    Due Diligence Plan for the provision of

    Life and pension administration and IT services

    Submitted to

    Lloyds Banking Group

    18 June, 2010

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    2/13

    HCL Technologies

    The Provision of Life and Pension Administration and IT Services

    Lloyds Banking Group

    Version No. : 1.0

    Date : 18 June, 2010

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    3/13

    1. Due Diligence Plan .............................................................................................. 31.1. Project Platform Efficiencies ADM review: ......................................................... 31.2. Project Platform Efficiencies Testing Review: ..................................................... 31.3. Third Party Contracts ........................................................................................... 31.4. HR and Rebadging .............................................................................................. 41.5. Key artifacts to be referenced during DD: ............................................................ 4

    2. Due Diligence Details .......................................................................................... 52.1. Due Diligence Timelines ..................................................................................... 52.2. DD Participants from HCL.................................................................................... 52.3. DD Location ......................................................................................................... 52.4. DD Infrastructure Requirements: ......................................................................... 52.5. Application Development, Maintenance and Testing ............................................ 62.6. Third Party Contracts ........................................................................................... 72.7. HR and Rebadging .............................................................................................. 7

    3. Illustrative Questions ........................................................................................... 83.1. Application Development ..................................................................................... 83.2. Application Maintenance ...................................................................................... 93.3. Testing ............................................................................................................... 103.4. Project Organization Structure, Workflows, Processes ...................................... 113.5. Third Party Contracts ......................................................................................... 113.6. HR and Rebadging ............................................................................................ 11

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    4/13

    3

    1. Due Diligence Plan

    HCL has divided the Due-diligence plan in the following segments:

    1.1. Project Platform Efficiencies ADM review:

    Key Objectives:

    To understand the Application Development and Maintenance strategy, projects, processes, SLAs.

    Also study the impact of integration project to help plan resourcing needs.

    Work Streams:

    For every application within, the HCL DD Team plans to cover the following:

    Functional Understanding

    Application development projects

    Application maintenance and support processes

    3rd Party Arrangements

    Organization Structure, Workflows, Processes

    1.2. Project Platform Efficiencies Testing Review:

    Key Objectives:

    To understand the testing process within the scope of the project

    Work Streams:

    For testing, the HCL DD Team plans to cover the following:

    Testing process followed

    Testing tools and level of automation

    Resources used and required for the future

    Service levels and metrics

    1.3. Third Party Contracts

    Key Objectives:

    To understand the current 3rd party contracts arrangements to ensure a smooth transfer of them to

    HCL. HCL would like to discuss and validate the following:

    List of 3rd

    Party Contracts in Scope

    Financial and Contractual Information

    Key issues

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    5/13

    4

    1.4. HR and Rebadging

    Key Objectives:

    To understand the existing employment contracts, skill-sets, current costs, performance elements,

    and any legal and regulatory issues around re-badging.

    HCL would like to discuss and validate the following if applicable:

    Compensation & Benefits

    HR Principles, Policies & Procedures

    Employment Agreements

    Legal Issues and Aspects

    Human Capital Data & Information

    Visa Details

    1.5. Key artifacts to be referenced during DD:

    The documents that have been referenced to understand the existing assets are listed below:

    High level technical and functional documentation

    Available Process Documentation

    Project Portfolio information

    Available SLA information application wise

    3rd party contracts

    Employee Costs and Health & Welfare Benefits

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    6/13

    5

    2. Due Diligence Details

    The following section describes the expected time lines, the HCL participants and the expectations

    from LBG across various segments.

    2.1. Due Diligence Timelines

    DD Start Date : 28th

    June 2010

    Information Gathering : 28th

    June 16th

    July 2010

    Review and Playback : 12th 16

    thJuly 2010

    BAFO Preparation : 19th 30

    thJuly 2010

    BAFO Submission Date : 30th

    July 2010

    2.2. DD Participants from HCLS. No Participant Area Location

    1. Mike Hogan Bid Director Need Basis

    2. Lynn Phillips Human Resources Need Basis

    3. Arun Albert DD Program Manager Bristol

    4. Sampath Gopalakrishnan LP&I Functional Specialist Bristol

    5. Vikrant Singhai Testing Bristol

    6. Subramaniam Sathakambodi P Systems, TPAM Bristol

    7. Sanjay Kapoor C Systems Aylesbury

    8. Process / CAPSIL Expert TBD Aylesbury

    2.3. DD Location

    The HCL team would be split across the following location based on the availability of LBG SME

    Aylesbury

    Bristol

    2.4. DD Infrastructure Requirements:

    Meeting room with ability to connect laptops

    Telephones

    Access to information via email/ SharePoint (atleast for 1 participant)

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    7/13

    6

    2.5. Application Development, Maintenance and Testing

    Work-stream A: Functional Solution: Coverage and Roadmap Revisit

    Discussion Topics

    Detailed Analysis of closed books business requirements processes of P and C systems. Detailed review of functional components and modules of asset

    Revisit of functional enhancement in flight and under discussion

    Work stream B: Application Development

    Discussion Topics:

    Application integration and migration done in last 18 months and experience sharing Asset

    impact analysis and implementation

    Detailed analysis and review of ADM, Testing (QA & UAT) and RM processes and respective

    environments.

    Detailed review of Prod and DR environment

    In flight projects revisit and categorization

    Application Development Process

    Technology-refresh initiatives in flight or under discussion.

    Work-stream C : Application Support and Maintenance

    Discussion topics:

    Activities and task level analysis for application support and maintenance roles

    Development support cycles

    Location based role and resource mapping

    Tools and utilities used

    Historical data around support and maintenance

    Current Workflow for incidence management, problem management and CR management

    Shifts management, rota and hand-off procedures

    Existing Service Levels and documentation

    Work-stream F: Organization Structure, Workflows, Processes

    Existing Structure

    Roles and Responsibility Definitions

    Managing interfaces with other technology groups

    Monitoring & Reportingbusiness reporting, management reporting

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    8/13

    7

    Work-stream G: Testing Processes

    Activities within the test cycle

    Internal Test Process

    Location based role and resource mapping Tools and utilities used

    Historical data around testing

    Defect Management

    Shifts management, rota and hand-off procedures

    Existing Service Levels and documentation

    Test Artifacts & Metrics

    Automation & Performance

    Tools for automation and allied interests

    Understanding of Estimation for testing projects

    2.6. Third Party Contracts

    Work-stream E: Third Party Management

    Work Deliveries

    Oversight and Governance arrangements

    Licenses and Novation possibilities

    2.7. HR and Rebadging

    HR policy and Rebadging

    Compensation & Benefits

    HR Principles, Policies & Procedures

    Employment Agreements

    Legal Issues and Aspects

    Human Capital Data & Information

    Visa Details

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    9/13

    8

    3. Illustrative Questions

    In this section we have put together a few sample questions across each of the work streams. The

    due-diligence would have detailed list of questions on similar lines for each of the work streams.

    3.1. Application Development

    Functional Understanding

    Objective: To understand the business landscape and roadmap given the closed book scenario to

    ensure that the technology solution is in line with the business objectives.

    Application Development

    Objective: To study the applications and projects currently in progress and proposed

    Some of the categories and few sample questions across them are illustrated below:

    Category DD Questions

    In flight projects

    revisit and

    categorization

    Details of the current enhancements and projects, their current phases, %age

    completion etc.

    What are the current in-flight projects for each of the assets?

    Please provide these key projects attributes

    o What is the current lifecycle stage of the project

    o Release Dates

    o Budget Allocation

    o Current Schedule , Effort , Cost compliance

    o Identified risks ( critical resources , technology risk , business risks etc )

    Activities, task

    level analysis

    and associated

    role mapping

    Revalidate the number of active projects/enhancements planned?

    What are the approved projects/initiatives in pipeline?

    Please provide these key project attributes based on

    o Strategic importance of the project

    o Priority of the project

    o Budgets allocated

    o Planned start / completion dates

    Identified risk ( critical staff , technology risk , business risks etc )

    Study of

    Development,

    Testing, Prod

    environment

    What are the various environments on which this application is deployed and what is

    the underlying H/W ,S/W, OS for these environments

    o Production, Staging, QA, UAT, Development environment

    Numbers of servers used in production for these application.

    Study of Prod and DR environment

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    10/13

    9

    3.2. Application Maintenance

    Objective: To identify details of the current application management practices, baselinedata, details

    on resource loading etc., to understand the financial impact if any.

    Category DD Questions

    Technology

    Overall application architecture, technology, OS etc.

    Please provide the number of instances/versions of this application that are

    installed and are currently being supported.

    Do the applications use any open source frameworks / components?

    Please specify the total number of interfaces to other applications, services or

    systems.

    What is the overall technical complexity of the applications

    What was the peak number of concurrent users for this application? (estimate)

    Peak transaction volume for the applications for a typical business day.

    Please mention if any technological challenges wrt. software, technology used,

    database design

    What is the quality of Inline comments in the source code for application?

    Study of inventory of all applications in P and C systems

    Role &

    Resource

    Mapping

    Where are the current Support FTEs operating from?

    Please rate the expected learning curve for a newly augmented staff.

    Validation of data provided for current employees & contractors

    How do you rate the staffing for maintenance & support for this application?

    Tools and

    utilities used

    What are the program - project management control / tracking tools deployed?

    Are the following processes defined / automated?

    o Configuration Management and Change Request Management

    o Release Management

    o Testing and Defect Tracking

    o Estimation

    o Risk Management

    o Disaster Recovery & Back- up

    Historical

    data around

    support and

    maintenance

    Details on the critical support / maintenance tickets logged in a month.

    Details on the number of adhoc/unplanned requests received in a month.

    Number of planned releases / enhancements in the past 12 months?

    Details of the past data in terms of SLA adherence and various metrics

    Current

    Support and

    Maintenance

    Workflows

    Details on the tools, processes and workflow for current incidence, problem

    management, release management, etc.

    Current effectiveness, issues around these systems, dependencies, feasibility to

    integrate this with HCL systems etc needs to be understood in detail.

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    11/13

    10

    Estimation of FTE required to carry BAU work

    Study of infrastructure in development, testing, production and BC environments.

    Study of various tools used in configuration management, defect tracking,

    document management, testing and build and release management

    Study of security requirements, processes and audit methods

    Shift

    managemen

    t, rota and

    hand-off

    procedures

    Understanding of current shift management and support model

    Details on the current application support team, locations, support hours, roles etc

    % of support resources who are techno functional team

    Skill level distribution of the staff supporting each of the assets

    % of FTEs shared between support, maintenance and development

    Details on the existing hand over procedures

    Existing

    Service

    Levels and

    Documentati

    on

    The service levels, key measurements and onetime deliverables. Study of such

    implementation and trend analysis of metrics

    Expected and minimum service levels for each of the service levels the baseline

    data availability

    Implementation of metrics (service points concept) and associated SLA

    parameters through tools, viz Incident, Problem management, Project

    Management dashboards etc which is currently being used to track SLA

    parameters.

    SLA adherence data for the past 6 months

    Dependencies on SLA measurement and tracking post transition phase :

    Open in flight initiatives on tools implementation and customization for datagathering and reporting

    Integration feasibility analysis with HCL tools like PM Smart, BMC Remedy etc.

    Other than the metrics which are tracked as a part of the SLA parameters, are

    there any other metrics which needs to be tracked and reported?

    Root Cause analysis report on SLA , if there are any

    3.3. Testing

    The questions in this category would comprise of: The types of testing followed

    Structure of testing organization including current offshore team and processes

    Level of automation followed

    Available SLAs for testing

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    12/13

    11

    3.4. Project Organization Structure, Workflows, Processes

    The questions in this category would comprise of:

    Existing Business and Technology Organization Structure

    Roles and Responsibility Definitions

    Managing interfaces with other groups

    How is resource management done effectively based upon resource estimations, including

    team member movement / transition & training?

    How is Stakeholders commitments & issues tracked to closure?

    3.5. Third Party Contracts

    Objective: To identify the 3rd

    Party assets in use and to understand the existing arrangements with

    them. As per available information, 3rd

    Party tools being used by LBG for application management.

    Some of the questions that HCL would like to ask LBG are:

    Operational Level Agreements with vendors for the tools that are being used by LBG

    Governance arrangements, PMO for 3rd

    party tools and applications

    3.6. HR and Rebadging

    Objective: To identify details of the current affected employees to be rebadged and its impact if any

    on the business plan HCL requires the below mentioned details for the in-scope employees:

    Category HR DD Requirements

    Compensation

    and Benefits

    Percentage/Actual amount break up of Annual Cost in terms of Base Salary, Allowances,Benefits, etc.

    Benefit Loading percentage.

    Policy and data on overtime, shift, and call allowances for the last two years.

    Policy and data on all kinds of perquisites being extended to in-scope employees.

    Details of Bonus policy, bonus cycle, actual bonus payout for the last two years,

    applicable bonus, discretionary bonus, fixed bonus, etc.

    Clarification on any bonus data.

    Details of salary increment including last salary increment date and percentage (%)

    increase made.

    Details of long term incentive plans applicable for UK employees

    Employer and Employee % contribution/cost for each of the benefits extended.

    Policies and

    Procedures

    Details of Leave Policy (covering details all kinds of leaves being extended to in-scope

    employees)

    Details of the Severance/ Redundancy policy applicable to UK employees.

    List of in-scope employees who have contractual exceptions to severance/redundancy

    and notice period policy.

    Details of LBG's view on handling severance/redundancy payments for the in-scopeemployees who are being transitioned to HCL.

  • 8/2/2019 Project Platform Efficiencies DD PlanV1.1

    13/13

    12

    Employee Manual/Handbook covering details of all benefits and policies applicable to

    the in-scope group.

    Employment

    Agreement

    Employment Agreement/Employment contracts of in-scope employees.

    Non -disclosure, Non-Compete, Confidentiality agreements applicable to in-scope

    employees.

    Employee

    Representation

    Details of any recognized trade unions and/or work councils operating in the Company

    that cover the in-scope employees.

    Contracts of Agreements with trade unions and/or work councils.

    Legal

    Issues/Aspects

    Details of any outstanding lawsuits, litigations, regulatory investigations, legal claims

    against any in-scope employee.

    Human Capital

    Data &

    Information

    Organization chart including Employee Names, Job descriptions and Vacant Positions

    for the in-scope group/s.

    Details of in-scope employees including Grade, Total and Relevant years of experience,employment type (exempt/non-exempt).

    Details of work hour schedule for UK in-scope employees.

    List of un-availed leaves for each in-scope employee.

    Performance ratings of the in-scope employees for the last two years.