PROJECTED RLC PROJECTS TIMELINES PROJECT STATUS COMPLETION GENSAN ( 5 MODELS ) SUBMITTED FOR RLC COMPLETED REVIEW AND CHECKING NIZANTA ( 5 MODELS ) APPROVAL OF SCHEMES 1 WEEK WORKING DRAWINGS 2 WKS UPON APPROVAL BLOOMFIELDS ( 5 MODELS ) WORKING DRAWINGS 2 WEEKS ( ON – GOING 30% ) BRIGHTON ( 5 MODELS ) WORKING DRAWINGS 2 WEEKS ( RECENTLY REVISED 20%) SPRINGDALE ( 5 MODELS ) WORKING DRAWINGS 3 WEEKS (5% ON GOING ) DISNEY MODELS ( 10 MODELS ) APPROVAL OF PLANS & SCHEMES 2 WEEKS

Projected Rlc Projects Timelines

Embed Size (px)

DESCRIPTION

Blank

Citation preview

Page 1: Projected Rlc Projects Timelines

PROJECTED RLC PROJECTS TIMELINES

PROJECT STATUS COMPLETION

GENSAN ( 5 MODELS ) SUBMITTED FOR RLC COMPLETED

REVIEW AND CHECKING

NIZANTA ( 5 MODELS ) APPROVAL OF SCHEMES 1 WEEK

WORKING DRAWINGS 2 WKS UPON APPROVAL

BLOOMFIELDS ( 5 MODELS ) WORKING DRAWINGS 2 WEEKS

( ON – GOING 30% )

BRIGHTON ( 5 MODELS ) WORKING DRAWINGS 2 WEEKS

( RECENTLY REVISED 20%)

SPRINGDALE ( 5 MODELS ) WORKING DRAWINGS 3 WEEKS

(5% ON GOING )

DISNEY MODELS ( 10 MODELS ) APPROVAL OF PLANS

& SCHEMES 2 WEEKS

WORKING DRAWINGS 4 WEEKS