29
Mehran University of Engineering & Technology Project: Quantity Estimation & Rate Analysis of Building Quantity Surveying & Estimation For Civil Works Submitted to Sir Dr. Nafees Ahmed Memon Prepared By: Group-9 11CE32(G.L) 11CE40(A.G.L) 11CE34 11CE52 11CE108 11CE48

Project QS&E

Embed Size (px)

DESCRIPTION

Quantity estimation

Citation preview

  • Mehran University of Engineering & Technology

    Project: Quantity Estimation & Rate Analysis of Building

    Quantity Surveying & Estimation For Civil Works

    Submitted to Sir Dr. Nafees Ahmed Memon

    Prepared By: Group-9

    11CE32(G.L)

    11CE40(A.G.L)

    11CE34

    11CE52

    11CE108

    11CE48

  • Calculations of Brickwork & other Essential items of R.C.C Framed Building. S.No Particulars of Items No Length(ft) Breadth(ft) Height(ft) Quantity(cuft) Explanatory

    1 Earthwork in Excavation

    in Foundation

    Columns

    In between Columns

    I. Section A wall

    II. Section B wall

    III. Section C wall

    IV. Section D wall

    V. Section E wall

    VI. Outer Verandah

    wall

    VII. Outer bathroom

    wall

    VIII. Separation wall of

    bathroom

    IX. Bathroom at

    corner

    X. Verandah wall

    along garden

    15

    02

    02

    02

    02

    02

    01

    01

    01

    01

    01

    4

    42.84

    8.5

    25.34

    15.33

    10.5

    31.09

    5.16

    5.5

    7.05

    29

    4

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    3.75

    .75

    .75

    .75

    .75

    .75

    .75

    .75

    .75

    .75

    .75

    900

    32.13

    6.375

    19.005

    11.4975

    7.875

    11.658

    1.935

    2.0625

    2.643

    10.875

    1006.056

    2 Lean concrete 1:4:8 in

    Base of column

    15 4 4 .25 60

    3 R.C.C work (1:2:4) in

    Beams ,Columns & Slabs

    Fair Finished excluding

    steel & its bending but

    including its centering,

    shuttering & Binding steel

    Footing of Columns

    Square Bottom

    Trapezoidal

    portion

    Columns

    Plinth Beam &

    Roof Beam

    XI. Section A wall

    XII. Section B wall

    XIII. Section C wall

    XIV. Section D wall

    XV. Section E wall

    XVI. Outer Verandah

    wall

    15

    15

    15

    04

    04

    04

    04

    04

    02

    4

    1.5

    50.34

    12

    12

    31.34

    15.33

    37.34

    4

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    1.667

    13.833

    1.5

    1.5

    1.5

    1.5

    1.5

    1.5

    400.08

    15x10.468

    =157.02

    155.621

    151.02

    36

    36

    94.02

    45.99

    56.01

    Using

    H/6[A1+A2+4AM]

  • XVII. Outer bathroom

    wall

    XVIII. Separation wall of

    bathroom

    XIX. Bathroom at

    corner

    XX. Verandah wall

    along garden

    02

    02

    02

    02

    8.66

    5.5

    9.55

    32

    .5

    .5

    .5

    .5

    1.5

    1.5

    1.5

    1.5

    12.99

    8.25

    14.325

    48

    214.06

    1215.326

    4 Mild Steel including

    Bending in reinforcement

    in R.C.C works

    R.C.C footing @

    0.5%

    R.C.C Column @

    1.5%

    R.C.C Beams@

    1.0%

    218.66q

    1059.75q

    606.05q

    Density of Mild

    steel 78.5q/cum

    557.1x.5/100x78.5q/cum

    5 1st Class Brickwork in (1:6)

    cement mortor

    I. Section A wall

    II. Section B wall

    III. Section C wall

    IV. Section D wall

    V. Section E wall

    VI. Outer Verandah

    wall

    VII. Outer bathroom

    wall

    VIII. Separation wall of

    bathroom

    IX. Bathroom at

    corner

    X. Verandah wall

    along garden

    02

    02

    02

    02

    02

    01

    01

    01

    01

    01

    50.34

    12

    12

    31.34

    15.33

    37.34

    8.66

    5.5

    9.55

    3.2

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    .5

    11.75

    11.75

    11.75

    11.75

    11.75

    11.75

    11.75

    11.75

    11.75

    11.75

    591.495

    141

    141

    368.245

    180.127

    219.37

    50.87

    32.312

    56.10

    18.8

    1799.319

  • 6 Deduction From Brickwork

    Doors

    D1

    D2

    D3

    Special

    Windows

    W1

    W2

    6

    2

    3

    1

    7

    1

    66.36

    14.7

    23.1

    14

    41.16

    5.565

    1799.319-164.885

    =1634.434cuft

    164.885

    7 .06ft thick Plastering

    1:6(Inside)

    Deduction

    1 378.1 10.75 4064.57ft2

    460.11ft2

    Inside means

    inside

    Rooms,kitchen,

    Verandah

    excluding Garden

    & outside

    3586.46 ft2

    8 .06ft thick Plastering

    1:6(outside)

    Deduction

    1 502.06 5617.145 ft2

    304 ft2

    Outside house,

    walls along

    garden& outside

    verandah

    including

    boundary wall

    5312.99 ft2

  • Calculation for Boundary wall

    S.No Particulars of Items No Length(ft) Breadth(ft) Height(ft) Quantity(cuft) Explanatory

    1 Earthwork in Excavation

    in Foundation

    01

    138.61 2 3.75 1039.57 60+50x2-12-

    .5x6-

    6.39=138.61ft

    2 Lean concrete 1:4:8 in

    Foundation

    01 138.61 2 1 277.22

    3 1st class brickwork in

    Foundation & Plinth

    1st footing

    2nd footing

    Wall portion below G.L

    01

    01

    01

    138.61

    138.61

    138.61

    1.5

    1

    0.5

    0.6

    0.6

    3.3

    124.74

    83.16

    228.7

    436.6

    4 1st class brickwork in

    Superstructure

    Wall portion above

    plinth

    01

    138.61

    0.5

    13.75

    952.87

    10+

    +3=13.75

  • P.L

    4'

    4'

    6"1'-6"

    4'

    Plan View of Footing

    3"

    1'-6"

    #4 Bars 6"c/c bothway

    Ties #3 Dia 6" Pitch

    Dowel Bars6 Nos #5 Dia

    Concrete Cover .75"

    Sectional View of Column

    Roof Beam

    Plinth Beam

    1'-6"

    1'-6"G.L

    10'-9"

    3'

    2'-5"

    1'

    1'-2"

    1'-3"

  • Calculation of columns

    S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory

    1

    Earthwork in

    Excavation in

    Foundation

    15 4 4 3.75 900 cuft

    2 Lean concrete 1:4:8

    in Base of column

    15 4 4 .25 60 cuft

    3 R.C.C work 1:2:4 in

    footing

    Excluding steel and

    its bending but

    including centering

    and shuttering and

    binding of steel

    Bottom square

    portion

    Trapezoidal Portion

    Column below

    Ground level

    15

    15

    15

    4

    1.5

    4

    .5

    1.667

    1.33

    400.05 cuft

    157.02 cuft

    14.96 cuft

    H/6[A1+A2+4AM]

    429.97 cuft

    4 R.C.C work 1:2:4 in

    column

    Excluding steel and

    its bending but

    including centering

    and shuttering and

    binding of steel

    Rectangular portion

    below plinth

    Rectangular portion

    above plinth

    15

    15

    1.5

    1.5

    .5

    .5

    1.75

    10.75

    19.68 cuft

    196.87 cuft

    Excluding

    bottom portion

    of G.L

    216.55 cuft

    5 Steel Reinforcing

    bars including

    bending

    #4 Dia bars @.308

    kg/ft in base

    #5Dia dowel bar

    @.48kg/ft

    #3Dia lateral ties

    @0.19kg/ft

    6x15x

    2

    6x15

    29x15

    19890

    1492.57

    1740

    61.26q

    7.16q

    3.30q

    71.72q

  • Abstract of Estimated Cost of columns S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    3

    4

    5

    Earthwork in Excavation in foundation

    Cement Concrete 1:4:8 in Base

    R.C.C work 1:2:4 in footing Excluding steel and its

    bending but including centering and shuttering

    and binding of steel

    R.C.C work 1:2:4 in column above & below G.L

    Excluding steel and its bending but including

    centering and shuttering and binding of steel

    Steel Reinforcements bars including Bending

    900cuft

    60cuft

    429.97cuft

    15+216.55cuft

    =231.55cuft

    71.72q

    7

    93.5

    220

    220

    6500

    cuft

    cuft

    cuft

    cuft

    q

    6300/-

    5610/-

    94593.4/-

    50941/-

    466180/-

    623624.4/-

    Add 5% Contingencies & workcharged Establishment 623624.4+31181.22=654805.62/-

  • 0'-6"

    1'-6"

    12'

    3" 3"

    .75" Concrete cover

    #7 Main bars 4 Nos

    #3 Stirrups

    #5 Top Bars 2 Nos

    #6 Bent up Bars,4Nos

    #7 Main bars 4 Nos

    #3 Stirrups

    #5 Top Bars 2 Nos

    #6 Bent up Bars,4Nos

    X-Section of Beam

    L-Section of Beam

    .75"

  • Calculation of Plinth Beam

    Abstract of Estimated Cost of A Plinth Beam

    S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending

    but including centering and shuttering and

    binding of steel

    Steel bars including bending in R.C.C

    9.375cuft

    97.425kg

    220

    65

    Cuft

    kg

    2062.5/-

    6332.3/-

    8394.8/-

    Now A beam having 12ft clear span has Quantity of 9.375 cuft of R.C.C

    Then for 335.06 Length* it will be 145.9 cuft of concrete.

    Similarly 12ft beam contains 97.425kg of steel

    Then for 186.76ft length it will be 1516.255kg

    *Sum of Total length of Plinth beams.

    S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory

    1 R.C.C work 1:2:4

    Excluding steel and its

    bending but including

    centering and shuttering

    and binding of steel

    01 12.5 .5 1.5 9.375cuft

    2 Steel Reinforcing

    bars(Mild Steel)

    including bending

    Bending in R.C.C Work

    #7 Main Straight Bars

    @.92kg/ft

    #6 Bentup bars @

    .680kg/ft

    #5 Top bars @.48kg/ft

    #3 Stirrups @0.19kg/ft

    @9c/c

    4

    4

    2

    17

    49.24

    48.748

    23.874

    39.66

    45.30kg

    33.14 kg

    11.45 kg

    7.535 kg

    L=T.L-

    2cover+2hooks

    97.425kg

  • Abstract of Estimated Cost of Plinth Beams S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending

    but including centering and shuttering and

    binding of steel

    Steel bars including bending in R.C.C

    261.76 cuft

    1516.255kg

    220

    65

    Cuft

    kg

    57588.43/-

    98556.57/-

    156144.9/-

    Add 5% Contingencies & workcharged Establishment 156144.9+7807.2=163952.1/-

  • Calculation of Roof Beam

    Abstract of Estimated Cost of A Roof Beam

    S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending

    but including centering and shuttering and

    binding of steel

    Steel bars including bending in R.C.C

    9.375cuft

    97.425kg

    220

    65

    Cuft

    kg

    2062.5/-

    6332.3/-

    8394.8/-

    Now A beam having 12ft clear span has Quantity of 9.375 cuft of concrete

    Then for 186.76 Length* it will be 145.9 cuft of concrete.

    Similarly 12ft beam contains 97.425kg of steel

    Then for 186.76ft length it will be 1516.255kg

    *Sum of Total length of Roof beams.

    S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory

    1 R.C.C work 1:2:4

    Excluding steel and its

    bending but including

    centering and shuttering

    and binding of steel

    01 12.5 .5 1.5 9.375cuft

    2 Steel Reinforcing bars

    (Mild Steel) including

    bending Bending in

    R.C.C Work

    #7 Main Straight Bars

    @.92kg/ft

    #6 Bentup bars @

    .680kg/ft

    #5 Top bars @.48kg/ft

    #3 Stirrups @0.19kg/ft

    @9c/c

    4

    4

    2

    17

    49.24

    48.748

    23.874

    39.66

    45.30kg

    33.14 kg

    11.45 kg

    7.535 kg

    L=T.L-

    2cover+2hooks

    97.425kg

  • Abstract of Estimated Cost of Roof Beams S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending

    but including centering and shuttering and

    binding of steel

    Steel bars including bending in R.C.C

    261.76 cuft

    1516.255kg

    220

    65

    Cuft

    kg

    57588.43/-

    98556.57/-

    156144.9/-

    Add 5% Contingencies & workcharged Establishment 156144.9+7807.2=163952.1/-

  • 12'

    3" 3"

    .75" Concrete cover

    #6 Main bars @9"

    #6 Alt.Bent up Bars @9"

    Cross Section of Slab

    .75"

    Plan showing Reinforcement BarsOuter Face of Wall

    5"

    Bottom Dist. BarsTop Dist. Bars

    Straight Main Bar

    Alt Bentup Bar

    #3 Bottom Distribution Bars @9"

    Top Distrib. Bars #3@11"

    15' Clear

  • Calculation of Slab

    S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory

    1

    R.C.C work 1:2:4

    Excluding steel and its

    bending but including

    centering and shuttering

    and binding of steel

    01 12.5 15.5 .416 80.72cuft

    2 Steel Reinforcing bars

    (Mild Steel)including

    bending Bending in

    R.C.C Work

    #6 Main bars @9" @

    0.675kg/ft

    #6 Alt.Bent up Bars @9"

    @ 0.675kg/ft

    Top Distrib. Bars

    #3@11" @ 0.168kg/ft

    #3 Bottom Distribution

    Bars @9 @ 0.168kg/ft

    20

    19

    4

    16

    242.5

    286.18

    21.25

    233

    162.47kg

    193.17kg

    3.57kg

    39.144kg

    398.35kg

  • Abstract of Estimated Cost of Slab S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending but

    including centering and shuttering and binding of

    steel

    Steel bars including bending in R.C.C

    80.72cuft

    398.35kg

    220

    65

    Cuft

    kg

    17758.4/-

    25892.75/-

    43651.15/-

    Now Slab having 12x15 clear span has Quantity of 80.72 cuft of R.C.C

    Then for 1698.16ft2 it will be 760.77 cuft of concrete.

    Similarly 12x15 slab contains 398.35kg of steel

    Then for 1698.16ft2 length it will be 3758.02kg.

    Abstract of Estimated Cost of Slab S.No Name of item & Detail of work Quantity Rate

    Rs.

    Per Amount

    Rs.

    1

    2

    R.C.C work 1:2:4 Excluding steel and its bending but

    including centering and shuttering and binding of

    steel

    Steel bars including bending in R.C.C

    760.77 cuft

    3758.02kg

    220

    65

    Cuft

    kg

    167354/-

    244271.3/-

    411625.3/-

    Add 5% Contingencies & workcharged Establishment 411625.3+20581.25=432206.55/-

  • Rate Analysis for Earthwork in Excavation in Foundation including Filling & up to 30m

    Lead & 1.5m lift

    Take Quantity = 100cum

    Cost of Material : NIL

    S.No Labour NO

    Rate

    Rs

    Total

    1

    2

    3

    4

    Head Mason

    Mazdoor(Helpers)

    Coolie

    Tools &

    Miscellaneous

    no

    20 no

    24no

    650/-

    350/-

    250/-

    325/-

    7000/-

    6000/-

    250/-

    13575/-

    Add 10% contractors profit = 1357.5/-

    So Total will be 14932.5/-

    For 100cum = 14932.5/-

    For 1cum= 149.32/-

    For 1cuft = .

    .=4.228/-

  • Rate analysis for lean concrete (1:4:8) in foundation

    Take quantity = 10cum

    Loose quantity =1.5x10=15cum

    Cement=[(

    )x15]=1.15cum

    F.A=[(

    )x15]=4.61cum

    C.A=[(

    )x15]=9.23cum

    1.15cum of cement

    1 beg of cement =0.035cum

    No of begs of cement =.

    .= 32.8 33begs

    Cost of material

    S.No Particulars Quantity Rate

    Rs/-

    Per Total

    Rs/-

    1

    2

    3

    Cement

    F.A

    C.A

    33Begs

    4.61cum

    9.32cum

    450/-

    300/-

    700/-

    Beg

    Cum

    Cum

    14850/-

    1383/-

    6524/-

    22757/-

    Cost of labour

    S.No

    Labour

    NO

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    4

    5

    Head Mason

    Masons

    Mazdoor(Helpers)

    Coolie

    Tools &

    Miscellaneous(Lump

    sum)

    no

    1.5no

    12no

    18no

    750/-

    600/-

    350/-

    250/-

    375/-

    900/-

    4200/-

    4500/-

    300/-

    10275/-

    Total=Material cost + Labour cost=33032/-

    Add 1.5% water charges = 495.45/-

    Add 10% contractors profit =3303.2/-

    For 10cum=36830.65/-

    For 1cum= 3683/-

    For 1cuft =

    .=104.3/-

  • Rate analysis for R.C.C 1:2:4

    Take quantity = 10cum

    Loose quantity =1.5x10=15cum

    Cement=[(

    )x15]=2.14cum

    F.A=[(

    )x15]=4.28cum

    C.A=[(

    )x15]=8.57cum

    1.15cum of cement

    1 beg of cement =0.035cum

    No of begs of cement =.

    .= 61.22 62begs

    Steel bars @1%=

    x10=0.1cum

    78.5 quintal/cum

    0.1cum steel=78.5x0.1=7.85x100kg=785kg

    Cost of material

    S.No Particulars Quantity Rate

    Rs/-

    Per Total

    Rs/-

    1

    2

    3

    4

    5

    Cement

    F.A

    C.A

    Steel

    Binding wire

    62Begs

    4.28cum

    8.57 cum

    785kg

    1.5kg

    450/-

    300/-

    700/-

    70/-

    75/-

    Beg

    Cum

    Cum

    Kg

    kg

    27900/-

    1284/-

    5999/-

    54950/-

    112.5/-

    90245.5/-

  • Cost of labour

    S.No

    Labour

    NO

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    4

    5

    6

    Head Mason

    Masons

    Mazdoor(Helpers)

    Coolie

    Waterman

    Tools &

    Miscellaneous(Lump

    sum)

    no

    3no

    12no

    20no

    6no

    750/-

    600/-

    350/-

    250/-

    200/-

    375/-

    1800/-

    4200/-

    4500/-

    1200/-

    300/-

    12375/-

    Bending,Cracking & Binding steel

    S.no

    Labour

    No

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    Black smith

    Mazdoor

    Tools & miscellaneous

    8No

    8no

    600/-

    350/-

    4800/

    2800/-

    150/-

    7750/-

  • Centering & Shuttering:

    NO

    Labour

    NO

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    4

    5

    Timber planks(Lump sum)

    Carpenters

    Helpers

    Nails

    T&P

    10NO

    10NO

    550/-

    350/-

    2000/-

    5500/-

    3500/-

    250/-

    150/-

    11400/-

    Total=M.Cost+L.Cost+L for steel Cost+Shuttering=121770/-

    Add 1.5% water charges = 1496.79/-

    Add 10% contractors profit =9978.6/-

    For 10cum=133244.7/-

    For 1cum= 13324.47/-

    For 1cuft =.

    .=377.46/-

  • Rate analysis for 1st class brickwork in Super structure with 1:6 Cement Sand mortar

    Take quantity = 10cum

    30% of dry volume of mortar is required =3cum

    1:6 ratio

    Cement=[(

    )x3]=0.428cum

    Sand=[(

    )x3]=2.57cum

    0.428 cum of cement

    1 beg of cement =0.035cum

    No of begs of cement =.

    .= 12.22 13begs

    Cost of material

    S.No Particulars Quantity Rate

    Rs/-

    Per Total

    Rs/-

    1

    2

    3

    Cement

    Bricks(500 per

    cum)

    Sand

    13Begs

    5000nos

    2.57 cum

    450/-

    7/-

    300/-

    Beg

    Cum

    Cum

    5850/-

    35000/-

    810/-

    41660/-

    Cost of labour

    S.No

    Labour

    NO

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    4

    5

    6

    7

    Head Mason

    Masons

    Mazdoor(Helpers)

    Coolie

    Tools &

    Miscellaneous(Lump

    sum)

    Scaffolding

    Water man

    no

    10 no

    7no

    10no

    2no

    750/-

    600/-

    350/-

    250/-

    250/-

    375/-

    6000/-

    2450/-

    2500/-

    1000/-

    350/-

    500/-

    13175/-

    Total=M.Cost+L.Cost= 54835/-

    Add 1.5% water charges = 822.525/-

    Add 10% contractors profit = 5483.5/-

    For 10 cum= 61141/-

    For 1 cum= 6114.1/-

    For 1 cuft .

    .=173.15/-

  • Rate analysis for (0.06ft) Plastering (1:6)

    Take 100 sq.m

    100x0.012m=1.2cum

    2 cum will be considered

    1:6 Ratio

    Cement=[(

    )x2]=0.0285 cum

    Sand=[(

    )x2]=1.71 cum

    Cost of material

    S.No Particulars Quantity Rate

    Rs/-

    Per Total

    Rs/-

    1

    2

    Cement

    Sand

    9Begs

    1.7cum

    450/-

    700/-

    Beg

    Cum

    4050/-

    1190/-

    5240/-

    Cost of labour

    S.No

    Labour

    NO

    Rate

    Rs/-

    Total

    Rs/-

    1

    2

    3

    4

    5

    Head Mason

    Masons

    Mazdoor(Helpers)

    Scaffolding

    Water man

    1/3 no

    10 no

    15no

    3/4no

    750/-

    600/-

    350/-

    250/-

    250/-

    6000/-

    5250/-

    500/-

    187.5/-

    12187.5/-

    Total=M.Cost+L.Cost=17427.5/-

    Add 1.5% water charges = 261.41/-

    Add 10% contractors profit =1742.7/-

    For 10 cum= 19431.6/-

    For 1 cum= 1943.16/-

    For 1 cuft .

    .=55.03/-

  • Summary of Quantities S.No Discription of items Quantity Cost

    Rs/-

    1 Earthwork in excavation in foundation 2045.6cuft 8648.7/-

    2 Lean concrete 1:4:8 in base of column & footing 337.22cuft 35172.04/-

    3 R.C.C work 1:2:4 in footing 557.02cuft 210252.76/-

    4 R.C.C work 1:2:4 in column 213.51cuft 80587.7/-

    5 Steel reinforcement bars including bending in column 71.72q 466180/-

    6 Quantity of R.C.C Roof beam 261.76cuft 98803.92/-

    7 Quantity of steel in Roof beam 1516.255kg Included

    8 Quantity of R.C.C for slab 760.77cuft 287133.8/-

    9 Quantity of steel for slab 3758.02 kg Included

    10 Masonry work in superstructure 2587.27cuft 447985.8/-

    11 0.06ft Thick Plastering(1:6) 8899.36ft2 489731.78/-

    12 Quantity of R.C.C in plinth beam 261.76cuft 98803.92/-

    13 Quantity of steel in plinth beam 1516.255kg Included

    2223299.52/-

    Plinth Area Rate is .

    =1111.6/-per cuft