PROJECT STATUS DECEMBER 2019
Building 4–Final slab completed
Building 5-Final slab completed
Building 6-10th floor with MIVAN work in progress
Building 7–8th floor with MIVAN work in progress
Building 8-20th floor Roof slab completed
Building 9-18th floor roof slab in progress
Building 1–6th slab completed, 7th slab work in progress
Building 2-(Parking-2) balance roof slab shuttering in progress
Building 3–Typical floor slab Completed
Club House 2nd Slab completed