Upload
yaseen-ali-shah
View
248
Download
3
Tags:
Embed Size (px)
DESCRIPTION
Quantity estimation
Citation preview
Mehran University of Engineering & Technology
Project: Quantity Estimation & Rate Analysis of Building
Quantity Surveying & Estimation For Civil Works
Submitted to Sir Dr. Nafees Ahmed Memon
Prepared By: Group-9
11CE32(G.L)
11CE40(A.G.L)
11CE34
11CE52
11CE108
11CE48
Calculations of Brickwork & other Essential items of R.C.C Framed Building. S.No Particulars of Items No Length(ft) Breadth(ft) Height(ft) Quantity(cuft) Explanatory
1 Earthwork in Excavation
in Foundation
Columns
In between Columns
I. Section A wall
II. Section B wall
III. Section C wall
IV. Section D wall
V. Section E wall
VI. Outer Verandah
wall
VII. Outer bathroom
wall
VIII. Separation wall of
bathroom
IX. Bathroom at
corner
X. Verandah wall
along garden
15
02
02
02
02
02
01
01
01
01
01
4
42.84
8.5
25.34
15.33
10.5
31.09
5.16
5.5
7.05
29
4
.5
.5
.5
.5
.5
.5
.5
.5
.5
.5
3.75
.75
.75
.75
.75
.75
.75
.75
.75
.75
.75
900
32.13
6.375
19.005
11.4975
7.875
11.658
1.935
2.0625
2.643
10.875
1006.056
2 Lean concrete 1:4:8 in
Base of column
15 4 4 .25 60
3 R.C.C work (1:2:4) in
Beams ,Columns & Slabs
Fair Finished excluding
steel & its bending but
including its centering,
shuttering & Binding steel
Footing of Columns
Square Bottom
Trapezoidal
portion
Columns
Plinth Beam &
Roof Beam
XI. Section A wall
XII. Section B wall
XIII. Section C wall
XIV. Section D wall
XV. Section E wall
XVI. Outer Verandah
wall
15
15
15
04
04
04
04
04
02
4
1.5
50.34
12
12
31.34
15.33
37.34
4
.5
.5
.5
.5
.5
.5
.5
1.667
13.833
1.5
1.5
1.5
1.5
1.5
1.5
400.08
15x10.468
=157.02
155.621
151.02
36
36
94.02
45.99
56.01
Using
H/6[A1+A2+4AM]
XVII. Outer bathroom
wall
XVIII. Separation wall of
bathroom
XIX. Bathroom at
corner
XX. Verandah wall
along garden
02
02
02
02
8.66
5.5
9.55
32
.5
.5
.5
.5
1.5
1.5
1.5
1.5
12.99
8.25
14.325
48
214.06
1215.326
4 Mild Steel including
Bending in reinforcement
in R.C.C works
R.C.C footing @
0.5%
R.C.C Column @
1.5%
R.C.C Beams@
1.0%
218.66q
1059.75q
606.05q
Density of Mild
steel 78.5q/cum
557.1x.5/100x78.5q/cum
5 1st Class Brickwork in (1:6)
cement mortor
I. Section A wall
II. Section B wall
III. Section C wall
IV. Section D wall
V. Section E wall
VI. Outer Verandah
wall
VII. Outer bathroom
wall
VIII. Separation wall of
bathroom
IX. Bathroom at
corner
X. Verandah wall
along garden
02
02
02
02
02
01
01
01
01
01
50.34
12
12
31.34
15.33
37.34
8.66
5.5
9.55
3.2
.5
.5
.5
.5
.5
.5
.5
.5
.5
.5
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
11.75
591.495
141
141
368.245
180.127
219.37
50.87
32.312
56.10
18.8
1799.319
6 Deduction From Brickwork
Doors
D1
D2
D3
Special
Windows
W1
W2
6
2
3
1
7
1
66.36
14.7
23.1
14
41.16
5.565
1799.319-164.885
=1634.434cuft
164.885
7 .06ft thick Plastering
1:6(Inside)
Deduction
1 378.1 10.75 4064.57ft2
460.11ft2
Inside means
inside
Rooms,kitchen,
Verandah
excluding Garden
& outside
3586.46 ft2
8 .06ft thick Plastering
1:6(outside)
Deduction
1 502.06 5617.145 ft2
304 ft2
Outside house,
walls along
garden& outside
verandah
including
boundary wall
5312.99 ft2
Calculation for Boundary wall
S.No Particulars of Items No Length(ft) Breadth(ft) Height(ft) Quantity(cuft) Explanatory
1 Earthwork in Excavation
in Foundation
01
138.61 2 3.75 1039.57 60+50x2-12-
.5x6-
6.39=138.61ft
2 Lean concrete 1:4:8 in
Foundation
01 138.61 2 1 277.22
3 1st class brickwork in
Foundation & Plinth
1st footing
2nd footing
Wall portion below G.L
01
01
01
138.61
138.61
138.61
1.5
1
0.5
0.6
0.6
3.3
124.74
83.16
228.7
436.6
4 1st class brickwork in
Superstructure
Wall portion above
plinth
01
138.61
0.5
13.75
952.87
10+
+3=13.75
P.L
4'
4'
6"1'-6"
4'
Plan View of Footing
3"
1'-6"
#4 Bars 6"c/c bothway
Ties #3 Dia 6" Pitch
Dowel Bars6 Nos #5 Dia
Concrete Cover .75"
Sectional View of Column
Roof Beam
Plinth Beam
1'-6"
1'-6"G.L
10'-9"
3'
2'-5"
1'
1'-2"
1'-3"
Calculation of columns
S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory
1
Earthwork in
Excavation in
Foundation
15 4 4 3.75 900 cuft
2 Lean concrete 1:4:8
in Base of column
15 4 4 .25 60 cuft
3 R.C.C work 1:2:4 in
footing
Excluding steel and
its bending but
including centering
and shuttering and
binding of steel
Bottom square
portion
Trapezoidal Portion
Column below
Ground level
15
15
15
4
1.5
4
.5
1.667
1.33
400.05 cuft
157.02 cuft
14.96 cuft
H/6[A1+A2+4AM]
429.97 cuft
4 R.C.C work 1:2:4 in
column
Excluding steel and
its bending but
including centering
and shuttering and
binding of steel
Rectangular portion
below plinth
Rectangular portion
above plinth
15
15
1.5
1.5
.5
.5
1.75
10.75
19.68 cuft
196.87 cuft
Excluding
bottom portion
of G.L
216.55 cuft
5 Steel Reinforcing
bars including
bending
#4 Dia bars @.308
kg/ft in base
#5Dia dowel bar
@.48kg/ft
#3Dia lateral ties
@0.19kg/ft
6x15x
2
6x15
29x15
19890
1492.57
1740
61.26q
7.16q
3.30q
71.72q
Abstract of Estimated Cost of columns S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
3
4
5
Earthwork in Excavation in foundation
Cement Concrete 1:4:8 in Base
R.C.C work 1:2:4 in footing Excluding steel and its
bending but including centering and shuttering
and binding of steel
R.C.C work 1:2:4 in column above & below G.L
Excluding steel and its bending but including
centering and shuttering and binding of steel
Steel Reinforcements bars including Bending
900cuft
60cuft
429.97cuft
15+216.55cuft
=231.55cuft
71.72q
7
93.5
220
220
6500
cuft
cuft
cuft
cuft
q
6300/-
5610/-
94593.4/-
50941/-
466180/-
623624.4/-
Add 5% Contingencies & workcharged Establishment 623624.4+31181.22=654805.62/-
0'-6"
1'-6"
12'
3" 3"
.75" Concrete cover
#7 Main bars 4 Nos
#3 Stirrups
#5 Top Bars 2 Nos
#6 Bent up Bars,4Nos
#7 Main bars 4 Nos
#3 Stirrups
#5 Top Bars 2 Nos
#6 Bent up Bars,4Nos
X-Section of Beam
L-Section of Beam
.75"
Calculation of Plinth Beam
Abstract of Estimated Cost of A Plinth Beam
S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending
but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C
9.375cuft
97.425kg
220
65
Cuft
kg
2062.5/-
6332.3/-
8394.8/-
Now A beam having 12ft clear span has Quantity of 9.375 cuft of R.C.C
Then for 335.06 Length* it will be 145.9 cuft of concrete.
Similarly 12ft beam contains 97.425kg of steel
Then for 186.76ft length it will be 1516.255kg
*Sum of Total length of Plinth beams.
S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory
1 R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel
01 12.5 .5 1.5 9.375cuft
2 Steel Reinforcing
bars(Mild Steel)
including bending
Bending in R.C.C Work
#7 Main Straight Bars
@.92kg/ft
#6 Bentup bars @
.680kg/ft
#5 Top bars @.48kg/ft
#3 Stirrups @0.19kg/ft
@9c/c
4
4
2
17
49.24
48.748
23.874
39.66
45.30kg
33.14 kg
11.45 kg
7.535 kg
L=T.L-
2cover+2hooks
97.425kg
Abstract of Estimated Cost of Plinth Beams S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending
but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C
261.76 cuft
1516.255kg
220
65
Cuft
kg
57588.43/-
98556.57/-
156144.9/-
Add 5% Contingencies & workcharged Establishment 156144.9+7807.2=163952.1/-
Calculation of Roof Beam
Abstract of Estimated Cost of A Roof Beam
S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending
but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C
9.375cuft
97.425kg
220
65
Cuft
kg
2062.5/-
6332.3/-
8394.8/-
Now A beam having 12ft clear span has Quantity of 9.375 cuft of concrete
Then for 186.76 Length* it will be 145.9 cuft of concrete.
Similarly 12ft beam contains 97.425kg of steel
Then for 186.76ft length it will be 1516.255kg
*Sum of Total length of Roof beams.
S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory
1 R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel
01 12.5 .5 1.5 9.375cuft
2 Steel Reinforcing bars
(Mild Steel) including
bending Bending in
R.C.C Work
#7 Main Straight Bars
@.92kg/ft
#6 Bentup bars @
.680kg/ft
#5 Top bars @.48kg/ft
#3 Stirrups @0.19kg/ft
@9c/c
4
4
2
17
49.24
48.748
23.874
39.66
45.30kg
33.14 kg
11.45 kg
7.535 kg
L=T.L-
2cover+2hooks
97.425kg
Abstract of Estimated Cost of Roof Beams S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending
but including centering and shuttering and
binding of steel
Steel bars including bending in R.C.C
261.76 cuft
1516.255kg
220
65
Cuft
kg
57588.43/-
98556.57/-
156144.9/-
Add 5% Contingencies & workcharged Establishment 156144.9+7807.2=163952.1/-
12'
3" 3"
.75" Concrete cover
#6 Main bars @9"
#6 Alt.Bent up Bars @9"
Cross Section of Slab
.75"
Plan showing Reinforcement BarsOuter Face of Wall
5"
Bottom Dist. BarsTop Dist. Bars
Straight Main Bar
Alt Bentup Bar
#3 Bottom Distribution Bars @9"
Top Distrib. Bars #3@11"
15' Clear
Calculation of Slab
S.No Description of items NO Length(ft) Breadth(ft) Depth(ft) Quantity Explanatory
1
R.C.C work 1:2:4
Excluding steel and its
bending but including
centering and shuttering
and binding of steel
01 12.5 15.5 .416 80.72cuft
2 Steel Reinforcing bars
(Mild Steel)including
bending Bending in
R.C.C Work
#6 Main bars @9" @
0.675kg/ft
#6 Alt.Bent up Bars @9"
@ 0.675kg/ft
Top Distrib. Bars
#3@11" @ 0.168kg/ft
#3 Bottom Distribution
Bars @9 @ 0.168kg/ft
20
19
4
16
242.5
286.18
21.25
233
162.47kg
193.17kg
3.57kg
39.144kg
398.35kg
Abstract of Estimated Cost of Slab S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending but
including centering and shuttering and binding of
steel
Steel bars including bending in R.C.C
80.72cuft
398.35kg
220
65
Cuft
kg
17758.4/-
25892.75/-
43651.15/-
Now Slab having 12x15 clear span has Quantity of 80.72 cuft of R.C.C
Then for 1698.16ft2 it will be 760.77 cuft of concrete.
Similarly 12x15 slab contains 398.35kg of steel
Then for 1698.16ft2 length it will be 3758.02kg.
Abstract of Estimated Cost of Slab S.No Name of item & Detail of work Quantity Rate
Rs.
Per Amount
Rs.
1
2
R.C.C work 1:2:4 Excluding steel and its bending but
including centering and shuttering and binding of
steel
Steel bars including bending in R.C.C
760.77 cuft
3758.02kg
220
65
Cuft
kg
167354/-
244271.3/-
411625.3/-
Add 5% Contingencies & workcharged Establishment 411625.3+20581.25=432206.55/-
Rate Analysis for Earthwork in Excavation in Foundation including Filling & up to 30m
Lead & 1.5m lift
Take Quantity = 100cum
Cost of Material : NIL
S.No Labour NO
Rate
Rs
Total
1
2
3
4
Head Mason
Mazdoor(Helpers)
Coolie
Tools &
Miscellaneous
no
20 no
24no
650/-
350/-
250/-
325/-
7000/-
6000/-
250/-
13575/-
Add 10% contractors profit = 1357.5/-
So Total will be 14932.5/-
For 100cum = 14932.5/-
For 1cum= 149.32/-
For 1cuft = .
.=4.228/-
Rate analysis for lean concrete (1:4:8) in foundation
Take quantity = 10cum
Loose quantity =1.5x10=15cum
Cement=[(
)x15]=1.15cum
F.A=[(
)x15]=4.61cum
C.A=[(
)x15]=9.23cum
1.15cum of cement
1 beg of cement =0.035cum
No of begs of cement =.
.= 32.8 33begs
Cost of material
S.No Particulars Quantity Rate
Rs/-
Per Total
Rs/-
1
2
3
Cement
F.A
C.A
33Begs
4.61cum
9.32cum
450/-
300/-
700/-
Beg
Cum
Cum
14850/-
1383/-
6524/-
22757/-
Cost of labour
S.No
Labour
NO
Rate
Rs/-
Total
Rs/-
1
2
3
4
5
Head Mason
Masons
Mazdoor(Helpers)
Coolie
Tools &
Miscellaneous(Lump
sum)
no
1.5no
12no
18no
750/-
600/-
350/-
250/-
375/-
900/-
4200/-
4500/-
300/-
10275/-
Total=Material cost + Labour cost=33032/-
Add 1.5% water charges = 495.45/-
Add 10% contractors profit =3303.2/-
For 10cum=36830.65/-
For 1cum= 3683/-
For 1cuft =
.=104.3/-
Rate analysis for R.C.C 1:2:4
Take quantity = 10cum
Loose quantity =1.5x10=15cum
Cement=[(
)x15]=2.14cum
F.A=[(
)x15]=4.28cum
C.A=[(
)x15]=8.57cum
1.15cum of cement
1 beg of cement =0.035cum
No of begs of cement =.
.= 61.22 62begs
Steel bars @1%=
x10=0.1cum
78.5 quintal/cum
0.1cum steel=78.5x0.1=7.85x100kg=785kg
Cost of material
S.No Particulars Quantity Rate
Rs/-
Per Total
Rs/-
1
2
3
4
5
Cement
F.A
C.A
Steel
Binding wire
62Begs
4.28cum
8.57 cum
785kg
1.5kg
450/-
300/-
700/-
70/-
75/-
Beg
Cum
Cum
Kg
kg
27900/-
1284/-
5999/-
54950/-
112.5/-
90245.5/-
Cost of labour
S.No
Labour
NO
Rate
Rs/-
Total
Rs/-
1
2
3
4
5
6
Head Mason
Masons
Mazdoor(Helpers)
Coolie
Waterman
Tools &
Miscellaneous(Lump
sum)
no
3no
12no
20no
6no
750/-
600/-
350/-
250/-
200/-
375/-
1800/-
4200/-
4500/-
1200/-
300/-
12375/-
Bending,Cracking & Binding steel
S.no
Labour
No
Rate
Rs/-
Total
Rs/-
1
2
3
Black smith
Mazdoor
Tools & miscellaneous
8No
8no
600/-
350/-
4800/
2800/-
150/-
7750/-
Centering & Shuttering:
NO
Labour
NO
Rate
Rs/-
Total
Rs/-
1
2
3
4
5
Timber planks(Lump sum)
Carpenters
Helpers
Nails
T&P
10NO
10NO
550/-
350/-
2000/-
5500/-
3500/-
250/-
150/-
11400/-
Total=M.Cost+L.Cost+L for steel Cost+Shuttering=121770/-
Add 1.5% water charges = 1496.79/-
Add 10% contractors profit =9978.6/-
For 10cum=133244.7/-
For 1cum= 13324.47/-
For 1cuft =.
.=377.46/-
Rate analysis for 1st class brickwork in Super structure with 1:6 Cement Sand mortar
Take quantity = 10cum
30% of dry volume of mortar is required =3cum
1:6 ratio
Cement=[(
)x3]=0.428cum
Sand=[(
)x3]=2.57cum
0.428 cum of cement
1 beg of cement =0.035cum
No of begs of cement =.
.= 12.22 13begs
Cost of material
S.No Particulars Quantity Rate
Rs/-
Per Total
Rs/-
1
2
3
Cement
Bricks(500 per
cum)
Sand
13Begs
5000nos
2.57 cum
450/-
7/-
300/-
Beg
Cum
Cum
5850/-
35000/-
810/-
41660/-
Cost of labour
S.No
Labour
NO
Rate
Rs/-
Total
Rs/-
1
2
3
4
5
6
7
Head Mason
Masons
Mazdoor(Helpers)
Coolie
Tools &
Miscellaneous(Lump
sum)
Scaffolding
Water man
no
10 no
7no
10no
2no
750/-
600/-
350/-
250/-
250/-
375/-
6000/-
2450/-
2500/-
1000/-
350/-
500/-
13175/-
Total=M.Cost+L.Cost= 54835/-
Add 1.5% water charges = 822.525/-
Add 10% contractors profit = 5483.5/-
For 10 cum= 61141/-
For 1 cum= 6114.1/-
For 1 cuft .
.=173.15/-
Rate analysis for (0.06ft) Plastering (1:6)
Take 100 sq.m
100x0.012m=1.2cum
2 cum will be considered
1:6 Ratio
Cement=[(
)x2]=0.0285 cum
Sand=[(
)x2]=1.71 cum
Cost of material
S.No Particulars Quantity Rate
Rs/-
Per Total
Rs/-
1
2
Cement
Sand
9Begs
1.7cum
450/-
700/-
Beg
Cum
4050/-
1190/-
5240/-
Cost of labour
S.No
Labour
NO
Rate
Rs/-
Total
Rs/-
1
2
3
4
5
Head Mason
Masons
Mazdoor(Helpers)
Scaffolding
Water man
1/3 no
10 no
15no
3/4no
750/-
600/-
350/-
250/-
250/-
6000/-
5250/-
500/-
187.5/-
12187.5/-
Total=M.Cost+L.Cost=17427.5/-
Add 1.5% water charges = 261.41/-
Add 10% contractors profit =1742.7/-
For 10 cum= 19431.6/-
For 1 cum= 1943.16/-
For 1 cuft .
.=55.03/-
Summary of Quantities S.No Discription of items Quantity Cost
Rs/-
1 Earthwork in excavation in foundation 2045.6cuft 8648.7/-
2 Lean concrete 1:4:8 in base of column & footing 337.22cuft 35172.04/-
3 R.C.C work 1:2:4 in footing 557.02cuft 210252.76/-
4 R.C.C work 1:2:4 in column 213.51cuft 80587.7/-
5 Steel reinforcement bars including bending in column 71.72q 466180/-
6 Quantity of R.C.C Roof beam 261.76cuft 98803.92/-
7 Quantity of steel in Roof beam 1516.255kg Included
8 Quantity of R.C.C for slab 760.77cuft 287133.8/-
9 Quantity of steel for slab 3758.02 kg Included
10 Masonry work in superstructure 2587.27cuft 447985.8/-
11 0.06ft Thick Plastering(1:6) 8899.36ft2 489731.78/-
12 Quantity of R.C.C in plinth beam 261.76cuft 98803.92/-
13 Quantity of steel in plinth beam 1516.255kg Included
2223299.52/-
Plinth Area Rate is .
=1111.6/-per cuft