enerMENA Project: Practical steps towards “Electricity from the desert”
www.dlr.de/enermena
Project Overview
Qoaider, Heller, Röger, Eck, Fend
13. Kölner Sonnenkolloquium Slide 2 www.dlr.de/enerMENA30. Juni 2010
enerMENA Project
Overall ObjectiveSustainable implementation of solar power plant technology in MENA region
Coordination: DLRDuration: 09/2009-12/2011Financed by: German Federal
Foreign Ministry
DESERTEC ConceptTechnical support in CSP Technology for MENA Countries
Partners: Jordan, Egypt, Tunisia, Algeria & Morocco
13. Kölner Sonnenkolloquium Slide 3 www.dlr.de/enerMENA30. Juni 2010
Background –
CSP implementation in MENA
Ambitious plans for CSP project but insufficient technical capacities:Existing plans to construct several large scale CSP power plants,Poor know-how level and limited technical capacities, Local participation is very limited,
Leads to unsustainable and slowing down of the development process as well as cause avoidable costs.
Creation of strong human capacity base will:Sustain the market and technology development,Support approaching the power generation targets, Cost reduction,Social dimensions.
13. Kölner Sonnenkolloquium Slide 4 www.dlr.de/enerMENA30. Juni 2010
Identified deficiencies
Public awareness to think greenInsufficient manpower to realize CSP projectsReliable and accurate solar resources data for project development purposesSkilled personnel to perform:
Project planningYield prognosisOperation and maintenance (O&M) of solar power plantsQuality Control of the power plant components
Optimization of optical efficiency of the collectorsOptimization of thermal efficiency of the power plant
13. Kölner Sonnenkolloquium Slide 5 www.dlr.de/enerMENA30. Juni 2010
Why is the quality control of a CSP power plant so important?
High investment costs of solar plants bear higher risks than conventional plants
Conventional Power Plant: Low Investment Costs, High Fuel Costs (Payments during the production phase)Solar Thermal Power Plant: High Investment Costs, No Fuel Costs (Investment at the beginning of the production phase)
A low-quality solar field affects project profitability strongly10-15% of solar field efficiency can be easily lost or gained
Solar fields are of big extentCorrection of assembly errors are expensive
Solar fields are a long-term investmentEach percent point contributes to profitability over more than 20 years
13. Kölner Sonnenkolloquium Slide 6 www.dlr.de/enerMENA30. Juni 2010
Objectives of enerMENA
Capacity Building
and Optimization
Targeted support
- Establish local technical capacities- Long term support of the established teams
- Transfer of CSP technology to educational and professional institutions- Support establishing skilled manpower for the CSP market
- Create a network of high precise meteorological stations in MENA region- Long term dissemination of information for scientific and development purposes
Transfer of Expert Knowledge – Advanced CSP teaching materials
Dissemination of information and Support of market development
13. Kölner Sonnenkolloquium Slide 7 www.dlr.de/enerMENA30. Juni 2010
Module 1
Module 3
Module 2
Capacity Building and Optimization
Dissemination and Support
Transfer of Expert Knowledge
R&D EPC ContractorsO&M companies
Academics in NetworksUniversities,High SchoolsVocational Training Centers
Project Developers,Utilities,Decision Makers,R&D
13. Kölner Sonnenkolloquium Slide 8 www.dlr.de/enerMENA30. Juni 2010
Module 1: Capacity
Building
eM-CB01
4-week intensive course at PSA, Spain
eM-CB02
Joint measurement campaign at CSP site
Upgrade Optical Efficiency
eM-CB03
Joint measurement campaign at CSP site
Upgrade Thermal Efficiency
Regional closing
Workshops
Q3 - 2010
Q1 & Q2 - 2011
Q3 - 2011
Technical Staff for CSP Plant Quality Control
Organization of advanced training courses:• Establish capable technical staffs to ensure the quality of CSP plants & knowledge multiplication. • Theoretical and practical modules for project planning, yield prognosis and efficiency upgrading. • Commitment for long term technical support by DLR.
13. Kölner Sonnenkolloquium Slide 9 www.dlr.de/enerMENA30. Juni 2010
Hardware and Training
Mobile Laboratory One mobile laboratory for each partner countryMechanical and electronic devices
Optical qualification of solar collectors “Photogrammetry”Evaluation of thermal characteristics of solar fields
Training to use this equipmenteM-CB01 at the PSA / SpainPossible candidates:
Foremen and engineers of construction sitesPersons playing a key role in the multiplication of know- how
Targeted announcement on enerMENA website
13. Kölner Sonnenkolloquium Slide 10 www.dlr.de/enerMENA30. Juni 2010
Measurements during construction
Close-Range PhotogrammetryMeasurement of 3D coordinates (accuracy <0.2 mm)Equipment: Digital Camera, Targets, PC, SoftwareApplication for parabolic trough and central receiver plants:
Collector steel structure shapeCollector surface, deformation analysisAxis and receiver position relative to parabola (trough)Validation of jigs for collector assembly
Measurement of Mechanical Collector PropertiesTorsion stiffness of HCE support and torque boxEquipment: Force-meter and inclinometers
13. Kölner Sonnenkolloquium Slide 11 www.dlr.de/enerMENA30. Juni 2010
Measurements during construction
Deflectometry
Measurements (TARMES)Spatial measurement of concentrator slopes (accuracy <1 mrad)Equipment: Digital Camera, PC, SoftwareAllows final check of the optical quality of completely mounted concentrators with influence of all components, including errors of structure, facets, facet mounting, transport, installation, gravity, etc.Allows checks of optical quality of solar field after some years of operation, after wind storms, etc. Serves as input data for raytracing simulations, which calculate the intercept factor
13. Kölner Sonnenkolloquium Slide 12 www.dlr.de/enerMENA30. Juni 2010
Measurements during operation: Thermal Performance
energy balance
Tflow
T T
network interface & management
local data logger
Twind
θ
Mobile Field LaboratoryNon-intrusive, No leakage hazardNo interference with plant operationLittle mounting effort
Measuring / MonitoringIrradiance (DNI, GHI, DHI)Wind, ambient temperatureHeat transfer fluid (HTF) flow rateInlet and Outlet HTF temperatureMirror cleanliness and Tracking
13. Kölner Sonnenkolloquium Slide 13 www.dlr.de/enerMENA30. Juni 2010
Measurements during operation: Thermal Performance
ResultsThermal characterization and qualification of loops/fieldPerformance evaluation and demonstration
Solar Resource
Temperature and Flow Rates at Inlet and Outlet
13. Kölner Sonnenkolloquium Slide 14 www.dlr.de/enerMENA30. Juni 2010
Module 2: Transfer of Expert Knowledge: Overview
Working force for CSP developmentPreparation of CSP teaching materials, Orientation Workshop 27 – 28.05.2010 in Cologne Support during the implementation (model university in each country)Workshops for professors, teachers and trainers.
Cooperation with:Education institutions in five MENA countriesUni KasselSolar-Institute Jülich (SIJ)
13. Kölner Sonnenkolloquium Slide 15 www.dlr.de/enerMENA30. Juni 2010
Transfer of Expert Knowledge: Concept
University module
advanced training for employees
Vocational Training School
module
High School/ College module
CSP companies define requested qualification of
future employees
enerMENA prepares advanced CSP lectures and supports the implementation
R&D institutions provide CSP knowledge
Result: Qualified manpower and awareness for CSP
13. Kölner Sonnenkolloquium Slide 16 www.dlr.de/enerMENA30. Juni 2010
Structural approach of CSP teaching materials
CSP
Grid Integration
Technologies
Opticaland Thermo-Dynamical
Basics
IntroductionSolar
Radiation
Economics
Site Criteria/Site
assessment
Social, Economical
and Legal Con-siderations
Maintenance and Operation
CSP Plantsworldwide: successive
update
technicaleconomical
13. Kölner Sonnenkolloquium Slide 17 www.dlr.de/enerMENA30. Juni 2010
Module 3: Dissemination and Support
Development of project planning methodology
Precise determination of local solar resource
Network of eight precision meteorological stations to provide data with highest reliability to support satellite data
Establishing of local contact points for long term support by DLR experts
Establishing of project office in Germany to communicate with contact points
Support of market development
13. Kölner Sonnenkolloquium Slide 18 www.dlr.de/enerMENA30. Juni 2010
Development of project planning methodology
Development of project planning materials with industrial consultancy partnerAnalysis of the relevant project types in the partner countries Definition of the local share during the planning and construction phases Development of Capacity Building material
Revenue forecast for CSP Plants Development of revenue forecasts for two reference plants (Andasol & ISCCS)Definition of a structured methodologyPreparation of Capacity Building materials
Preparation and upgrading of a simulation softwareAdjustment/Extension of Greenius SoftwareIntegration of the meteorological data of MENA in the programsPreparation of Documentation
13. Kölner Sonnenkolloquium Slide 19 www.dlr.de/enerMENA30. Juni 2010
Precise determination of local solar resource
Network of high-precision meteorological stations for solar resource assessment
Eight high precise measurement of DNI, global and diffuse irradiance Deviation only between 1 and 2%Measurement of relative humidity, air temperature and barometric pressureMeasurement of wind speed and direction at 10m heightAutomatic Data Retrieval (via GSM) and Processing
Maintenance personnel for regular (daily) cleaning and 230V~ power supply required
Establish a reliable meteorological database for the MENA regionSupport network of Rotating Shadowband Pyranometer (RSP) and satellite data
13. Kölner Sonnenkolloquium Slide 20 www.dlr.de/enerMENA30. Juni 2010
Sites of the high precision meteorological stations
High Precision Meteorological Station to support CSP development
13. Kölner Sonnenkolloquium Slide 21 www.dlr.de/enerMENA30. Juni 2010
Status
Stakeholders’ and activities’ AnalysisRegional networkingPartners identified and cooperation agreements signedCapacity building courses in preparation (materials & Equipment)Mobile laboratories availablePreparation of CSP teaching materials in progressReviewing panel established during the Orientation WorkshopHigh precision meteorological stations to be installed nextSites for meteorological stations are definedContact points in start-up phase
13. Kölner Sonnenkolloquium Slide 22 www.dlr.de/enerMENA30. Juni 2010
Dr. –Ing. Louy Qoaider, German Aerospace Center, Institute of Technical
Thermodynamics, Solar Research Plataforma
Solar de Almeria, Spain, ([email protected]) +34-950-278817, www.dlr.de/enermena