PROJECTS 2012

Contents:1. Access Projects2. Spec-In Projects3. Award Projects

4. Follow Ups5. Lost Jobs

Item Project Client Sales Person In-charge

Proposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

1 Haandi Restaurant WestlandsNairobi, Kenya

Haandi Restaurant

Multi V System + Mech. Vent.

3,917,150.00Kshs

May-31-2012 A AC layouts revisions

2 Restaurant & Commercial Devt. Jubilee Arcade-Nairobi,Kenya

Pierluciano Senzani

Mutli V System

6,220,827.70Kshs

June-05-2012 N/A N/A

3 Kilua Resort Mombasa Kiluwa Limited

Multi V System

Pending Pending N/A N/A

4 Sierra Hotel Migori Mr. Sylvan Onyango

Multi V System + Mech. Vent

11,911,250.00Kshs

June-28-2012 N/A N/A

5 The Ark Aberdares Country Club

Multi V System + Mech. Vent

Pending July-03-2012 N/A N/A

6 Kinangop Cottage Aberdares Country Club

Multi V System + Mech. Vent

Pending July-03-2012 N/A N/A

7 AGOL Distribution Terminal

AGOL Distribution Terminal

Split System 5,245,346.00Kshs

June-26-2012 N/A N/A

8 G.D.C. Nakuru G.D.C. Multi V System

4,500,000.00Kshs

Pending N/A N/A

9 G.D.C. Riverside Nairobi

G.D.C. Mutli V System

Pending N/A N/A

10 Co-op Bank Ngonr’ Rd. Br.

Co-operative Bank Of Kenya

Split System 1,464,000.00Kshs

Pending N/A N/A

Access Projects

Access ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

11 K.P.L.C. K.P.L.C. CAC Split System

13,530,000.00Kshs

Pending N/A N/A

12 C.B.K. Nairobi. Central Bank Of Kenya

Multi V System + Mech. Vent

54,000,000.00Kshs

Pending N/A N/A

13 Serena Basement Vent.

Serena Group Of Hotels

Mech. Vent Pending July-03-2012 N/A N/A

14 Delta Corner Regus Offices

AMS Propeties

Multi V System

14,299,064.00Kshs

July-06-2012 N/A N/A

15 Ford Foundation O.S.I.T. Office for Eastern Africa

Split System/Multi V System

9,315,000.00Kshs

July-03-2012 N/A N/A

16 Co-op Bank Githunguri Br.

Co-operative Bank Of Kenya

Split System/Mech Vent.

1,728,140.00Kshs

July-09-2012 N/A N/A

17 Co-op Bank Corporate Centre

Co-operative Bank Of Kenya

Multi V System

4,436,500.00Kshs

Pending N/A N/A

18 HFB HFB Mech Vent Pending July-19-2012 N/A N/A

19 Laico Regency Ballrooms

Laico Regency Hotel

Multi V System

1,707,000.00Kshs

July-09-2012 N/A N/A

20 DTB Courtyard Gen. Mathenge, Nairobi.

Diamond Trust Bank

Multi V System

8,175,000.00Kshs

Pending N/A N/A

21 Co-op Bank Lamu Br. Co-operative Bank Of Kenya

Multi V, Split System + Mech Vent.

6,497,261.00Kshs

Pending N/A N/A

Access ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

22 Co-op Bank Juja Br. Co-operative Bank Of Kenya

Split System + Mech Vent.

4,504,046.00Kshs

Pending N/A N/A

23 Platinum Package Ltd. Ramco Group Ltd.

Multi Power System

1,549,102.00Kshs

Pending N/A N/A

24 Proposed Dev. Of Ph.2 at Nairobi Business Pack

Nairobi Business Park Ltd.

Mechanical Ventilation

43,325,971.07Kshs

Pending N/A N/A

25 Proposed Office Fit Out for Acorn Management Ltd.

Acorn Management Ltd.

Multi V Sys + Mech Vent.

Pending July-27-2012 N/A N/A

26 Proposed Extension for J.K.I.A. Existing Departure Terminal

J.K.I.A. Multi V Sys + Mech Vent.

Pending Pending N/A N/A

27 The Voyager Hotel Heritage Hotels

Multi V Sys + Mech Vent.

Pending Pending N/A N/A

28 Amani Tiwi Beach Resort

Amani Tiwi Beach Resort

Multi V Sys + Mech Vent.

Pending Aug-08-2012 N/A N/A

29 Mombasa Beach Hotel Mombasa Beach Hotel

Multi V Sys + Mech Vent.

Pending Pending N/A N/A

30 The Stima Hotel, Nairobi

The Stima Hotel, Nairobi

Multi V Sys + Mech Vent.

Pending Pending N/A N/A

31 Le -Mac Le -Mac Multi V Sys + Mech Vent.

Pending Pending N/A N/A

32 Proposed Office Fit Out for Alpha Management Ltd.

Alpha Management Ltd.

Split Sys Pending July-17-2012 N/A N/A

Item Project Client Sales Person In-charge

Proposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

33 Gulf Power Ltd. Athi River II Power Plant.

Gulf Power Ltd.

Packaged Units

20,000,000.00Kshs

July-16-2012 N/A N/A

34 Construction & Office Fit Out Services for World Bank In Nairobi, Kenya

The World Bank Group

Multi V & Split Sys. + Mech. Vent.

352,149,413.60Kshs

Pending N/A N/A

35 Riverside Park Residents

Plumbing Systems Ltd

Mech. Vent. 197,750.00 Kshs

Pending N/A N/A

36 K.C.B. Juba Br. Kenya Commercial Bank

Multi V & Split Sys.

Pending Pending N/A N/A

37 Co-op Bank Marsabit Br.

Co-operative Bank Of Kenya

Split System + Mech Vent.

7,417,271.00Kshs

Pending N/A N/A

38 Proposed Montana Hotel andMall on LR No. 209/1413/38-39,Gaborone Lane, Nairobi.

Comat Trading Company Ltd.

Multi V & Split Sys. + Mech. Vent.

Pending Pending N/A N/A

39 First Community Bank First Community Bank of Kenya

Multi V & Split Sys. + Mech. Vent.

Pending Pending N/A N/A

40 Enashipai Sportsbar Enashipai Ltd. Multi V & Split Sys. + Mech. Vent.

Pending Aug-08-2012 N/A N/A

41 Tuskys Bamburi Br. Tuskys Supermarket

Multi V & Split Sys. + Mech. Vent.

Pending Pending N/A N/A

Access Projects

Item Project Client Sales Person In-charge

Proposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

42 Proposed Corporate Office Park at Westend Towers.

Corporate Office Park

Multi V/Split System

3,500,000.00 July-30-2012 N/A N/A

43 Text Book Centre Lang’ata

Text Book Centre

Multi V System

Pending Aug-08-2012 N/A N/A

44 Proposed Refurbishments at Hilton Hotel Nairobi.

Hilton Hotels Multi V/Split/Mech. Vent. Systems

Pending Pending N/A N/A

45 Maanzoni Lodge Athi River

Maanzoni Lodge

Multi V System

Pending Pending N/A N/A

46 Proposed Office Development for Newport Africa Ltd, Karen, Nairobi.

Newport Africa Ltd.

Multi V/Split System

1,205,800.00Kshs

July -30-2012 N/A N/A

47 Proposed Housing Development on Pepo Lane & Miotoni Rd.

Slydon & Partners (Client Reps.)

Multi V System

15,156,168.00Kshs

Aug-02-2012 N/A N/A

48 Proposed Office Development at Konza City Nairobi.

Konza City Development

Split System Pending Aug-01-2012 N/A N/A

49 Offices Fit - Out at NineWest Towers, Westlands

ADDAX ORYX (K)

Multi V System

Pending Pending N/A N/A

50 Proposed Pinecourt Hotel

Pinecourt Hotel

Multi V System

Pending Pending N/A N/A

Access Projects

Item Project Client Sales Person In-charge

Proposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

51 Proposed Office Fit Out for I-HUB Centre

I-HUB Centre Ltd.

Multi V Sys./Mech. Vent.

1,200,000.00Kshs

Pending N/A N/A

52 Multi Choice Mu lti Choice Kenya

Multi V Sys. 1,637,222.00Kshs

Pending N/A N/A

53 BID Apartments BID Apartments

Mech. Vent 6,702,830.00Kshs

Pending N/A N/A

54 Chase Bank Strathmore Br.

Chase Bank of Kenya

Multi V System

Pending N/A N/A

55 Proposed Golf Club Multi V Sys./Mech Vent.

10,883,361.00Kshs.

Pending N/A N/A

56 Proposed Office Block for Kestral Management Ltd. Msa.

Kestral Management Ltd. Msa.

Multi V Sys./Split Sys./Mech Vent.

Pending Aug-16-2012 N/A N/A

57 Proposed Drama Studios for SSMS Africa Ltd.

SSMS Africa Ltd.

MPS Sys./Split Sys.

1,243,500.00Kshs

Aug-15-2012 N/A N/A

58 Proposed Airport in Juba South Sudan

Multi V Sys./Split Sys./Mech Vent.

Pending Pending N/A N/A

Access Projects

Spec-In & Design ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

1 Haandi Restaurant WestlandsNairobi, Kenya

Haandi Restaurant

Multi V System + Mech. Vent.

3,917,150.00Kshs

July-13-2012 A AC layouts revisions

2 Kilua Resort Mombasa Kiluwa Limited

Multi V System

Pending Pending N/A N/A

3 Serena Basement Vent.

Serena Group Of Hotels

Mech. Vent Pending July-03-2012 N/A N/A

4 HFB HFB Mech Vent Pending July-19-2012 N/A N/A

5 Laico Regency Ballrooms

Laico Regency Hotel

Multi V System

1,707,000.00Kshs

July-09-2012 N/A N/A

6 Proposed Dev. Of Ph.2 at Nairobi Business Pack

Nairobi Business Park Ltd.

Mechanical Ventilation

43,000,000.00Kshs

Pending N/A N/A

7 Proposed Extension for J.K.I.A. Existing Departure Terminal

J.K.I.A. Multi V Sys + Mech Vent.

Pending Pending N/A N/A

8 Construction & Office Fit Out Services for World Bank In Nairobi, Kenya

The World Bank Group

Multi V & Split Sys. + Mech. Vent.

352,149,413.60Kshs

Pending N/A N/A

9 Proposed Montana Hotel andMall on LR No. 209/1413/38-39,Gaborone Lane, Nairobi.

Comat Trading Company Ltd.

Multi V & Split Sys. + Mech. Vent.

Pending Pending N/A N/A

10 Enashipai Sportsbar Enashipai Ltd. Multi V & Split Sys. + Mech. Vent.

Pending Aug-08-2012 N/A N/A

Spec-In & Design ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

12 Amani Tiwi Beach Resort

Amani Tiwi Beach Resort

Multi V Sys + Mech Vent.

Pending Aug-08-2012 N/A N/A

13 Gulf Power Ltd. Athi River II Power Plant.

Gulf Power Ltd.

Packaged Units

20,000,000.00Kshs

July-16-2012 N/A N/A

14 Riverside Park Residents

Plumbing Systems Ltd

Mech. Vent. 197,750.00 Kshs

Pending N/A N/A

15 K.C.B. Juba Br. Kenya Commercial Bank

Multi V & Split Sys.

21,000,000.00Kshs

Pending N/A N/A

16 Co-op Bank Marsabit Br.

Co-operative Bank Of Kenya

Split System + Mech Vent.

7,417,271.00Kshs

Pending N/A N/A

17 Tuskys Bamburi Br. Tuskys Supermarket

Multi V & Split Sys. + Mech. Vent.

Pending Pending N/A N/A

18 Proposed Corporate Office Park at Westend Towers.

Corporate Office Park

Multi V/Split System

Pending July-30-2012 N/A N/A

19 Text Book Centre Lang’ata

Text Book Centre

Multi V System

Pending Aug-08-2012 N/A N/A

20 Proposed Office Development for Newport Africa Ltd, Karen, Nairobi.

Newport Africa Ltd.

Multi V/Split System

1,205,800.00Kshs

July-30-2012 N/A N/A

21 Proposed Office Fit Out for Acorn Management Ltd.

Acorn Management Ltd.

Multi V Sys + Mech Vent.

Pending July-27-2012 N/A N/A

Spec-In & Design ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

22 Proposed Office Fit Out for Alpha Management Ltd.

Alpha Management Ltd.

Split Sys Pending July-17-2012 N/A N/A

23 Proposed Housing Development on Pepo Lane & Miotoni Rd.

Slydon & Partners (Client Reps.)

Multi V System

15,156,168.00Kshs

Aug-02-2012 N/A N/A

24 Proposed Office Development at Konza City Nairobi.

Konza City Development

Split System Pending Aug-01-2012 N/A N/A

25 Proposed Refurbishments at Hilton Hotel Nairobi.

Hilton Hotel Multi V/Split/Mech. Vent. Systems

Pending Pending N/A N/A

26 Offices Fit - Out at NineWest Towers, Westlands

ADDAX ORYX (K)

Multi V System

Pending Pending N/A N/A

27 Proposed Pinecourt Hotel

Pinecourt Hotel

Multi V System

Pending Pending N/A N/A

28 Proposed Office Fit Out for I-HUB Centre

I-HUB Centre Ltd.

Multi V Sys./Mech. Vent.

Pending Pending N/A N/A

29 Multi Choice Mu lti Choice Kenya

Multi V Sys. 1,637,222.00Kshs

Pending N/A N/A

30 BID Apartments BID Apartments

Mech. Vent 6,702,830.00Kshs

Pending N/A N/A

31 Chase Bank Strathmore Br.

Chase Bank of Kenya

Multi V System

Pending N/A N/A

Spec-In & Design ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

32 Proposed Golf Club Multi V Sys./Mech Vent.

10,883,361.00Kshs.

Pending N/A N/A

33 Proposed Office Block for Kestral Management Ltd. Msa.

Kestral Management Ltd. Msa.

Multi V Sys./Split Sys./Mech Vent.

Pending Aug-16-2012 N/A N/A

34 Proposed Drama Studios for SSMS Africa Ltd.

SSMS Africa Ltd.

MPS Sys./Split Sys.

1,243,500.00Kshs

Aug-15-2012 N/A N/A

35 Proposed Airport in Juba South Sudan

Multi V Sys./Split Sys./Mech Vent.

Pending Pending N/A N/A

Award ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

1 The Oval Offices Property House Ltd

Multi V System + Mech. Vent

Pending Pending Basement vent. Revisions

N/A

2 Proposed Office Fit-Out at Lynwood House

U.N.H.C.R. Mutli V System + Mech. Vent

40,973,617.00Kshs

June-18-2012 AC layouts revisions

N/A

3 Co-operative Bank Of Kenya - Malaba Br.

Co-operative Bank Of Kenya

Multi V System + Mech. Vent

5,862,553.00Kshs

June-06-2012 N/A N/A

4 Co-operative Bank Of Kenya - Embakasi Br.

Co-operative Bank Of Kenya

Multi V System

1,387,000.00 Kshs

June-26-2012 AC layouts revisions

N/A

5 Guardian Bank Of Kenya - Ngong' Rd. Branch

Guardian Bank Of Kenya

Multi V System

2,863,290.00Kshs

June-27-2012 AC layouts revisions

N/A

6 MP Shah Hospital, Maternity Ward

MP Shah Hospital

Split System 1,172,000.00Kshs

June-25-2012 AC layouts revisions

N/A

7 JKIA Data Centre ARINC RH10 9AY

Split System Pending June-14-2012 AC layouts revisions

N/A

8 Co-op Bank Githunguri Br.

Co-operative Bank Of Kenya

Split System/Mech Vent.

1,728,140.00Kshs

July-09-2012 N/A N/A

9 Ford Foundation O.S.I.T. Office for Eastern Africa

Split System/Multi V System

9,315,000.00Kshs

July-03-2012 N/A N/A

10 Delta Corner Regus Offices

AMS Propeties

Multi V System

14,299,064.00Kshs

July-06-2012 Fresh air system included

N/A

Award ProjectsItem Project Client Sales Person

In-chargeProposed System

Contract Sum Design Completion/Handover Date

Revision History

Misc

Project Information Required/Pending Action

Ramgarhia Sikh Temple Pangani, Nairobi Installation ongoing & to be complete by Aug 15 2012

Haandi Restaurant WestlandsNairobi, Kenya

Revised proposal & quotation pending.

Restaurant & Commercial Devt. Jubilee Arcade-Nairobi,Kenya

Ritu to discuss with Rahul and revert. Still Pending. Waiting or client communicaion

Kilua Resort Mombasa Design proposals & approvals.Quotation/Bills of Quantities.

JKIA Data Centre Installation, testing & commissioning completed. Handover pending.

Sierra Hotel Migori Design proposals completed.Quotation/Bills of Quantities submitted. Follow up pending.

The Ark Design proposals completed.Quotation/Bills of Quantities pending, client to revert back after going through the proposals.

Kinangop Cottage As Above

Guardian Bank Of Kenya - Ngong’ Rd. Br. Installation ongoing. Approved working drawings + revisions pending

Co-operative Bank Of Kenya - Embakasi Br.

Installation ongoing. Approved working drawings + revisions pending

Co-operative Bank Of Kenya - Malaba Br. Installation ongoing. Approved working drawings + revisions pending

Proposed Office Fit-Out at Lynwood House

Installation ongoing.

The Oval Offices Design proposals completed. Follow up pending.

MP Shah Hosp. Maternity Ward Installation ongoing. Approved working drawings + revisions pending

AGOL Distribution Terminal Waiting on client feedback. Dennis to follow up.

Follow Ups

Project Information Required/Pending Action

Bruce Scott Site Installation, testing & commissioning completed. Handover pending.

Co-op Bank Ngong’ Rd. Br. Tender Document submitted. Awaiting results end month

K.P.L.C. Tender Document submitted, awaiting results

Serena Basement Vent. Design submitted.Quotation/Bills of Quantities pending. Awaiting Varsani’s input.

Delta Corner Regus Offices Design proposals completed.Quotation/Bills of Quantities submitted. Verbal confirmation on award status.

Ford Foundation Awarded & awaiting mobilization.

Co-op Bank Githunguri Br. Design submitted.Quotation/Bills of Quantities submitted

Co-op Bank Corporate Centre Tender Document submitted. Awaiting results end month

HFB Design proposals completed.Quotation/Bills of Quantities & follow up pending.

Laico Regency Ballrooms Design proposals completed.Quotation/Bills of Quantities submitted. Follow up pending.

DTB Courtyard Gen. Mathenge, Nairobi. Tender submitted awaiting results

Uniserv Education Offices Installation, testing & commissioning completed. Handover pending.

Platinum Packaging Ltd Follow up

Proposed Dev. Of Ph.2 at Nairobi Business Park

Tender submitted awaiting results.

Follow Ups

Project Information Required/Pending Action

Proposed Office Fit Out for Acorn Management Ltd.

Design proposals completed.Quotation/Bills of Quantities submitted. Follow up pending.

Proposed Extension for J.K.I.A. Existing Departure Terminal

Design proposals & approvals.Quotation/Bills of Quantities.

The Voyager Hotel Design proposals & approvals.Quotation/Bills of Quantities.

Amani Tiwi Beach Resort Design proposals completed.Quotation/Bills of Quantities.

Mombasa Beach Hotel Design proposals & approvals.Quotation/Bills of Quantities.

The Stima Hotel, Nairobi Design proposals & approvals.Quotation/Bills of Quantities.

Le Mac Design proposals & approvals.Quotation/Bills of Quantities.

Alpha Management Offices Design proposals completed.Quotation/Bills of Quantities submitted. Follow up pending.

Gulf Power Ltd. Athi River II Power Plant Design proposals completed.Quotation/Bills of Quantities submitted. Follow up pending.

Construction & Office Fit Out Services for World Bank In Nairobi, Kenya

Design proposals & approvals.Quotation/Bills of Quantities.

Co-op Bank Marsabit Br. Design proposals & approvals.Quotation/Bills of Quantities submitted. Follow up pending.

Riverside Park Residence Design proposals & approvals.Quotation/Bills of Quantities submitted. Follow up pending.

First Community Bank Design proposals & approvals.Quotation/Bills of Quantities.

K.C.B. Juba Br. Design proposals & approvals.Quotation/Bills of Quantities.

Enashipai Sportsbar Design proposals completed.Quotation/Bills of Quantities.

Follow Ups

Project Information Required/Pending Action

Proposed Montana Hotel andMall on LR No. 209/1413/38-39,Gaborone Lane, Nairobi.

Design proposals & approvals.Quotation/Bills of Quantities.

Tuskys Bamburi Design proposals & approvals.Quotation/Bills of Quantities.

Proposed Corporate Office Park at Westend Towers.

Design proposals completedQuotation/Bills of Quantities submitted. Follow up pending.

Text Book Centre Lang’ata Design proposals completedQuotation/Bills of Quantities submitted. Follow up pending.

Proposed Office Development for Newport Africa Ltd, Karen, Nairobi.

Design proposals completedQuotation/Bills of Quantities submitted. Follow up pending.

Proposed Refurbishments at Hilton Hotel Nairobi.

Design proposals & approvals.Quotation/Bills of Quantities.

Maanzoni Lodge Athi River Design proposals & approvals.Quotation/Bills of Quantities.

Proposed Office Development at Konza City Nairobi.

Design proposals completedQuotation/Bills of Quantities. Follow up pending.

Offices Fit - Out at NineWest Towers, Westlands

Design proposals & approvals.Quotation/Bills of Quantities submitted. Follow up pending.

Proposed Pinecourt Hotel Design proposals & approvals.Quotation/Bills of Quantities.

Proposed Office Fit Out for I-HUB Centre Design proposals & approvalsQuotation/Bills of Quantities submitted. Follow up pending.

Multi Choice Design proposals & approvalsQuotation/Bills of Quantities submitted. Follow up pending.

BID Apartments Design proposals & approvalsQuotation/Bills of Quantities submitted. Follow up pending.

Chase Bank Strathmore Br. Design proposals & approvals.Quotation/Bills of Quantities.

Follow Ups

Project Information Required/Pending Action

Proposed Airport in Juba South Sudan Design proposals & approvals.Quotation/Bills of Quantities.

Proposed Golf Club Design proposals & approvals.Quotation/Bills of Quantities submitted.

Proposed Office Block for Kestral Management Ltd. Msa.

Design proposals & completed.Quotation/Bills of Quantities.

Proposed Drama Studios for SSMS Africa Ltd.

Design proposals completed.Quotation/Bills of Quantities submitted.

Follow Ups

Project Reason Solution/Suggestion

G.D.C. Nakuru

G.D.C. Riverside Nairobi

CFC Conference Room

C.B.K. Nairobi

Lost Projects