Project Plan forGo2WorkSource.com
Development
Version 7.0
ITSD
Table of ContentsProject Statement......................................................................................2
Project Scope......................................................................................2
Project Goal........................................................................................2
Project Organization..................................................................................3
Project Roles.......................................................................................3
Authorizing Environment......................................................................3
xxxxxx.......................................................................................................4
Project Details...........................................................................................4
Project Assumptions............................................................................4
Project Constraints..............................................................................6
Project Impacts...................................................................................6
Critical Success Factors.......................................................................6
Acquisition Requirements....................................................................7
Work Plan.................................................................................................7
Milestones...........................................................................................7
Development Effort..............................................................................7
Development required activities prior to implementation.........................8
Development testing effort focus..........................................................8
Resource Requirements............................................................................8
Facilities Requirements........................................................................8
Management Controls...............................................................................8
Risk Mitigation.....................................................................................8
Change Management..........................................................................8
Development and Business Meeting Schedule.....................................9
Issue Management..............................................................................9
Appendix A.......................................................................................10
2
Plan Overview
Project Statement
Project Scope
The version 7.0 scope is to:
Increase customer satisfaction by improving usability and responding to customer requests;
Improve the web site’s competitive position by designing, developing and implementing a state of the art web presence meeting or exceeding the industry standard recruitment web site feature sets
Increase efficiency and accountability for staff-mediated Pending List transactions and Central Office administrative functions (Admin Tool).
Complete an infrastructure upgrade (both hardware and software)
defined as the GO2WORKSOURCE.COM application
Project Goal
“The primary goal of the WorkSource Washington web site is to support Washington State employers and job seekers in need of labor exchange services by providing self service access to the WorkSource service delivery system. To achieve this goal, the following objectives have been adopted as guidelines for the Version 7 enhancements:
1. Introduce new features and expand current functionality
Enhance employer and seeker account management features
Provide job and resume saved searches and scouts
Enhance the user interface for improved content and usability
Provide multiple language translation for all content, navigation, resumes and jobs
2. Enhance Pending List and Administration utilities for increased efficiency
Enhance WorkSource Operations staff “Pending List” task by automating routine processes and enhancing their capabilities to support the public.
3. Increase integration of WorkSource with WorkForce Explorer, America’s Job Bank, and Career OneStop”
4. Provide a stable and state of the art website.
Upgrade to .NET Enterprise
Renovate the architectural design of the SQL Server database to support the new technologies of .NET
3
Ensure that personal data security is enforced.
Improve Central Office staff control over static web page data
Establish a methodology to library archived data
5. Improve the WorkSource/SKIES interface
6. Improve the alert and notification processes for the various environments.
7. Reduce maintenance costs
Project Organization
Project Roles
Authorizing Environment
The following resources are intricately involved with the success of the version 7.0 project.
Business Input
Employment & Training Division
Peggy Zimmerman
WorkSource Operations Division
Deanna Bures and Ron Byington
ITSD Julie LeClair and Bob Miller
UI Division Barbara Flaherty
DIS Cammy Webster
4
Field representatives:
Puget Sound Region Paul Christopherson
SouthWest Region Gary Plendl
Cascade East Region Kathy Mertes
West Region Tammy ONeal
Technical input
DIS EBS Windows Support DIS Team
DIS has an internal requirement to rebuild the servers if we use their “Full Meal Deal” room.
IT Architecture team TBD
Possible host for website
IT Infrastructure team Gary Mortenson
Negotiate temporary arrangements of servers
Production Control team Mark Bogaard
Security Accounts for FTP connection
Data Warehouse Reporting team
Julie LeClair
Coordinate understanding of data interface
UI Tax Systems Sam Simpson & Daryl Wright
Scheduled Export of employer data to ftp file
Integrated System Dev & Web Admin
Hal Greenbaum and Jim Job
Fortress mappings
Special Projects & Strategic Planning
Rick Sandler
Budgetary counsel
5
Technical input
LMEA Greg Weeks
WorkForce Explorer data
WorkSource Office Directory Dong Zhang, Xpand Corp (703)742-0900
Web service provider for the 3rd party Offices data
SKIES Reporting Team Julie LeClair
Ensure common understanding of new handling of seeker accounts.
Project Details
Project Assumptions
Two contract Developers
One FTE Developer
Two FTE Business Analyst / Testers
One FTE Project Manager
Dedicated staff (listed above) remains in their current roles
No new service requests into version 6.8 adding functionality.
Project Oversight Committee (POC) has final approval on all changes to scope and schedule.
Change Orders are all subject to the change control process
Built into the schedule the following:
Peer reviews
Code Reviews
Test plan reviews
6
Project Assumptions
The following teams are requiring two weeks notice:
Availability of ESD Networking and Facilities staff as needed.
Availability for communications and coordination with the following teams / groups:
IT Architecture – Possible hosting of web site
IT Infrastructure team – temporary housing of servers
Mercury LoadRunner developer -- expertise
Production Control – Security accounts for FTP of mainframe data
UI Tax Systems – Text file generation of Employer data
Special Projects & Strategic Planning – Budgetary control and assistance
Integrated System Development & Web Administration – support from Access.WA.GOV
Workforce Investment Act / Workforce Development Area – Offices data webservice provided by third party
LMEA – Job & pay information data provider
DIS – Continued support of servers
A new Service Level Agreement with DIS for hosting/support fees of the application and web servers.
Normal availability of DIS support.
New hardware is functional.
IBM Replacement parts will be on site within four hours of notification. (Review of terms is suggested)
Performance and stress testing tools are available.
Little to no production incidents.
LoadRunner scripts developed by Business Analysts
Performance testing coordinated with LAN group
Stress Testing should be coordinated with LAN group at least 2.5 months before.
Project Constraints
Any planned production environment changes will only occur during specified non-business
7
Project Constraints
hour maintenance windows. Every effort will be made to have changes occur between 8 pm to 12 am Saturday or Sunday. Other options for maintenance will be weekdays from midnight to 3 am.
Coordinating 7.0 changes with the SKIES development efforts.
Project Impacts
SKIES -- Code and design changes to SKIES may affect 7.0 scope and design particularly in the interface, Employer and Job order components.
The Data Warehouse reporting system – new concepts for handling seekers with multiple resumes may affect the total number of new seekers count.
UI Employer Tax flat file – New code development and scheduled job to gather Employer Data (required for automatic approval process)
WorkSource Operations – Communication of improved Pending list process changes – training may be required
Fortress 2 – new IP mapping changes
Development Network Infrastructure – temporary housing for WorkSource servers during development
Critical Success Factors
Management of clearly defined and documented change control process.
Effective coordination between all affected business and ITSD units
Active risk management
A sound, methodical approach to design, tuning, testing and documentation
Effective and timely coordination with SKIES.
Acquisition Requirements
Hardware – Already purchased two IBM servers
8
Work Plan
Milestones
Development Effort
All documentation versions will be saved using SourceSafe software. A published version with read access will be found on \\Resource2\WorkSource Website\7.0 Documentation.
Stakeholders sign off the vision and scope document.
Milestone is to have documentation approved and signed off by interested parties. Documentation List:
70_Project_Plan.docchange_control_process.doc (T)changeMatrix.doc (T)Data Retention PolicyGraphical User Interface RequirementsDevelopment Issue Log Risk ManagementSYSTRANLinks Executive SummaryVERSION 7.0 Business Requirements Final 6-12-03Conversion Plan Implementation plan Version 70 Func Spec Admin
Version 70 Func Spec JobsVersion 70 Functional Spec EmployersVersion 70 Functional Spec GenericAppVersion 70 Functional Spec MsgSpecVersion 70 Functional Spec SeekerVersion 7.0 ReportsWorkSource Use AgreementWorkSource Interface Technical Requirements SpecificationsDevelopment Status ReportUse CasesHardware setup and configuration documentationTechnical Specifications
.
Project plan drafted with estimated plan dates – baseline – updates as necessary
Start of the coding effort.
9
Development Effort
Dev Interface data documentation walk through
Test Plan documentation walk through
Conversion plan walkthrough
Development code complete – Version 7.0 Bronze
Documentation of setup configurations – DIS to review with development team.
Conversion plan executed
Implementation plan walkthrough
Testing complete – Version 7.0 Silver
Version 7.0 Golden
Implementation plan executed
Development required activities prior to implementation
Production environment will be developed and tested based upon current user levels factoring in a growth rate of 15% per year for 3 years (45% total). See Appendix A for complete details.
Performance testing scenarios will be developed and executed to establish baseline measurements against the existing application (6.8) and used later to assure performance requirements are met.
Production system performance testing results will document system performance at or better than current performance levels as defined by baseline.
Current alert and notification processes will be documented and utilized.
All production setups, procedures and processes will be documented.
Development testing effort focus
Optimizing hardware and software configurations
Ensuring database integrity and security
Ensuring data integrity throughout conversion process and new functionalities
Successful failover and recovery processes -- Recovery to include the web application and administrative data
Website performance and stress testing
10
Resource Requirements
Facilities Requirements
IBM hardware must have the following requirements met:
Proper electrical access for each type of component. Guaranteed electrical redundancy. Guaranteed network redundancy. Physical space to accommodate all components in a secure environment. SSL certificate (to protect seeker personal data)
Management Controls
Risk Mitigation
TBD – Business Analysts to insert here
Change Management
TBD– Business Analysts to insert here
Development and Business Meeting Schedule
Biweekly team meetings will occur between development and business during development to provide status updates and coordinate upcoming events.
– Business Analysts to insert here
schedule TBD
Issue Management
TBD– Business Analysts to insert here
11
Appendix A
Assume a 15% growth rate per year (45% for 3 years):Go2WorkSource Usage
Total User SessionsEmployer User Sessions
Job SearchesResume Searches
Job ApplicationsReferrals Requested
AdministrationWS Jobs Coded
WS Resumes RejectedWS Job Orders RejectedWS Employers RejectedAJB Employers Rejected
New WS Employer RegistrationsNew AJB Employer Registrations
WS Help Desk CallsFeedback Submittals
Feedback RepliesPending List Referrals ApprovedPending List Referrals Rejected
HoldingsNew WS JobsNew AJB Jobs
New SKIES JobsTotal Active WS JobsTotal Active AJB Jobs
Total Active SKIES JobsTotal Unsuppressed Jobs
Total JobsNew WS Resumes
Total Active WS ResumesWS Employers Posting Jobs
Total WS EmployersNew WS Seeker RegistrationsTotal WS Seekers Registered
User Sessions - GeneralSite Map
WorkSource OfficesUse Agreement
Data Sharing NoticeUser Sessions - Job Seeker
Average Seeker Session TimeContact Us
Help
January 2004421,3269,0371,318,9996,827118,72437,886
2,6121,045735153696417925525522,25413,486
2,3129,2071,8582,6347,5541,56510,18811,7538,60957,6131,03011,9318,29752,977
4,62612,081675237
5:062,8911,797
12