*Sources: DMS Projects EP: Engineering & Procurement *Sources: DMS Projects EP: Engineering & Procurement PROJECT WATCH – SAUDI ARABIA * Project Facility Budget Status Saudi Aramco - Marjan - Oil Field Expansion (Overview) GOSP 15,000,000,000 Construction Aramco - Berri - Two Drilling Islands Project Dredging/ Reclamation 150,000,000 Engineering & Procurement Satorp - Jubail - Debottlenecking Train 2 Refinery 200,000,000 Engineering & Procurement Saudi Aramco - Hawiyah Gas Plant Expansion Gas Processing 1,200,000,000 Construction Saudi Aramco - Uthmaniya Gas Treatment Plant Gas Treatment Plant 800,000,000 Construction Maaden - Gold Mines Development Program Gold 600,000,000 Engineering & Procurement Saudi Aramco - Zuluf Oilfield Expansion Oil Field Development 1,700,000,000 Engineering & Procurement Saudi Aramco - Abqaiq Main Oil Refinery Liquefied Petroleum Drain Petroleum Oil Refinery 75,000,000 On Hold Saudi Aramco - Jizan Export Refinery (Overview) Petroleum Oil Refinery 2,100,000,000 Construction Saudi Aramco - Jizan Export Refinery - Marine Terminal Facilities Marine Terminal 650,000,000 Commissioning Saudi Aramco - Jizan Export Refinery - Naphtha Processing and Aromatics Hydrotreating 1,040,000,000 Construction Saudi Aramco - Jizan Export Refinery - Utilities Package Offsites & Utilities 510,000,000 Commissioning Sasref - Jubail - Refinery Modernization and Expansion Petroleum Oil Refinery 360,000,000 Construction Saudi Aramco - Fadhili Gas Plant - Downstream Packages Gas Processing 650,000,000 Commissioning Saudi Aramco - Yanbu - Storage Tanks and Associated Equipment Gas Storage Tanks 400,000,000 Construction Saudi Aramco - Fadhili Gas Plant - Sulphur Recovery Unit SRU (Package 2) Gas Treatment Plant 2,500,000,000 Commissioning Midchem - Riyadh - Chlor Alkali Plant and Calcium Chloride Plant Chlor Alkali 60,000,000 Engineering & Procurement Saudi Aramco - Berri - Water Injection System Expansion Water Injection 200,000,000 Engineering & Procurement Saudi Aramco - Qatif - GOSP Pipeline Pumping Expansion Pipeline 100,000,000 Construction Advanced Petrochemical Company - Jubail - Pyoil & Pygas Plant Industrial Production 580,000,000 Shelved Aramco - Ras Tanura Pipeline Oil 270,000,000 Construction Saudi Aramco - Fadhili Gas Plant - Industrial Support Facilities (FISF) Gas Treatment Plant 100,000,000 Commissioning Saudi Aramco - North Jeddah Bulk Plant Bulk Storage Plant 270,000,000 Construction Saudi Aramco - Haradh Gas Increment Program (Overview) Gas Compression 1,200,000,000 Construction Saudi Aramco - Haradh Gas Increment Program - South Haradh Field Flowlines 1,200,000,000 Construction Saudi Aramco - Haradh Gas Increment Program - Satellite Gas Compression Gas Compression 1,200,000,000 Construction Natpet - Yanbu - Polypropylyene Plant Redevelopment Polypropylene 72,000,000 Engineering & Procurement Saudi Aramco - Berri - Sour Water Stripper and Disposal System Waste Water Treatment 100,000,000 Engineering & Procurement Umm Al-Qura Development & Construction Company - King Abdul Aziz Road Roads 1,600,000,000 Construction Saudi Aramco - Fadhili Gas Plant (Overview) Gas Treatment Plant 6,600,000,000 Construction GACA - Jeddah - King Abdul Aziz International Airport (KAIA) Expansion Airport 6,000,000,000 Commissioning DCOMM - Makkah Mass Rail Transit (MMRT) Railway 16,500,000,000 Construction Ministry of Transport - Jeddah Public Transport Program (JPTP) Railway 5,600,000,000 EPC

PROJECT WATCH – SAUDI ARABIA * Saudi Aramco - Marjan - Oil

  • Upload
    others

  • View
    12

  • Download
    2

Embed Size (px)

Citation preview

Page 1: PROJECT WATCH – SAUDI ARABIA * Saudi Aramco - Marjan - Oil

39Business

*Sources: DMS ProjectsEP: Engineering & Procurement

MAY 2019

INDUSTRY NEWS

*Sources: DMS ProjectsEP: Engineering & Procurement

Fertilizer

IndustrialInfrastructure

MiningConstruction

Gas

Refining

Oil

Pipeline

Petrochemicals

Renewables

Power

Offshore

Water

SECTORS COVERED

SUBSCRIBE TODAY

• Tel: +973 1740 5590 • [email protected]• www.dmsprojects.net

Contact us for further information A Division of

REGIONS COVERED

• China• Europe

• India• Asia Pacific

• Latin America• Middle East

• East Africa• North Africa• West Africa

• Central America• North America

• Russia & CIS

resized advert OGN.pdf 1 8/31/2016 10:36:54 AM

*

PROJECT WATCH – SAUDI ARABIA *

Saudi Aramco - Hawiyah Gas Plant Expansion

The Hawiyah plant

Name of Client : Saudi Aramco - Saudi Arabian Oil Company :Budget : $1.2 billionFacility Type : Gas ProcessingSector : GasStatus : ConstructionLocation : HawiyahFeed : WorleyParsonsMain Contractor : Saipem

BackgroundRaising gas production is key to Saudi Arabia’s plan to diversify its energy mix by cutting its use of crude oil and liquids for power generation. Hawiyah gas plant currently processes 2.5 billion scfd of gas. The HGP expansion project is meant to process an additional 1,260 mmscfd of raw sweet gas from the South Gha-war Region.

Project StatusMay 2019 Cleveland Bridge Steel confirms fabrica-tion, galvanization and delivery works of the project is progressing according to schedule.

Project ScopeThe project scope involves the expansion of Hawiyah processing capacity by 1.3 billion standard cubic feet per day (scfd). The current gas processing capacity is 2.5 billion scfd. Haradh and Hawiyah are part of Aramco’s Southern Area Energy Efficiency Program, and the pro-gram includes the development of 9 gas compression plants & associated infrastructure to improve the reser-voir recovery rate and extend the production plateau of both gas fields by reducing the wellhead pressure.

Once completed, the contractors will have installed a 2,900 km of pipelines, which include construction & modification of multiple associated facilities.

Project FinanceSaudi Aramco is the Project Client.

Project Schedule Feasibility Study Q1-2014Feed Q3-2015EPC ITB Q1-2017Engineering & Procurement Q4-2017Construction Q1-2018Completion Q2-2021

MARSOL International has introduced an innovative solution for a more effective and efficient hose assembly system that generates con-siderable savings on changeout time and cost. The new system allows overall faster management time and ensures long-term, cost-effective functionality of the terminal facility and assets, reducing risks while optimising the client’s assets and resources.

“Our new hose launch system is an overall upgrade to ensure reli-ability and maintenance of the marine hoses,” Mike Young, director of Marsol International explained. “It is aimed at reducing degradation problems that arise over time. We are now in a position to grant the customer a complete line of hose management service.”

At a recent seminar at the Oceanic Khorfakkan Resort and Spa in Fujai-rah, Marsol were able to showcase their latest product to major oil and gas companies, EPCs and end-users, as well as hosting a site demonstration. The company unveiled the new hose assembly and launch system and an-swered questions and provided information about the services they offer.

Oil and gas marine hoses are the main conduits for offshore product transfer. These critical components constitute a major investment, of-ten with long lead times, and are the most vulnerable link in the dis-tribution chain. These hoses are exposed to harsh environmental and operating conditions, operating to high levels of availability, yet must comply with exacting quality, health, safety, and environment (QHSE) standards. Oil leaks, reduced reliability, reduced asset integrity and un-planned shutdowns, constitute major QHSE, reputation and economic impacts for the asset-owner, all other stakeholders and the environment.

The Marsol Hose Management Service is structured specifically to avoid such shutdowns, improve reliability and asset availability while focusing on maximising efficiency and minimising operational costs. “Our proven operational engineering capabilities and experience com-bined with our proprietary ASIM Programmes is the foundation of our hose management initiative,” Young added.

Marsol launches innovative system

Project Facility Budget StatusSaudi Aramco - Marjan - Oil Field Expansion (Overview) GOSP 15,000,000,000 ConstructionAramco - Berri - Two Drilling Islands Project Dredging/ Reclamation 150,000,000 Engineering & ProcurementSatorp - Jubail - Debottlenecking Train 2 Refinery 200,000,000 Engineering & ProcurementSaudi Aramco - Hawiyah Gas Plant Expansion Gas Processing 1,200,000,000 ConstructionSaudi Aramco - Uthmaniya Gas Treatment Plant Gas Treatment Plant 800,000,000 ConstructionMaaden - Gold Mines Development Program Gold 600,000,000 Engineering & ProcurementSaudi Aramco - Zuluf Oilfield Expansion Oil Field Development 1,700,000,000 Engineering & ProcurementSaudi Aramco - Abqaiq Main Oil Refinery Liquefied Petroleum Drain Petroleum Oil Refinery 75,000,000 On HoldSaudi Aramco - Jizan Export Refinery (Overview) Petroleum Oil Refinery 2,100,000,000 ConstructionSaudi Aramco - Jizan Export Refinery - Marine Terminal Facilities Marine Terminal 650,000,000 CommissioningSaudi Aramco - Jizan Export Refinery - Naphtha Processing and Aromatics Hydrotreating 1,040,000,000 ConstructionSaudi Aramco - Jizan Export Refinery - Utilities Package Offsites & Utilities 510,000,000 CommissioningSasref - Jubail - Refinery Modernization and Expansion Petroleum Oil Refinery 360,000,000 ConstructionSaudi Aramco - Fadhili Gas Plant - Downstream Packages Gas Processing 650,000,000 CommissioningSaudi Aramco - Yanbu - Storage Tanks and Associated Equipment Gas Storage Tanks 400,000,000 ConstructionSaudi Aramco - Fadhili Gas Plant - Sulphur Recovery Unit SRU (Package 2) Gas Treatment Plant 2,500,000,000 CommissioningMidchem - Riyadh - Chlor Alkali Plant and Calcium Chloride Plant Chlor Alkali 60,000,000 Engineering & ProcurementSaudi Aramco - Berri - Water Injection System Expansion Water Injection 200,000,000 Engineering & ProcurementSaudi Aramco - Qatif - GOSP Pipeline Pumping Expansion Pipeline 100,000,000 ConstructionAdvanced Petrochemical Company - Jubail - Pyoil & Pygas Plant Industrial Production 580,000,000 ShelvedAramco - Ras Tanura Pipeline Oil 270,000,000 ConstructionSaudi Aramco - Fadhili Gas Plant - Industrial Support Facilities (FISF) Gas Treatment Plant 100,000,000 CommissioningSaudi Aramco - North Jeddah Bulk Plant Bulk Storage Plant 270,000,000 ConstructionSaudi Aramco - Haradh Gas Increment Program (Overview) Gas Compression 1,200,000,000 ConstructionSaudi Aramco - Haradh Gas Increment Program - South Haradh Field Flowlines 1,200,000,000 ConstructionSaudi Aramco - Haradh Gas Increment Program - Satellite Gas Compression Gas Compression 1,200,000,000 ConstructionNatpet - Yanbu - Polypropylyene Plant Redevelopment Polypropylene 72,000,000 Engineering & ProcurementSaudi Aramco - Berri - Sour Water Stripper and Disposal System Waste Water Treatment 100,000,000 Engineering & ProcurementUmm Al-Qura Development & Construction Company - King Abdul Aziz Road Roads 1,600,000,000 ConstructionSaudi Aramco - Fadhili Gas Plant (Overview) Gas Treatment Plant 6,600,000,000 ConstructionGACA - Jeddah - King Abdul Aziz International Airport (KAIA) Expansion Airport 6,000,000,000 CommissioningDCOMM - Makkah Mass Rail Transit (MMRT) Railway 16,500,000,000 ConstructionMinistry of Transport - Jeddah Public Transport Program (JPTP) Railway 5,600,000,000 EPC