PROJECT MINUTES
Project: New Holbrook PreK-12 School Project No.: 13006
Prepared by: Joel Seeley Meeting Date: 11/18/2015
Re: Permanent School Building Committee Meeting Meeting No: 58
Location: H-CAM Studios Time: 7:00 PM
Distribution: Attendees, E. Kinsherf, (MF)
Attendees:
PRESENT NAME AFFILIATION VOTING MEMBER
Daniel F. Moriarty PSBC Chair Voting Member
James Day PSBC Vice-Chair Voting Member
Patricia Lally HPS Superintendent of Schools Non-Voting Member
Matthew Moore Board of Selectmen Chair Voting Member
Barbara Davis School Committee Voting Member
Patricia Coppola-Lugo HPS Procurement Administrator Non-Voting Member
Timothy Gordon Town Administrator Voting Member
HJSHS Principal Non-Voting Member
Beth Tolson School Committee Voting Member
Tom Taylor Member at Large Voting Member
Peter Mahoney Finance Committee Voting Member
Fred White Member at Large Voting Member
Scott Towne Member at Large Voting Member
Mike Bolger HPS Director of Facilities Non-Voting Member
Kent Kovacs Flansburgh Architects (FAI)
Vince Dubé Flansburgh Architects (FAI)
Betsy Garcia Flansburgh Architects (FAI)
Christian Riordan Consigli Construction Company (CCC)
Tim Vautour Consigli Construction Company (CCC)
John Laperle Consigli Construction Company (CCC)
Sarah Traniello Symmes Maini & McKee Associates (SMMA)
Joel Seeley Symmes Maini & McKee Associates (SMMA)
New Holbrook Pre-K – 12 School
11/18/2015
58
2
Item # Action Discussion
58.1 Record Call to Order, 7:00 PM, meeting opened.
58.2 Record D. Moriarty welcomed back Tim Gordon, the Board of Selectmen designee, to the
Committee.
58.3 Record A motion was made by J. Day and seconded by F. White to approve the 10/28/15
Permanent School Building Committee meeting minutes. No discussion, motion passed
unanimous by those attending, one abstention.
58.4 Record J. Seeley distributed and reviewed the Budget Tracking Form thru 10/31/15, attached, for
the Total Project Budget.
58.5 Record J. Seeley distributed and reviewed Change Order No. 5, and the Change Order, GMP
Contingency and Allowance Budget Summary Form, both attached.
A motion was made by M. Moore and seconded by F. White to approve Change Order No.
5, dated 11/17/15 in the amount of $3,634.00 and recommend signature by M. Moore. No
discussion, motion passed unanimous.
58.6 Record J. Seeley distributed and reviewed PFA Budget Revision Request No. 6, dated 11/18/15
corresponding to Change Order No. 5.
A motion was made by P. Mahoney and seconded by F. White to approve PFA Budget
Revision Request No. 6, dated 11/18/15. No discussion, motion passed unanimous.
58.7 Record Vouchers for reimbursement to FAI for $204,000.00 for Contract Document services,
Consigli for $19,350.00 for Preconstruction services, Consigli for $1,529,297.03 for
Construction, SMMA for $45,867.12 for OPM services, SMMA for $9,747.76 for Owner’s
Testing and Inspection Services, SMMA for $7,210.04 for Bid Document Printing were
reviewed, including the MSBA Payment Tracking Log, attached
Committee Discussion:
1. P. Mahoney asked for clarification on the overtime charges for the Owner’s
Testing and Inspection Services.
J. Seeley will provide at the next Committee meeting.
A motion was made by M. Moore and seconded by P. Mahoney to approve the Vouchers,
except the amounts for the Owner’s Testing and Inspection Services. No discussion,
motion passed unanimous.
58.8 Record J. Seeley distributed and reviewed the PSBC Meetings Schedule for the Construction
Phase thru 2017.
A motion was made by F. White and seconded by P. Mahoney to approve the PSBC
Meetings Schedule. No discussion, motion passed unanimous.
58.9 M. Moore J. Seeley distributed and reviewed a letter from P. Lally to the MSBA, dated 10/31/15 and
attached, requesting approval to appoint Julie Hamilton, Assistant Superintendent to the
PSBC in lieu of one of the school principals. The letter has not been sent to the MSBA.
A motion was made by F. White and seconded by J. Day to recommend to the Selectmen
to appoint Julie Hamilton to the PSBC. No discussion, motion passed unanimous.
58.10 Record M. Moore led a discussion on future PSBC appointments and asked if the Committee
would allow a current member that is on the PSBC under their capacity as an elected
official or other Town board position, to remain on the committee as a non-voting member
once their term expires. The reason being that each current member has invested a great
New Holbrook Pre-K – 12 School
11/18/2015
58
3
Item # Action Discussion
deal of time in the project so far, and this would allow them to see the project through,
should their term expire before the project is finished.
Committee Discussion:
1. J. Day asked for how long would that person stay on the PSBC?
M. Moore indicated for as long as the person wanted to be on the Committee.
2. J. Day asked would this increase the PSBC membership, in that the Selectmen
would still need to appoint a replacement to comply with MSBA requirements?
M. Moore indicated yes.
A motion was made by M. Moore and seconded by F. White to recommend to the
Selectmen to allow any current member that is on the PSBC due to their elected position
or other Town board position, to remain on the committee as a non-voting member once
their term expires for as long as they want to be on the PSBC. No discussion, motion
passed unanimous.
58.11 K. Kovacs K. Kovacs will update the model to reflect the final interior materials.
58.12 M. Bolger
K. Kovacs
T. Vautour
K. Kovacs distributed and reviewed a listing of the specified types and quantities of attic
stock material, dated 11/18/15 and attached.
Committee Questions:
1. T. Taylor recommended not reducing the amount of specified types and quantities
of attic stock material.
2. M. Moore asked what is the size of the storage room that the District needs to
store their regular maintenance materials?
P. Lally will ask M. Bolger to determine.
3. S. Towne asked K. Kovacs to provide direction on what attic stock materials are
temperature sensitive.
K. Kovacs will determine and work with Consigli to provide options for increased
storage capacity in the building.
58.13 Record K. Kovacs presented options for providing a second vehicular access/egress roadway
from the site to either Route 139 or to Plymouth Street, attached, that FAI developed and
presented during the Schematic Design Phase. K. Kovacs indicated the roadways would
require approximately 50,000 to 55,000 s.f. of wetland filling. K. Kovacs reviewed the
permitting levels, from local Conservation Commission, if under 5,000 s.f. of wetland filling,
to the State DEP and Federal Corps of Engineers when over. Permitting could take
between 1 and 2 years and the project civil engineer does not believe a permit for the
roadway would be granted. The roadway is estimated to cost over $1,000,000 and is not
reimbursable.
58.14 K. Kovacs
C. Riordan
J. Seeley
C. Riordan distributed and reviewed the Trade Contractor Bid Results Form, dated
11/18/15 and attached. There were 72 bids received and the tally of all the low bids in
each category is approximately $2.9 million under budget. There are several anomalies
with the bids that will be reviewed by CCC, FAI and SMMA over the next few days. J.
Seeley indicated some of the anomalies will be reviewed by town counsel.
Once the bids are checked, the final list of bid results will be forwarded to the Committee.
New Holbrook Pre-K – 12 School
11/18/2015
58
4
Item # Action Discussion
58.15 Record T. Vautour provided a construction status update. The concrete foundations will be
complete in Wing A next week and have commenced in Wing C. Structural steel will arrive
on site January 11. Masonry bearing walls have commenced.
T. Vautour distributed and reviewed a Ledge Location Plan, attached, defining the
approximate location of discovered ledge that is required to be removed due to conflicts
with the storm drainage piping and structures. The ledge quantity is approximately 195
cubic yards which will be attributed to the 400 cubic yard allowance in the GMP. The
blasting is tentatively scheduled for when the school is vacant, either Wednesday
afternoon or Saturday, 11/25/15 or 11/28/15.
58.16 T. Gordon
P. Lally
T. Gordon and P. Lally will develop the plan for the ceremonial steel signing for Committee
review.
58.17 Record Next PSBC Meeting: December 16, 2015 at 7:00 pm at the H-Cam Studios.
58.18 Record A Motion was made by P. Mahoney and seconded by F. White to adjourn the meeting. No
discussion, voted unanimously.
Attachments: Agenda, Budget Tracking Form, Change Order and GMP Contingency Budget Summary Form, Listing
of attic stock material, Analysis of potential new roads at the existing wetlands to the north and east of the site,
Trade Contractor Bid Results Form, Ledge Location Plan
The information herein reflects the understanding reached. Please contact the author if you have any questions or are not in agreement with these
Project Minutes.
JGS/sat/P:\2013\13006\04-MEETINGS\4.3 Mtg_Notes\3-PSBC Meetings\2015\58_2015_18novemberpsbcmeeting\Permanentschoolbuildingcommitteemeeting_18November2015-
FINAL.Docx
AGENDA
Project: New Holbrook PreK-12 School, Holbrook, MA Project No.: 13006
Re: Permanent School Building Committee Meeting Meeting Date: 11/18/2015
Prepared by: Joel G. Seeley Meeting Time: 7:00 PM
Distribution: Attendees (MF)
1. Call to Order
2. Approval of Minutes
3. Approval of Invoices and Commitments
4. PSBC Member Update
5. Review Trade Contractor Bid Results
6. Construction Update
7. Committee Questions
8. Public Comments
9. Next Meeting: December 9, 2015 or December 16, 2015
10. Adjourn
JGS/sat/P:\2013\13006\04-MEETINGS\4.2 Agendas\PSBC Meetings\2015\59_2015_18November2015_Psbcmeeting\Agenda_18November2015.Doc
Symmes Maini & McKee Associates, Inc. (SMMA)
Holbrook School District
New Holbrook PreK-12 School
BUDGET SUMMARY
BUDGET TRACKING FORM as of: 10/31/2015 Budget Revisions
Propay Name A B C D E
code # Feasibility Study Agreement
1 0001-0000 OPM Feasibility Study 160,000.00 160,000.00 159,250.00 159,250.00 - - 750.00
2 0002-0000 A&E Feasibility Study 450,000.00 450,000.00 450,000.00 450,000.00 - - -
3 0003-0000 Environmental and Site 100,000.00 100,000.00 63,706.00 63,039.69 666.31 - 36,294.00
4 0004-0000 Other 86,272.00 86,272.00 8,416.38 8,416.38 - - 77,855.62
Feasibility Study Agreement Subtotal 796,272.00$ -$ 796,272.00$ 681,372.38$ 680,706.07$ 666.31$ -$ 114,899.62$
Administration
6 0101-0000 Legal Fees 120,000.00 120,000.00 94,019.26 23,516.76 70,502.50 - 25,980.74
Owner's Project Manager
7 0102-0400 > Design Development 254,666.00 254,666.00 254,666.00 254,666.00 0.00 - -
8 0102-0500 > Construction Contract Documents 382,226.00 382,226.00 382,226.00 336,358.88 45,867.12 - -
9 0102-0600 > Bidding 138,889.00 138,889.00 138,889.00 - 138,889.00 - -
10 0102-0700 > Construction Contract Administration 1,802,699.00 1,802,699.00 1,802,699.00 54,080.97 1,748,618.03 - -
11 0102-0800 > Closeout 61,004.00 61,004.00 61,004.00 - 61,004.00 - -
12 0102-0900 > Extra Services 100,000.00 100,000.00 - - - - 100,000.00
13 0102-1000 > Reimbursable & Other Services 40,000.00 40,000.00 3,960.00 3,960.00 - - 36,040.00
14 0102-1100 > Cost Estimates 100,000.00 100,000.00 52,250.00 52,250.00 - - 47,750.00
15 0103-0000 Advertising 20,000.00 20,000.00 820.38 820.38 - - 19,179.62
16 0104-0000 Permitting 50,000.00 50,000.00 1,757.94 1,757.94 - - 48,242.06
17 0105-0000 Owner's Insurance 80,000.00 80,000.00 - - - - 80,000.00
18 0199-0000 Other Administrative Costs 60,000.00 60,000.00 20,000.00 2,686.26 17,313.74 - 40,000.00
Administration Subtotal 3,209,484.00$ -$ 3,209,484.00$ 2,812,291.58$ 730,097.19$ 2,082,194.39$ -$ 397,192.42$ Architecture and Engineering
Basic Services
21 0201-0400 > Design Development 1,730,000.00 1,730,000.00 1,730,000.00 1,730,000.00 - - -
22 0201-0500 > Construction Contract Documents 2,550,000.00 2,550,000.00 2,550,000.00 2,346,000.00 204,000.00 - -
23 0201-0600 > Bidding 330,000.00 330,000.00 330,000.00 - 330,000.00 - -
24 0201-0700 > Construction Contract Administration 2,450,000.00 2,450,000.00 2,450,000.00 - 2,450,000.00 - -
25 0201-0800 > Closeout 200,000.00 200,000.00 200,000.00 - 200,000.00 - -
26 0201-9900 > Other Basic Services 300,000.00 300,000.00 300,000.00 - 300,000.00 - -
27 BASIC SERVICES SUBTOTAL 7,560,000.00$ -$ 7,560,000.00$ 7,560,000.00$ 4,076,000.00$ 3,484,000.00$ -$ -$
Reimbursable Services
28 0203-0100 > Construction Testing 25,000.00 25,000.00 - - - - 25,000.00
29 0203-0200 > Printing (over minimum) 120,000.00 120,000.00 - - - - 120,000.00
30 0203-9900 > Other Reimbursable Costs 180,000.00 180,000.00 12,078.98 - 12,078.98 - 167,921.02
31 0204-0200 > Hazardous Materials 240,000.00 240,000.00 - - - - 240,000.00
32 0204-0300 > Geotech & Geo-Env. 200,000.00 200,000.00 32,230.00 6,237.00 25,993.00 - 167,770.00
33 0204-0400 > Site Survey 80,000.00 80,000.00 57,475.00 57,475.00 - - 22,525.00
34 0204-0500 > Wetlands 80,000.00 80,000.00 2,970.00 2,970.00 - - 77,030.00
35 0204-1200 > Traffic Studies 100,000.00 100,000.00 - - - - 100,000.00
Architectural and Engineering Subtotal 8,585,000.00$ -$ 8,585,000.00$ 7,664,753.98$ 4,142,682.00$ 3,522,071.98$ -$ 920,246.02$
(A - B - E)
Budget
Balance
Original
PS&B Budget
7/23/14
Current
Budget
Contract
Amount Expended
(B - C)
Remaining
Contract Amount
Additional
Projected Amount
Symmes Maini & McKee Associates, Inc. (SMMA)
Holbrook School District
New Holbrook PreK-12 School
BUDGET SUMMARY
BUDGET TRACKING FORM as of: 10/31/2015 Budget Revisions
(A - B - E)
Budget
Balance
Original
PS&B Budget
7/23/14
Current
Budget
Contract
Amount Expended
(B - C)
Remaining
Contract Amount
Additional
Projected Amount
CM @ Risk Preconstruction Services
36 0501-0000 Pre-Construction Services 600,000.00$ (400,000.00)$ 200,000.00$ 193,500.00$ 154,800.00$ 38,700.00$ -$ 6,500.00$
0502-0001 Construction Budget 79,835,240.00$ 400,000.00$ 80,235,240.00$ 24,741,135.00$ 3,988,764.72$ 20,752,370.29$ -$ 55,494,105.00$
89 CSI Code CSI Description
89 0502-0010 CM Fee 459,033.35 459,033.35 91,751.00 367,282.35 - -
89 0502-0020 Bonds and Insurances 780,698.60 780,698.60 694,605.80 86,092.80 - -
89 0502-0030 Total GMP Construction Contingency 1,404,755.50 1,404,755.50 24,946.05 1,379,809.45 - -
89 0502-0100 CM Staffing 1,843,849.30 1,843,849.30 312,774.68 1,531,074.63 - -
89 0502-0100 GC's 250,320.25 250,320.25 63,021.89 187,298.36 - -
89 0502-0100 Division 1 - General Requirements 854,306.50 854,306.50 107,974.50 746,332.00 - -
89 0502-0200 Division 2 - Existing Conditions - - - - -
89 0502-0300 Division 3 - Concrete 2,986,420.00 2,986,420.00 175,417.50 2,811,002.50 - -
89 0502-0400 Division 4 - Masonry 3,208,150.00 3,208,150.00 - 3,208,150.00 - -
89 0502-0500 Division 5 - Metals 3,404,562.50 3,404,562.50 - 3,404,562.50 - -
89 0502-0600 Division 6 - Wood, Plastics and Composites - - - - -
89 0502-0700 Division 7 - Thermal & Moisture Protection - - - - -
89 0502-0800 Division 8 - Openings - - - - -
89 0502-0900 Division 9 - Finishes - - - - -
89 0502-1000 Division 10 - Specialties - - - - -
89 0502-1100 Division 11 - Equipment - - - - -
89 0502-1200 Division 12 - Furnishings - - - - -
89 0502-1400 Division 14 - Conveying Systems - - - - -
89 0502-2100 Division 21 - Fire Suppression - - - - -
89 0502-2200 Division 22 - Plumbing - - - - -
89 0502-2300 Division 23 - HVAC - - - - -
89 0502-2600 Division 26 - Electrical - - - - -
89 0502-2700 Division 27 - Communications - - - - - -
89 0502-2800 Division 28 - Electronic Safety & Security - - - - - -
89 0502-3100 Division 31 - Earthwork 2,829,185.50 2,829,185.50 1,090,813.75 1,738,371.75 - -
89 0502-3200 Division 32 - Exterior Improvements 1,721,400.00 1,721,400.00 121,837.50 1,599,562.50 - -
89 0502-3300 Division 33 - Utilities 3,668,005.10 3,668,005.10 1,097,960.60 2,570,044.50 - -
89 0502-9900 Retainage 1,232,141.40 1,232,141.40 217,820.75 1,014,320.65 - -
89 0508-0000 Change Orders 98,307.00$ 98,307.00 98,307.00 (10,159.30) 108,466.30 - -
89 Construction Budget Subtotal 79,835,240.00$ 98,307.00$ 24,741,135.00$ 24,741,135.00$ 3,988,764.72$ 20,752,370.29$ -$ 55,494,105.00$
Alternates
90 0506-0000 Ineligible Work (Maint Blg, Press Box, Concession and Restrooms) 404,800.00 404,800.00 - - - - 404,800.00
Alternates Subtotal 404,800.00$ -$ 404,800.00$ -$ -$ -$ -$ 404,800.00$
0600-0000 Miscellaneous Project Costs
94 0601-0000 Utility Company Fees 280,000.00 280,000.00 - - - - 280,000.00
95 0602-0000 Testing Services 300,000.00 300,000.00 110,000.00 1,262.25 108,737.75 - 190,000.00
96 0603-0000 Swing Space / Modulars - - - - - - -
97 0699-0000 Other Project Costs (Mailing & Moving) 200,000.00 200,000.00 - - - - 200,000.00
0600-0000 Miscellaneous Project Costs Subtotal 780,000.00$ -$ 780,000.00$ 110,000.00$ 1,262.25$ 108,737.75$ -$ 670,000.00$
0700-0000 Furnishings and Equipment
99 0701-0000 Furnishings 1,971,000.00 1,971,000.00 - - - - 1,971,000.00
0702-0000 Equipment
101 0703-0000 Computer Equipment 1,971,000.00 1,971,000.00 - - - - 1,971,000.00
Furnishings and Equipment Subtotal 3,942,000.00$ -$ 3,942,000.00$ -$ -$ -$ -$ 3,942,000.00$
103 0507-0000 Owner's Construction Contingency 4,012,002.00 (98,307.00) 3,913,695.00 - - - - 3,913,695.00
104 0801-0000 Owners' (soft cost) Contingency 802,400.00 802,400.00 - - - - 802,400.00
Contingency Subtotal 4,814,402.00$ (98,307.00)$ 4,716,095.00$ -$ -$ -$ -$ 4,716,095.00$
Total Project Budget 102,967,198.00$ -$ 47,374,786.00$ 36,203,052.94$ 9,698,312.23$ 26,504,740.72$ -$ 66,665,838.06$
Town of Holbrook
New Holbrook PreK-12 School
Project Payment History Matrix
Updated: November 6, 2015
Estimated
Reimbursement
# Date @ 69.12%
4/24/13, 5/15/13, 5/29/13,
7/10/13, 7/31/13, 8/21/13,
10/2/13, 10/30/13, 11/18/13,
12/4/13, 1/29/14, 3/5/2014
4/10/2014 1 5/1/2014 273,046.00$
4/2/14, 4/16/14, 5/21/14,
6/5/14, 7/10/14, 7/14/14,
7/31/14, 9/17/14, 10/15/14
11/17/2014 2 12/24/2014 179,491.00$
1/21/2015 1/02-1/30/2015 593,005.26$ 1/30/2015 2/19/2015 3/12/2015 3 3/12/2015 409,174.00$ 4/2/2015 408,119.00$
2/4/2015 2/13/2015 5,956.50$ 3/19/2015 3/19/2015 4/2/2015 4 4/2/2015 4,110.00$ 4/30/2015 18,183.00$
2/18/2015 3/27/2015 433,999.20$ 3/31/2015 4/2/2015 4/17/2015 5 4/22/2015 299,459.00$ 5/7/2015 298,276.00$
3/18/2015 5/1/2015 461,017.27$ 4/30/2015 5/8/2015 5/20/2015 6 5/20/2015 318,102.00$ 6/5/2015 315,716.00$
4/15/2015 5/15/2015 543,417.75$ 6/2/2015 6/2/2015 7/9/2015 7 7/15/2015 374,958.00$ 7/31/2015
5/20/2015 6/5/2015 446,946.15$ 6/9/2015 6/11/2015 7/9/2015 7 7/15/2015 308,393.00$ 7/31/2015
6/17/2015 6/26/2015 505,349.45$ 6/29/2015 7/2/2015 7/9/2015 8 7/15/2015 348,691.00$ 7/31/2015 1,029,071.00$
7/15/2015 7/24/2015 544,274.43$ 7/29/2015 8/4/2015 8/21/2015 9 8/4/2015 375,549.00$ 9/4/2015 375,635.00$
8/19/2015 8/28/2015 2,206,680.00$ 8/27/2015 9/1/2015 9/17/2015 10 9/24/2015 1,522,609.00$ 10/9/2015 1,509,585.00$
9/16/2015 9/25/2015 1,257,803.59$ 9/30/2015 10/8/2015 10/15/2015 11 10/19/2015 867,884.00$ 11/5/2015 880,762.00$
10/28/2015 12
PSBC Meeting
Approving Voucher
Date
CPA Received
Signed Voucher from
Town
Date
CPA Mailing Signed
Forms Submittal to
MSBA
Date
MSBA Log-in Date
and
Number of SubmissionReimbursement
Received from
MSBA
Amount
Reimbursement
Received from MSBA
Date
Payment by Town
Amount
Payment by Town
Date
CPA Electronic
Submittal of Request
for Reimbursement
through Propay
to MSBA
Date
PROJECT MANAGEMENT
AGENDA
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
July 19, 2017
September 21, 2016
June 21, 2017
July 20, 2016
August 17, 2016
May 18, 2016
June 15, 2016
February 17, 2016
March 16, 2016
April 20, 2016
October 19, 2016
November 16, 2016
December 21, 2016
Construction Phase
April 19, 2017
January 20, 2016
February 15, 2017
Permanent School Building Committee
New Holbrook PreK-12 School
October 22, 2015
DATE
MEETINGS SCHEDULE AND AGENDAS
DRAFT
All meetings held at H-CAM Studios, 140 North Franklin Street at 7:00 PM unless otherwise noted
May 17, 2017
January 18, 2017
March 15, 2017
Project Management SMMA
AGENDA
Construction Phase
Permanent School Building Committee
New Holbrook PreK-12 School
October 22, 2015
DATE
MEETINGS SCHEDULE AND AGENDAS
DRAFT
All meetings held at H-CAM Studios, 140 North Franklin Street at 7:00 PM unless otherwise noted
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
BUILDING COMMITTEE MEETING
Construction Progress
ADDITIONAL MEETINGS TO BE SCHEDULED
December 20, 2017
October 18, 2017
November 15, 2017
September 20, 2017
August 16, 2017
Project Management SMMA
Holbrook Public Schools 245 South Franklin Street Holbrook, MA 02343 Patricia A. Lally, Ph.D. Superintendent of Schools
245 South Franklin Street ♦ Holbrook, MA 02343-1599 ♦ Telephone: 781-767-1226 ♦ Fax: 781-767-1312
October 31, 2015 Massachusetts School Building Authority 40 Broad Street Boston, MA 02109 Dear Mr. McCarthy, Since there is a vacancy for the position of Principal on the Holbrook Permanent School Building Committee, I would like to propose the replacement be Julie Hamilton, Assistant Superintendent of Schools. The project now includes all three schools/levels in one building instead of a junior-senior high school building; therefore, having one of the principals join the committee would exclude the other two who are involved. The Assistant Superintendent is highly involved in all aspects of the three schools and would be an effective representative of their needs. Thank you for considering this request. Sincerely, Patricia A. Lally, Ph.D. Superintendent of Schools
PROJECT MANAGEMENT SMMAMassachusetts School Building Authority
Flansburgh Architects
1650'-0"
1850
'-0"
J.F.K. SCHOOL
JUNIOR/SENIOR HIGH SCHOOL
PLYMOUTH STREET
SOUTH FRANKLIN STREET
PLYMOUTH STREET
J.F.K. SCHOOL WETLANDS LINE
JUNIOR/SENIOR HIGH SCHOOL WETLANDS LINE
NEW ROAD+/- 1850’ x 30’ = 55,500 sf (road over wetlands area)
FLOOD ZONE
NEW ROAD+/- 1650’ x 30’ = 49,500 sf (road over wetlands area)
PROPERTY LINE
Holbrook: Potential New Roads @ existing wetlandsN
Page 1 of 3
TO: Director of Capital Planning
FROM: Superintendent Patricia Lally
Holbrook Public Schools
New Holbrook PreK-12 School
MSBA Project ID Number: 200801330505
DATE: November 18, 2015
RE: Project Funding Agreement Budget Revision Request, NUMBER: 6
Pursuant to Section 3.6 of the Project Funding Agreement between the TOWN OF HOLBROOK, MASSACHUSETTS (the “District”) and the MASSACHUSETTS SCHOOL BUILDING AUTHORITY (the “Authority”), the District hereby requests a revision to the Total Project Budget, Exhibit A, dated October 23, 2014, for the New Holbrook PreK-12 School. As required, the District has provided the information outlined in the table below to indicate the Total Project Budget categories (line items) affected, the amounts needed and the reasons for the proposed revision.
The District acknowledges and agrees that it will not seek reimbursement from the Authority for any costs that exceed the already approved line item limits set forth in Exhibit A until after the Authority has accepted this Total Project Budget Revision Request, and the Authority’s ProPay system has been adjusted accordingly.
The District further acknowledges and agrees that in accordance with Sections 3.6 and 3.7 of the Project Funding Agreement, any revisions to the Total Project Budget will not result in an increase to the Total Facilities Grant amount set forth in Section 2.1 of the Project Funding Agreement.
The District further acknowledges and agrees that the need for these revisions to the Total Project Budget have been identified in the OPM monthly report as required pursuant to the Contract for Owner’s Project Management Services between the District and the OPM.
The District further acknowledges and agrees that all of the information contained in this Total Project Budget Revision Request has been reviewed and approved by Permanent School Building Committee, and it further certifies and acknowledges that the funds to pay for the costs associated with these proposed revisions are available as indicated by the signatures noted below.
Use Table 1 for identification of expenditures against the Owner’s contingency. The Total Owner’s Contingency in the Current Total Project Budget, Exhibit A of the PFA dated January 8, 2015 is $802,400.00.
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Owner’s Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
$802,400
Page 2 of 3
Use Table 2 for identification of expenditures against the Construction Contingency. The Total Construction Contingency in the Current Total Project Budget, Exhibit A of the PFA January 8, 2015 is $4,012,002.00
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Construction Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
0507-0000 Owner’s Construction Contingency
0508-0000 Change Orders $3,634.00 Change Order No. 5, dated November 17, 2015 $3,910,061.00
Use Table 3 for identification of expenditures against the Allowances.
From Classifi-cation Code
From Classification Name
To Classifi-cation Code
To Classification Name
Budget Revision Amount
Reason for transfer (Attach all supporting documentation, e.g., executed contracts, amendments and or supporting invoices for reimbursable expenses)
Amount Remaining in Construction Contingency
Ineligible/Cost/Scope Items excluded from the Total Facilities Grant
0502-3100 Earthwork 0502-0030 GMP Construction Contingency
$60,000.00 CT-03 was included in Change Order No. 2
0502-0030 GMP Construction Contingency
0502-0100 General Requirements $3,085.00 CT-04 was included in Change Order No. 2
0502-0100 General Requirements
0502-3300 Utilities $2,578.00 BT-01 was included in Change Order No. 3
0502-0030 GMP Construction Contingency
0502-3100 Earthwork $2,534.00 CT-01 was included in Change Order No. 3
0502-0030 GMP Construction Contingency
0502-3100 Earthwork $17,635.00 CT-02 was included in Change Order No. 3
0502-0030 GMP Construction Contingency
0502-3100 Earthwork $23,665.00 CT-09 and CT-10 were included in Change Order No. 4
0502-0030 GMP Construction Contingency
0502-0500 Metals $3,575.00 CT-12 was included in Change Order No. 4
0502-0030 Allowances 0502-0500 Metals $17,694.00 AT-01, AT-02, AT-03 and AT-04 was included in Change Order No. 5
Page 3 of 3
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Matthew V. Moore
Title: Chief Executive Officer
Date: November 18, 2015
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Patricia Lally
Title: Superintendent of Schools
Date: November 18, 2015
By signing this Total Project Budget Revision Request, I hereby certify that I have read and understand the terms of this Request and further certify that the information supplied by the District in the tables is true, accurate and complete.
________________________________________
By: Arthur George
Title: Chair of the School Committee
Date: November 18, 2015
MASSACHUSETTS SCHOOL BUILDING AUTHORITY
________________________________________
By:
Title: Director of Capital Planning
Date: __________________________________ P:\2013\13006\00-INFO\0.9 Budget Revisions\PFA Budget Revision Requests\PFA_BudgetRevisionRequestNo.6_18November2015\MASTER PFA Budget Revision Request Rev 6.doc
PROJECT MANAGEMENT
UPDATED: 11/18/2015
NEW HOLBROOK PREK-12 SCHOOL, HOLBROOK, MASSACHUSETTS
Change Order Budget Summary
Change
Order No.
Change Order
Amount
Owner's Contingency
Budget
4,012,002.00$ Original PFA Budget
1 (19,298.00)$
2 (924.00)$
3 44,268.00$
4 74,261.00$
5 3,634.00$
Change Order
Total
Budget
Total
Budget
Balance
TOTAL 101,941.00$ 4,012,002.00$ 3,910,061.00$
GMP Contingency Transfer Budget Summary
Change
Order No.
Contingency Transfer
Amount
GMP Contingency
Budget
273,972.00$ Amendment No. 1
1 NA
2 (56,915.00)$ CT-003; CT-004
3 19,569.00$ CT-001; CT-002
4 27,240.00$ CT-009; CT-010; CT-012
231,210.00$ Amendment No. 2
154,304.00$ Amendment No. 3
Contingency Transfer
Total
GMP Contingency
Total
Contingency
Balance
TOTAL (10,106.00)$ 659,486.00$ 669,592.00$
Allowance Transfer Budget Summary
Change
Order No.
Allowance Transfer
Amount
Allowance Transfer
Budget
376,500.00$ Amendment Nos. 1 through 3
1 NA
2 NA
3 NA
4 NA
5 17,694.00$ AT-01, AT-02, AT-03 and AT-04
Allowance Transfer
Total
Allowance Transfer
Budget
Allowance Transfer
Balance
TOTAL 17,694.00$ 376,500.00$ 358,806.00$
1 OF 1
Change Order
Date:
Project:
Consigli Construction Co., Inc.72 Sumner StreetMilford, MA 01757
1484 Holbrook - New PreK-12 School
5
11/17/2015
To Contractor:
Holbrook, MA 02343245 South Franklin Street
Change Order:
The Contract is changed as follows:
AT001-P2 Allowance Transfer - ASI-5 Change Thickness of Deck at Loading Dock $0.00
AT002-P2 Allowance Transfer - PR #P2-1.1 Steel Beam Change $0.00
AT003-P2 Allowance Transfer - PR4 Modified Tapered Canopy $0.00
AT004-P2 Allowance Transfer - PR5 Entry Framing $0.00
CR018-P1 New Flood Light at Exterior of Existing Building $3,634.00
$3,634.00Total:
NOT VALID UNTIL SIGNED BY THE ARCHITECT, CONTRACTOR AND OWNER.
Town of Holbrook
OWNERARCHITECT CONTRACTOR
Consigli Construction Co., Inc.
The Contract Time will be unchanged.
$24,642,828.00
$24,744,769.00
The original Contract Amount was
Net change by previously authorized Change Orders
The Contract Amount prior to this Change Order was
The Contract will be increased by this Change Order in the amount of
The new Contract Amount including this Change Order will be
$98,307.00
$24,741,135.00
77 North Washington Street
Holbrook, MA 02343
50 North Franklin Street
Boston, MA 02114
72 Sumner Street
Milford, MA 01757
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
Flansburgh Associates, Inc
$3,634.00
Page 1 of 1
Consigli Construction Co., Inc.Construction Managers and General Contractors
72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.comHartford CT ● Portland ME ● Milford MA
Change Request
Phone:
Job: 1484 Holbrook - New PreK-12 School
Number:
Date:
AT001-P2
10/14/15
To: Joel G. Seeley AIA
Symmes Maini & Mckee
Ph: (617)520-9403 Fax: (800)648-4920
Description: ASI-5 Change Thickness of Deck at Loading Dock
We offer the following specifications and pricing to make the changes as described below:
This allowance transfer is being issued to change the thickness of the metal deck at the loading from 20 gage to 18 gage per sketch ASI #5.3, dated 9/23/15 and issued with ASI 5.
Description Material Subcontract Other PriceLabor Equipment
Allowance - Trimax COR-02, dated 9/30/15 $-1,225.00$-1,225.00
Trimax COR-02, dated 9/30/15 $1,225.00$1,225.00
$0.00Subtotal:
$0.00Fee (5%)
$0.00SDI (1.4%)
$0.00GL (1.2%)
$0.00Builders Risk (.1%)
$0.00P&P Bond (.75%)
$0.00Total:
SCHEDULE IMPACT
We have proceeded with this change to achieve schedule.
As directed, we will not proceed with this change until formal direction from OWNER is received.
(Signature)(Signature)
Date DateDate
ByBy By
(Signature)
OWNERARCHITECT CONTRACTOR
Milford, MA 01757
72 Sumner Street
Consigli Construction Co., Inc.
Boston, MA 02114
77 North Washington Street
Flansburgh Associates, Inc
Holbrook, MA 02343
50 North Franklin Street
Timothy Vautour
Page 1 of 1Consigli Construction Co., Inc.
Construction Managers and General Contractors72 Sumner Street, Milford MA 01757 ● phone: 508-473-2580 ● fax: 508-473-3588 ● web: www.consigli.com
Hartford CT ● Portland ME ● Milford MA
Holbrook PK-‐12 School -‐ Extra Materials List 11/18/15 Tile: Tile and Trim – 3% for each type, composition, color, pattern and size Grout – 3% for each type, composition and color (40 boxes at 20 sf each) Painting: 5% but not less than 1 gallon of each material and color (14 gallons) ACT: Tile -‐ 5% of full size panels of each installed (230 cases at 32 sf each) Suspension System – 2% of each installed Metal ACT: Tile -‐ 2% of full size panels of quantity installed (Part of ACT above) Suspension System – 2% of each grid, exposed molding and trim installed Sound Diffusing Ceiling Units: 10% of quantity installed but not less than 10 units
Mounting devices – full size units -‐ 5% of quantity installed but not less than 10 units
Resilient Base: 10 linear feet for each 500 linear feet installed of each type, color,
pattern and size. (5 boxes at 100 lf per box = 500 LF total) Floor Tile 1 box for each 50 boxes installed of each type, color, pattern and size of
landing floor tile. (49 boxes at 45 sf each) Resilient Sheet Flooring: 10 linear feet for each 500 linear feet installed in roll form and in
full roll width of each type, color, pattern and size. Resilient Tile Flooring: 1 box for each 50 boxes installed of each type, color, pattern and
size of floor tile. Resilient Athletic Flooring: 1 box for each 50 boxes installed of each type, color, pattern and
size of floor installed. (10 boxes of 50 sf each – 24”x24”) Tile Carpeting: Full size units equal to 5% of amount installed for each type
indicated, but not less than 10 sq.yds. (20 boxes of 50 sf each – 18”x18”)
Sheet Carpeting: Full width rolls equal to 5% of amount installed for each type
indicated, but not less than 10 sq.yds. (Included with carpet above)
Sound Reflective Ceiling Panels: Mounting Devices -‐ full size units equal to 5% of quantity
installed but not less than 5 devices -‐ (6) 4’x4’ panels
Sound Absorbing Wall Units: Full size units equal to 5% of amount installed -‐ (6) 4’x4’
panels Sound Absorbing Wood Wall Units: Full size units equal to 5% of amount installed, but
no fewer than 3 units. – (3) units Plastic Toilet Compartments: Door Hinges: 2 Latch and Keeper: 1 Door Bumper: 1 Door Pull: 1 Fasteners: 10 Plastic Shower and Dressing Compartments: Door Hinges: 2 with associated fasteners Latch and Keeper:1 with associated fasteners Clothing Hook: 1 with associated fasteners Door Bumper: 1 with associated fasteners Door Pull: 1 with associated fasteners Fasteners: 10 with associated fasteners Curtain Rod: 1 with associated fasteners Curtain Hooks: 5 with associated fasteners Soap Holder: 1 with associated fasteners Seat: 1 with associated fasteners Cubicle Curtains and Tracks: Curtain Carriers and Track End Caps: Full size units equal to
3% of amount installed for each size indicated, but no fewer than 10 units. – (10) units
Curtains: Full size units equal to 10% of amount installed
for each size indicated, but no fewer than 2 units.-‐ (2) units Folding Panel Partition: Panel Finish Facing Material – Full width in quantity to
cover both sides of two panels when finished.
Metal Lockers: 10% of full size units to match the hardware items installed for each type and finish, but not fewer than 5 units to include locks, identification plates and hooks. (5) Lockers
Roller Window Shades: Full size units equal to 5% of quantity installed for each
size, color and shadeband material indicated, but no fewer than 2 units. -‐ (17) units
Entrance Floor Mats: Full size tile units equal to 2% of quantity installed, but no fewer than 10 units. – (10) units
Fixed Audience Seating: Chair Seats and Backs – 5% of quantity installed for each
type and size (16) units Armrests – 5% of quantity installed for each type -‐ (16)
units Chair Seat Hinge -‐ 5% of quantity installed -‐ (16) units Stacking Chairs: 5% of quantity installed for each type and size -‐ (1) unit HVAC:
§ 4 complete sets of filters for each rooftop unit (15 RTUs)
§ 4 complete set of filters for each energy recover unit
§ 4 complete set of filters for each heating and ventilation unit
§ 1 spare set of belts for each belt driven air handling unit
§ 1 spare set of belts for each belt driven power ventilator -‐ (25) Exhaust Fans
§ 1 case of filters for each make-‐up air unit § 3 complete filter change outs for each cabinet unit
heater -‐ (34) Unit Heaters Electrical:
§ Lighting Fixtures -‐ 5% of quantity of LED of each type, but no fewer than 2 of each type -‐ (70) fixture types
§ 2% of quantity of louvers and lenses of each type but not less than 1 of each type.
§ 2% of quantity of LED drivers of each type, but not less than 1 of each type,
§ 10% of single faced exit signs, but not fewer than 10, include 100 feet of type MC cable branch circuiting and installation labor
§ 10% of double faced exit signs, but not fewer than 5, include 100 feet of type MC cable branch circuiting and installation labor
§ A spare set of fuses of each different type and Ampere rating installed
§ 10 spare smoke detectors § 2 spare manual pull stations
Stage Lighting
§ 25% spare lamps for each type of fixture specified § Additional 15% spare lamps for each type of fixture
specified Telephones:
§ Office Phones -‐ 20% spare § Classroom Phones -‐ 20% spare § Principal and Superintendent Phones -‐ 20% spare § Conference Phones 20% spare § Receptionist Console -‐ 1 spare
Structured Cabling
§ 50 additional single data outlets, including box and conduit stub – assume 290 feet of cable runs
§ 10 Spare single gang technology outlet faceplates including voice, data and video inserts
§ 4 spare 48 port patch panels § 4 spare horizontal wire managers § 8 spare fiber connectors – (4) singlemode and (4)
multimode § 5000 feet of spare Cat 6A cable § 2000 feet of spare Fiber Optic cable (1000 feet of
12 strand Multimode and 1000 feet of 6 strand Singlemode
§ MDF/IDF Room – various spare Transceiver, module, cable
Assistive Listening PK-‐5 Cafeteria -‐ 24 spare ear cushions 6-‐12 Cafeteria -‐ 24 spare ear cushions Gymnasium -‐ 96 spare pair ear cushions Fire Protection Spare heads of each type installed per NFPA 13-‐2013 2 spare sets of gaskets and repair kits for double check
valve assembly Plumbing 1 Back flow preventer spare parts kit
PROJECT MANAGEMENT
NEW HOLBROOK PREK-12 SCHOOL
Holbrook, Massachusetts
TRADE CONTRACTOR BID ANALYSIS
Bids Received November 18, 2015
Filed Sub-Trade
# of
Bids 90% CD Estimate Low Bid
Delta between
estimate and low
bid Bidder Next Low
Delta between low
and next low Remarks
Miscellaneous & Ornamental Metal 5 978,706.00$ 991,270.00$ 12,564.00$ SUPERIOR 1,540,000.00$ 548,730.00$
Waterproofing, Dampproofing and Caulking 5 937,014.00$ 676,100.00$ (260,914.00)$ CHAPMAN 898,925.00$ 222,825.00$
Roofing 7 2,128,880.00$ 2,164,000.00$ 35,120.00$ GREENWOOD 2,332,000.00$ 168,000.00$
Metal Windows 4 2,027,261.00$ 2,297,000.00$ 269,739.00$ LOCKHEED 2,537,000.00$ 240,000.00$
Glass and Glazing 3 156,326.00$ 128,550.00$ (27,776.00)$ KAPILOFF'S 139,316.00$ 10,766.00$ Kapiloff's Glass did not submit Attachments A-F
Tile 8 489,731.00$ 560,000.00$ 70,269.00$ BONOMO 593,346.00$ 33,346.00$
Acoustical Tile 4 767,593.00$ 595,442.00$ (172,151.00)$ K&K 621,260.00$ 25,818.00$ K&K did not submit Attachments A-F
Resilient Flooring 5 867,126.00$ 722,459.00$ (144,667.00)$ WEST 763,847.00$ 41,388.00$
Painting 6 546,454.00$ 467,000.00$ (79,454.00)$ KING 472,480.00$ 5,480.00$
Elevators 2 282,000.00$ 271,000.00$ (11,000.00)$ DELTA 320,800.00$ 49,800.00$
Fire Protection 8 890,681.00$ 815,900.00$ (74,781.00)$ SIMPLEX 863,175.00$ 47,275.00$
Plumbing 5 2,703,771.00$ 2,496,000.00$ (207,771.00)$ ARAUJO 2,587,000.00$ 91,000.00$
HVAC 6 8,205,210.00$ 6,757,000.00$ (1,448,210.00)$ N B KENNEY 6,957,000.00$ 200,000.00$
Electrical 4 7,958,729.00$ 7,059,000.00$ (899,729.00)$ GRIFFIN 7,555,000.00$ 496,000.00$
Total of Trade Contractors 72 28,939,482.00$ 26,000,721.00$ (2,938,761.00)$
PROJECT MANAGEMENT SMMAMassachusetts School Building Authority
Flansburgh Architects
1650'-0"
1850
'-0"
J.F.K. SCHOOL
JUNIOR/SENIOR HIGH SCHOOL
PLYMOUTH STREET
SOUTH FRANKLIN STREET
PLYMOUTH STREET
J.F.K. SCHOOL WETLANDS LINE
JUNIOR/SENIOR HIGH SCHOOL WETLANDS LINE
NEW ROAD+/- 1850’ x 30’ = 55,500 sf (road over wetlands area)
FLOOD ZONE
NEW ROAD+/- 1650’ x 30’ = 49,500 sf (road over wetlands area)
PROPERTY LINE
Holbrook: Potential New Roads @ existing wetlandsN