Project Sheffield2

Embed Size (px)

Citation preview

  • 7/23/2019 Project Sheffield2

    1/1

    www.pennine.co.uk

    SheffieldSheffieldSheffieldSheffield Dynamic CompactionDynamic CompactionDynamic CompactionDynamic Compaction

    Dynamic Compaction Rig in operation at Project True North site, Sheffield

    Clients RequirementsClients RequirementsClients RequirementsClients Requirements

    Consulting engineers Burke Green were

    designing a new print works on the site of the

    former wire works at Tinsley, close to the M1 in

    Sheffield. The development, known as Project

    True North, with a building footprint of some

    55,660 m2required floor slab loads from 60 to

    150kN/m2 and stanchion base loads of

    175kN/m2. The site had been filled with

    between 3.5 and 10.5 metres of colliery spoil

    prior to the previous development some 20years before.

    Pennines SolutionPennines SolutionPennines SolutionPennines Solution

    Working as a sub-contractor to UK GSE Ltd

    Pennine designed and carried out a dynamic

    compaction solution to provide the required

    bearing capacities. The method consists of

    dropping a large weight on individual positions

    (or footprints) on a grid pattern, the footprints

    are filled and subsequent treatment passes

    carried out. Design criteria were established by

    comparing predicted and actual ground

    response measured by heave tests; load tests

    demonstrate overall effect. The deepest areas of

    fill were treated with two passes of a 10 tonne

    weight falling 15 metres on a 7.5 metre grid,

    this was followed by two passes of 8 tonnes

    falling 15 metres on a 5 metre grid. Where fill

    was less deep the treatment was similar but

    omitted the first two passes. A final tampingpass of 2 tonnes falling 5 metres completed the

    sequence.

    The design and performance was verified by 10

    heave tests, 50 plate tests, 2 dummy footing

    tests, 2 zone tests and 20 post-treatment CPT

    tests. The 150,000 lump sum design and

    construct package was completed in a 10 week

    period during the summer of 2004.