa

    32/89

    advance6. Interest on term loan 30.00 28.50 22.50 16.50 10.50 4.507. Profit before tax 48.67 77.94 102.46 120.81 135.04 146.53

    8. Tax 24.335 38.97 51.23 60.405 67.52 73.2659. Profit after tax 24.335 38.97 51.23 60.405 67.52 73.26510. Preference dividend11. Net salvage value of fixed assets 20012. Net salvage value of current

    assets- 40 40 40 40 40

    13. Repayment of term-loans14. Redemption of preference capital15. Repayment of short-term bank

    borrowings100

    16. Retirement of trade creditors 5017. Initial investment (1) (100)18. Operating cash flows (9-10+4) 107.665 94.53 88.27 85.095 83.98 84.23519. Liquidation and retirement cash

    flows (11+12-13-14-15-16)107.665 54.53 48.27 45.095 43.98 90

    20. Net cash flows (17+18+19) (100) 107.665 54.53 48.27 45.095 43.98 174.235

    Net Cash Flows Relating to Long-term Funds (Rs. in million)

    Particulars Year

    0 1 2 3 4 5 61. Fixed assets (250)2. Working capital margin (50)3. Revenues 500 500 500 500 500 5004. Operating costs 320 320 320 320 320 3205. Depreciation 83.33 55.56 37.04 24.69 16.46 10.976. Interest on working capital

    advance18.00 18.00 18.00 18.00 18.00 18.00

    7. Interest on term loan 30.00 28.50 22.50 16.50 10.50 4.508. Profit before tax 48.67 77.94 102.46 120.81 135.04 146.53

    9. Tax @ 50% 24.335 38.97 51.23 60.405 67.52 73.26510. Profit after tax 24.335 38.97 51.23 60.405 67.52 73.26511. Net salvage value of fixed assets 80

    12.Net recovery of working capitalmargin

    50

    13. Initial investment (1+2) (300)

    14. Operating cash inflow (9+5+7(1-T) )

    122.665 108.78 99.52 93.345 89.23 86.845

    15. Terminal cash flow (11+12) 130.00

    16. Net cash flow (13+14+15) (300) 122.665 108.78 99.52 93.345 89.23 216.485 Cash Flows Relating to Total Funds

    (Rs. in million)

    Year0 1 2 3 4 5 6

    1. Total funds (450)2. Revenues 500 500 500 500 500 5003. Operating costs 320 320 320 320 320 3204. Depreciation 83.33 55.56 37.04 24.69 16.46 10.97

    5. Interest on term loan 30.00 28.50 22.50 16.50 10.50 4.50

  • 7/31/2019 Projects Solutions Pfa

    33/89

    6. Interest on working capitaladvance

    18.00 18.00 18.00 18.00 18.00 18.00

    7. Profit before tax 48.67 77.94 102.46 120.81 135.04 146.53

    8. Tax 24.34 38.97 51.23 60.41 67.52 73.2659. Profit after tax 24.34 38.97 51.23 60.41 67.52 73.26510. Net salvalue of fixed assets 8011. Net salvage value of current assets 20012. Initial investment (1) (450)

    13. Operating cash inflow 9+4+6 (1-t)+ 5(1-t)

    131.67 117.78 108.52 102.35 98.23 95.485

    14. Terminal cash flow (10+11) 28015. Net cash flow (12+13+14) (450) 131.67 117.78 108.52 102.35 98.23 375.485

    Chapter 10

    THE COST OF CAPITAL

    1(a) Define rD as the pre-tax cost of debt. Using the approximate yield formula, rDcan be calculated as follows:

    14 + (100 108)/10

  • 7/31/2019 Projects Solutions Pfa

    34/89

    rD = ------------------------ x 100 = 12.60%0.4 x 100 + 0.6x108

    (b) After tax cost = 12.60 x (1 0.35) = 8.19%

    2. Define rp as the cost of preference capital. Using the approximate yield formularp can be calculated as follows:

    9 + (100 92)/6rp = --------------------

    0.4 x100 + 0.6x92

    = 0.1085 (or) 10.85%

    3. WACC= 0.4 x 13% x (1 0.35)+ 0.6 x 18%

    = 14.18%

    4. Cost of equity = 10% + 1.2 x 7% = 18.4%(using SML equation)Pre-tax cost of debt = 14%After-tax cost of debt = 14% x (1 0.35) = 9.1%Debt equity ratio = 2 : 3WACC = 2/5 x 9.1% + 3/5 x 18.4%

    = 14.68%

    5. Given0.5 x 14% x (1 0.35) + 0.5 x rE = 12%

    where rE is the cost of equity capital.Therefore rE 14.9%Using the SML equation we get

    11% + 8% x = 14.9%where denotes the beta of Azeezs equity.

    Solving this equation we get = 0.4875.

    6 (a) The cost of debt of 12% represents the historical interest rate at the time the debtwas originally issued. But we need to calculate the marginal cost of debt (costof raising new debt); and for this purpose we need to calculate the yield tomaturity of the debt as on the balance sheet date. The yield to maturity will notbe equal to 12% unless the book value of debt is equal to the market value ofdebt on the balance sheet date.

  • 7/31/2019 Projects Solutions Pfa

    35/89

    (b) The cost of equity has been taken asD1/P0 ( = 6/100) whereas the cost of equityis (D1/P0) + gwhere grepresents the expected constant growth rate in dividendper share.

    7. The book value and market values of the different sources of finance areprovided in the following table. The book value weights and the market valueweights are provided within parenthesis in the table.

    (Rs. in million)

    Source Book value Market value

    Equity 800 (0.54) 2400 (0.78)

    Debentures first series 300 (0.20) 270 (0.09)Debentures second series 200 (0.13) 204 (0.06)Bank loan 200 (0.13) 200 (0.07)Total 1500 (1.00) 3074 (1.00)

    8.

    (a) GivenrD x (1 0.3) x 4/9 + 20% x 5/9 = 15%rD = 12.5%,where rD represents the pre-tax cost of debt.

    (b) Given13% x (1 0.3) x 4/9 + rE x 5/9 = 15%rE = 19.72%, where rErepresents the cost of equity.

    9. Cost of equity = D1/P0 +g

    = 3.00 / 30.00 + 0.05= 15%

    (a) The first chunk of financing will comprise of Rs.5 million of retained earningscosting 15 percent and Rs.25 million of debt costing 14 (1-.3) = 9.8 percent.The second chunk of financing will comprise of Rs.5 million of additionalequity costing 15 percent and Rs.2.5 million of debt costing 15 (1-.3) = 10.5percent.

    (b) The marginal cost of capital in the first chunk will be :5/7.5 x 15% + 2.5/7.5 x 9.8% = 13.27%The marginal cost of capital in the second chunk will be :

    5/7.5 x 15% + 2.5/7.5 x 10.5% = 13.50%

    Note : We have assumed that(i) The net realisation per share will be Rs.25, after floatation costs, and(ii) The planned investment of Rs.15 million is inclusive of floatation costs

  • 7/31/2019 Projects Solutions Pfa

    36/89

    10. The cost of equity and retained earningsrE = D1/PO +g

    = 1.50 / 20.00 + 0.07 = 14.5%

    The cost of preference capital, using the approximate formula, is :11 + (100-75)/10

    rE = = 15.9%0.6x75 + 0.4x100

    The pre-tax cost of debentures, using the approximate formula, is :13.5 + (100-80)/6

    rD = = 19.1%0.6x80 + 0.4x100

    The post-tax cost of debentures is19.1 (1-tax rate) = 19.1 (1 0.5)

    = 9.6%The post-tax cost of term loans is

    12 (1-tax rate) = 12 (1 0.5)= 6.0%

    The average cost of capital using book value proportions is calculated below:

    Source of capital Component Book value Book value Product of

    cost Rs. in million proportion (1) & (3)(1) (2) (3)

    Equity capital 14.5% 100 0.28 4.06Preference capital 15.9% 10 0.03 0.48Retained earnings 14.5% 120 0.33 4.79

    Debentures 9.6% 50 0.14 1.34Term loans 6.0% 80 0.22 1.32

    360 Average cost 11.99%capital

    The average cost of capital using market value proportions is calculated below :

    Source of capital Component Market value Market value Product of

    cost Rs. in million(1) (2) (3) (1) & (3)

    Equity capitaland retained earnings 14.5% 200 0.62 8.99Preference capital 15.9% 7.5 0.02 0.32Debentures 9.6% 40 0.12 1.15Term loans 6.0% 80 0.24 1.44

  • 7/31/2019 Projects Solutions Pfa

    37/89

    327.5 Average cost 11.90%capital

    11.(a) WACC= 1/3 x 13% x (1 0.3)

    + 2/3 x 20%= 16.37%

    (b) Weighted average floatation cost= 1/3 x 3% + 2/3 x 12%

    = 9%

    (c) NPV of the proposal after taking into account the floatation costs= 130 x PVIFA (16.37%, 8) 500 / (1 - 0.09)= Rs.8.51 million

    Chapter 11

    RISK ANALYSIS OF SINGLE INVESTMENTS

    1.(a) NPV of the project = -250 + 50 x PVIFA (13%,10)

    = Rs.21.31 million

    (b) NPVs under alternative scenarios:(Rs. in million)

  • 7/31/2019 Projects Solutions Pfa

    38/89

    Pessimistic Expected Optimistic

    Investment 300 250 200

    Sales 150 200 275Variable costs 97.5 120 154Fixed costs 30 20 15Depreciation 30 25 20Pretax profit - 7.5 35 86Tax @ 28.57% - 2.14 10 24.57Profit after tax - 5.36 25 61.43Net cash flow 24.64 50 81.43

    Cost of capital 14% 13% 12%

    NPV - 171.47 21.31 260.10

    Assumptions: (1) The useful life is assumed to be 10 years under all threescenarios. It is also assumed that the salvage value of theinvestment after ten years is zero.

    (2) The investment is assumed to be depreciated at 10% perannum; and it is also assumed that this method and rate ofdepreciation are acceptable to the IT (income tax)authorities.

    (3) The tax rate has been calculated from the given table i.e. 10/ 35 x 100 = 28.57%.

    (4) It is assumed that only loss on this project can be offsetagainst the taxable profit on other projects of the company;and thus the company can claim a tax shield on the loss inthe same year.

    (c) Accounting break even point (under expected scenario)

    Fixed costs + depreciation = Rs. 45 millionContribution margin ratio = 60 / 200 = 0.3Break even level of sales = 45 / 0.3 = Rs.150 millionFinancial break even point (under expected scenario)

    i. Annual net cash flow = 0.7143 [ 0.3 x sales 45 ] + 25= 0.2143 sales 7.14

    ii. PV (net cash flows) = [0.2143 sales 7.14 ] x PVIFA (13%,10)

  • 7/31/2019 Projects Solutions Pfa

    39/89

    = 1.1628 sales 38.74

    iii. Initial investment = 200

    iv. Financial break even levelof sales = 238.74 / 1.1628 = Rs.205.31 million

    2.(a) Sensitivity of NPV with respect to quantity manufactured and sold:

    (in Rs)

    Pessimistic Expected Optimistic

    Initial investment 30000 30000 30000Sale revenue 24000 42000 54000Variable costs 16000 28000 36000Fixed costs 3000 3000 3000Depreciation 2000 2000 2000Profit before tax 3000 9000 13000Tax 1500 4500 6500

    Profit after tax 1500 4500 6500Net cash flow 3500 6500 8500NPV at a cost ofcapital of 10% p.aand useful life of5 years -16732 - 5360 2222

    (b) Sensitivity of NPV with respect to variations in unit price.

    Pessimistic Expected Optimistic

    Initial investment 30000 30000 30000Sale revenue 28000 42000 70000Variable costs 28000 28000 28000Fixed costs 3000 3000 3000Depreciation 2000 2000 2000

    Profit before tax -5000 9000 37000Tax -2500 4500 18500Profit after tax -2500 4500 18500Net cash flow - 500 6500 20500NPV - 31895 (-) 5360 47711

    (c) Sensitivity of NPV with respect to variations in unit variable cost.

    Pessimistic Expected Optimistic

  • 7/31/2019 Projects Solutions Pfa

    40/89

    Initial investment 30000 30000 30000Sale revenue 42000 42000 42000

    Variable costs 56000 28000 21000Fixed costs 3000 3000 3000Depreciation 2000 2000 2000Profit before tax -11000 9000 16000Tax -5500 4500 8000Profit after tax -5500 4500 8000Net cash flow -3500 6500 10000NPV -43268 - 5360 7908

    (d) Accounting break-even point

    i. Fixed costs + depreciation = Rs.5000ii. Contribution margin ratio = 10 / 30 = 0.3333iii. Break-even level of sales = 5000 / 0.3333

    = Rs.15000

    Financial break-even point

    i. Annual cash flow = 0.5 x (0.3333 Sales 5000) = 2000ii. PV of annual cash flow = (i) x PVIFA (10%,5)

    = 0.6318 sales 1896iii. Initial investment = 30000iv. Break-even level of sales = 31896 / 0.6318 = Rs.50484

    2. DefineAtas the random variable denoting net cash flow in yeart.

    A1 = 4 x 0.4 + 5 x 0.5 + 6 x 0.1= 4.7

    A2 = 5 x 0.4 + 6 x 0.4 + 7 x 0.2= 5.8

    A3 = 3 x 0.3 + 4 x 0.5 + 5 x 0.2= 3.9

    NPV = 4.7 / 1.1 +5.8 / (1.1)2 + 3.9 / (1.1)3 10= Rs.2.00 million

    12 = 0.41

    22 = 0.56

    32

    = 0.49

  • 7/31/2019 Projects Solutions Pfa

    41/89

    12 22 32

    2NPV = + +(1.1)2 (1.1)4 (1.1)6

    = 1.00

    (NPV) = Rs.1.00 million

    3. Expected NPV4 At

    = - 25,000 t=1 (1.08)t

    = 12,000/(1.08) + 10,000 / (1.08)2 + 9,000 / (1.08)3

    + 8,000 / (1.08)4 25,000

    = [ 12,000 x .926 + 10,000 x .857 + 9,000 x .794 + 8,000 x .735]- 25,000

    = 7,708

    Standard deviation of NPV

    4 t t=1 (1.08)t

    = 5,000 / (1.08) + 6,000 / (1.08)2 + 5,000 / (1,08)3 + 6,000 / (1.08)4

    = 5,000 x .926 + 6,000 x .857 + 5000 x .794 + 6,000 x .735

    = 18,152

    4. Expected NPV4 At

    = - 25,000 . (1) t=1 (1.06)t

    A1 = 2,000 x 0.2 + 3,000 x 0.5 + 4,000 x 0.3= 3,100

    A2 = 3,000 x 0.4 + 4,000 x 0.3 + 5,000 x 0.3= 3,900

    A3 = 4,000 x 0.3 + 5,000 x 0.5 + 6,000 x 0.2= 4,900

    A4 = 2,000 x 0.2 + 3,000 x 0.4 + 4,000 x 0.4

  • 7/31/2019 Projects Solutions Pfa

    42/89

    = 3,200Substituting these values in (1) we get

    Expected NPV = NPV

    = 3,100 / (1.06)+ 3,900 / (1.06)2 + 4,900 / (1.06)3 + 3,200 / (1,06)4

    - 10,000 = Rs.3,044

    The variance of NPV is given by the expression

    4 2t2 (NPV) = .. (2)

    t=1 (1.06)2t

    12 = [(2,000 3,100)2 x 0.2 + (3,000 3,100)2 x 0.5+ (4,000 3,100)2 x 0.3]

    = 490,000

    22 = [(3,000 3,900)2 x 0.4 + (4,000 3,900)2 x 0.3+ (5,000 3900)2 x 0.3]

    = 690,000

    32 = [(4,000 4,900)2 x 0.3 + (5,000 4,900)2 x 0.5+ (6,000 4,900)2 x 0.2]

    = 490,000

    42 = [(2,000 3,200)2 x 0.2 + (3,000 3,200)2 x 0.4+ (4,000 3200)2 x 0.4]

    = 560,000

    Substituting these values in (2) we get490,000 / (1.06)2 + 690,000 / (1.06)4

    + 490,000 / (1.06)6 + 560,000 / (1.08)8

    [ 490,000 x 0.890 + 690,000 x 0.792+ 490,000 x 0.705 + 560,000 x 0.627 ]= 1,679,150

    NPV = 1,679,150 = Rs.1,296

    NPV NPV 0 -NPVProb (NPV < 0) = Prob. 0.2 x 10,000)Prob (NPV > 2,000)

    Prob (NPV >2,000)= Prob (Z> 2,000- 3,044 / 1,296)Prob (Z> - 0.81)

    The required probability is given by the shaded area of the following normalcurve:P(Z> - 0.81) = 0.5 +P(-0.81

  • 7/31/2019 Projects Solutions Pfa

    44/89

    = [ 0.5Q (PV) 500] x PVIFA (10,5) 30,000= [0.5Q (PV) 500] x 3.791 30,000

    = 1.8955Q (PV) 31,895.5

    Exhibit 1 presents the correspondence between the values of exogenous variablesand the two digit random number. Exhibit 2 shows the results of the simulation.

    Exhibit 1Correspondence between values of exogenous variables and

    two digit random numbers

    QUANTITY PRICE VARIABLE COST

    Value ProbCumulative

    Prob.

    Two digit

    randomnumbers Value Prob

    CumulativeProb.

    Two digit

    randomnumbers Value Prob

    Cumu-lative

    Prob.

    Two digit

    randomnumbers

    800 0.10 0.10 00 to 09 20 0.40 0.40 00 to 39 15 0.30 0.30 00 to 29

    1,000 0.10 0.20 10 to 19 30 0.40 0.80 40 to 79 20 0.50 0.80 30 to 79

    1,200 0.20 0.40 20 to 39 40 0.10 0.90 80 to 89 40 0.20 1.00 80 to 99

    1,400 0.30 0.70 40 to 69 50 0.10 1.00 90 to 991,600 0.20 0.90 70 to 89

    1,800 0.10 1.00 90 to 99

    Exhibit 2Simulation Results

    QUANTITY (Q) PRICE (P) VARIABLE COST (V) NPV

    Run Random

    Number

    Corres-

    pondingValue

    Random

    Number

    Corres-

    pondingvalue

    Random

    Number

    Corres-

    pondingvalue

    1.8955 Q(P-V)-31,895.5

    1 03 800 38 20 17 15 -24,314

    2 32 1,200 69 30 24 15 2,224

    3 61 1,400 30 20 03 15 -18,627

    4 48 1,400 60 30 83 40 -58,433

    5 32 1,200 19 20 11 15 -20,523

    6 31 1,200 88 40 30 20 13,597

    7 22 1,200 78 30 41 20 -9,150

    8 46 1,400 11 20 52 20 -31,896

  • 7/31/2019 Projects Solutions Pfa

    45/89

    9 57 1,400 20 20 15 15 -18,627

    QUANTITY (Q) PRICE (P) VARIABLE COST (V) NPV

    Run Random

    Number

    Corres-

    pondingValue

    Random

    Number

    Corres-

    pondingvalue

    Random

    Number

    Corres-

    pondingvalue

    1.8955 Q(P-V)-31,895.5

    10 92 1,800 77 30 38 20 2,224

    11 25 1,200 65 30 36 20 -9,150

    12 64 1,400 04 20 83 40 -84,970

    13 14 1,000 51 30 72 20 -12,941

    14 05 800 39 20 81 40 -62,224

    15 07 800 90 50 40 20 13,597

    16 34 1,200 63 30 67 20 -9,150

    17 79 1,600 91 50 99 40 -1,568

    18 55 1,400 54 30 64 20 -5,35919 57 1,400 12 20 19 15 -18,627

    20 53 1,400 78 30 22 15 7,910

    21 36 1,200 79 30 96 40 -54,642

    22 32 1,200 22 20 75 20 -31,896

    23 49 1,400 93 50 88 40 -5,359

    24 21 1,200 84 40 35 20 13,597

    25 08 .800 70 30 27 15 -9,150

    26 85 1,600 63 30 69 20 -1,568

    27 61 1,400 68 30 16 15 7,91028 25 1,200 81 40 39 20 13,597

    29 51 1,400 76 30 38 20 -5,359

    30 32 1,200 47 30 46 20 -9,150

    31 52 1,400 61 30 58 20 -5,359

    32 76 1,600 18 20 41 20 -31,896

    33 43 1,400 04 20 49 20 -31,896

    34 70 1,600 11 20 59 20 -31,896

    35 67 1,400 35 20 26 15 -18,627

    36 26 1,200 63 30 22 15 2,224QUANTITY (Q) PRICE (P) VARIABLE COST (V) NPV

    Run Random

    Number

    Corres-

    pondingValue

    Random

    Number

    Corres-

    pondingvalue

    Random

    Number

    Corres-

    pondingvalue

    1.8955 Q(P-V)-31,895.5

    37 89 1,600 86 40 59 20 28,761

    38 94 1,800 00 20 25 15 -14,836

    39 09 .800 15 20 29 15 -24,314

    40 44 1,400 84 40 21 15 34,447

    41 98 1,800 23 20 79 20 -31,896

    42 10 1,000 53 30 77 20 -12,94143 38 1,200 44 30 31 20 -9,150

    44 83 1,600 30 20 10 15 -16,732

    45 54 1,400 71 30 52 20 -5,359

    46 16 1,000 70 30 19 15 -3,463

    47 20 1,200 65 30 87 40 -54,642

    48 61 1,400 61 30 70 20 -5,359

    49 82 1,600 48 30 97 40 -62,224

    50 90 1,800 50 30 43 20 2,224

  • 7/31/2019 Projects Solutions Pfa

    46/89

    ExpectedNPV = NPV50

    = 1/ 50 NPVii=1

    = 1/50 (-7,20,961)= 14,419

    50

    Variance of NPV = 1/50 (NPVi NPV)2

    i=1

    = 1/50 [27,474.047 x 106]= 549.481 x 106

    Standard deviation of NPV = 549.481 x 106

    = 23,441

    6. To carry out a sensitivity analysis, we have to define the range and the most likely

    values of the variables in the NPV Model. These values are defined below

    Variable Range Most likely value

    I Rs.30,000 Rs.30,000 Rs.30,000k 10% - 10% 10%F Rs.3,000 Rs.3,000 Rs.3,000D Rs.2,000 Rs.2,000 Rs.2,000

    T 0.5 0.5 0.5N 5 5 5S 0 0 0Q Can assume any one of the values - 1,400*

    800, 1,000, 1,200, 1,400, 1,600 and 1,800P Can assume any of the values 20, 30, 30**

    40 and 50V Can assume any one of the values 20*

    15,20 and 40----------------------------------------------------------------------------------------* The most likely values in the case ofQ,Pand Vare the values that

    have the highest probability associated with them

    ** In the case of price, 20 and 30 have the same probability ofoccurrence viz., 0.4. We have chosen 30 as the most likely valuebecause the expected value of the distribution is closer to 30

  • 7/31/2019 Projects Solutions Pfa

    47/89

    Sensitivity Analysis with Reference to Q

    The relationship between Q and NPV given the most likely values of other

    variables is given by5 [Q (30-20) 3,000 2,000] x 0.5 + 2,000 0

    NPV = + - 30,000 t=1 (1.1)t (1.1)5

    5 5Q - 500

    = - 30,000 t=1 (1.1)t

    The net present values for various values ofQ are given in the following table:

    Q 800 1,000 1,200 1,400 1,600 1,800NPV -16,732 -12,941 -9,150 -5,359 -1,568 2,224

    Sensitivity analysis with reference to P

    The relationship betweenPand NPV, given the most likely values of othervariables is defined as follows:

    5 [1,400 (P-20) 3,000 2,000] x 0.5 + 2,000 0

    NPV = + - 30,000 t=1 (1.1)t (1.1)5

    5 700P 14,500

    = - 30,000 t=1 (1.1)t

    The net present values for various values ofPare given below :P(Rs) 20 30 40 50

    NPV(Rs) -31,896 -5,359 21,179 47,716

    8. NPV - 5 0 5 10 15 20(Rs.in lakhs)PI 0.9 1.00 1.10 1.20 1.30 1.40

    Prob. 0.02 0.03 0.10 0.40 0.30 0.15

    6

  • 7/31/2019 Projects Solutions Pfa

    48/89

    Expected PI = PI= (PI)jPj j=1= 1.24

    6

    Standard deviation = (PIj - PI)2Pjo fP1 j=1

    = .01156= .1075

    The standard deviation ofP1 is .1075 for the given investment with an expectedPI of 1.24. The maximum standard deviation of PI acceptable to the company

    for an investment with an expected PI of 1.25 is 0.30.

    Since the risk associated with the investment is much less than the maximumrisk acceptable to the company for the given level of expected PI, the companyshould accept the investment.

    9. Investment AOutlay : Rs.10,000

    Net cash flow : Rs.3,000 for 6 yearsRequired rate of return: 12%

    NPV(A) = 3,000 x PVIFA (12%, 6 years) 10,000= 3,000 x 4.11 10,000 = Rs.2,333

    Investment BOutlay : Rs.30,000

    Net cash flow : Rs.11,000 for 5 yearsRequired rate of return: 14%NPV(B) = 11,000 x PVIFA (14%, 5 years) 30,000

    = Rs.7763

    10. The NPVs of the two projects calculated at their risk adjusted discount rates areas follows:

    6 3,000

    ProjectA: NPV = - 10,000 = Rs.2,333t=1 (1.12)t

    5 11,000

    ProjectB: NPV = - 30,000 = Rs.7,763t=1 (1.14)t

    PIand IRR for the two projects are as follows:

  • 7/31/2019 Projects Solutions Pfa

    49/89

    Project A B

    PI 1.23 1.26IRR 20% 24.3%

    B is superior toA in terms of NPV, PI, and IRR. Hence the company mustchooseB.

    Chapter 12

    RISK ANALYSIS OF SINGLE INVESTMENTS

    1. 2p = wiwjijij

    2

    p = w

    2

    12

    1 + w

    2

    22

    2 + w

    2

    32

    3 + w

    2

    42

    4 + w

    2

    52

    5

    + 2 w1 w2 12 12 + 2 w1 w3 13 13 + 2 w1 w4 14 14 + 2 w1 w5 1515 + 2 w2 w3 23 23 + 2 w2 w4 24 24 + 2 w2 w5 25 25 + 2 w3 w434 34 + 2 w3 w5 35 35 + 2 w4 w5 45 45

    = 0.12 x 82 + 0.22 x 92 + 0.32 x 102 + 0.32 x 162 + 0.12 x 122 + 2 x 0.1 x 0.2 x 0.1 x 8 x 9 + 2 x 0.1 x 0.3 x 0.5 x 8 x 10

    + 2 x 0.1 x 0.3 x 0.2 x 8 x 16 + 2 x 0.1 x 0.1 x 0.3 x 8 x 12

  • 7/31/2019 Projects Solutions Pfa

    50/89

    + 2 x 0.2 x 0.3 x 0.4 x 9 x 10 + 2 x 0.2 x 0.3 x 0.8 x 9 x 16+ 2 x 0.2 x 0.1 x 0.2 x 9 x 12 + 2 x 0.3 x 0.3 x0.1 x 10 x 16+ 2 x 0.3 x 0.1 x 0.6 x 10 x 12 + 2 x 0.3 x 0.1 x 0.1 x 16 x 12

    = 66.448p = (66.448)1/2 = 8.152

    2. (i) Since there are 3 securities, there are 3 variance terms and 3 covariance terms.Note that if there are n securities the number of covariance terms are: 1 + 2 ++

    (n + 1) = n (n 1)/2. In this problem all the variance terms are the same (2A) allthe covariance terms are the same (AB) and all the securities are equally weighted( wA = )

    So,

    2p = [3 w2A 2A + 2 x 3 AB]2p = [3 w2A 2A + 6 wA wB AB]

    1 2 1 1

    = 3 x x 2A + 6 x x x AB3 3 3

    1 2

    = 2A + AB3 3

    (ii) Since there are 9 securities, there are 9 variance terms and 36 covarianceterms. Note that if the number of securities is n, the number of covarianceterms is n(n 1)/2.

    In this case all the variance terms are the same (2A), all the covariance terms are1

    the same (AB) and all the securities are equally weighted wA =9

    So,n(n-1)

    2p = 9 w2A 2A t 2 x wA wB AB2

    1 2 1 1

    = 9 x x 2A + 9(8) x x AB9 9 9

    1 72

    = 2A + AB9 81

    3. The beta for stock B is calculated below:

    Period Return of Return on Deviation of Deviation Product of Square of

  • 7/31/2019 Projects Solutions Pfa

    51/89

    stock B,

    RB (%)

    market

    portfolio,

    RM(%)

    return on

    stock B from

    its mean

    (RB - RB)

    of return

    on market

    portfolio

    from itsmean

    (RM RM)

    the

    deviation

    (RB RB)

    (RM RM)

    the

    deviation

    of return

    on marketportfolio,

    from its

    mean

    (RM RM)2

    1 15 9 6 -1 -6 12 16 12 7 2 14 43 10 6 1 -4 -4 16

    4 -15 4 -24 -6 144 365 -5 16 -14 6 -84 366 14 11 5 1 5 17 10 10 1 0 0 08 15 12 6 2 12 49 12 9 3 -1 -3 110 -4 8 -13 -2 26 411 -2 12 -11 2 -22 4

    12 12 14 3 4 12 1613 15 -6 6 -16 -96 25614 12 2 3 -8 -24 6415 10 8 1 -2 -2 416 9 7 0 -3 0 917 12 9 3 -1 -3 118 9 10 0 0 0 019 22 37 13 27 351 729

    20 13 10 4 0 0 0180 200 (RB RB) (RB RB)2

    RB = 180 RM= 200 (RM RM) = 1186RB = 9% RM= 10% = 320

    Beta of stock B is equal to:

    Cov (RB,RM)

    2M (RB -RB) (RMRM) 320

    Cov (RB,RM) = = = 16.84n 1 19

    (RMRM)2 1186

    2M = = = 62.42

    n 1 19

  • 7/31/2019 Projects Solutions Pfa

    52/89

    So the beta for stockB is:16.84

    = 0.27062.42

    4. According to the CAPM, the required rate of return is:

    E(Ri) =Rf+ (E(RMRf)i

    Given a risk-free rate (Rf) of 11 percent and the expected market risk premium(E(RMRf) of 6 percent we get the following:

    Project Beta Required rate(%) Expected rate (%)A 0.5 11 + 0.5 x 6 = 14 15B 0.8 11 + 0.8 x 6 = 15.8 16C 1.2 11 + 1.2 x 6 = 18.2 21D 1.6 11 + 1.6 x 6 = 20.6 22E 1.7 11 + 1.7 x 6 = 21.2 23

    a. The expected return of all the 5 projects exceeds the required rate as per the CAPM.

    So all of them should be accepted.b. If the cost of capital of firm which is 16 percent is used as the hurdle rate, project A

    will be rejected incorrectly.

    5. The asset beta is linked to equity beta, debt-equity ratio, and tax rate as follows:

    EA =

    [1 +D/E(1 T)]

    The asset beta of A, B, and C is calculated below:

    Firm Asset Beta

    1.25A = 0.49

    [1 + (2.25) x 0.7]

    1.25

    B = 0.48[1 + (2.00) x 0.7]

    1.10C = 0.45

    [1 + (2.1) x 0.7]

  • 7/31/2019 Projects Solutions Pfa

    53/89

    0.49 + 0.48 + 0.45Average of the asset betas of sample firms = = 0.47

    3The equity beta of the cement project is

    E= A [ 1 +D/E(1 T)]= 0.47 [1 + 2 (1-0.3)] = 1.128

    As per the CAPM model, the cost of equity of the proposed project is:12% + (17% - 12%) x 1.128 = 17.64%

    The post-tax cost of debt is:16% (1 0.3) = 11.2%

    The required rate of return for the project given a debt-equity ratio of 2:1 is:1/3 x 17.64% + 2/3 x 11.2% = 13.35%

    6. EA =

    [1 +D/E(1 T)]E = 1.25 D/E= 1.6 T= 0.3

    So, Pariman Companys asset beta is:1.25

    = 0.59[1 + 1.6 (0.7)]

    7. (a) Asset beta for a petrochemicals project is:

    E 1.30A = =

    [1 +D/E( 1 T)] [1 + 1.5 (1 .4)]

    = 0.68

    The equity beta (systematic risk) for the petrochemicals project of Growmore,whenD/E= 1.25 and T= 0.4, is

    0.68 [1 + 1.25 (1 .4)] = 1.19

  • 7/31/2019 Projects Solutions Pfa

    54/89

    (b) The cost of equity for the petrochemicals project is12% + 1.19 (18% - 12%) = 19.14%

    The cost of debt is

    12% (1 0.4) = 7.2%Given, a debt equity ratio of 1.25 the required return for the petrochemicals

    project is1 1.25

    19.14% x + 7% x = 12.4%2.25 2.25

    Chapter 13

    SPECIAL DECISION SITUATIONS

    1. PV Cost UAE =

    PVIFAr,n

    Cost of plastic emulsion painting = Rs.3,00,000 Life = 7 yearsCost of distemper painting = Rs. 1,80,000 Life = 3 yearsDiscount rate = 10%UAEof plastic emulsion painting = Rs.3,00,000 / 4.868 = Rs.61,627

  • 7/31/2019 Projects Solutions Pfa

    55/89

    UAEof distemper painting = Rs.1,80,000 / 2.487 = Rs.72,376

    Since plastic emulsion painting has a lowerUAE, it is preferable.

    2. Present value of the operating costs :3,00,000 3,60,000 4,00,000 4,50,000 5,00,000

    = + + + +1.13 (1.13)2 (1.13)3 (1.13)4 (1.13)5

    = Rs.1,372,013Present value of salvage value = 3,00,000 / (1.13)5 = Rs.162,828

    Present value of costs of internal transportation = 1,500,000 1,372,013system 162,828 = Rs.27,09,185UAEof the internal transportation system = 27,09,185 / 3.517 = Rs.7,70,311

    3. Cost of standard overhaul = Rs.500,000Cost of less costly overhaul = Rs.200,000Cost of capital = 14%UAEof standard overhaul = 500,000 / 3.889 = Rs.128,568

    UAEof less costly overhaul = 200,000 / 1.647 = Rs.121,433

    Since the less costly overhaul has a lowerUAE, it is the preferred alternative

    4. The details for the two alternatives are shown below :

    Gunning plow Counter plow

    1. Initial outlay Rs.2,500,000 Rs.1,500,0002. Economic life 12 years 9 years3. Annual operating and maintenance costs Rs.250,000 Rs.320,0004. Present value of the stream of operating and

    maintenance costs at 12% discount rateRs.1,548,500 Rs.1,704,960

    5. Salvage value Rs.800,000 Rs.500,0006. Present value of salvage value Rs.205,600 Rs.180,5007. Present value of total costs (1+4-6) Rs.3,842,900 Rs.3,024,460

  • 7/31/2019 Projects Solutions Pfa

    56/89

    8. UAEof 7 Rs.3,842,900PVIFA (12%,12)= 3,842,900

    6.194= Rs.620,423

    Rs.3,024,460PVIFA (12%,9)= 3,024,460

    5.328= Rs.567,654

    The Counter plow is a cheaper alternative

    5. The current value of different timing options is given below :

    Time Net Future Value Current Value

    Rs. in millionRs. in million0 10 101 15 13.3952 19 15.1433 23 16.3764 26 16.536

    The optimal timing of the project is year 4.

    6. Calculation of UAE (OM) for Various Replacement Periods (Rupees)

    Time

    (t)

    Operating

    and

    maintenance

    costs

    Post-tax

    operating &

    maintenance

    costs

    PVIF

    (12%,t)Present

    value

    of(3)

    Cumulative

    present

    value

    PVIFA

    (12%,t)UAE

    (OM)

    (1) (2) (3) (4) (5) (6) (7) (8)

    1 20,000 12,000 0.893 10,716 10,716 0.893 12,0002 25,000 15,000 0.797 11,955 22,671 1.690 13,4153 35,000 21,000 0.712 14,952 37,623 2.402 15,6634 50,000 30,000 0.636 19,080 56,703 3.037 18,6715 70,000 42,000 0.567 23,814 80,517 3.605 22,335

    Calculation of UAE (IO) for Various Replacement Periods

    Time (t) Investment Outlay Rs. PVIFA ( 12%, t) UAE of investment outlay Rs.1 80,000 0.893 89,586

    2 80,000 1.690 47,3373 80,000 2.402 33,3064 80,000 3.037 26,3425 80,000 3.605 22,191

    Calculation of UAE (DTS) for Various Replacement PeriodsTime

    (t)Depreciation

    charge R.s.Depreciation

    tax shieldPVIF

    (12%, t)PV of

    depreciation

    tax shield Rs..

    Cumulativepresent

    value Rs..

    PVIFA(12%, t)

    UAE ofdepreciation

    tax shield Rs..

  • 7/31/2019 Projects Solutions Pfa

    57/89

    (1) (2) (3) (4) (5) (6) (7) (8)1 20,000 8,000 0.893 7,144 7,144 0.893 8,0002 15,000 6,000 0.797 4,782 11,926 1.690 7,0573 11,250 4,500 0.712 3,204 15,130 2.402 6,2994 8,438 3,375 0.636 2,147 17,277 3.037 5,6895 6,328 2,531 0.567 1,435 18,712 3.605 5,191

    Calculation of UAE (SV) for Various Replacement Periods

    Time Salvage

    value Rs.

    PVIF

    (12%, t)Present value of

    salvage value Rs.

    PVIFA

    (12%, t)UAE of salvage

    value Rs. (4) / (5)(1) (2) (3) (4) (5) (6)1 60,000 0.893 53,580 0.893 60,000

    2 45,000 0.797 35,865 1.690 21,2223 32,000 0.712 22,784 2.402 9,4854 22,000 0.636 13,992 3.037 4,6075 15,000 0.567 8,505 3.605 2,359

    Summary of Information Required to Determine the Economic Life

    Replacement

    period

    UAE

    (OM) Rs.

    UAE (IO)

    Rs.

    UAE

    (DTS) Rs.

    UAE (SV)

    Rs.

    UAE

    (CC) Rs.

    UAE (TC)

    Rs.

    (1) (2) (3) (4) (5) (6) (7)1 12,000 89,586 8,000 60,000 21,586 33,5862 13,415 47,337 7,057 21,222 19,058 32,4733 15,663 33,306 6,299 9,485 17,522 33,1854 18,671 26,342 5,689 4,607 16,046 34,7175 22,335 22,191 5,190 2,359 14,642 36,977

    OM - Operating and Maintenance Costs

    IO - Investment OutlayDTS - Depreciation Tax ShieldSV - Salvage ValueCC - Capital CostTC - Total CostUAE (CC) = UAE (IO) [UAE (DTS) + UAE (SV)]UAE (TC) = UAE (OM) + UAE (CC)

    7. Calculation of UAE (OM) for Various Replacement periodsTime O&M costsRs.

    Post-tax

    O&M costs

    Rs.

    PVIF

    (12%,t)PV of post-

    tax O&M

    costs Rs.

    Cumulative

    present

    value Rs.

    PVIFA

    (12%, t)UAE of

    O&M

    costs Rs.

    (1) (2) (3) (4) (5) (6) (7) (8)1 800,000 560,000 0.893 500,080 500,080 0.893 560,0002 1,000,000 700,000 0.797 557,900 1,057,980 1.690 626,0243 1,300,000 910,000 0.712 647,920 1,705,9000 2.402 710,2004 1,900,000 1,330,000 0.636 845,880 2,551,780 3.037 840,230

  • 7/31/2019 Projects Solutions Pfa

    58/89

    5 2,800,000 1,960,000 0.567 1,111,320 3,663,100 3.605 1,016,117

    Calculation of UAE (IO) for Various Replacement Periods

    Time Investment outlay Rs. PVIFA ( 12%, t) UAE of investment outlay Rs.1 4,000,000 0.893 4,479,2832 4,000,000 1.690 2,366,8643 4,000,000 2.402 1,665,2794 4,000,000 3.037 1,317,0895 4,000,000 3.605 1,109,570

    Calculation of UAE (DTS) for Various Replacement Periods

    Time(t)

    Depreciationcharge Rs.

    Depreciatontax shield

    Rs.

    PVIF(12%, t)

    PV ofdepreciationtax shield Rs.

    Cumulativepresentvalue Rs.

    PVIFA(12%, t)

    UAE ofdepreciationtax shield Rs.

    1 1,000,000 300,000 0.893 267,940 267,900 0.893 300,0002 750,000 225,000 0.797 179,325 447,225 1.690 264,6303 562,500 168,750 0.712 120,150 567,375 2.402 236,2094 421,875 126,563 0.636 80,494 647,869 3.037 213,3255 316,406 94,922 0.567 53,821 701,690 3.605 194,643

    Calculation of UAE (SV) for Various Replacement Peiods

    Time Salvage

    value Rs.

    PVIF

    (12%, t)Present value of

    salvage value Rs.

    PVIFA

    (12%, t)UAE of salvage

    value Rs. (4)/ (5)(1) (2) (3) (4) (5) (6)1 2,800,000 0.893 267,900 0.893 2,800,0002 2,000,000 0.797 1,594,000 1.690 943,1953 1,400,000 0.712 996,80 2.402 414,9884 1,000,000 0.636 636,000 3.037 209,4175 800,000 0.567 453,600 3.605 125,825

    Summary of Information Required to Determine the Economic Life

    Replacement

    period

    UAE

    (OM)

    Rs.

    UAE (IO)

    Rs.

    UAE

    (DTS)

    Rs.

    UAE (SV)

    Rs.

    UAE (CC)

    Rs.

    UAE (TC)

    Rs.1 560,000 4,479,283 300,000 2,800,000 (-)1,379,283 -819,2832 626,024 2,366,864 264,630 943,195 1,159,039 1,785,0633 710,200 1,665,279 236,209 414,988 1,014,082 1,724,2824 840,230 1,317,089 213,325 209,417 894,347 1,734,5775 1,016,117 1,109,570 194,643 125,825 789,102 1,805,219

    The economic life of the well-drilling machine is 3 years

  • 7/31/2019 Projects Solutions Pfa

    59/89

    8. Adjusted cost of capital as per Modigliani Miller formula:r* = r(1 TL)r* = 0.16 (1 0.5 x 0.6)

    = 0.16 x 0.7 = 0.112Adjusted cost of capital as per Miles Ezzell formula:

    1 + rr* = rLrDT

    1 + rD1 + 0.16

    = 0.16 0.6 x 0.15 x 0.5 x1 + 0.15

    = 0.115

    9.a. Base case NPV = -12,000,000 + 3,000,000 x PVIFA (20%, b)

    = -12,000,000 + 3,000,000 x 3,326= - Rs.2,022,000

    b. Adjusted NPV = Base case NPV Issue cost + Present value of tax shield.

    Term loan = Rs.8 million Equity finance = Rs.4 millionIssue cost of equity = 12%Rs.4,000,000

    Equity to be issued = = Rs.4,545,4550.88

    Cost of equity issue = Rs.545,455

    Computation of Tax Shield Associated with Debt Finance

    Year (t) Debt outstanding

    at the beginning

    Rs.

    Interest

    Rs.

    Tax shield

    Rs.

    Present value of

    tax shield

    Rs.

    1 8,000,000 1,440,000 432,000 366,1022 8,000,000 1,440,000 432,000 310,2563 7,000,000 1,260,000 378,000 230,0624 6,000,000 1,080,000 324,000 167,1165 5,000,000 900,000 270,000 118,0196 4,000,000 720,000 216,000 80,013

    1,271,568

  • 7/31/2019 Projects Solutions Pfa

    60/89

    Adjusted NPV = - Rs.2,022,000 Rs.545,455 + Rs.1,271,568= - Rs.1,295,887

    Adjusted NPV if issue cost alone is considered = Rs.2,567,455Present Value of tax shield of debt finance = Rs.1,271,568

    10.a. Base Case NPV = - 8,000,000 + 2,000,000 x PVIFA (18%, 6)

    = - 8,000,000 + 2,000,000 x 3,498= - Rs.1,004,000

    b. Adjusted NPV = Base case NPV Issue cost + Present value of tax shield.Term loan = Rs.5 millionEquity finance = Rs.3 millionIssue cost of equity = 10%

    Rs.3,000,000Hence, Equity to be issued = = Rs.3,333,333

    0.90

    Cost of equity issue = Rs.333,333

    Computation of Tax Shield Associated with Debt Finance

    Year Debt outstanding at the

    beginning

    Interest Tax shield Present value of tax

    shield

    1 Rs.5,000,000 Rs.750,000 Rs.300,000 Rs.260,8692 5,000,000 750,000 300,000 226,843

    3 4,000,000 600,000 240,000 157,8044 3,00,000 450,000 180,000 102,9165 2,000,000 300,000 120,000 59,666 1,000,000 150,000 60,000 25,940

    843,033

    Adjusted NPV = - 1004000 333333 + 834033 = - Rs.503,300Adjusted NPV if issue cost of externalequity alone is adjusted for = - Rs.1,004000 Rs.333333

    = Rs.1337333

    c. Present value of tax shield of debt finance = Rs.834,033

    11. Adjusted cost of capital as per Modigliani Miller formula:r* = r(1 TL)r* = 0.19 x (1 0.5 x 0.5) = 0.1425 = 14.25%

  • 7/31/2019 Projects Solutions Pfa

    61/89

    Adjusted cost of capital as per Miles and Ezzell formula:1 + r

    r* = rLrDT

    1 + rD1 + 0.19

    = 0.19 0.5 x 0.16 x 0.5 x1 + 0.16

    = 0.149 = 14.9%

    12. S0 = Rs.46 , rh = 11 per cent , rf = 6 per centHence the forecasted spot rates are :

    Year Forecasted spot exchange rate

    1 Rs.46 (1.11 / 1.06)1 = Rs.48.172 Rs.46 (1.11 / 1.06)2 = Rs.50.443 Rs.46 (1.11 / 1.06)3 = Rs.52.824 Rs.46 (1.11 / 1.06)4 = Rs.55.315 Rs.46 (1.11 / 1.06)5 = Rs.57.92

    The expected rupee cash flows for the project

    Year Cash flow in dollars Expected exchange Cash flow in rupees

    (million) rate (million)

    0 -200 46 -92001 50 48.17 2408.52 70 50.44 3530.83 90 52.82 4753.84 105 55.31 5807.65 80 57.92 4633.6

    Given a rupee discount rate of 20 per cent, the NPV in rupees is :

    2408.5 3530.8 4753.8NPV = -9200 + + +

    (1.18)2 (1.18)3 (1.18)4

    5807.6 4633.6+ +

    (1.18)5 (1.18)6

    = Rs.3406.2 million

    The dollar NPV is :

  • 7/31/2019 Projects Solutions Pfa

    62/89

    3406.2 / 46 = 74.05 million dollars

    Chapter 14

    SOCIAL COST BENEFIT ANALYSIS

    1. Social Costs and Benefits

    Nature Economic

    value (Rs

    in million)

    Explanation

    Costs

    1. Construction cost One-shot 400

  • 7/31/2019 Projects Solutions Pfa

    63/89

    2. Maintenance cost Annual 3Benefits

    3. Savings in the operation

    cost of existing ships

    Annual 40

    4. Increase in consumersatisfaction

    Annual 3.6 The number of passenger hourssaved will be : (75,000 x 2 +50,000 + 50,000 x 2) = 600000.Multiplying this by Rs.6 givesRs.3.6 million

    The IRR of the stream of social costs and benefits is the value ofrin the

    equation

    50 40 + 3.6 3.0 50 40.6

    400 = = t=1 (1+r)t t=1 (1+r)t

    The solving value ris about 10.1%

    2. Social Costs and BenefitsCosts

    Decrease in customer satisfaction as reflected Rs.266,667in the opportunity cost of the extra time takenby bus journey

    800 x (2/3) x 250 x Rs.2

    Benefits

    1. Resale value of the diesel train (one time) Rs.240,0002. Avoidance of annual cash loss Rs.400,000Fare collection = 1000 x 250 x Rs.4

    = Rs.1,000,000Cash operating expenses = Rs.1,400,000

    3. The social costs and benefits of the project are estimated below:Rs. in million

    Costs & Benefits Time Economic

    value

    Explanation

    1. Construction cost 0 242. Land development cost 0 1503. Maintenance cost 1-40 14. Labour cost 0 40 This includes the cost of

    transport and rehabilitation

    5. Labour cost 1-40 12 The shadow price of labourequals what others are willingto pay.

  • 7/31/2019 Projects Solutions Pfa

    64/89

    6. Decrease in the value of the timberoutput

    2-40 4

    Benefits

    7. Savings in the cost of shipping theagriculture produce 1-40 0.5

    8. Income from cash crops 1-5 109. Income from the main crop 6-40 5010. Increase in the value of timber output 1 20

    Assuming that the life of the road is 40 years, the NPV of the stream of social costs and benefits ata discount rate of 10 percent is:

    40 1 + 12 40 4

    NPV = - 24 - 150 - 40 - - t=1 (1.1)t t=2 (1.1)t

    40 0.5 5 10 40 50 20

    + + + +t=1 (1.1)t t=1 (1.1)t t=6 (1.1)t (1.1)1

    = - Rs.9.93 million

    4.Table 1

    Social Costs Associated with the Initial Outlay

    Rs. in millionItem Financial

    cost

    Basis of

    conversion

    Tradeable value

    ab initio

    T L R

    Land 0.30 SCF = 1/1.5 0.20Buildings 12.0 T=0.50,L=0.25

    R=0.256.0 3.0 3.0

    Imported equipment 15.0 CIF value 9.0Indigeneous equipment 80.0 CIF value 60.0

  • 7/31/2019 Projects Solutions Pfa

    65/89

    Transport 2.0 T=0.65,L=0.25R=0.10

    1.3 0.5 0.2

    Engineering and know-how

    fees

    6.0 SCF=1.5 9.0

    Pre-operative expenses 6.0 SCF=1.0 6.0Bank charges 3.7 SCF=0.02 0.074Working capitalrequirement

    25.0 SCF=0.8 20.0

    150.0 104.274 7.3 3.5 3.2

    Table 2

    Conversion of Financial Costs into Social Costs

    Rs. in millionItem Financial

    cost

    Basis of

    conversion

    Tradeable value

    ab initio

    T L R

    Indigeneous raw materialand stores

    85 SCF=0.8 68

    Labour 7 SCF=0.5 3.5Salaries 5 SCF=0.8 4.0Repairs and maintenance 1.2 SCF=1/1.5 0.8Water, fuel, etc 6 T=0.5,L=0.25

    R=0.25

    3 1.5 1.5

    Electricity (Rate portion) 5 T=0.71,L=0.13R=0.16

    3.55 0.65 0.8

    Other overheads 10 SCF=1/1.5 6.667119.2 82.967 6.55 2.15 2.3

    As per table 1, the social cost of initial outlay is worked out as follows :

    Rs. in millionTradeable value ab initio 104.274Social cost of the tradeable component 4.867

    (7.3 / 1.5)Social cost of labour component 1.75(3.5 x 0.5)

    Social cost of residual component 1.60(3.2 x 0.5)

    Total 112.491

    As per Table 2, the annual social cost of operation is worked out as follows :

  • 7/31/2019 Projects Solutions Pfa

    66/89

    Tradeable value ab initio 82.967Social cost of the tradeable component 4.367

    ( 6.55 x 1/1.5 )

    Social cost of labour component 1.075(2.15 x 0.5)

    Social cost of residual component 1.150(2.3 x 0.5)

    Total 89.559

    The annual CIF value of the output is Rs.110 million. Hence the annual socialnet benefit will be : 110 89.559 = Rs.20.441 million

    Working capital recovery will be Rs.20 million at the end of the 20th

    year.

    Putting the above figures together the social flows associated with the projectwould be as follows :

    Year / s Social flow (Rs. in million)

    0 -112.4911-19 20.441

    Chapter 15

    MULTIPLE PROJECTS AND CONSTRAINTS

    1. The ranking of the projects on the dimensions of NPV, IRR, and BCR is given belowProject NPV (Rs.) Rank IRR (%) Rank BCR Rank

    M 60,610 3 34.1 2 2.21 1N 58,500 4 34.9 1 1.59 3O 40,050 5 18.6 4 1.33 5P 162,960 1 26.2 3 2.09 2Q 72,310 2 14.5 5 1.36 4

  • 7/31/2019 Projects Solutions Pfa

    67/89

    2. The ranking of the projects on the dimensions of NPV and BCR is given below

    Project NPV (Rs.) Rank BCR Rank

    A 61,780 5 1.83 2

    B 208,480 2 1.52 3C 315,075 1 2.05 1D 411,90 6 1.14 6E 95,540 4 1.38 4F 114,500 3 1.23 5

    3. The two hypothetical projects are:

    A BInitial outlay 10000 1000Cash inflows

    Year 1 5000 600Year 2 5000 600Year 3 5000 600

    NPV @ 10% Rank IRR Rank

    A 2435 1 about 23% 2B 492 2 above 35% 1

    4. The two hypothetical 4-year projects for which BCR and IRR criteria give differentrankings are given below

    Project A B

    Investment outlay 20000 20000Cash inflow

    Year 1 2000 8000Year 2 2000 8000Year 3 2000 8000Year 4 31500 8000

    Project NPV Rank IRR Rank

    A 4822 1 19% 2B 4296 2 about 22% 1

    5. The NPVs of the projects are as follows:NPV (A) = 6000 x PVIFA(10%,5) + 5000 x PVIF(10%,5) 20,000 = Rs.5851NPV (B) = 8000 x PVIFA(10%,8) 50,000 = - Rs.840NPV (C) = 15,000 x PVIFA(10%,8) 75,000 = Rs.5025NPV (D) = 15,000 x PVIFA(10%,12) 100,000 = Rs.6,995NPV (E) = 25,000 x PVIFA (10%,7) + 50,000 x PVIF(10%,7)

    150,000 = Rs.2,650

  • 7/31/2019 Projects Solutions Pfa

    68/89

    SinceB andEhave negative NPV, they are rejected. So we consider onlyA, C,and D. Further CandD are mutually exclusive. The feasible combinations, theiroutlays, and their NPVs are given below.

    Combination Outlay

    (Rs.)

    NPV

    (Rs.)

    A 20,000 5,851C 75,000 5,025D 100,000 6,995

    A & C 95,000 10,876A & D 120,000 12,846

    The preferred combination isA &D.

    6. The linear programming formulation of the capital budgeting problem under variousconstraints is as follows:

    Maximise 10X1 + 15X2 + 25X3 + 40X4 + 60X5 + 100X6Subject to

    15X1 + 12X2 + 8X3 + 35X4 + 100X5

    + 50X6 + SF1 = 150 Funds constraint for year 1

    5X1 + 13X2 + 40X3 + 25X4 + 10X5+ 110X6 200 + 1.08 SF1 Funds constraint for year 2

    5X1 + 6X2 + 5X3 + 10X4 + 12X5+ 40X6 60 Power constraint

    15X1 + 20X2 + 30X3 + 35X4 + 40X5+ 60X6 120 Managerial constraint

    0 Xj 1 (j = 1,.8) and SF1 0Rupees are expressed in 000s. Power units are also expressed in 000s.

    7. Given the nature of the problem, in addition to the decision variablesX1 throughX10for the original 10 projects, two more decision variables are required as follows:

    X11 is the decision variable to represent the delay of projects 8 by one yearX12 is the decision variable for the composite project which represents the

    combination of projects 4 and 5.The integer linear programming formulation is as follows:

    Maximise 55X1 + 75X2 + 50X3 + 60X4 + 105X5 + 12X6 + 60X7 + 120X8+ 50X9 + 40X10 + 100X11+ 178.2X12

  • 7/31/2019 Projects Solutions Pfa

    69/89

    Subject to 75X1 + 80X2 + 75X3 + 35X4 + 80X5 + 20X6 + 70X7 + 155 X8 +55X9 + 10X10 + 109.3X12 + SF1 = 400

    40X1 + 85X2 + 8X3 + 100X4 + 160X5 + 9X6 + 5X7 + 100 X8 + 20X9 + 90X10 + 155X11+ 247X12 +SF2 = 350 + SF1 (1 + r)

    X3 +X7 1X5 +X8 + X9 +X10 2X2 X6

    X8 X9 X4 +X5 + X12 1

    X8 +X11 1

    Xj = {0,1} j = 1, 2.12SFi 0 i = 1, 2

    It has been assumed that surplus funds can be shifted from one period to the nextand they will earn a post-tax return ofrpercent.

    +

    8. Minimise [P1(3d1+ 2 d2 + d3) +P2 (4 d4 + 2 d5 + d6) +P3 (d7 d7

    )]

    Subject to:Economic Constraints

    12X1 + 14X2 + 15X3 + 16X4 + 11X5 + 23X6 + 20X7 65

    Goal Constraints

    1.2X1 + 1.6X2 + 0.6X3 + 1.5X4 + 0.5X5 +

    + 0.9X6 + 1.8X7 + d1d1 = 6 Net income for year 1

    1.1X1 + 1.2X2 + 1.2X3 + 1.6X4 + 1.2X5 +

    + 2.5X6 + 2.0X7 + d2d2 = 8 Net income for year 2

    1.6X1 + 1.5X2 + 2.0X3 + 1.8X4 + 1.5X5 +

    + 4.0X6 + 2.2X7 + d3d3 = 10 Net income for year 3

    1.0X1 + 1.2X2 + 0.5X3 + 1.8X4 + 0.6X5 +

    + 1.0X6 + 2.0X7 + d4d4 = 6 Sales growth for year 1

    1.5X1 + 1.0X2 + 1.2X3 + 2.0X4 + 1.4X5

  • 7/31/2019 Projects Solutions Pfa

    70/89

    +

    + 3.0X6 + 3.0X7 + d5d5 = 8 Sales growth for year 2

    1.8X1 + 1.2X2 + 2.5X3 + 2.2X4 + 1.8X5 +

    + 3.5X6 + 3.5X7 + d6d6 = 10 Sales growth for year 3

    4X1 + 5X2 + 6X3 + 8X4 + 4X5 +

    + 9X6 + 7X7 + d7d7 = 50 NPV +

    Xj 0 di, di 0

    9. The BCRs of the projects are converted into NPVs as of now as follows

    Project Outlay (Rs.) BCR NPV (Rs.)

    1 800,000 1.08 64,0002 200,000 1.35 70,0003 400,000 1.20 80,000

    4 300,000 1.03 9,0005 200,000 0.98 - 4,0006 500,000 1.03 15,000/1.10 = 13,6367 400,000 1.21 84,000/1.10 = 76,3648 600,000 1.17 102,000/1.10 = 92,7279 300,000 1.01 3,000/1.10 = 2,727

    The integer linear programming formulation of the problem is as follows :

    Maximise 64,000X1 + 70,000X2 + 80,000X3 + 9,000X4 + 13,636X6+ 76,364X7 + 92,727X8 + 2,727X9

    Subject to800,000X1 + 200,000X2 + 400,000X3 + 300,000X4 + SF1 = 20,00,000500,000X6 + 400,000X7 + 600,000X8 + 300,000X9 500,000 + SF1 (1.032)

    Xj = {0,1} j = 1, 2, 3, 4, 6, 7, 8, 9

  • 7/31/2019 Projects Solutions Pfa

    71/89

    Chapter 16

    VALUATION OF REAL OPTIONS

    1. S= 100 , uS= 150, dS= 90u = 1.5 , d= 0.9, r= 1.15 R = 1.15E= 100

    Cu= Max (uSE, 0) = Max (150 100,0) = 50Cd= Max (dSE, 0) = Max (90 100,0) = 0

    CuCd 50

    = = = 0.833(u-d)S 0.6 x 100

    uCddCu 0 0.9 x 50

  • 7/31/2019 Projects Solutions Pfa

    72/89

    B = = = - 65.22(u-d)R 0.6 x 1.15

    C = S+B = 0.833 x 100 65.22 = 18.08

    2. S= 60 , dS= 45, d= 0.75, C= 5r= 0.16, R = 1.16, E= 60

    Cu= Max (uSE, 0) = Max (60u E, 0)Cd= Max (dSE, 0) = Max (45 60, 0) = 0

    CuCd 60u 60 u 1 = = =

    (u-d)S (u0.75)60 u 0.75

    uCddCu 0.75 (60u 60) 45 (1 u) B = = =

    (u-d)R (u 0.75) 1.16 1.16 (u 0.75)

    C = S+B

    (u 1) 60 45 (1 u)5 = +

    u 0.75 1.16 (u 0.75)Multiplying both the sides by u 0.75 we get

    455(u 0.75) = (u 1) 60 + (1 u)

    1.16

    Solving this equation foru we getu = 1.077

    So Betas equity can rise to60 x 1.077 = Rs.64.62

    3. EC0 = S0 N(d1) - N(d2)

    ert

    S0 = 70,E= 72, r= 0.12, = 0.3, t= 0.50

    S0 1

    ln + r+ 2 t E 2

  • 7/31/2019 Projects Solutions Pfa

    73/89

    d1=

    t 70

    ln + (0.12 + 0.5 x .09) x 0.50 72

    =0.30 0.50

    - 0.0282 + 0.0825= = 0.2560

    0.2121

    d2 = d1 - t = 0.2560 0.30 0.50 = 0.0439

    N(d1) = 0.6010N(d2) = 0.5175

    E 72= = 67.81

    ert e0.12x 0.50

    C0 = S0 x 0.6010 67.81 x 0.5175= 70 x 0.6010 67.81 x 0.5175 = Rs.6.98

    4. EC0 = S0 N(d1) - N(d2)

    ert

    E= 50, t= 0.25, S= 40, = 0.40, r= 0.14

    S0 1

    ln + r+ 2 t E 2

    d1=

    t

    40

    ln + (0.14 + 0.5 x 0.16) 0.25 50d1=

    0.40 0.25

    - 0.2231 + 0.055= = - 0.8405

    0.20

  • 7/31/2019 Projects Solutions Pfa

    74/89

    d2 = d1 - t = - 0.8405 0.40 0.25 = -1.0405

    N(d1) = 0.2003N(d2) = 0.1491

    E 50= = 48.28

    ert e0.14 x 0.25

    C0 = S0 x 0.2003 48.28 x 0.1491= 40 x 0.2003 48.28 x 0.1491 = 0.8135

    5. The NPV of the proposal to make Comp-I is:20 50 50 20 + 10

    -100 + + + +1.20 (1.20)2 (1.20)3 (1.20)4

    = -100 + 16.66 + 34.70 + 28.95 + 14.46= - Rs.5.23 million

    The present value of the cash inflows of Comp II proposal, four years from nowwill be Rs.189.54 million (Two times the present value of the cash inflows of Comp-I).

    So, we haveS0 = present value of the asset = 189.54 x e

    0.20 x 4 = Rs.85.17 millionE = exercise price = $ 200 million

    = 0.30t = 4 years

    r = 12

    Step 1 : Calculate d1 and d2

    S0 2

    ln + r+ t E1 2 -0.854 + (0.12 + (.09/2)) 4 -0.194

    d1 = = = = -0.323

    t 0.3 4 0.6

    d2 = d1 - t = -0.323 0.60 = -0.923Step 2 : FindN(d1) andN(d2)

    N(d1) = 0.3733N(d2) = 0.1780

    Step 3 : Estimate the present value of the exercise price

  • 7/31/2019 Projects Solutions Pfa

    75/89

    E. e-rt = 200 / 1.6161 = Rs.123.76 million

    Step 4 : Plug the numbers obtained in the previous steps in the Black-Scholes formula:

    C0 = 85.17 x 0.3733 123.76 x 0.1780= Rs.9.76

    6. Presently a 9 unit building yields a profit of Rs.1.8 million (9 x 1.2 9) and a 15 unitbuilding yields a profit of Rs.1.0 million (15 x 1.2 17). Hence a 9 unit building isthe best alternative if the builder has to construct now.

    However, if the builder waits for a year, his payoffs will be as follows:

    Market Condition

    Alternative Buoyant (Apartment price:Rs.1.5 million)

    Sluggish (Apartment price:Rs.1.1million)

    9 unit building 1.5 x 9 9 = 4.5 1.1 x 9 9 = 0.9

    15 unit building 1.5 x 15 17 = 5.5 1.1 x 15 17 = -0.5

    Thus, if the market turns out to be buoyant the best alternative is the 15 unitbuild