Support to the Establishment of Single Window for Export, Import and Transit Procedures in the Republic of Tajikistan. Project Steering Committee Meeting No. 5 18 th September 2013. Intrasoft International Presentation. Activities since Meeting #4. - PowerPoint PPT Presentation

Citation preview

Page 1: Project Steering Committee Meeting No. 5 18 th  September 2013

Project Steering Committee

Meeting No. 518th September 2013

Intrasoft International Presentation

Project Steering Committee Meeting No. 5 (18 September 2013) 1

Support to the Establishment of Single Window for Export, Import and Transit Procedures in the

Republic of Tajikistan

Page 2: Project Steering Committee Meeting No. 5 18 th  September 2013

Activities since Meeting #4

• Six month “Interim Report No. 2” submitted to EU• Interim Report No. 1 + Annexes circulated to SC• SLA Resolution completed (English, Russian + Tajik) and

submitted to MEDT (Russian + Tajik versions)• ICT equipment contract signed and equipment en route• Athens mission for Mr. Roziev and 2 SUE SW staff members

(July)• Development for Pilot Release completed • Factory Acceptance Testing (FAT) completed• Pilot training completed in Dushanbe

Project Steering Committee Meeting No. 5 (18 September 2013) 2

Page 3: Project Steering Committee Meeting No. 5 18 th  September 2013

Activities since Meeting #4 (cont.)

• Pilot Tests (UAT) commenced on 16th September• Advanced discussions in formalizing interfaces with the

Treasury and Commercial bank• Further refinement of the SW-Treasury Memorandum• Press release ready for after this meeting • Training Material delivered • User Manual delivered

Project Steering Committee Meeting No. 5 (18 September 2013) 3

Page 4: Project Steering Committee Meeting No. 5 18 th  September 2013

Pilot Training

• Detailed preparation and testing for Pilot Training environment in the Customs Service Training Centre.

• Pilot agencies training in Dushanbe completed (Russian speaking trainers from Athens)

• SUE SW staff trained and operated as “Trainers”• Excellent evaluations for the training were achieved• The helpful feedback from trainees and training

activities has identified software improvements • Khujand and Kurgan Tube starts 23rd September

Project Steering Committee Meeting No. 5 (18 September 2013) 4

Page 5: Project Steering Committee Meeting No. 5 18 th  September 2013

The Pilot Activities• Internet Communications arrangements in

place• Installation and maintenance of Pilot

Environment Infrastructure• UAT Commenced 16th September 2013• Testing at Pilot sites• SLA with Pilot agencies will be finalized• SWIS will run in parallel with existing manual

proceduresProject Steering Committee Meeting No. 5

(18 September 2013) 5

Page 6: Project Steering Committee Meeting No. 5 18 th  September 2013

Development Update

• Factory Acceptance Tests (FAT) completed • Release focus is on Pilot• Full integration is not included:

– Payment integration functionality is ready from the SWIS perspective

– No working interfaces (BRIS, UAIS, Treasury, Bank) included in the Pilot software version

– Digital signature is not included

Project Steering Committee Meeting No. 5 (18 September 2013) 6

Page 7: Project Steering Committee Meeting No. 5 18 th  September 2013

Interfaces Update

• Integration with Bank/Treasury– Some minor details still under discussion– Formalisation of agreement in progress (memo, contract)

• Integration with SimBASE system– Awaiting Extensions Proposal approval before proceeding

• BRIS interface– No technical issue – Awaiting meeting to resolve political deadlock• UAIS interface– No progress.– Considered as almost not possible in current project state.

Project Steering Committee Meeting No. 5 (18 September 2013) 7

Page 8: Project Steering Committee Meeting No. 5 18 th  September 2013

Problems Regarding Definition of Agency’s TNVED Codes

• No Definition yet of TNVED subset for each Agency based on existing regulation R-310;

• Each Agency has to validate this set and prepare when required their own TNVED based lists of goods not covered by R-310 for future discussion;

• System – even pilot cannot operate properly without these subset definitions

• The issue is pending for some time now. Assistance is needed here

Project Steering Committee Meeting No. 5

(18 September 2013) 8

Page 9: Project Steering Committee Meeting No. 5 18 th  September 2013

Supervision of ICT EquipmentSupervision activities will commence once the ICT equipment

has been delivered and made available in Dushanbe

• Supervised supply and installation of Central Servers• Supervised supply and installation of workstations and

network equipment• Acceptance and commissioning• Infrastructure Installation Report

Project Steering Committee Meeting No. 5 (18 September 2013)

9

Page 10: Project Steering Committee Meeting No. 5 18 th  September 2013

Extensions Proposal

• Integration with SimBASE software• Additional SW certification member (Cotton)• Potentially, some new requirements for the

SWIS identified during Pilot training and feedback from SUE SW, agencies and Customs Brokers

• In addition: Extension of warranty period (to one year)

Project Steering Committee Meeting No. 5 (18 September 2013) 10

Page 11: Project Steering Committee Meeting No. 5 18 th  September 2013

Remaining Open Issues

1. BRIS Integration

2. Bank/Treasury integration

3. TNVED Subsets definition

4. Single/multiple payment(s)

5. Integration with SimBASE software

6. UAIS Integration

Project Steering Committee Meeting No. 5( (18 September 2013) 11

Page 12: Project Steering Committee Meeting No. 5 18 th  September 2013

Upcoming Deliverables

1. Administration Manual will be delivered end of September

2. I.P.R will be delivered early October.3. New release resolving most of the SUE

SW and training findings was deployed on 17 September

4. Further software release is planned for early October to solve the remaining issues

Project Steering Committee Meeting No. 5( (18 September 2013) 12

Page 13: Project Steering Committee Meeting No. 5 18 th  September 2013

Project Phases

• Inception 12 Jun 12 11 July 12• Elaboration 16 July 12 9 Jan 13• Construction 2 Jan 13 1 Aug 13• Transition 15Aug 13 11 Apr 14

– Pilot 15 Aug 13 15 Oct 13– Installation 10 Sep 13 15 Oct 13– Replication 16 Oct 13 20 Dec 13– Warranty 23 Dec 13 11 Apr 14

Project Steering Committee Meeting No. 4 (11 June 2013) 13

Page 14: Project Steering Committee Meeting No. 5 18 th  September 2013

Summary

• ICT equipment en route (end September)• Service Level Agreement Resolution submitted

to MEDT• Factory Acceptance Tests completed and Pilot

Implementation underway • Pilot training on SWIS underway• Extensions proposal being updated

Project Steering Committee Meeting No. 5 (18 September 2013) 14

Page 15: Project Steering Committee Meeting No. 5 18 th  September 2013

Thank you for you attention