PROJECT STATUS UPDATE for Pierce College - May 2015
Master Project/Planning
Access analyst completed and provided to PMO design director a definition of scope of work document for completion of campus-wide ADA path-of-travel update so that College Project Team can procure architectural services to complete the update. Work on landscaping and access improvements is currently not moving forward. Limited programming work completed for campus-wide improvements. Design work to be coordinated with completion of other projects. This project includes funds reserved for campus-wide landscaping and accessibility compliance needs. PMO estimate is underway and considerations for High-Low Campus P.O.T is under study.
Project Name: Sustainable Landscape and Campus Accessibility Compliance
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542Andrew Ramsay
PSOMAS / BERLINER AND ASSOCIATES ARC / TBDMaster Project/Planning
Current Highlights:
Frequency
Locaton
Meeting Schedule As needed
Pierce CPT Trailer
Date
Time
Construction Budget
Construction Start N/A
Substantial Completion
Percent Complete 90%
Potentially Deferred
Project is pending confirmation of project priorities and timelines under the revised updated master plan.Project is packaged with the SLE-South of Mall campus improvement project. Lanscaping scope to be deferred.
Project Name: Landscaping - Park, Access Road, DeSoto and Mason Entrances
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542.02Andrew Ramsay
Potentially Deferred
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $4,224,122
Construction Start 5/21/2018
Substantial Completion 9/27/2018
Percent Complete 50%
Project is packaged with the Digital Arts and Media Building campus improvement project and follows the schedule activities and progress of that project.Project scope to be deferred.
Project Name: Lot 5 & 6 East
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.01Andrew Ramsay
PSOMAS / TBD
Potentially Deferred
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $3,319,843
Construction Start 4/19/2018
Substantial Completion 5/13/2020
Percent Complete 50%
p. 1 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
The master plan revision and update have not impacted this scope. Progress is on hold due to prioritization.Project scope to be deferred.
Project Name: Village Road
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.04Andrew Ramsay
Potentially Deferred
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,916,931
Construction Start 3/16/2018
Substantial Completion 1/20/2019
Percent Complete 50%
Programming RFP
Project was re-evaluated for scope adjustment as part of the revised updated master plan that was approved by BOT. Project is packaged as part of the Digital Arts and Media Building campus improvement project. Negotiation for AOR services have concluded and agreement issuance is underway.
Project Name: Horticulture Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-521Andrew Ramsay
TBD
PHILLIPS METSCH SWEENEY M / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start See 05P-521.03
Substantial Completion
Percent Complete
Project was re-evaluated for scope adjustment as part of the revised updated master plan that was approved by BOT. Project is packaged as part of the Digital Arts and Media Building campus improvement project. Negotiation for AOR services for demolition of existing facilities have concluded and agreement issuance is underway. Demolition will be procured as a separate construction contract.
Project Name: Horticulture Facility
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-521.03Andrew Ramsay / Nicolas Haddad
J.D. DIFFENBAUGH, INC. / TBD
HILL Partnership / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $3,654,484
Construction Start 2/15/2017
Substantial Completion 12/11/2017
Percent Complete 50%
p. 2 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.
Project Name: Digital Arts and Media Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-533Andrew Ramsay
TBD
DLR GROUP WWCOT / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $20,393,866
Construction Start 4/19/2018
Substantial Completion 2/9/2020
Percent Complete 50%
Project is part of the revised updated master plan approved by the BOT. Project scope is being evaluated by campus.
Project Name: Agricultural Education Center
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-534Andrew Ramsay
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $3,063,041
Construction Start 3/23/2018
Substantial Completion 3/22/2019
Percent Complete 50%
Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.
Project Name: SLE - South of Mall - Classroom Modernization/Technology/Low Voltage
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.03Andrew Ramsay
TBD
BERLINER AND ASSOCIATES ARC / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $6,120,458
Construction Start 11/13/2017
Substantial Completion 3/11/2019
Percent Complete 50%
Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.
Project Name: Expanded Automotive and New Technical Education Facilities
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-536Andrew Ramsay
TBD
CARDE TEN ARCHITECTS / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $16,997,181
Construction Start 8/29/2017
Substantial Completion 3/13/2019
Percent Complete 60%
p. 3 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.
Project Name: Campus Fire Access Road Improvements
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542.01Andrew Ramsay
PSOMAS / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $228,010
Construction Start 8/29/2017
Substantial Completion 3/14/2019
Percent Complete 60%
Based on revised updated master plan approved by BOT, preparation for presentation of project to workshop for validation of scope and delivery method is pending.
Project Name: SLE - South of Mall - ADA/Landscaping
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542.07Andrew Ramsay
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,553,635
Construction Start 11/13/2017
Substantial Completion 3/11/2019
Percent Complete 50%
Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.
Project Name: Parking Lots and Roadways - Anthropology/Geography
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.02Andrew Ramsay
TBD
PSOMAS / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,529,509
Construction Start 2/9/2016
Substantial Completion 11/22/2017
Percent Complete 60%
Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.
Project Name: Central Plant Expansion - West Central Plant
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-544.05Andrew Ramsay
CARDE TEN ARCHITECTS / TBD
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $4,232,749
Construction Start 8/10/2017
Substantial Completion 11/19/2018
Percent Complete 60%
p. 4 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Remaining restrooms will be grouped with other projects in the SLE-South of Mall campus improvement package.
Project Name: Restrooms Renovations Campus
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-575Andrew Ramsay
TBD (See 05P-535.03)
Berliner & Associates Arc
Programming RFP
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $233,630
Construction Start 11/13/2017
Substantial Completion 2/19/2018
Percent Complete 27%
In Design
Completion of construction documents is in progress and submission to DSA Awaits close-out of PE General project.
Project Name: P.E. Facilities - Improvements
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-527.04Andrew Ramsay
Carde Ten Architects
In Design
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $600,785
Construction Start 10/6/2017
Substantial Completion 6/11/2018
Percent Complete 90%
AOR activities are needed beyond the 5 year current contract limit for professional services.
Project Name: SLE - Center for the Sciences Technology Upgrades
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.10Keykhosrow (Kay) Khadem
TBD
James Heimler, Architect,
In Design
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $542,576
Construction Start 11/29/2017
Substantial Completion 3/28/2018
Percent Complete 90%
Bid Award
BOT approved award of contractor services.
Project Name: Campus-wide Security Upgrade
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.11Nicolas Haddad
Diebold, Inc.
Bid Award
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,133,540
Construction Start 8/17/2015
Substantial Completion 2/16/2016
Percent Complete 95%
p. 5 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
In Construction
Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: Life Science, Chemistry, Physics Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-502Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $15,622,748
Construction Start 10/7/2010
Substantial Completion 5/12/2016
Percent Complete 88%
Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: Phase II Renovations - Administration Building - Interior and Exterior
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-505.02Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $8,552,658
Construction Start 10/7/2010
Substantial Completion 5/12/2016
Percent Complete 93%
General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: Phase II Renovations - Computer Science and Computer Learning
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-507Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $6,568,511
Construction Start 10/7/2010
Substantial Completion 5/29/2017
Percent Complete 36%
p. 6 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: Phase II Renovations - Behavioral Science, Social science, Mathematics, and English Buildings
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-510Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects
In Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $12,766,418
Construction Start 10/7/2010
Substantial Completion 5/29/2017
Percent Complete 16%
Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: Campus Center (Existing) - General
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-530.01Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $1,966,972
Construction Start 10/7/2010
Substantial Completion 5/12/2016
Percent Complete 85%
General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: SLE - North of Mall - Classroom Modernization/Technology/Low Voltage
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.02Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $3,868,939
Construction Start 10/7/2010
Substantial Completion 5/29/2017
Percent Complete 0%
p. 7 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
General Contractor preconstruction services are underway and field investigation has been initiated. AOR has received BUG info for reprogramming.
Project Name: SLE Community Services/Agriculture Science Building Renovation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.05Nicolas Haddad
H. A. NICHOLS CO., INC. / Balfour Beatty Construction LLCBERLINER & ASSOCIATES ARC / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule As needed
Pierce CPT Trailer
Date
Time
Construction Budget $3,504,745
Construction Start 11/14/2011
Substantial Completion 5/17/2016
Percent Complete 31%
Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: SLE Faculty Center/Campus Center
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.07Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $2,748,103
Construction Start 10/7/2010
Substantial Completion 5/12/2016
Percent Complete 85%
LLB Contractor has mobilized. Visitor side recorrective work is underway.
Project Name: Stadium ADA Improvements
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-537Nicolas Haddad
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCFTR INTERNATIONAL, INC. / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Every Thursday
8:00 AM
Construction Budget $10,687,653
Construction Start 7/26/2011
Substantial Completion 8/18/2015
Percent Complete 86%
p. 8 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
General Contractor preconstruction services are underway. Guaranteed Maximum Price (GMP) under development for Phase 1 of the North of Mall.
Project Name: SLE - North of Mall - ADA/Landscaping
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542.06Kurt Supinger
FTR INTERNATIONAL, INC. / Balfour Beatty Construction LLCBerliner & Associates Arc / PBWS Architects, LLPIn Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $5,710,748
Construction Start 10/7/2010
Substantial Completion 5/29/2017
Percent Complete 47%
Procurement package for AOR services has been advertised. Procurement package for LLB contractor has been developed by CPT.
Project Name: Mason Reroute
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.03Andrew Ramsay
Kanaan Construction, Inc. / TBD (See 05P-536)PSOMAS / TBD
In Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,095,319
Construction Start 5/25/2011
Substantial Completion 3/4/2018
Percent Complete 22%
CPT has received GMP from contractor. Contract executed. Notice to proceed with construction issued to start on June 10, 2015.
Project Name: Campus-wide Telecommunications Upgrade (VoIP)
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-544.04Kurt Supinger
Balfour Beatty Construction LLC
PSOMAS / PBWS Architects, LLP
In Construction
Current Highlights:
Frequency
Locaton
Meeting Schedule Weekly
Pierce CPT Trailer
Date
Time
Thursday
10:00 AM
Construction Budget $2,211,299
Construction Start 2/21/2013
Substantial Completion 9/9/2015
Percent Complete 0%
p. 9 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
In Close Out
Project merged with the Digital Arts and Media Building project. Based on revised updated master plan approved by BOT, project scope development and project initiation is pending.
Project Name: Convert Existing Library
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-508.01Andrew Ramsay
In Close Out
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start See 05P-533
Substantial Completion
Percent Complete 100%
Close-out is incomplete construction contract to complete corrections to the ADA parking has been awarded. This completion contract has been packaged with the NOM CIP. AOR revising drwgs to reflect existing conditions.
Project Name: Photovoltaic Arrays for Parking Lots 1 & 8
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-544.03Kurt Supinger
Chevron Energy Solutions Co. / Balfour Beatty Construction LLCChevron Energy Solutions Co. / PBWS Architects, LLPIn Close Out
Current Highlights:
Frequency
Locaton
Meeting Schedule As needed
Pierce CPT Trailer
Date
Time
Construction Budget $10,135,944
Construction Start 12/28/2010
Substantial Completion 1/10/2012
Percent Complete 90%
In DSA Closeout
Fire sprinkller CCD submission to DSA has ocurred. AOR preparing Smart board Bid package. PL7 accessible parking CD's have been reviewed by CPT - AOR to provide revisions.
Project Name: Center for the Sciences
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-501Ed Cadena
Sinanian Development, Inc
Hellmuth, Obata & Kassaba / CWA AIA, Inc.
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $47,842,460
Construction Start 8/27/2007
Substantial Completion 8/6/2010
Percent Complete 87%
p. 10 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Close-out ongoing. Acoustical treatment in corridor for noise attenuation will be added to the SLE-South of Mall campus improvements package.
Project Name: Phase I Renovations - Business Education
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-513.01Doug Cottone
Delmac Construction
Fsy Architects, Inc.
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,431,008
Construction Start 1/9/2009
Substantial Completion 8/9/2010
Percent Complete 66%
Close-out ongoing.
Project Name: Phase I Renovations - Faculty Office
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-515Doug Cottone
FEI Enterprises, Inc / A.G. Araja EngineeringJohnson Fain Inc. / FSY Architects, Inc.
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,203,305
Construction Start 1/9/2009
Substantial Completion 6/22/2009
Percent Complete 86%
Close-out ongoing.
Project Name: Phase I Renovations - Fine Arts and Music
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-516Doug Cottone
FEI Enterprises, Inc / Delmac Construction / A.G. Araja EngineeringJohnson Fain Inc. / FSY Architects, Inc.
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $3,037,300
Construction Start 1/9/2009
Substantial Completion 12/30/2009
Percent Complete 86%
p. 11 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Building occupied effective 1/31/2015. Rented swing space has been demobilized. Intercom for Arena Theater is being sourced by the completing contractor.
Project Name: Early Renovations - Theater Building - Performing Arts
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-518.03Doug Cottone
TAISEI CONSTRUCTION / GMZ Engineering, Inc. / TBDFSY ARCHITECTS, INC. / TAISEI CONSTRUCTIONIn DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As needed
Pierce CPT Trailer
Date
Time
Construction Budget $798,384
Construction Start 4/17/2012
Substantial Completion 1/26/2015
Percent Complete 99%
Building occupied effective 1/31/2015. Rented swing space has been demobilized. Intercom for Arena Theater is being sourced by the completing contractor.
Project Name: Performing Arts Building Improvements
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-518.04Doug Cottone
TAISEI CONSTRUCTION / GMZ Engineering, Inc. / TBDTAISEI CONSTRUCTION
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As needed
Pierce CPT Trailer
Date
Time
Construction Budget $12,323,577
Construction Start 4/17/2012
Substantial Completion 9/10/2014
Percent Complete 99%
Original contract scope completed with the exception of some isolated outstanding items remaining to be completed under a separate close-out construction contract. AOR is reengaged in developing CCD and construction documents.
Project Name: P.E. Facilities - General
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-527.01Doug Cottone
FTR INTERNATIONAL, INC. / TBD
Steinberg Architects
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $17,423,876
Construction Start 8/25/2008
Substantial Completion 2/1/2010
Percent Complete 56%
p. 12 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Close-out ongoing.
Project Name: P.E. Facilities - Pool Piping and Deck
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-527.03Doug Cottone
Ftr International, Inc.
Steinberg Architects
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $825,000
Construction Start 8/25/2008
Substantial Completion 2/1/2010
Percent Complete 56%
Project has been submitted for DSA close-out. Punchlist has been satisfied.
Project Name: New Maintenance and Operations Facility
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-540Doug Cottone
Gkkworks
Gkkworks
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $13,120,963
Construction Start 7/13/2010
Substantial Completion 12/1/2011
Percent Complete 77%
Close-out and follow-on punch list closeout ongoing.
Project Name: Library/Learning Crossroads Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-541Doug Cottone
Bernards Bros. Inc.
Bernards Bros. Inc. (HMC)
In DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $36,861,971
Construction Start 4/12/2011
Substantial Completion 3/22/2013
Percent Complete 10%
Corrective work partially completed. CPT to prepare Scope of Work for AOR RFP.
Project Name: FTA Bus Rapid Transit Extension & Winnetka / Mason DeSoto Entrances
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-588.03Ed Cadena
PIMA CORPORATION / GMZ Engineering
BERLINER AND ASSOCATIONS ARC / TBDIn DSA Closeout
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,281,226
Construction Start 4/20/2009
Substantial Completion 4/6/2010
Percent Complete 77%
p. 13 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Completed
Close-out ongoing.
Project Name: Child Development Center
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-509Doug Cottone
L.A. Builders, Inc.
Carde Ten Architects
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $8,794,230
Construction Start 6/11/2008
Substantial Completion 8/2/2010
Percent Complete 100%
Close-out ongoing.
Project Name: Measure J Animal Science Facilities
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-521.04Ed Cadena
Gmz Engineering, Inc.
Ktgy Group, Inc.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $245,057
Construction Start 6/7/2012
Substantial Completion 9/4/2012
Percent Complete 100%
Completed.
Project Name: Animal Science Facilities
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-522Ed Cadena
Tobo Construction, Inc.
PMSM / Berliner & Associates Architects
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,179,607
Construction Start 7/28/2008
Substantial Completion 7/31/2009
Percent Complete 100%
Completed.
Project Name: Campus Sheriff Station
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-525Ed Cadena
Profile Structures, Inc.
Amador Whittle Architects
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $530,263
Construction Start 10/7/2006
Substantial Completion 4/10/2007
Percent Complete 100%
p. 14 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Close-out ongoing. DSA Certification obtained.
Project Name: Exhibition & Events Center - Phase 1B
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-526.03Doug Cottone
Tobo Construction, Inc.
Froehlich, Kow & Gong
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,022,152
Construction Start 9/18/2007
Substantial Completion 6/11/2009
Percent Complete 100%
Close-out ongoing. DSA Certification obtained.
Project Name: Exhibition & Events Center - Phase 1B - Fence Relocation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-526.06Doug Cottone
ENVIRONMENTAL CONSTRUCTION / GMZ Engineering, Inc. / TBDFROEHLICH, KOW & GONG
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,525,904
Construction Start 4/18/2011
Substantial Completion 3/28/2014
Percent Complete 98%
Completed.
Project Name: Student Services Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-528Ed Cadena
Akg Construction, Inc.
Wwcot
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $17,835,704
Construction Start 9/28/2007
Substantial Completion 10/12/2009
Percent Complete 100%
Close-out ongoing.
Project Name: Old Book Store Renovation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-529Ed Cadena
Kahromic Contracting, Inc
Johnson Fain Inc.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,436,714
Construction Start 3/2/2007
Substantial Completion 4/4/2008
Percent Complete 100%
p. 15 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Close-out ongoing.
Project Name: SLE - College Services (CSB) Building Mailroom Relocation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.01Ed Cadena
G. Coast Construction,Inc
Berliner & Associates Arc
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $631,448
Construction Start 1/26/2010
Substantial Completion 9/24/2010
Percent Complete 100%
Close-out ongoing.
Project Name: SLE Temporary CDC Reuse
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.06Ed Cadena
Gmx Construction, Inc.
Steinberg Arch Inactive
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $772,094
Construction Start 9/1/2010
Substantial Completion 3/15/2011
Percent Complete 100%
Close-out ongoing.
Project Name: SLE - Faculty Office Replastering
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.08Ed Cadena
Ranbay Construction Corp. / GMZ Engineering, Inc.Fsy Architects, Inc.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $470,922
Construction Start 6/23/2011
Substantial Completion 8/17/2012
Percent Complete 100%
Close-out ongoing.
Project Name: SLE- Campus Wide Improvements
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-535.09Doug Cottone
Simple Design
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $96,115
Construction Start 7/25/2011
Substantial Completion 11/30/2012
Percent Complete 100%
p. 16 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Close-out ongoing.
Project Name: SMP - Irrigation Systems Replacement/Lot 5
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-542.05Keykhosrow (Kay) Khadem
Pierre Sprinkler & Landscape
Cwa Aia, Inc.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $438,836
Construction Start 3/19/2012
Substantial Completion 5/22/2012
Percent Complete 100%
Master project. Programming study on campus wide improvements to parking lots and roadways was previously completed.
Project Name: Parking Lots and Roadways
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543Ed Cadena
BERLINER AND ASSOCIATES ARC
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start N/A
Substantial Completion
Percent Complete 100%
Completed.
Project Name: RWGPL - Horticulture Intersection at Brahma Drive
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.06Ed Cadena
Ranbay Construction Corpo
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $397,870
Construction Start 6/1/2010
Substantial Completion 8/15/2010
Percent Complete 100%
Completed.
Project Name: PLRW - Lot 6 West
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.07Ed Cadena
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $3,079,724
Construction Start
Substantial Completion 9/15/2010
Percent Complete 100%
p. 17 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Master project. Programming study on campus-wide infrastructure upgrades completed. Scope has been distributed to appropriate new construction projects. May need to be revisited for adjustments based on revised and updated master plan.
Project Name: Infrastructure Expansion Master
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-544Ed Cadena
PSOMAS
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start N/A
Substantial Completion
Percent Complete 100%
Completed.
Project Name: Waterless urinals
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-554.01Ed Cadena
Brej Corporation
Winzler & Kelly
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $65,513
Construction Start 8/21/2008
Substantial Completion 11/21/2008
Percent Complete 100%
Completed.
Project Name: RWGPL - Brahma Drive
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.01Doug Cottone
Djm Construction Company
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,957,333
Construction Start 4/23/2007
Substantial Completion 8/25/2008
Percent Complete 100%
Completed.
Project Name: Campus-Wide Improvements - Parking Lot 7
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.02Ed Cadena
Griffith Company
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,909,200
Construction Start 6/20/2002
Substantial Completion 10/9/2002
Percent Complete 100%
p. 18 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Completed as a part of 05P-526.03 Exhibition & Events Center - Phase 1B. Close-out underway.
Project Name: RWGPL - West Parking Lot
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.04Ed Cadena
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start
Substantial Completion
Percent Complete 100%
Close-out underway.
Project Name: RWGPL - East Parking Lot @ Exhibition / Ag Science
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.05Ed Cadena
Griffith Company
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,358,846
Construction Start 6/2/2008
Substantial Completion 9/2/2008
Percent Complete 100%
Completed.
Project Name: RWGPL - Parking Lot 1
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.06Doug Cottone
Griffith Company
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,238,763
Construction Start 10/1/2008
Substantial Completion 2/9/2009
Percent Complete 100%
Program close-out ongoing.
Project Name: Landscape and Site Master Plan
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.09Ed Cadena
United Contractors Co.,
Berliner & Associates Arc
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $6,521,113
Construction Start 4/24/2009
Substantial Completion 5/31/2011
Percent Complete 100%
p. 19 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Completed.
Project Name: Early Release Package - El Rancho Road
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.12Ed Cadena
Djm Construction Company
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,417,899
Construction Start 4/23/2007
Substantial Completion 8/25/2008
Percent Complete 100%
Close-out is ongoing.
Project Name: RWGPL - Botanical Garden
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-573.13Ed Cadena
Grounds Control, Inc.
Division Of The State Arc
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $232,204
Construction Start 1/9/2007
Substantial Completion 2/15/2008
Percent Complete 100%
Completed.
Project Name: Temporary Facilities - Relocation, Acquisition (Village)
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-577.01Ed Cadena
Profile Structures, Inc.
Amador Whittle Architects
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $7,674,188
Construction Start 4/3/2006
Substantial Completion 4/9/2007
Percent Complete 100%
Completed.
Project Name: Temporary Facilities - SMCI Trailers & Swing Space Utilities
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-577.02Ed Cadena
Tek Up Construction, Inc.
Division Of The State Arc
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $675,433
Construction Start 2/2/2004
Substantial Completion 4/15/2005
Percent Complete 100%
p. 20 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Completed.
Project Name: Temporary Village Expansion
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-577.05Ed Cadena
Singpoli Construction
Gonzalez Goodale Architec
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $2,689,437
Construction Start 5/28/2008
Substantial Completion 9/2/2008
Percent Complete 100%
Close-out underway.
Project Name: Temporary Village Expansion - Electrical / Low Voltage
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-577.06Ed Cadena
Unique Home Remodeling
Steinberg Arch Inactive
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $70,131
Construction Start 6/9/2009
Substantial Completion 8/20/2009
Percent Complete 100%
Close-out underway.
Project Name: Temporary Village Expansion - Partitions
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-577.07Ed Cadena
Barrett Robinson Inc.
Steinberg Arch Inactive
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $20,800
Construction Start 7/1/2009
Substantial Completion 7/27/2009
Percent Complete 100%
Close-out underway.
Project Name: Campus Improvements - Utilities
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-579.01Ed Cadena
Chevron Energy Solutions
Psomas
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $20,870,331
Construction Start 1/24/2008
Substantial Completion 3/16/2010
Percent Complete 100%
p. 21 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Program close-out ongoing.
Project Name: Campus-Wide Improvements - Central Plant
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-579.05Ed Cadena
Chevron Energy Solutions
Tetra Design, Inc.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $7,341,577
Construction Start 7/28/2009
Substantial Completion 1/7/2011
Percent Complete 100%
Completed.
Project Name: Campus Improvements - Utilities Early Release Package
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-579.06Ed Cadena
Djm Construction Company
Pc Associates
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $8,644,052
Construction Start 4/23/2007
Substantial Completion 8/25/2008
Percent Complete 100%
Program close-out ongoing.
Project Name: SMP - Remove & Replace Transit Pipes
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-588.08Ed Cadena
FTR INTERNATIONAL, INC.
Completed
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $398,424
Construction Start 7/21/2009
Substantial Completion 11/24/2009
Percent Complete 100%
Cancelled
Project cancelled.
Project Name: Green Technologies Building
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-532Ed Cadena
Cancelled
ZIMMER GUNSUL FRASCA ARCHITECT
Cancelled
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $196,970
Construction Start N/A
Substantial Completion N/A
Percent Complete 0%
p. 22 of 23Data Date: 06/04/2015
PROJECT STATUS UPDATE for Pierce College - May 2015
Project has been fully defunded. Project has been cancelled.
Project Name: Agoura Satellite Center - Land Acquisition
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-538.01Ed Cadena
Cancelled
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start
Substantial Completion
Percent Complete 0%
Project has been cancelled as an outcome of the revision and updating of the master plan.
Project Name: Parking Lots and Roadways - Off-site Traffic Mitigation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-543.05Ed Cadena
Cancelled
PSOMAS
Cancelled
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start
Substantial Completion
Percent Complete 0%
Scope has been distributed to related new construction projects. Electrical feeders remained under this project. Project to be deferred.
Project Name: Infrastructure - Campus-Wide Utilities Extensions
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-544.01Andrew Ramsay
Berliner & Associates Arc
Deferred
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget $1,347,473
Construction Start 7/13/2018
Substantial Completion 7/13/2018
Percent Complete 90%
Project has been cancelled as an outcome of the revision and updating of the master plan.
Project Name: Campus Improvements - Traffic Mitigation
Project Manager:
Contractor:
Architect:
Phase:
Project No.: 05P-579.02Ed Cadena
Cancelled
PSOMAS
Cancelled
Current Highlights:
Frequency
Locaton
Meeting Schedule As Needed Date
Time
Construction Budget
Construction Start
Substantial Completion
Percent Complete 0%
p. 23 of 23Data Date: 06/04/2015