Project Update for the Muon Ionization Cooling Experiment
(RAL)
Mark PalmerFermilab
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 2
Ionisation cooling formalism• Exponential decrease in normalised emittance:
• Competition between:– dE/dx [cooling] and MCS [heating]
• Optimum:– Low Z, large X0
– Tight focus
– H2 gives best performance
2
2 30
0.014 GeV
2tn nd dE
dX E dX Em X
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 3
MICE Steps IV & V
Plan endorsed by MICE Project Board in April 2014
-SS1-
-Tracker1-
-AFC-
-FC-
-Absorber-
-SS2-
-Tracker2-
MICE Step IVConfiguration
-SS2-
-Tracker2-
-SS1-
-Tracker1-
-AFC1-
-FC1-
-Absorber1-
-RFCC-
CCM
-AFC2-
-Absorber2-
-FC2-
MICE Step VConfiguration
December 15, 2014
Operational 2015
Operational 2018
Legend:-SS = Spectrometer Solenoid--FC = Focus Coil--AFC = Absorber-Focus Coil Module- CCM = Coupling Coil Magnet-RFCC = RF-Coupling Coil Module-
M. A. Palmer | FNAL All Experimenter's Meeting 4
Expedited Muon Cooling Demonstration
Plan developed in response to P5 recommendations
-SS1-
-Tracker1-
-AFC-
-FC-
-Absorber-
-SS2-
-Tracker2-
Legend:-SS = Spectrometer Solenoid--FC = Focus Coil--AFC = Absorber-Focus Coil Module--RFA = RF-Absorber Module-
-SS2-
-Tracker2-
-SS1-
-Tracker1-
-AFC1-
-FC1-
-AFC2-
Primary-Absorber-
-FC2-
RFA1- RFA2-
Secondary-Absorber2-
Secondary-Absorber1-
NEW Expedited
MICE CoolingDemonstration
December 15, 2014
Operational 2017
Represents reduced cost and technical risk relative to MICE Step V
Operational 2015
M. A. Palmer | FNAL All Experimenter's Meeting 5
September-November 2014
• August DOE Review of MAP– Detailed report for the new MICE Cooling Demonstration requested on the 1
month timescale
• September 25th
– Report to DOE accepted
• September 29th
– Plan for 3-year MAP Conclusion presented to HEPAP• Supports completion of the MICE Demonstration• And controlled closeout of other activities
• November 24-25– MICE Project Board Review
• Expedited MICE Demonstration endorsed by the review committee and the international Funding Agencies Committee
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 6
MICE-US Construction Project Scope
• Step IV – Spectrometer Solenoids (2) – Delivered to RAL– LiH Absorber – Delivered RAL– Partial Return Yoke - In Fabrication– Installation and Commissioning
• Spectrometer Solenoids• Fiber Trackers• PRY
• Cooling Demonstration– RF Test and Characterization Program in MTA– 2 Single-Cavity RF Modules
• NO RFCC MODULE
– Final Step PRY– Installation and Commissioning
• Reconfigured Step IV Hardware• RF Systems• Extended PRY
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 7
MICE Hall: Being readied for PRY Installation
• PRY:– Preparation for installation of bases
and restraints on track:• Expect to be installing first set of
“uprights” starting January 2015
Emphasis now shiftingto commissioning
and operations …December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 8
Step IV Wrapped with Partial Return Yoke (PRY)
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting 9
MICE Steps
• Step IV: Study of material, lattice, momentum and emittance to start Q2 CY2015
• Ionization cooling demonstration:– RF Components under test in the
MTA and at Daresbury Lab– Expect that all necessary hardware
will be deployed by Spring 2017– Full demonstration with RF
commences by Summer 2017
December 15, 2014
M. A. Palmer | FNAL All Experimenter's Meeting
Cooling demonstration performance
10
Cooling
Transmission
December 15, 2014
Starting Summer 2017
M. A. Palmer | FNAL All Experimenter's Meeting 11