Project Plan
Project Name:PC CleaningFocal Person :Amirul Hariz Bin Yunus
Begin Date: 22 June 2015Target End Date: 19 Sept 2015Final End Date: 30 Sept 2015
Project Scope
Cover 130 desktop computer to be cleaned from virus, unwanted file and malicious software installed by users and resetting new network connection after network migration from Nortel Server to Cisco Server.
Project Result
1) Stop virus from spreading in the system.2) Reduce virus from spreading in the system by removing unwanted files.3) Remove unwanted malicious software that will harm and slow down the system.4) User able to surfing internet without any interruption by network problems.
Project Impact
Extend the lifetime for each PC to work properly.
Project Challenges
1) Time constraint due to administrative task to be completed during non-counter hours.2) Delay / difficult to obtain fast approval for any changes from respective Department. 3) Each PC has unique problems.4) Unstable network.
Project Effort
1) Liaise with focal person for computer handled by ITMS to get new windows image for cleaning process.
Project Task Overview
Number Of PC: LEVEL G 18 Units LEVEL 1 31 Units LEVEL 2 61 Units LEVEL 3 20 Units
Task: 1) Removing unwanted files2) Remove activated virus3) Remove malicious software4) Setting new network configuration5) Installing Desktop Freezing Tools (Toolwiz Freeware)6) Installing new windows image.
Duration: 3 Months (13 Weeks) | 22 June 2015 to 19 September 2015
Project Timeline
LOCATIONWEEK
12345678910111213
LEVEL GOPAC
E-Resources
LEVEL1PG Lounge
IT Zone 1A
Carrel PC
LEVEL2IT Zone 2A
IT Zone 2B
Carrel PC
LEVEL 3IT Training Zone
Carrel PC