Upload
group2sd1314
View
59
Download
0
Embed Size (px)
DESCRIPTION
Project Scope Statement
Citation preview
PROJECT SCOPE STATEMENT
KEADUE WWTP UPGRADE WORKS
KMCF ENGINEERING
DUBLIN ROAD
ATHLONE
2014
Table of Contents 1.0 INTRODUCTION .............................................................................................................................. 1 2.0 PROJECT PURPOSE AND JUSTIFICATION ............................................................................................... 1 3.0 SCOPE DESCRIPTION ....................................................................................................................... 2 4.0 HIGH LEVEL REQUIREMENTS ............................................................................................................. 3 5.0 BOUNDARIES ................................................................................................................................. 3 6.0 STRATEGY ..................................................................................................................................... 4 7.0 DELIVERABLES ................................................................................................................................ 4 8.0 ACCEPTANCE CRITERIA .................................................................................................................... 4 9.0 CONSTRAINTS ................................................................................................................................ 5 10.0 ASSUMPTIONS ............................................................................................................................. 5 11.0 COST ESTIMATE ........................................................................................................................... 6
1
1.0 INTRODUCTION
This Project Scope Statement serves as a baseline document for defining the scope of the
Keadue WWTP Upgrade Works Project, project deliverables, work which is needed to
accomplish the deliverables, and ensuring a common understanding of the projects scope
among all stakeholders. All project work should occur within the framework of the project
scope statement and directly support the project deliverables. Any changes to the scope
statement must be vetted through the approved Project Change Management Process prior to
implementation. This completion date for this project is 17th April 2014.
2.0 PROJECT PURPOSE AND JUSTIFICATION
The Keadue WWTP Upgrade Works Project has been approved to plan, design and develop a
programme to manage the development of a new, upgraded WWTP located off the R285
outside the village of Keadue in Co. Roscommon. The purpose of the project is two-tiered:
Firstly, the project team has been drafted to develop a tender selection system capable
of comparing a series of WWTP options for the planned improvement works at Keadue
WWTP, develop the schedule for said development and a cost performance system to
be used during the contract phase.
Secondly, the project team is to develop a generic tender selection system with the
same capabilities as listed previously. This generic system is to be applicable to all future
works of a similar nature and is to be based on, and verified through, the Keadue
development.
This project brief has been development with the overall goal of streamlining the tender
selection process for small community WWTP upgrade works. Once completed, this system is
to greatly reduce the man-hours required for such works in the future while simultaneously
providing a check to the selection process, thus reducing the risk of miss-calculation or omission
on the part of the individual responsible for the task.
2
3.0 SCOPE DESCRIPTION
The scope of the Keadue WWTP Upgrade Works project is to develop a tender selection system
for the planned development of the existing WWTP. This system is then to be used as the basis
for the development of a generic system which may then be tailored and used in all future
works of a similar nature. This system is to comprise of several key components:
A feasibility assessment
A schedule of works
A construction schedule
A performance management system
All associated project management documentation
The above list has been generated with the view of providing future Tendering teams with all
required information and tools in one collaborative system. The system will be designed to take
all submitted tenders through one simple process.
Firstly all tender information will be entered into the relevant fields within the feasibility
assessment along with all relevant information relating to the planned site (available size, PE
etc.), all data will then be automatically compared and two systems chosen as the most suitable
for the planned development. These two systems will then be examined in further detail with
such elements compared as cost performance and resultant effluent standards. Once this
information has been compiled the system will select a final system to be passed on to the next
stage whereupon a generic construction and works schedule will be tailored to suit its
requirements. These schedules may then be passed along to the contractor to commence
construction while the project is constantly monitored by the system throughout the contract
stage. Providing that the system is regularly updated with the status of all current processes, it
will be capable of adjusting the projects schedule and budget accordingly as delays are
encountered. It will also have the facility to provide documentation for the request of
remediation in the event that unforeseen delays are incurred.
3
In addition to the above functionalities, the proposed tender selection system is to include all
relevant project management documentation; project scope, project charter, risk register, WBS
etc. Once again, all of this documentation will be developed in relation to the planned Keadue
works, with the generic versions based upon these.
4.0 HIGH LEVEL REQUIREMENTS
The Tender Selection System for Keadue WWTP Upgrade works has been approved to meet a
business need for KMCF Consulting. In order to meet this business need there are several
requirements which must be met as part of the successful execution of this project. The
following high level requirements have been identified for this project:
The system must be capable of running a minimum of two tender submissions through a
detailed feasibility assessment.
The system must be capable of developing a detailed works and construction schedule
of the chosen tender option.
The system must be capable of monitoring the ongoing performance of the project in
relation to cost and schedule.
The end product must be sufficient of managing all wastewater requirements for the
Keadue are and meet all relevant environmental legislation.
5.0 BOUNDARIES
The Keadue WWTP Upgrade Works Project includes all of the works associated with the tender
selection, scheduling and monitoring for the planned development works. This is to include a
preliminary design of the submitted tenders in relation to expected size and resultant effluent
standards, the initial costing of the proposed tenders (for two options), the scheduling of the
required works for the chosen tender and the development of a system capable of monitoring
the performance of the project on an on-going basis. This project is also to include the drafting
of all relevant project management documentation.
Not included in the scope of this project is a detailed design of the chosen WWTP or scheduling
of future maintenance.
4
6.0 STRATEGY
For the Keadue WWTP Upgrade Works Project, the project team is to operate in tandem for as
much of the project as possible. Each team member is to be assigned a unique role in the
project with its own unique responsibilities. The project is to be separated in such a way so as
to maximize the overall efficiency of its development, while maintaining a level of simplicity in
its eventual collaboration. All work is to be checked by an assigned member of staff with the
overall development of the project to be constantly monitored by the teams project manager.
7.0 DELIVERABLES
There are several deliverables which will be produced as a result of the successful completion
of the Keadue WWTP Upgrade Works Project. If all of the following deliverables are not met
then the project will not be considered successful. The Project Manager is responsible for
ensuring the completion of these deliverables.
1. Deliverable 1 A feasibility assessment system capable of comparing a minimum of two
WWTP tender submissions and identifying the most appropriate option for the desired
site.
2. Deliverable 2 A construction and works schedule tailored to the development
requirements of the chosen WWTP tender.
3. Deliverable 3 A monitoring system capable of measuring the on-going performance of
the project in relation to cost and schedule throughout the contract phase.
4. Deliverable 4 All associated project management documentation.
8.0 ACCEPTANCE CRITERIA
Acceptance criteria have been established for the Keadue WWTP Upgrade Works Project to
ensure thorough vetting and successful completion of the project. The acceptance criteria are
both qualitative and quantitative in nature. All acceptance criteria must be met in order to
achieve success for this project:
1. Meet all deliverables within scheduled time.
2. Chosen system to be suitable for Keadue current/future requirements.
5
3. Designed system to significant reduce workload involved in future tender selection
process.
4. Designed monitoring system to significantly reduce the risk involved in the contract
phase on behalf of the consultant involved.
9.0 CONSTRAINTS
Several constraints have been identified for the Keadue WWTP Upgrade Works Project. It is
imperative that considerations be made for these constraints throughout the project lifecycle.
All stakeholders must remain mindful of these constraints as they must be carefully planned for
to prevent any adverse impacts to the projects schedule, cost, or scope. The following
constraints have been identified for the Keadue WWTP Upgrade Works Project:
1. Project must be completed within allocated timeframe.
2. Designed WWTP system must satisfy associated criteria within a budget realistic to the
developments size.
10.0 ASSUMPTIONS
Several assumptions have been identified for the Keadue WWTP Upgrade Works Project. All
stakeholders must be mindful of these assumptions as they introduce some level of risk to the
project until theyre confirmed to be true. During the project planning cycle every effort must
be made to identify and mitigate any risk associated with the following assumptions:
1. In keadew wastewater treatment plant need to ensure there is adequate resources
available for the water.
2. Due to a manufacturers production backlog, the servers are not available for large scale
application testing causing a delay in the project schedule. The project manager will
mitigate this risk by using servers from the backup data centre if needed.
6
11.0 COST ESTIMATE
The estimated costs for this project are included in the table below. As the project proceeds
and any additional costs become known, this cost will be refined and communicated to all
project stakeholders.
Package System Costs
Element 1 Groundwork's
Excavation 1,000
Groundwork's 500
Element 2 Construction
BMS System X2 136,450
Slab 1,000
Pump/Pump Sump 5,500
Commissioning of the system 1,500
Delivery of system 1,200
Element 3 Maintenance
Operation Costs 80,000
General Maintenance 20,000
Program Grand Total Cost 280,515
7
SPONSOR ACCEPTANCE
Approved by the Project Sponsor: __________________________________________ Date: ___________________