ES-1

Project Name Central Florida Freight Corridor (US

27/SR 60) Multimodal Mobility Enhancement Improvements

Was a FASTLANE application for this project submitted previously?

No

If yes, what was the name of the project in the previous application?

N/A

Previously Incurred Project Cost $0

Future Eligible Project Cost $100,597,380

Total Project Cost $170,504,033

FASTLANE Request $100,597,380

Total Federal Funding (including FASTLANE) $100,597,380

Are matching funds restricted to a specific project component? If so, which one?

No

Is the project or a portion of the project currently located on National Highway Freight Network?

US 27 portions of application are awaiting FHWA approval for CRFC/CUFC designation

Is the project or a portion of the project located on the NHS?

Does the project add capacity to the Interstate system?

Is the project in a national scenic area?

Yes

Yes

No

Do the project components include a railway-highway grade crossing or grade separation project?

If so, please include the grade crossing ID.

Yes

# 625419N

Do the project components include an intermodal or freight rail project, or freight project within the boundaries of a public or private freight rail, water (including ports), or intermodal facility?

No

If answered yes to either of the two component questions above, how much of requested FASTLANE funds will be spent on each of these projects components?

$57,475,095 for grade crossing separation

State(s) in which project is located Florida

Small or large project Large

Urbanized Area in which project is located, if applicable Portion of the project (less than 50%) is in Winter Haven, FL Urbanized Area

Population of Urbanized Area 201,289

Is the project currently programmed in the:

TIP

STIP

MPO Long Range Transportation Plan

State Long Range Transportation Plan

State Freight Plan?

The project components are in Florida’s State Transportation Improvement Program (STIP), the FDOT District One Adopted Five-Year Work Program Projects, and the Polk Transportation Planning Organization’s Long-Range Transportation Plan (LRTP), the State Freight Plan (2014) and in District One Freight Needs Assessment from 2015.

Page 3: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

i

Contents

1.0 Project Description.............................................................................................. 1

1.1 Overview ............................................................................................................ 1

Significance ............................................................................................................... 5

Expected Users ......................................................................................................... 8

Transportation Challenges and Solutions .................................................................. 9

2.0 Project Location ................................................................................................ 11

3.0 Project Parties ................................................................................................... 12

4.0 Grant Funds and Sources and Uses of Project Funds ................................... 14

5.0 Merit Criteria ...................................................................................................... 16

5.1 Economic Outcomes ........................................................................................ 16

5.2 Mobility Outcomes ............................................................................................ 17

5.3 Safety Outcomes .............................................................................................. 18

5.4 Community and Environmental Outcomes ....................................................... 18

5.5 Partnership and Innovation .............................................................................. 19

5.6 Cost Share ....................................................................................................... 19

6.0 Large Project Requirements ............................................................................. 19

7.0 Cost Effectiveness ............................................................................................ 21

8.0 Project Readiness ............................................................................................. 23

8.1 Technical Feasibility ......................................................................................... 23

8.2 Project Schedule .............................................................................................. 24

8.3 Required Approvals .......................................................................................... 25

Environmental Reviews and Approvals ................................................................... 25

State and Local Planning and Approvals ................................................................. 25

8.4 Project Risks and Mitigation Strategies ............................................................ 25

9.0 Project’s FASTLANE Website .......................................................................... 25

Page 4: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

ii

List of Figures

Figure 1: US 27 and SR 60 in Relation to Southeast Interstates and US Highways ....... 6

Figure 2: International Distribution of Goods through Florida Customs Districts ............. 7

Figure 3: Project Location in Relation to Annual Freight Tonnage by Mode .................... 8

Figure 4: Project Location ............................................................................................. 11

Figure 5: Article from the Lakeland Ledger with Photo of Overpass Damage ............... 18

Figure 6: Project Schedule ............................................................................................ 24

List of Tables

Table 1: Transportation Challenges and Solutions Provided by the Central Florida

Freight Corridor (US 27/SR 60) Multimodal Mobility Enhancement

Improvements ................................................................................................. 9

Table 2: Population Statistics for Central Florida MSAs .............................................. 12

Table 3: Listing of Letters of Support ........................................................................... 14

Table 4: Funding Sources and Uses for Central Florida Freight Corridor

(US 27/SR 60) Multimodal Mobility Enhancement Improvements ................. 15

Table 5: Large Project Requirements .......................................................................... 19

Table 6: Cost Effectiveness Analysis Summary Result – Full Project .......................... 21

Table 7: Overall Results of the Benefit Cost Analysis for the Full Project

(Millions of 2016 Dollars) ............................................................................... 22

Table 8: Cost Effectiveness Analysis Summary Result – US 27/SR 60 Interchange

and US 27 Widening Only ............................................................................. 22

Table 9: Cost Effectiveness Analysis Summary Result – SR 60 At-Grade

Separation Crossing Only ............................................................................. 23

Page 5: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

1

1.0 Project Description

1.1 Overview

The Central Florida Freight Corridor Multimodal Mobility Enhancement Improvements

will upgrade a critical freight junction for the State of Florida currently hampered by

safety issues and future capacity constraints. This multi-component project enhances

and improves multimodal mobility at and around this critical freight junction by modifying

an inefficient interchange configuration to a Single Point Urban Interchange (SPUI) at

US 27/SR 60, separating the at-grade rail crossing on SR 60 four miles west of the

interchange, and widening a 5-mile section of US 27 leading into the interchange from 4

to 6 lanes so as to accommodate the significant increases in truck volume. These

improvements will facilitate more efficient movements providing for quicker and safer

truck travel, reduce crashes, eliminate train crossing delays, and increase overall

capacity where two important freight corridors cross and connect the three largest

metropolitan areas of the state, Tampa-Orlando-Miami.

The north-south US 27 and east-west SR 60 highways are integral to trade and

shipping within and outside of Florida. US 27, the #1 trucking route in the State per the

Florida Trucking Association,

is a major regional route for

goods shipment and vital link

between Miami north through

central Florida and beyond. SR

60 is one of the highest

volume coast-to-coast routes

in the State, carrying

significant amounts of freight

between two of the state’s

largest cities, Tampa and

Orlando. Both highways are

part of the State’s Strategic

Intermodal System (SIS), the state’s network of high priority transportation facilities and

are designated hurricane evacuation routes. In September 2016, US 27 was submitted

for designation as a Critical Rural/Urban Freight Corridor.

Both highways are integral to the State’s economy, mobility, and residents’ safety. But

their efficiency is currently hampered by an inefficient partial cloverleaf interchange

configuration with an accident rate higher than the state average for similar facilities, an

overpass which is too low for some trucks, and a nearby at-grade rail crossing with

more than a dozen train crossings per day.

Page 6: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

2

To address these issues, The Central Florida Freight Corridor Multimodal Mobility

Enhancement Improvements will:

• Modify the current interchange configuration to a Single Point Urban Interchange

(SPUI) at US 27/SR 60;

• Separate the at-grade rail crossing on SR 60;

• Widen the existing US 27 highway leading into US 27/SR 60 Interchange from 4

to 6 lanes to accommodate the expected significant increases in truck volume.

While all parts of Central Florida Freight Corridor Multimodal Mobility Enhancement

Improvements Project are critical needs for the state and the region, the need

interchange improvements are the most immediately pressing, followed by the rail

crossing separation.

US 27 / SR 60 Interchange and US 27 Widening

US 27 is one of the state’s most important freight routes and is considered the spine of

Florida’s freight transportation. Significant increases in traffic volumes are forecasted

along US 27 in Polk County, and it is

projected to reach or exceed capacity by

2040 (US 27 Transportation Alternatives, US

27 Purpose and Need Technical

Memorandum, February 2016, Florida

Department of Transportation District One,

at http://www.US 27polk.com/images/reports/US

27_Purp-n-Need_TM_FHWA_Responses.pdf .)

Currently, the US 27 / SR 60 Interchange is

a partial cloverleaf. It experiences a high

percentage of truck traffic, which causes

congestion on the interchange ramps; it has

no traffic signals for the ramps; and,

experiences a higher crash rate than the

national average (US 27 Purpose and Need

Technical Memorandum).

The interchange’s on and off ramps are

currently inadequate to meet the current

demand. The US 27 northbound and the SR

60 eastbound on ramps are currently operating at Level of Service (LOS) F in both am

and pm. The US 27 southbound and the SR 60 eastbound off ramps are currently

Page 7: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

3

operating at LOS F in am and at LOS D in pm. Both are projected to operate at LOS F

with significant delays by 2040 (US 27 Purpose and Need Technical Memorandum).

The Central Florida Freight Corridor Multimodal Mobility Enhancement Improvements

will replace this inadequate interchange with a single point interchange, similar to a

diamond interchange except the two ramp intersections at US 27 are combined into a

single signalized intersection.

Additional improvements to US 27 will specifically cater to the high percentage of heavy

truck traffic on the highways (upwards of 20% trucks) by creating “truck loons” (paved

areas beside the road that allow for wide turns at crossovers) and ramps that allow for a

wide turning radius on US 27, enabling less restrictive turning movements. In addition,

concrete will be used extensively in the improved interchange due to the high volume of

trucks through this location, and will extend the life cycle of the interchange. The project

will also create more clearance under the overpass to mitigate trucks hitting the bridge,

and, thus, facilitate improved traffic flow.

To support traffic as it passes through the interchange, this project will also expand a

portion of US 27 from south of Presidents Drive to north of SR 60 in Lake Wales, a

distance of approximately 5.25 miles. The expansion will create three 12-foot lanes in

each direction separated by a 40-foot grass median, paved outside shoulders to

accommodate bicyclists, and five-foot sidewalks on both sides near the outside travel

lanes. These improvements will increase traffic capacity of the road, improve safety,

and provide for future transportation demand. The Polk Transportation Planning

Organization (TPO) includes six-laning this portion of US 27 as a feasible project in the

county’s LRTP.

Page 8: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

4

SR 60/At-Grade Rail Crossing Separation

Currently, SR 60 is a four-lane divided roadway with a posted speed of 65 mph and a

40-foot depressed grass median. SR 60 intersects CSX Railroad at grade crossing #

625419-N at Roadway Milepost 25.544 and Railway Milepost SX 834.53, approximately

four miles west of the US 27/ SR 60 Interchange in Lake Wales, FL. In 2015, existing

traffic volumes reached over 23,000 daily vehicles near this crossing.

The grade separation for

SR 60 comprises three pairs of

bridges, one carrying the

SR 60 roadway over the Peace

Creek Drainage Canal, one for

a driveway and gas line, and

one for the CSX Railroad. The

planned roadway includes two

12-foot lanes in each direction with retaining walls approaching the bridges over the

railroad. The lanes will be separated by a 24-foot median that includes 10-foot paved

shoulders and a barrier wall. Ten-foot paved outside shoulders will include seven-foot

buffered bicycle lanes and sidewalks. Additional pavement will be constructed to

accommodate future widening of SR 60 to six lanes. Two-way, two-lane frontage roads

will also be provided in the northwest, southwest, and northeast quadrants of SR 60 and

the CSX Railroad to restore access to the properties and businesses disconnected from

grade separating SR 60.

The grade separation is needed to improve safety for trucks, cars, school buses and

trains by separating train and vehicle traffic (PD&E study of SR 60 and At-grade Rail

Crossing). The project will improve safety not only during train crossings, but whenever

schools buses or trucks carrying hazardous materials pass, since they must all stop at

the crossing and wait at least 3 seconds, regardless of a train’s presence. These stops

can lead to rear-end collisions from other vehicles traveling on this 65-mph roadway.

Page 9: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

5

Additional benefits of this component are reductions in travel delays, train/vehicle

conflicts, and vehicle/vehicle conflicts by removing the need to stop traffic for trains, and

safely accommodating future traffic growth. Future benefits of this improvement would

be the ability to expand the rail line from one to two tracks, when the nearby Central

Florida Intermodal Logistics Center (ILC) in Winter Haven expands.

Implementing these improvements to the interchange, multimodal crossing, and

highway facilitates safer and more efficient truck travel, reduces crashes, eliminates

train crossing delays, and increases the overall capacity of this integral freight junction

along the spine of Florida serving the three largest metropolitan areas of the State,

Tampa-Orlando-Miami.

Significance

Freight continues to grow in Florida, increasing the demand for transportation

infrastructure improvements. Currently, over 762 million tons of freight moves

throughout Florida annually. By 2040, FHWA estimates that Florida’s transportation

system will be moving an estimated $2.5 trillion worth of cargo, predominantly freight by

truck through and out of the state.

As noted previously, both US 27 and SR 60 are designated as SIS Highways. Florida’s

SIS program, established in 2003, is a high priority network of those transportation

facilities in the state which are most significant for interregional, interstate, and

international travel. These significant corridors connect all of Florida's economic regions,

including economic markets beyond Florida. Within the state, they facilitate the

movement of passengers and goods between the major airports, seaports, rail facilities,

and notable intermodal hubs. Figure 1 illustrates the significance of both roadways.

US 27 is a major corridor from Miami up through the central Florida, west to

Tallahassee and further north through Chattanooga, Tennessee; Lexington, Kentucky;

Page 10: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

6

Cincinnati, Ohio; and ending at Fort Wayne, Indiana. In 2015, US 27 carried an

estimated 3,100 to 3,700 trucks per day south and north of the interchange with SR 60,

which is approximately 13% of total traffic. Overall traffic along US 27 just south of the

interchange is expected to increase from 29,000 in 2015 to 52,800 in 2040. SR 60 is

one of Florida’s major east-west corridors, and carries even more trucks than US 27 at

their crossing. In 2015, approximately 4,200 trucks per day traveled on SR 60 west of

the interchange with US 27, which was more than 20% of total traffic on the roadway.

Both highways are critical to local industry and freight. Manufacturing, warehousing,

distribution, and Third Party Logistics (3PL) are key industries in the region. Polk

County is home to

19,800,000 sq. feet of

manufacturing and

50,300,000 sq. feet of

warehousing and

distribution (Florida

Department of

Transportation District One,

Freight Mobility & Trade

Plan 2016).

US 27 and SR 60 are

located in the heart of

Florida’s $10.7 billion citrus

industry – Florida’s Natural,

Minute Maid, and Simply

Orange package their juice

at one of Polk County’s five

citrus processing plants

before shipping them out

across the country. Almost

all of the citrus harvested in

Polk, Hardee, Highlands,

Okeechobee, and Glades

Counties and nearly half of

the citrus harvested in Hendry and Collier Counties is shipped into Polk County for

processing. During the 2014-2015 harvest year, an estimated 99,000 citrus truck

shipments traveled to the citrus processing plants in Polk County, all of them traveling

on US 27 and many using SR 60 as well. Other agriculture also flourishes in the area,

including cattle, vegetables, and other fruits. Approximately 25 miles to the northwest of

Figure 1: US 27 and SR 60 in Relation to Southeast Interstates and

US Highways

Page 11: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

7

the US 27/SR 60 Interchange is the Cattlemen's Livestock Auction in Lakeland.

Together with the livestock markets in Okeechobee (in neighboring Okeechobee

County) and Arcadia (in DeSoto County), approximately 220,000 head of cattle were

sold at auction in the area during 2015, valued at $212.3 million. Much of the cattle

going to or from these markets traveled on US 27 and SR 60.

The Central Florida ILC, managed by CSX Transportation, is a centralized hub for

transportation, logistics, and distribution serving

Tampa, Orlando, and Southern Florida, and is

situated just 2 miles off SR 60, west of the US 27

Interchange. It is jointly served by SR 60 and US 27,

which provide the vital transportation links necessary

to ensure the efficient movement of goods and

services through the state and nation-wide

multimodal network. The Central Florida ILC is the

largest master-planned inland port in Florida,

surrounded by 930 acres being developed for

manufacturing and distribution facilities. Freight flows

to and from this facility towards Atlanta, New York, Chicago, Detroit, San Francisco, and

Los Angeles, and other major metropolitan regions in the US.

As the Florida Chamber of Commerce notes, Florida is a crossroad for international

trade, not just domestic shipments. Figure 2 indicates the distribution of international

goods through Florida. Figure 3 shows that US 27 and SR 60 are on key routes for

freight traveling from southern and central Florida north to the rest of the nation. With

the widening of the Panama

Canal and development of

South American and

Caribbean economies, Florida

can expect to see continued

increases in freight activity at

major ports, including Tampa,

Orlando, and Miami – three

corners of the US 27 and SR

60 freight corridors that

converge in the project area.

“Today, nearly all of the trucks accessing

the ILC for inbound and outbound trips

use SR60 and US27. Seamless

connectivity between these

transportation facilities is critical to

economic development and freight

mobility throughout Florida.”

Louis Renjel, Jr., Vice President, Strategic

Infrastructure Initiatives, CSX

Transportation

Figure 2: International Distribution of Goods through

Florida Customs Districts

Page 12: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

8

Expected Users

Direct beneficiaries of the Central Florida Freight Corridor Multimodal Mobility

Enhancement Improvements will be the businesses and communities on or near these

segments of US 27 and SR 60. Currently, approximately 29,000 vehicles per day travel

along US 27 in the vicinity of SR 60, with approximately 13% trucks. Future 2040 traffic

volumes along US 27 are forecasted to increase significantly throughout the corridor,

with the largest absolute increases located near SR 60. On SR 60, existing traffic

volumes near the CSX crossing averaged approximately 23,000 vehicles per day.

Among other potential beneficiaries, CSX will benefit from the improved reliability and

safety on the roadways just outside its ILC facility at its crossing with SR 60. In

addition, many businesses in the area, including growers, shippers, and other industry

will benefit from more reliable shipping and potential reductions in shipping costs.

Figure 3: Project Location in Relation to Annual Freight Tonnage by Mode

Page 13: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

9

Transportation Challenges and Solutions

US 27 and SR 60 are important freight corridors for central Florida, facilitating the

transportation of goods through and out of the state. Currently, the movement of goods

and people along the two corridors and at their intersection are hampered by an

inefficient interchange and an at-grade crossing which are causing significant number of

crashes and creating inefficiencies and reducing the reliability of transportation in the

region. These challenges, and how the Central Florida Freight Corridor (US 27/SR 60)

Multimodal Mobility Enhancement Improvements address them, are presented in

greater detail in Table 1 below.

Table 1: Transportation Challenges and Solutions Provided by the Central Florida Freight Corridor

(US 27/SR 60) Multimodal Mobility Enhancement Improvements

The Transportation Challenges

The Solutions

Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility

Enhancement Improvements

US 27/SR 60 Interchange & US 27 widening

� High accident rates and reliability problems � Replace partial cloverleaf with Single Point Urban Interchange (SPUI) at US 27/SR 60

� Widen 5.25-mile section of US 27 leading into the interchange

Interchange bridge too low, trucks periodically hit it o Such collisions have required repairs averaging

$11,000 per year o Travel delays for other vehicles due to closures

from initial collisions and repairs

New interchange will have more clearance under SR 60 bridge over US 27

o Eliminates repairs from trucks hitting overpass o Eliminates delays to other vehicles associated

with trucks hitting overpass

Interchange ramp curves are too small for trucks, causing accidents and turnovers; notably higher crash rate than state average for similar facilities.

Ramps are currently at LOS F

o Injuries, fatalities, economic losses o Travel delays for other vehicles created by

crashes

Improvements to the interchange ramps and truck loons will allow for wide turns

o Decreases Injuries, fatalities, economic costs o Reduces travel delays associated with crashes

for other vehicles o Reduced congestion and delays at interchange

due to greater capacity

US 27 projected to reach capacity limits by 2040 o Future congestion and travel delays

Additional lanes for 5 miles along one of most heavily traveled sections of US 27

o Reduces congestion and travel delays in future

Page 14: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

10

The Transportation Challenges

The Solutions

Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility

Enhancement Improvements

CSX Crossing at SR 60

� Safety, travel efficiency and reliability problems

� Limits to future growth of Central Florida ILC and nearby development

� Grade separation of CSX Crossing at SR 60

Trucks and cars must wait for trains to cross 12 – 14 times a day

o Increases travel time for some truck and cars o Reduces reliability for trucks and cars

Eliminates the need for vehicles to stop and wait for trains

o Improves travel time o Improves reliability

Car and truck collisions (when stopped for trains) – almost one each year

o Injuries, fatalities, economic losses o Travel delays for other vehicles as respond to

crashes

Removing need to stop at crossing when trains pass will reduce vehicle collisions

o Decreases Injuries, fatalities, economic costs o Reduces travel delays associated with crashes

for other vehicles

All school buses and trucks carrying hazardous materials must stop at crossing regardless of train presence

o Increases travel time for school buses and some trucks

o Injuries, fatalities, economic losses

Removing need school buses and trucks carrying hazardous materials to always stop at crossing

o Improves travel time o Decreases risk of crashes and related injuries,

fatalities, economic costs

Potential train/vehicles collisions Separating vehicle and rail traffic reduces train/vehicle conflicts

Potential collisions with: o School buses (21 crossings a day) o Trucks carrying hazardous materials

Removes possibility of train collisions with school buses/trucks carrying hazardous materials; reduces risk of vehicle collisions with school buses/trucks carrying hazardous materials when stopped at the crossing

Single rail with at-grade crossing for trains leaving ILC.

o Limits expansion of ILC once it reaches capacity o Limit to ILC expansion and crash risk at crossing

may stifle future development plans at large nearby parcels

SR 60 will be built over rail line leaving room for future expansion with second parallel line

o ILC can be expanded to handle more intermodal freight, creating additional shipping efficiencies

o Possibility of added rail capacity together with safer roads can encourage development of large nearby parcels

Page 15: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

11

2.0 Project Location The Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility Enhancement

Improvements project is located in Polk County, in the heart Florida as shown in Figure

4.

US 27 runs up the

length of Florida from

Miami through the

interchange with SR 60,

connecting Miami to

central Florida and

beyond. The US 27/SR

60 Interchange near the

at-grade rail crossing is

situated partway

between three of the

biggest metropolitan

areas in Florida,

Tampa-Orlando-Miami.

The project’s specific

geospatial coordinates

are:

• US 27/SR 60 Interchange (middle of bridge, middle of median)

o 27°53'51.3"N 81°35'59.5"W

• SR 60 Railroad Crossing (middle of crossing between roads)

o 27°54'11.2"N 81°39'32.8"W

• US 27 and Presidents Drive (middle of intersection)

o 27°49'33.0"N 81°35'35.3"W

As shown in Table 2, Central Florida has experienced consistent population growth

over the last decade in the metropolitan areas of Tampa, Orlando, and Polk County,

indicating that highway usage will only increase. The surrounding metropolitan areas

have grown by approximately 12% to 24% during the last 10 years.

Figure 4: Project Location

Page 16: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

12

Table 2: Population Statistics for Central Florida MSAs

2005 2010 2015 Percent

(%) change 2005-2015

Tampa-St Petersburg-Clearwater MSA 2,647,658 2,783,243 2,975,225 12.4%

Orlando-Kissimmee-Sanford MSA 1,933,255 2,134,411 2,387,138 23.5%

Lakeland-Winter Haven MSA (Polk County) 542,912 602,095 650,092 19.7%

Note: MSA Populations for 2005 & 2015 are July 1 Census population estimates, populations for 2010 are Census

counts.

Significant portions of the project are in both rural and urban areas of the state. A

portion of this project is in the southern end of the Winter Haven urbanized area

(population 201,289). Based upon USDOT guidance on using project costs to

determine whether a project is urban or rural, the Florida Department of Transportation

concludes that this is a rural project under FASTLANE guidelines. Specifically:

• The US 27/SR 60 Interchange Improvements are located entirely in the Winter

Haven urbanized area. Total cost of the component is $64,629,798.

• The SR 60/At-Grade Rail Crossing Separation is located entirely in a non-

urbanized area of the state. Its total cost is $57,475,095.

• The Widening of US 27 south of the interchange is in the Winter Haven

urbanized area for 0.876 miles, and outside that urbanized area for 3.9 miles.

Total cost of the widening is $48,399,140, with $39,521,910 of those costs in a

non-urbanized area and $8,877,229 in an urbanized area.

• Thus, $96,997,006 of the total $170,504,033 project costs, or 57%, are in a non-

urbanized area and $73,507,027, or 43% of total costs, are in an urbanized area.

3.0 Project Parties The Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility Enhancement

Improvements project is supported by local, regional, and State partnerships. The

Florida Department of Transportation is collaborating with the Polk TPO, the local

transportation planning organization, and CSX Transportation, a large Class I railroad

owner and operator. Together, these public and private entities represent the vested

interest in the improvements to the local and regional highway and railway infrastructure

in this area.

Page 17: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

13

Florida Department of Transportation

This project is sponsored by the Florida Department of Transportation (FDOT) and will

be managed out of FDOT’s District One Office. FDOT’s primary statutory responsibility

is to coordinate the planning and development of a safe, viable, and balanced state

transportation system serving all regions of the state, and to assure the compatibility of

all components, including multimodal facilities. FDOT oversees the transportation

system for the 3rd most populous state, including 122,392 highway miles, 3,842 railway

miles, 20 commercial airports, 31 urban transit systems, 15 seaports, and 2 spaceports.

District One, with a land area of nearly 12,000 square miles, represents 12 counties in

Southwestern Florida. Its 1.8 million residents contribute to the 21 million miles traveled

daily on its state highways.

FDOT is known nationally for efficient and innovative transportation projects. Over the

last seven years, the FDOT has received six prizes in the America's Transportation

Awards competition: two Grand Prize awards and four People’s Choice awards. These

awards attest to the FDOT’s ability to deliver on project schedules, budgets, and

innovative solutions for transportation problems.

All FDOT Districts have a District Freight Coordinator who serves as the primary contact

for their district in coordinating matters of freight mobility with public agencies and

private businesses. District One’s Freight Mobility & Trade Plan, released earlier this

year, is designed to help the District and its freight stakeholders: i) increase operational

efficiency of goods movement; ii) align public and private efforts for trade and logistics;

iii) raise awareness and support for freight movement investments; and iv) transform

organizational culture to consider supply chain and freight movement issues.

Additionally, the FDOT’s Highway Safety Plan exemplifies their collaboration and

partnership input on safety priorities and activities. The compilation of these efforts

means that the FDOT partners with thousands of people to work toward their goal of

zero fatalities on Florida’s highways.

Polk County and the Polk TPO

Polk County is centrally located north-south and east-west on the Florida peninsula, and

is home to the Lakeland-Winter Haven MSA. The Polk TPO provides a forum for

cooperative decision-making regarding countywide transportation issues. As the lead

transportation planning agency for the area, it develops transportation plans and

programs designed to meet the community’s short and long term travel needs. The Polk

TPO collaborates with FDOT, transportation operators, and local governments on a

variety of transportation projects that serve the community, supported by federal and

Page 18: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

14

state funding. The policy board is comprised of local elected officials, staff, and advisory

committees that include representatives from cities and towns in the county.

Another critical party to this project, CSX Transportation, based in Jacksonville, Fla., is

one of the nation’s leading transportation companies, providing rail, intermodal, and

transload services. The company’s rail transportation network spans approximately

21,000 miles, with service to 23 eastern states and the District of Columbia, and

connects to more than 70 ocean, river, and lake ports. The Central Florida ILC is one of

only 3 intermodal terminals of its kind across CSX’s network.

FDOT received many letters of support for the Central Florida Freight Corridor (US

27/SR 60) Multimodal Mobility Enhancement Improvements project (included on the

project’s FASTLANE website) as shown in Table 3 below.

Table 3: Listing of Letters of Support

Elected Officials Governmental Agencies Businesses and Trade

Associations

US Senator Bill Nelson Central Florida Regional Planning Council

CSX Transportation

US Congressman Thomas J. Rooney

Florida Citrus Commission Oakley Transport

US Congressman Dennis Ross Heartland Regional Transportation Planning Organization

Florida’s Natural

Florida Representative Ben Albritton

Lake Wales Economic Development Council

Saddle Creek Transportation

Florida Representative Neil Combee

Winter Haven Economic Development Council

Statewide Harvesting & Hauling

Florida Representative Mike La Rosa

Central Florida Development Council

Florida Trucking Association

Florida Representative Sam Killebrew

Polk Transportation Planning Organization

Florida Representative Colleen Burton

Florida Senator Denise Grimsley

Florida Senator Kelli Stargel

Mayor of Winter Haven,

Bradley T. Dantzler

4.0 Grant Funds and Sources and Uses of Project Funds

Should FDOT be awarded a FASTLANE grant for the Central Florida Freight Corridor

(US 27/SR 60) Multimodal Mobility Enhancement Improvements, the project will be

Page 19: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

15

funded with a combination of Florida state funds and the FASTLANE grant. The Florida

state funds for this project are committed and total approximately 41% of the total

project costs, as shown in Table 4 below. No other federal funding for this project is

anticipated at the time of application.

A FASTLANE grant would allow FDOT to complete the US 27/SR 60 Interchange

improvements, separate the at-grade rail grade crossing on SR 60 over the CSX tracks

which carry trains from the nearby ILC, and widen approximately five miles of US 27

leading into the US 27/SR 60 interchange. Currently, FDOT does not have sufficient

funds to complete the entire project.

Table 4: Funding Sources and Uses for Central Florida Freight Corridor (US 27/SR 60) Multimodal

Mobility Enhancement Improvements

Project Components

& Cost Categories

FASTLANE Amount

% of Total

Project Cost

FDOT Amount

% of Total

Project Cost

Total

% of Total

Project Cost

US 27/SR 60 Interchange Improvements - FM#419243-4 $64,629,798 37.9%

Construction 38,131,581 22% 15,715,517 9% 53,847,098 32%

ROW 3,620,852 2% 3,620,852 2%

Professional Services 7,161,848 4% 7,161,848 4%

SR 60/At-Grade Rail Crossing Separation - FM#436559-1 $57,475,095 33.7%

Construction 33,910,306 20% 19,006,748 11% 52,917,054 31%

ROW 1,160,000 1% 1,160,000 1%

Professional Services 3,398,041 2% 3,398,041 2%

US 27 Widening - FM#419243-5 $48,399,140 28.4%

Construction 28,555,493 17% 19,843,647 12% 48,399,140 28%

ROW

Professional Services

Total $100,597,379 59% $69,906,654 41% $170,504,033

Table 4 also presents costs for the Central Florida Freight Corridor (US 27/SR 60)

Multimodal Mobility Enhancement Improvements separated by each component of the

project: the interchange improvements (approximately $64.6 million, which is 37.9% of

the entire project cost), the rail crossing separation (approximately $57.5 million, which

is 33.7% of the entire project cost), and the widening portion of US 27 (approximately

$48.4 million, which is 28.4% of the entire project cost).

Page 20: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

16

Each of these components can be constructed separately and have independent utility.

The widening of US 27 presented here is a section of a larger planned expansion of US

27 further south to the Highlands County Line. The interchange improvements and the

widening of this section of US 27 were modeled together in the cost-effectiveness

analysis because of the contiguous relationship of the two projects.

Table 4 details the portions of the total budget that will be spent on major cost

categories: construction, right-of-way, and professional services (including design and

engineering), and how the requested FASTLANE grant will be distributed among the

project components. FDOT plans for the entire FASTLANE grant to be spent on

construction activities.

FDOT has set aside contingencies in the budgeting for these projects, which are

included in FDOT District One Adopted Five-Year Work Program. Contingencies for the

project total $12,557,952, which is 7.4 percent of the total estimated project costs.

As previously stated, FDOT is the project sponsor and will be responsible for managing

the project funds, delivery and schedule. FDOT has a history of excellent project

delivery, public management and responsibility with public funds. The department has

surpassed its 80% on-time completion target for the past 7 years; this year completing

87.2% of projects on-time. FDOT also met its target to complete at least 90% of projects

within budget for the past 3 years, and have achieved over 80% for the last 6 years.

The FDOT also received good (Aa) credit ratings for all of its projects reviewed by

Moody’s in the last 10 years.

5.0 Merit Criteria

5.1 Economic Outcomes

Considering the significant percentage of truck

traffic on US 27, SR 60, and their interchange,

and the expected increases in traffic volumes,

the interchange improvement and the associated

roadway expansion will reduce travel delays and

improve reliability for a significant number of

trucks shipping goods in central Florida.

Page 21: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

17

This project improves the connections between

the ILC and US 27, the #1 trucking route in the

state. Currently over 800 trucks per day leave

the ILC, carrying regional, national, and

international cargo on their ‘last mile.’ The vast

majority of these trucks use SR 60 and US 27

on their outbound and inbound trips. Removing

the delays through the interchange and the at-

grade rail crossing and reducing crashes in this

area will increase road capacity and cater to the high level of freight through the area,

which will reduce shipping costs for many international and domestic goods passing

through the ILC.

In addition, the Rail Crossing Separation will be built large enough to accommodate

additional rail and vehicle travel lanes and thus will allow for the expansion of the

Central Florida ILC. Together, these transportation investments will encourage

economic development, including the use of large nearby parcels for additional freight

and distribution facilities.

The improvements will generate an estimated $0.9 million in vehicle operating cost

savings and another $0.3 million in savings from avoided congestion generated by

crashes on US 27 (calculated using a 7% discount rate). Additional benefits that were

not estimated include long-term efficiencies in freight shipments due to more reliable

transportation and long-term regional economic growth.

5.2 Mobility Outcomes

US 27 near SR 60 is already heavily traveled. The interchange improvements provide

reductions in congestion and enable better traffic flow, which will improve system

performance and better facilitate trucks moving goods through the ILC. Additionally, the

grade-separation for the rail crossing will provide uninterrupted traffic flow for both

vehicle and rail modes of transportation. These

improvements will enhance interregional connectivity

between Florida's economic regions.

Further, the bridge taking SR 60 over US 27 is too low.

In recent years, more than one truck has hit the bridge’s

bottom edges, causing damage and substantial traffic

delays as shown in Figure 5. Improving the interchange

layout and adding lanes to the south will reduce

congestion, leading to fewer crashes, and improve

“Florida’s Natural Growers is located

on US27 and less than half a mile from

SR60. With the combination of Fruit

trailers and Product trailers we have

over 200 loads per day that travel

these roads.”

Carson Weeks, Director of Global Supply

Chain, Citrus World, Inc.

“This project is critical to our community

for several reasons including the correction

of current safety and functional deficiencies

of the freight corridor and the economic

opportunity that will be realized upon

completion.”

Bruce Lyon, President, Winter Haven Economic

Development Council

Page 22: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

18

interactions between roadway users along this

segment of US 27, resulting in safe and efficient

operations between transportation modes in this area.

Both the lane widening along US 27 and the grade

crossing improvement on SR 60 will add lanes for

bicycle travel, enhancing local residents’ ability to

utilize active transportation options.

5.3 Safety Outcomes

The interchange has a high crash rate.

According to the Project Traffic Report

(PTR): US 27 from the Highlands County Line to

North of SR 60 PD&E Study, prepared for Polk County in 2016, the US 27/SR 60

Interchange crash rate exceeds the FDOT average for similar facilities. Between 2007

and 2011, the US 27/SR 60 Interchange had 105 crashes, more than any of the other

major intersection studied along that section of US 27.

The principle purpose behind improving the SR 60 at-grade crossing is to improve

safety. The 1-mile segment of SR 60, including the at-grade crossing, has an average

crash rate 6 times higher than the statewide average. A grade-separation crossing

alleviates vehicle-rail conflicts and reduces crashes that cause delays at this critical

location.

This project will lead to an estimated $150.3 million is safety benefits from fewer motor

vehicle accidents at the US 27/SR 60 interchange, the grade crossing, and on US 27.

5.4 Community and Environmental Outcomes

Replacing the at-grade crossing

removes a temporary barrier to local traffic which

will significantly benefit the local community

through reduced vehicle travel times, crashes on

SR 60, emissions, and noise generated by vehicle

idling. It will also enhance transportation

alternatives for the region’s population and

support growth in the Central Florida area.

Figure 5: Article from the Lakeland

Ledger w ith Photo of Overpass

Damage

Page 23: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

19

Both roads are hurricane evacuation routes in Central Florida. Implementing the

improvements will help ensure Florida's Transportation Systems can meet national

defense, emergency response, and evacuation needs, while providing adequate

capacity for the efficient movement of freight, goods and services for all users of the

transportation system.

.

5.5 Partnership and Innovation

The Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility Enhancement

Improvements is composed of improvements that are promoted by state, local, and

private stakeholders and it facilitates multi-jurisdictional and multimodal collaboration

and solutions for multiple public and private stakeholders across the State of Florida.

All elements of the project are in Polk TPO’s LRTP and have strong support from the

Winter Haven business community, as well as CSX Corporation. Multiple letters of

support for the project can be found on the project website (see Section 9.0).

5.6 Cost Share

FDOT is planning to use $69,906,654 of state funds to cover 41% match of the

total $170,504,033 project cost, as discussed in Section 4.0 Grant Funds and Sources

and Uses of Project Funds. These funds are State DOT funds and are programmed

within the current District One Work Program for construction by 2020.

6.0 Large Project Requirements As a large project, Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility

Enhancement Improvements must meet certain criteria as specified in the FASTLANE

Notice of Funding Opportunity (NOFO) for FY 2017. The applicable questions from the

NOFO are listed below in Table 5, with references to the appropriate sections of this

application in which the information can be found, with additional notations.

Large Project Question Response and Referral

Does the project generate national or regional economic, mobility, safety benefits?

Yes; see Sections 5.1, and 5.2.

Is the project cost effective? Yes; see Section 7.0

Table 5: Large Project Requirements

Page 24: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

20

Large Project Question Response and Referral

Does the project contribute to one or more of the Goals listed under 23 USC 150 (and shown below)? (b) National Goals.—It is in the interest of the United States to focus the Federal-

aid highway program on the following national goals:

(1) Safety.—To achieve a significant reduction in traffic fatalities and serious injuries on all public roads.

(2) Infrastructure condition.—To maintain the highway infrastructure asset system in a state of good repair.

(3) Congestion reduction.—To achieve a significant reduction in congestion on the NHS.

(4) System reliability.—To improve the efficiency of the surface transportation system.

(5) Freight movement and economic vitality.—To improve the national freight network, strengthen the ability of rural communities to access national and international trade markets, and support regional economic development.

(6) Environmental sustainability.—To enhance the performance of the transportation system while protecting and enhancing the natural environment.

(7) Reduced project delivery delays.—To reduce project costs, promote jobs and the economy, and expedite the movement of people and goods by accelerating project completion through eliminating delays in the project development and delivery process, including reducing regulatory burdens and improving agencies’ work practices.

Yes, particularly (1), (2), (5), and (7). See Sections 2.0, 4.0, 5.2, and 5.1.

Is the project based on the results of preliminary engineering?

Yes. Preliminary engineering and related documents are available at:

http://www.us27polk.com/

http://www.swflroads.com/sr60/over-csx/

a) With respect to non-federal financial commitments, does the project have one or more stable and dependable funding or financing sources to construct, maintain, and operate the project?

b) Are contingency amounts available to cover unanticipated cost increases?

Yes. State funds are committed in the FDOT District One Adopted Five-Year Work Program Projects.

Yes, contingencies are included. See Section 4.0.

Is it the case that the project cannot be easily and efficiently completed without other federal funding or financial assistance available to the project sponsor?

Funds are available for part of the project, but not for all of it. See Section 4.0

Is the project reasonably expected to begin construction not later than 18 months after the date of obligation of funds for the project?

Yes. See detailed schedule in Section 8.2.

Page 25: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

21

7.0 Cost Effectiveness The cost effectiveness of the Central Florida Freight Corridor (US 27/SR 60) Multimodal

Mobility Enhancement Improvements was estimated through a complete Benefit-Cost

Analysis (BCA) to monetize, as thoroughly as possible, benefits generated under each

of the merit criteria defined in the FASTLANE program and compare them against the

project’s cost. Benefits that are not easily monetized, but important to understand, are

discussed in other sections of this application. The BCA shows that the project has a

net overall positive impact on the nation’s economy. For every $1 invested in the

project, $1.17 to $2.12 (using a 7% and 3% discount rate, respectively) in public

benefits are likely to be generated.

A 33-year period of analysis was used in the estimation of the project’s benefits and

costs. This includes 3 years of construction taking place in 2020 through 2022 and 30

years of full operation with annual costs and benefits being estimated through 2052.

Table 6 below summarizes the monetization of the main benefits for proposed

improvements, categorized under the main criteria established in the FASTLANE

program. The benefits are discounted by 7% and 3%, as per USDOT guidance. The

largest benefits are obtained from improved safety, totaling $150.3 million when using a

7% discount rate and $325.6 million using a 3% discount rate.

Table 6: Cost Effectiveness Analysis Summary Result – Full Project

Benefits Estimates by Merit Criteria for the Full Project (Millions of 2016 Dollars)

Merit Criteria Benefit Categories 7% Discount

Rate 3% Discount

Rate

Economic Outcomes

Avoided Congestion Related Costs from Accidents

$0.3 $0.6

Vehicle Operating Cost Savings

$0.9 $2.1

Mobility Outcomes Travel Time Savings ($1.7) $9.8

Safety Outcomes Injury Cost Reduction

Fatality Cost Reduction $150.3 $325.6

Community and Environmental Outcomes

Emission Cost Reduction $0.2 $0.2

Overall benefits and costs are presented in Table 7. Benefits total $150.1 million over

the 33-year benefit accrual period when using a 7% discount rate, and $338.4 million

when using a 3% discount rate. With a 7% discount rate, the project is expected to

result in a net present value of nearly $22.2 million and a benefit-cost ratio of 1.17. With

Page 26: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

22

a 3% discount rate, the expected net present value of the project increases to $179.1

million, and the benefit-cost ratio to 2.12.

Table 7: Overall Results of the Benefit Cost Analysis for the Full Project (Millions of 2016 Dollars)

Project Evaluation Metric 7% Discount Rate 3% Discount Rate

Total Discounted Benefits $150.1 $338.4

Total Discounted Costs $127.9 $159.3

Net Present Value $22.2 $179.1

Benefit/Cost Ratio 1.17 2.12

When considering only the US 27/SR 60 Interchange and US 27 Widening components,

the largest benefits are safety related and total $130.4 million (using a 7% discount

rate). Overall benefits and costs of this portion of the project are presented in Table 8.

Table 8: Cost Effectiveness Analysis Summary Result – US 27/SR 60 Interchange and US 27

Widening Only

Benefits Estimates by Merit Criteria for the US 27/SR 60 Interchange and US 27 Widening (Millions of 2016 Dollars)

Merit Criteria Benefit Categories 7% Discount

Rate 3% Discount

Rate

Total Discounted Benefits $116.1 $265.3

Safety Outcomes Injury Cost Reduction

Fatality Cost Reduction $130.4 $282.7

Mobility Outcomes

Travel Time Savings (losses due to lower speed limit)

($14.7) ($18.0)

Avoided Congestion -Related Costs from Crashes

$0.3 $0.6

Improved Reliability not quantified not quantified

Economic Outcomes Inventory cost saving from reduced recurring delays

not quantified not quantified

Total Discounted Costs $81.6 $99.4

Net Present Value $34.4 $165.9

Benefit/Cost Ratio 1.42 2.67

For this US 27/SR 60 Interchange and US 27 Widening only, the project would result in

a net present value of nearly $34.4 million and a benefit-cost ratio of 1.42, when using a

Page 27: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

23

7% discount rate. When using a 3% discount rate, the project would result in net

present value of nearly $165.9 million and a benefit-cost ratio of 2.67.

For the SR 60 At-Grade Separation alone, the largest benefits are also safety related,

totaling $19.9 million with a 7% discount rate. Overall benefits and costs of just this

portion of the project are presented in Table 9. For this portion of the project only, when

using a 3% discount rate, the project would result in a net present value of nearly $13.2

million and a benefit-cost ratio of 1.22.

Table 9: Cost Effectiveness Analysis Summary Result – SR 60 At-Grade Separation Crossing Only

Benefits Estimates by Merit Criteria for the SR 60 At-Grade Crossing Separation (Millions of 2016 Dollars)

Merit Criteria Benefit Categories 7% Discount

Rate 3% Discount

Rate

Total Discounted Benefits $34.0 $73.1

Safety Outcomes Injury Cost Reduction

Fatality Cost Reduction $19.9 $42.9

Mobility Outcomes Travel Time Savings $13.0 $27.9

Improved Reliability not quantified not quantified

Economic Outcomes Vehicle Operating Cost Savings $0.9 $2.1

Total Discounted Costs $46.3 $59.9

Net Present Value ($12.3) $13.2

Benefit/Cost Ratio 0.73 1.22

8.0 Project Readiness The improvements to the US 27/SR 60 Interchange and widening of all of US 27 in Polk

County have completed the initial preliminary design and engineering, the NEPA

package has been submitted, and the project is included in relevant state and local

planning documents. The SR 60 at-grade rail crossing separation preliminary design

and engineering is nearing completion. The Project is ready to advance upon receipt of

FASTLANE funding.

8.1 Technical Feasibility

The Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility Enhancement

Improvements project has initiated and advanced work activities associated with

environmental analysis and design as well as a highly coordinated planning and review

process to vet potential technical issues. The project is ready to advance upon receipt

of additional funding. The technical feasibility assessment included advanced design

Page 28: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

24

work and an in-depth public involvement process that has allowed for meaningful input

from the general public and affected stakeholders. The planning and review process

was undertaken to maximize the benefits of the proposed improvements while

minimizing impacts to the adjacent property owners and the road users (motorized and

non-motorized). In particular, consideration to the type of vehicles traversing through

the project was accounted for, with heavy vehicles (i.e. freight-related) being a major

emphasis. To improve high crash areas, those locations were vetted to establish proper

sight distances, which are critical to improve safety. In addition, preliminary design

aspects were evaluated by traffic and roadway engineers so all project elements will

function safely and efficiently.

The FASTLANE grant award will allow the project to finalize design, commence right-of-

way acquisition, and initiate construction activities for all three components.

8.2 Project Schedule

The project schedule is illustrated in Figure 6 below.

Figure 6: Project Schedule

Final environmental approvals are expected in mid-2017. Construction of the SR 60 rail

crossing separation is expected to begin in June of 2019. Construction of the US 27/SR

60 Interchange and the widening of the portion of US 27 into the interchange are

planned to begin in March 2020.

Page 29: Project Name 27/SR 60) Multimodal Mobilityswflroads.com/us27sr60/fastlanegrantapplication/... · 2016-12-15 · 27/SR 60) Multimodal Mobility ... SR 60 intersects CSX Railroad at

25

8.3 Required Approvals

Environmental Reviews and Approvals

In cooperation with Federal Highway Administration (FHWA), FDOT District One staff is

working through the NEPA process to obtain appropriate approvals. As part of this

process, FDOT completed the necessary technical reports to address any potential

environmental impacts during the planning phase. A NEPA package for the widening of

all of US 27 in Polk County, as well as improving the US 27/SR 60 Interchange, was

submitted and the NEPA assignment for FDOT Office of Environmental Management

became effective on December 14, 2016.

This advanced environmental work addressed any potential significant impacts and will

streamline the project delivery process, and, thus, eliminate potential surprises.

State and Local Planning and Approvals

All portions of the Central Florida Freight Corridor (US 27/SR 60) Multimodal Mobility

Enhancement Improvements project are included in the state and local planning

documents. The project components are in the FDOT District One Adopted Five-Year

Work Program Projects, and the Polk TPO LRTP.

8.4 Project Risks and Mitigation Strategies

The three components of the project are considered together because the risks for

implementation are similar and minimal. As preliminary design is completed in the near

term and environmental approvals are obtained, the greatest risk to implementation is

funding. Due to funding limitations, this project will experience delays in delivering

needed upgrades to the project area, particularly hampering efficient freight movement.

FDOT will continue to pursue alternative funding options to complete these projects.

As stated previously, FDOT has set aside contingencies the project totaling

$12,557,952, which is 7.4 percent of the total estimated project costs (construction,

right-of-way, and design and engineering).

9.0 Project’s FASTLANE Website FDOT has prepared a Website for the Central Florida Freight Corridor (US 27/SR 60)

Multimodal Mobility Enhancement Improvements project which contains copies of this

application, the Technical Appendix for the BCA, a Wage Rate Certification Letter,

Letters of Support, and other documents for USDOT as it reviews this application. The

Website location is: www.swflroads.com/us27sr60/fastlanegrantapplication. The BCA

model is also available on the website with a password to access it of: FASTLANE2.