Project Management @ UF. Practical management of projects Randy Graff, PhD. Goals. Basic understanding of a Project Experience planning tools. Terms Example Brainstorm tasks Share documents and tasks Enter WBS and Resources. Objectives. Formal Project Management. Introduction - PowerPoint PPT Presentation

Citation preview

Project Managem

ent @ U

F

Practical management of projects Randy Graff, PhD

Goals• Basic understanding of a Project• Experience planning tools

Objectives• Terms• Example

• Brainstorm tasks• Share documents and tasks• Enter WBS and Resources

Formal Project Management• Introduction• Framework• Charter• Workload• Estimating• Scheduling• Timeline• Risk Management• Resources• Implementation• Tracking• Reporting• Life Cycle• Closure

• Tools– MS Project– MS Outlook

• Email• Tasks• Calendar

Day 1 Day 2 Day 3 Day 4

Practical Project Management

Scope Document

Work Breakdown Schedule

Gantt Chart

ResourcesImplementation

Tracking

Reporting

Hour 1

Planning and Management

MS Project

Collaborative Work Space

Brainstorm Tools

Tools

Hour 2

Scope Document

Very well defined “What”

Scope DocumentIntroduction and Background

Description

Objectives

Measures of Success

Impact (customers, operations, systems)

Costs

Constraints

Team

Work Breakdown Schedule

• Tasks• Duration• Grouping• Order

Task1 Hour1 Day1 Week1 Month

Task

1 Hour1 Day1 Week1 Month

Task

1 Hour1 Day1 Week1 Month

Task

1 Hour1 Day1 Week1 Month

Task

1 Hour1 Day1 Week1 Month

Task

1 Hour1 Day1 Week1 Month

Group

Group

1

2

3

4

5

Gantt Chart

• Visual of tasks and resourcesID Task Nam e Start

4 CANOES- TDC grant $ available Thu 9/18/085 GALLERIA- Expend Soltis NSF $ (or extend 1 yr) Tue 6/30/096 CANOES/GAL- Bid process, contract award Mon 7/20/097 CANOES/GAL- Expend all state match funds Fri 5/28/108 CANOES/GAL -- Fabrication Wed 7/1/099 CANOES/GAL- Outsourced const.dwgs&Fabrication Mon 9/14/0910 CANOES/GAL- In-house fabrication Wed 7/1/0911 CANOES/GAL- Object mounts Tue 6/1/1012 CANOES/GAL- Install (outsource components) Mon 5/3/1013 CANOES/GAL- Install Contingency Mon 5/24/1014 CANOES Tue 1/1/0815 CANOES -- Content Development Tue 1/1/0816 CANOES/GALLERIA- Prelim content develop Tue 1/1/0817 CANOES- Final script Mon 9/29/0818 CANOES- Graphics Wed 10/8/0819 CANOES- Objects Fri 8/1/0820 CANOES- Preliminary Object list Fri 8/1/0821 CANOES- Final Object List Mon 3/2/0922 CANOES- Finalizing Object Loans Fri 8/1/0823 CANOES- Initial Condition Reports (exhibit) Fri 8/1/0825 CANOES- Final Condition Reports Mon 5/3/1026 CANOES- Spanish translation Wed 7/1/0927 CANOES- Educators' Guide Mon 5/4/0928 CANOES- Programming Ideas due Mon 3/1/1029 CANOES -- Design Tue 4/1/0830 CANOES- Concept/Schematic Design Tue 4/1/0831 CANOES- Design Concept Tue 7/1/0832 CANOES- Schematic/Specs Mon 6/1/0933 CANOES- Bid Package Wed 7/1/0934 CANOES -- Media Mon 11/3/08

Darcie,Purchasing,Pam

Darcie,Ian,Purchasing

Darcie

contractors

in-house team

TBD

contractors,staff

Darcie,Donna Haritha

Darcie,Donna,Haritha

Darcie,Donna,Haritha

Outsource -- Carlos Plaza

Jay F,Ian

Ian,Prov idence

Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q2 Q3 Q4 Q1 Q22006 2007 2008 2009 2010 2011 2012 2013Tasks Duration

Group

Resources• People• Things• Schedules• Cost

Implementation• Signed approvals– Project– Time commitments– Funding– Equipment

• Getting started– You– Others

Tracking

Being aware of everything Nagging Communicating Updating Gantt

and WBS

Regular progress Milestones Problems Completion

and closure

Reporting

Getting Started

MS Project

Collaborative Work Space

Brainstorm Tools

Tools

• http://bubbl.us/ • www.inspiration.com• http://www.mindjet.com/

Collaborative Workspace

• http://pbworks.com• http://www.activecollab.com• http://docs.google.com• http://lss.at.ufl.edu

– http://sakaiproject.org

Google docsPB Works

Active Colab

Agenda

Brief Overview

Project Components

Glimpse of Project

Task

Recurring Task

Report

Backup

Brief Overview

Project•Group of linked tasks•Particular sequence•Predefined resources

Manage a project Schedule

Views and reports

Project Components

• Toolbars• Properties

Window• Tasks• Linking• Milestones

• Lag and lead time

• Resources• Printing• Saving• Backing up

ID Task Name Duration

1 Project meetings 96 days

22 Test standards 9 days

23 Develop test plan 3 hrs

24 Conduct test 5 days

25 Evaluate results and modify as needed 1 day

26 Update project plan 3 hrs

27 Review with stakeholders 2 hrs

28 Phase end 0 days

29 Implementation 19 days

30 Develop implementation plan 6 hrs

31 Develop training plan 5 days

32 Execute training plan 2 wks

33 Implement 1 wk

34 Review with stakeholders 2 hrs

35 Phase end 0 days

Tom,Jane,Erin

Tom,Erin

Project Team

Project Team

Tom,Jane,Erin

3/27

Jane

Erin

Erin

Erin,Jane

Jane,Erin,Project Team

4/10

Mar 2, '03 Mar 9, '03 Mar 16, '03 Mar 23, '03 Mar 30, '03 Apr 6, '03 Apr 13, '03 Apr 20, '03 Apr 27, '03

Final Product: Gantt Chart

ID Task Name Duration

1 Project meetings 96 days

22 Test standards 9 days

23 Develop test plan 3 hrs

24 Conduct test 5 days

25 Evaluate results and modify as needed 1 day

26 Update project plan 3 hrs

27 Review with stakeholders 2 hrs

28 Phase end 0 days

29 Implementation 19 days

30 Develop implementation plan 6 hrs

31 Develop training plan 5 days

32 Execute training plan 2 wks

33 Implement 1 wk

34 Review with stakeholders 2 hrs

35 Phase end 0 days

Tom,Jane,Erin

Tom,Erin

Project Team

Project Team

Tom,Jane,Erin

3/27

Jane

Erin

Erin

Erin,Jane

Jane,Erin,Project Team

4/10

Mar 2, '03 Mar 9, '03 Mar 16, '03 Mar 23, '03 Mar 30, '03 Apr 6, '03 Apr 13, '03 Apr 20, '03 Apr 27, '03

ID Task Name Duration

1 Project meetings 96 days

22 Test standards 9 days

23 Develop test plan 3 hrs

24 Conduct test 5 days

25 Evaluate results and modify as needed 1 day

26 Update project plan 3 hrs

27 Review with stakeholders 2 hrs

28 Phase end 0 days

29 Implementation 19 days

30 Develop implementation plan 6 hrs

31 Develop training plan 5 days

32 Execute training plan 2 wks

33 Implement 1 wk

34 Review with stakeholders 2 hrs

35 Phase end 0 days

Tom,Jane,Erin

Tom,Erin

Project Team

Project Team

Tom,Jane,Erin

3/27

Jane

Erin

Erin

Erin,Jane

Jane,Erin,Project Team

4/10

Mar 2, '03 Mar 9, '03 Mar 16, '03 Mar 23, '03 Mar 30, '03 Apr 6, '03 Apr 13, '03 Apr 20, '03 Apr 27, '03

Task SideTask Side

ID Task Name Duration

1 Project meetings 96 days

22 Test standards 9 days

23 Develop test plan 3 hrs

24 Conduct test 5 days

25 Evaluate results and modify as needed 1 day

26 Update project plan 3 hrs

27 Review with stakeholders 2 hrs

28 Phase end 0 days

29 Implementation 19 days

30 Develop implementation plan 6 hrs

31 Develop training plan 5 days

32 Execute training plan 2 wks

33 Implement 1 wk

34 Review with stakeholders 2 hrs

35 Phase end 0 days

Tom,Jane,Erin

Tom,Erin

Project Team

Project Team

Tom,Jane,Erin

3/27

Jane

Erin

Erin

Erin,Jane

Jane,Erin,Project Team

4/10

Mar 2, '03 Mar 9, '03 Mar 16, '03 Mar 23, '03 Mar 30, '03 Apr 6, '03 Apr 13, '03 Apr 20, '03 Apr 27, '03

ID Task Name Duration

1 Project meetings 96 days

22 Test standards 9 days

23 Develop test plan 3 hrs

24 Conduct test 5 days

25 Evaluate results and modify as needed 1 day

26 Update project plan 3 hrs

27 Review with stakeholders 2 hrs

28 Phase end 0 days

29 Implementation 19 days

30 Develop implementation plan 6 hrs

31 Develop training plan 5 days

32 Execute training plan 2 wks

33 Implement 1 wk

34 Review with stakeholders 2 hrs

35 Phase end 0 days

Tom,Jane,Erin

Tom,Erin

Project Team

Project Team

Tom,Jane,Erin

3/27

Jane

Erin

Erin

Erin,Jane

Jane,Erin,Project Team

4/10

Mar 2, '03 Mar 9, '03 Mar 16, '03 Mar 23, '03 Mar 30, '03 Apr 6, '03 Apr 13, '03 Apr 20, '03 Apr 27, '03

Gantt Side

Tasks Entered

Alternate Task Input/Edit

Enter Recurring Tasks

Recurring Tasks Entered

Viewing and Printing Reports

Backup

Backup

MS Project Review• Task• Recurring Task• Report• Backup

Review• Terms• Example

• Brainstorm tasks• Enter WBS and Resources• Share documents and tasks