Upload
alfredo-a-lopez
View
216
Download
0
Embed Size (px)
Citation preview
7/23/2019 Project Sheffield2
1/1
www.pennine.co.uk
SheffieldSheffieldSheffieldSheffield Dynamic CompactionDynamic CompactionDynamic CompactionDynamic Compaction
Dynamic Compaction Rig in operation at Project True North site, Sheffield
Clients RequirementsClients RequirementsClients RequirementsClients Requirements
Consulting engineers Burke Green were
designing a new print works on the site of the
former wire works at Tinsley, close to the M1 in
Sheffield. The development, known as Project
True North, with a building footprint of some
55,660 m2required floor slab loads from 60 to
150kN/m2 and stanchion base loads of
175kN/m2. The site had been filled with
between 3.5 and 10.5 metres of colliery spoil
prior to the previous development some 20years before.
Pennines SolutionPennines SolutionPennines SolutionPennines Solution
Working as a sub-contractor to UK GSE Ltd
Pennine designed and carried out a dynamic
compaction solution to provide the required
bearing capacities. The method consists of
dropping a large weight on individual positions
(or footprints) on a grid pattern, the footprints
are filled and subsequent treatment passes
carried out. Design criteria were established by
comparing predicted and actual ground
response measured by heave tests; load tests
demonstrate overall effect. The deepest areas of
fill were treated with two passes of a 10 tonne
weight falling 15 metres on a 7.5 metre grid,
this was followed by two passes of 8 tonnes
falling 15 metres on a 5 metre grid. Where fill
was less deep the treatment was similar but
omitted the first two passes. A final tampingpass of 2 tonnes falling 5 metres completed the
sequence.
The design and performance was verified by 10
heave tests, 50 plate tests, 2 dummy footing
tests, 2 zone tests and 20 post-treatment CPT
tests. The 150,000 lump sum design and
construct package was completed in a 10 week
period during the summer of 2004.