41
Project Management, Unit 6 Managing Project Time, Cost, and Procurements Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 1

Project Management, Unit 6

  • Upload
    miach

  • View
    25

  • Download
    0

Embed Size (px)

DESCRIPTION

Project Management, Unit 6. Managing Project Time, Cost, and Procurements. Unit Objectives. At the end of this unit the learner will be able to: Define project time management activities Define project cost management activities Define project procurement activities. Unit Outline. - PowerPoint PPT Presentation

Citation preview

Page 1: Project Management, Unit 6

Project Management, Unit 6

Managing Project Time, Cost, and Procurements

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 1

Page 2: Project Management, Unit 6

Unit ObjectivesAt the end of this unit the learner will be able to:

1.Define project time management activities2.Define project cost management activities3.Define project procurement activities

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 2

Page 3: Project Management, Unit 6

Unit OutlineThis unit consists of the following lesson topics:

1.Unit Introduction and Overview2.Define project activities and develop project schedule 3.Develop project cost and develop the project budget 4.Develop a project procurement management plan and evaluate make-or-buy decisions

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 3

Page 4: Project Management, Unit 6

Unit Introduction and Overview

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 4

Page 5: Project Management, Unit 6

.

PROJECT

INITIATION PROJECT

PLANNING

PROJECT

EXECUTION

PROJECT CLOSURE

MONITOR & CONTROL

PROJECT

PLANNING

5Health IT Workforce Curriculum Version 1.0/Fall 2010Component 19/Unit 6

Process Group Sequence

Page 6: Project Management, Unit 6

Essential Planning Processes

1. Collect Requirements Process2. Define Scope Process 3. Create WBS Process 4. Define Activities Process5. Developing Schedule, Determining Budget &

Making Procurement Decisions

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 6

Page 7: Project Management, Unit 6

TIME MANAGEMENT

COST MANAGEMENT PROCUREMENT MANAGEMENT

Define activities Estimate costs Plan procurements

Sequence activities Determine budget Conduct procurements

Estimate activity resources

Control costs Administer procurements

Estimate activity durations

Close procurements

Develop schedule

Control scheduleComponent 19/Unit 6 Health IT Workforce Curriculum

Version 1.0/Fall 2010 7

Project Activities by Process Group

Page 8: Project Management, Unit 6

Collect Requirements Process

Project Charter+ Requirements Documentation

Stakeholder Register

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 8

Page 9: Project Management, Unit 6

Define the Scope Process

Requirements Documentation

Project Scope Statement

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 9

Page 10: Project Management, Unit 6

Create the WBS Process

Project Scope Statement Work Breakdown Structure

+ +

Requirements Documentation Scope Baseline

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 10

Page 11: Project Management, Unit 6

Work Breakdown Structure (WBS)

PROJECT

1.1 1.2 1.3

1.1.1

1.1.2 1.2.1 1.2.2

1.1.1.1

1.1.1.2

1.1.1.3

WORK PACKAGE LEVELdiscrete activities w/definable

end results

Level 1

Level 2

Level 3

Component 19/Unit 6 11Health IT Workforce Curriculum Version 1.0/Fall 2010

Page 12: Project Management, Unit 6

PLAN PURCHASES & ACQUISITION

QUALITYPLANNING

RISKMANAGEMENT

PLANNING

HR PLANNING

COST ESTIMATING

WBSWORK PACKAGE

Work Breakdown Structure (WBS)

ACTIVITYDEFINITION

& ACTIVITY

RESOURCE PLANNING

COMMUNICATIONPLANNING

Component 19/Unit 6 12Health IT Workforce Curriculum Version 1.0/Fall 2010

Page 13: Project Management, Unit 6

Define Activities Process

Scope Baseline Activity List

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 13

Page 14: Project Management, Unit 6

Developing Schedule, Determining Budget & Making Procurement Decision

Develop ScheduleActivity List Determine Budget

Make-or-Buy Decisions

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 14

Page 15: Project Management, Unit 6

Schedule and Cost Constraints

Early in the project it is important for the project team to work with the key stakeholders to identify project constraints related to scope, time, cost and other (technical, legal, etc).

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 15

Page 16: Project Management, Unit 6

Class Exercise

1. Ask the students to list project constraints inherent in their organization (2 minutes)

2. Ask the students to list unique constraints they have encountered on individual projects (2 minutes).

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 16

Page 17: Project Management, Unit 6

PROJECT MANAGERManages the Project Constraints

Component 19/Unit 6 17Health IT Workforce Curriculum Version 1.0/Fall 2010

Project Constraints

Page 18: Project Management, Unit 6

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 18

Triple Constraint: Basic Foundation of Project

Management

Competing demands on projects:

1. Scope 2. Time3. Cost

Consider all constraints equal unless otherwise stated

Cost Time

Scope

Page 19: Project Management, Unit 6

Strategies to Manage Schedule and Cost Constraints

Questions to ask:•Importance of each constraint?•Is possible to prioritize the constraints (rank order)? •What is the flexibility of a constraint?•Can the deadline or budget be negotiated?•What is the customers’ risk tolerance?

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 19

Page 20: Project Management, Unit 6

Time Management Process Sequence

20Health IT Workforce Curriculum Version 1.0/Fall 2010Component 19/Unit 6

Page 21: Project Management, Unit 6

PROCESS GROUP

PROCESS NAME KEY OUTPUTS

1 Planning Define Activities Activity listMilestone list

2 Planning Sequence Activities Project schedule network diagrams

3 Planning Estimate Activity Resources Activity resource requirements Resource breakdown structure

4 Planning Estimate Activity Durations Activity duration estimates

5 Planning Develop Schedule Project scheduleSchedule baseline

6 Monitor & Control

Control Schedule Work performance measurements, Change requests

Component 19/Unit 6 21Health IT Workforce Curriculum Version 1.0/Fall 2010

Time Management Processes and Outputs

Page 22: Project Management, Unit 6

Developing a Project Schedule

1) Activities are sequenced (predecessors and successors are determined)

2) Activity paths are determined 3) Duration of each path is calculated4) Critical path is identified (longest path &

determines the soonest the project will complete)

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 22

Page 23: Project Management, Unit 6

Schedule Terminology

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 23

• Duration• Effort• Project schedule

network• Activity relationships• Schedule

Page 24: Project Management, Unit 6

Activity Duration Estimates

The project team can estimate the likely number of work periods required to perform an activity by using any of the following techniques:

•Analogous•Expert Judgment•Parametric•Three point estimate•PERT (three point estimate with weighted average)

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 24

Page 25: Project Management, Unit 6

Dependency Determinations

The project team must determine the existence of dependencies between activities when preparing a schedule. There are three types of dependencies or relationships between activities.

•Mandatory•Discretionary•External

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 25

Page 26: Project Management, Unit 6

Activity Sequencing - Precedence Diagramming Method (PDM)

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 26

B 5

E 5

C 12

F 14

D 2

G 17

H 11

A 8

FINISHSTART

Page 27: Project Management, Unit 6

Student exercise:(5 minutes)

Identify other paths thru the above network, calculate the duration of the paths, and then determine which path is the critical path.

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 27

PATHS DURATION CRITICAL PATH

ABCDH 8 + 5 + 12 + 2 + 11= 38

Page 28: Project Management, Unit 6

Duration Compression Techniques

• Crashing - involves adding additional resources to perform an activity to compress the schedule, but may result in increased cost to the project

• Fast tracking - involves over lapping activities which normally are performed in sequence. Compressing the schedule by performing activities at the same time or in parallel may result in increased project risk and rework.

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 28

Page 29: Project Management, Unit 6

Project Cost Management - Develop Estimates for Project Cost and Budget

• The project team aggregates the estimated costs of individual activities or work packages to establish a cost baseline.

• A cost management plan is developed by the project team and describes how project costs will be planned, managed and controlled (i.e. cost estimates, cost budgeting, cost baseline, cost variances).

• During project execution the project team uses the cost performance baseline to monitor and control project costs.

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 29

Page 30: Project Management, Unit 6

Project Cost Management - Develop Estimates for Project Cost and Budget

Project Cost Management Processes which Occur in Project Planning, Execution, and Monitor & Control: • Estimate costs• Determine budget• Control Costs

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 30

Page 31: Project Management, Unit 6

PROCESS GROUP

PROCESS NAME KEY OUTPUTS

1 Planning Estimate Costs Activity cost estimates,Basis of estimates

2 Planning Determine Budget Cost Performance Baseline,Project funding requirements

3 Monitor & Control

Control Costs Work Performance Measurements,Budget Forecasts,Change requests

Component 19/Unit 6 31Health IT Workforce Curriculum Version 1.0/Fall 2010

3 project cost management processes and key outputs

Page 32: Project Management, Unit 6

Types of Project Costs1. Direct cost 2. Indirect cost 3. Fixed cost 4. Variable cost

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 32

Page 33: Project Management, Unit 6

How are Costs Estimated?• Analogous• Parametric• Bottom-up

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 33

Page 34: Project Management, Unit 6

How are Costs Controlled?• Cost management plan• Project performance• Change request

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 34

Page 35: Project Management, Unit 6

Project Procurement Management Processes

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 35

Project Procurement Management Processes which occur in Project Planning, Execution, Monitor & Control, and Closing:1. Plan Procurements2. Conduct Procurements3. Administer Procurements4. Close Procurements

Page 36: Project Management, Unit 6

Project Procurement Management Processes and Key Outputs

PROCESS GROUP

PROCESS NAME KEY OUTPUTS

1 Planning Plan ProcurementsProcurement management planProcurement statements of workMake-or-buy decisionsProcurements documentsSource selection criteria

2 Executing Conduct ProcurementsSelected SellersProcurement contract awardResource calendars

3Monitor & Control

Administer Procurements Procurement documentation

4 Closing Close Procurements Closed procurements

Component 19/Unit 6 36Health IT Workforce Curriculum Version 1.0/Fall 2010

Page 37: Project Management, Unit 6

Types of ContractsThere are three main types of contracts. The type of contract selected may be based on the good or service to be purchased or level of scope of work definition.

1. Fixed-Price or Lump-Sum Contracts2. Cost-Reimbursable Contracts 3. Time and Material Contracts

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 37

Page 38: Project Management, Unit 6

What are Procurement or Bid Documents?

• Invitation for Bid (IFB)• Request for Proposal (RFP)• Request for Quotation (RFQ)

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 38

Page 39: Project Management, Unit 6

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 39

Contracting Environments: Centralized & Decentralized

Advantages Disadvantages

Centralized • Greater contracting expertise• Economical and more efficient

• Working multiple projects

Decentralized

• Greater focus on a specific project• PM has authority to execute and control contract • Greater loyalty to a project

• Duplication of effort • Inconsistent contracting practices

Page 40: Project Management, Unit 6

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 40

Administer Procurements Process & Close Procurements Process

Administering the procurement process involves monitoring and controlling the contract performance, managing procurement relationships, and making changes and corrections when required.

A procurement audit is performed at the completion of each contract.

Contracts must be closed before the project can be closed.

Page 41: Project Management, Unit 6

Summary• Developing a realistic schedule and budget and

accurately making procurement decisions is based on having well defined project scope

• The project manager must continually monitor and control the schedule, budget, and procurements to ensure project success.

Component 19/Unit 6 Health IT Workforce Curriculum Version 1.0/Fall 2010 41