Page 1: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E
Page 2: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Project Management Support Services for the

495 Express Lanes Northern Extension

Pre-Proposal Conference

March 26, 2019 Ken Connors, P.E. – Project Manager, VDOT Mega Projects – Northern Virginia District

Suril R. Shah, P.E., DBIA – Senior Alternative Project Delivery Engineer

Page 3: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Overview of 495 Northern Extension Project

495 Express Lanes

Current Activities

Overview of the Professional Services RFP

Questions

Agenda Items

Virginia Department of Transportation

Page 4: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

PROJECT OVERVIEW

Page 5: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Early 2000s: VDOT begins planning a highway

expansion to address traffic on the Capital

Beltway in Virginia.

2002: The private sector proposal. VDOT

approves it.

2007: VDOT finalizes its long-term agreement

2008: Construction kicks off

2012: The 495 Express Lanes open

2018: VDOT initiates NEPA Study

2019: VDOT Enters into framework agreement

with Capital Beltway Express Partners

Virginia Department of Transportation

Page 6: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Ranked number 1 as most

congested segment in the

region

I-495 congestion routinely

extends between American

Legion Bridge and Tysons

(south of Dulles Toll Road)

Multiple hours of congestion

during AM and PM peak periods

and weekends

Cut-through traffic using local

roads and residential streets on

either side of I-495

Virginia Department of Transportation

Existing Conditions

Page 7: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Virginia Department of Transportation

Northbound Traffic Congestion

Page 8: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Virginia Department of Transportation

Southbound Traffic Congestion

Page 9: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Virginia Department of Transportation

Ongoing NEPA – Environmental Assessment

Current Schedule:

NEPA Initiated - 2018

Public Information Meeting – May 2019

NEPA Public Hearing – September 2019

Anticipated FONSI – December 2019

Page 10: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Virginia Department of Transportation

• A 2.5-mile extension of the 495

Express Lanes north to the

American Legion Bridge

• Four general purpose (GP) lanes

and two new Express Lanes in

each direction of the Capital

Beltway

• Express Lanes connections with

the George Washington Memorial

Parkway and the Dulles Toll Road

• Reconstruction of 2 overpass

bridges

• Reconstruction of Interchange at

Georgetown Pike

• Independent from Maryland project

Project Scope

Page 11: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Dulles Toll Road

Virginia Department of Transportation

• I-495/Dulles Toll Road Interchange

design in progress

• Ultimate configuration will not be

precluded by Build Alternative

Page 12: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

George Washington Memorial Parkway

Virginia Department of Transportation

• Direct connection

Express Lanes ramps to

and from the South

• Coordination with

Maryland ongoing

Page 13: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

http://www.495northernextension.org/

Virginia Department of Transportation

Page 14: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Professional Services RFP - Overview

Virginia Department of Transportation

Page 15: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

The Scope of this contract anticipates providing Project Management Support services for the 495

Express Lanes. The Scope of services mainly includes but is not limited to the following disciplines:

Estimated Contract Value is $36 Million with an anticipated duration of 5 years

o The estimated contract value is not guaranteed under the contract.

o Scope of work and budget established through Annual Wok Plans (AWP) each year

15

Scope

• Project Management

• Contract Management

• Engineering Support Services

• Procurement Support services

• Environmental Services

• Right-of-Way and Utility Services

• Traffic Management Plans and Coordination

• Traffic Planning, Forecasting, Design

• Intelligent Transportation Systems

• Tolling

• Public Affairs/Outreach Management

• Construction Management and Inspection Services

• Materials Services

• Safety Program

• DBE and SWaM Support

• Project Controls

• Agency Coordination

Page 16: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

• Optional Pre-Proposal Conference 03/26/2019

• Questions/Clarifications due 03/29/2019

• Expression of Interest Due 04/05/2019 at 2:00 PM

• Short List Posted on VDOT website 04/19/2019

• Interviews/Technical Presentations 05/03/2019

• Final Consultant Selection 05/14/2019

• Pre-Award Documents Due 05/29/2019

• Completed Negotiations/Agreement Due 06/19/2019

• Consultant Contract Signed 07/10/2019

16

Anticipated Procurement Schedule

Page 17: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

17

Project Organization

Page 18: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

The following are the Key Personnel positions for this Project:

1) Consultant Project Manager (P.E. Required) - Consultant leadership role for the contract, and directly

supports VDOT’s project leadership to enable successful on-time, and on-schedule delivery of the Project.

2) Consultant Contracts Manager - Management and administrative lead for consultant staff resourcing

and contract management

3) Engineering Task Manager (VA P.E. Required) - Responsible for managing and overseeing all

Engineering tasks.

4) Construction Task Manager (P.E. Required) – Responsible for managing and overseeing all

Construction tasks.

18

Key Personnel & Other Classifications

Page 19: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

5) Senior Environmental Specialist – Will oversee Environmental tasks. Prepares/reviews documentation

in accordance with National Environmental Policy Act (NEPA) and/or with Virginia requirements.

6) Senior Public Relations Specialist – Leads and/or supports all public relation efforts

• Resumes are required for the Key Personnel only.

• Only One individual permitted for all Key Personnel Classifications

• P.E. Licenses are required at the time of submitting EOI

All other anticipated Classifications and associated responsibilities are also included in the RFP.

The Department anticipates that these classifications will require a standard/ average level of

expertise, and plans to negotiate accordingly.

19

Key Personnel & Other Classifications (Cont’d.)

Page 20: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

20

Contract Administration – AWP Approach

AWP

- Will describe the work for the upcoming year and establish anticipated budget for the Work

- An Annual Work Plan will be prepared by the Consultant each year and approved by the

Department on a fiscal-year basis (July 1 to June 30).

- First Annual Work Plan will be from the date of Contract execution to June 30, 2020

- Please note that VDOT does not pay for the development of AWPs; and the Consultant’s

preparation of invoices to VDOT.

Page 21: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Travel • Staff assigned to a VDOT office location: Travel calculated from the assigned VDOT office location.

• Staff not assigned to VDOT office location: Travel calculated from the staff’s Virginia office

• Staff from an out-of-state office: Travel calculated from the firm’s Virginia office closest to the staff’s out-

of-state office

• Sub-consultant staff with no Virginia office: Travel calculated from the Prime Consultant’s Virginia office

closest to the sub-consultant’s out-of-state office.

• VDOT does not pay consultants for travel time.

Travel And Overtime

Virginia Department of Transportation

Page 22: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Overtime • Key Personnel and Senior Personnel classifications will not be eligible for overtime

compensation for work hours exceeding 40 hours/week.

• Other classifications may be allowed overtime compensation (for work hours exceeding 40

hours/week) on a case-by-case basis with prior written approval from the VDOT Project

Manager provided the Consultant submits supporting documentation for the overtime payment

to the individual(s).

Travel And Overtime (Cont’d.)

Virginia Department of Transportation

Page 23: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

The following firms that are affiliated with the Maryland Department of Transportation (MDOT)

and/or the Maryland State Highway Administration (MSHA) and providing services on their I-

495 & I-270 P3 program are precluded from participating in this procurement due to a Conflict

of Interest:

23

Conflict of Interest

• ATCS, P.L.C.

• Capital Project Strategies, LLC

• CDM Smith, Inc.

• Louis Berger Group, Inc., The

• Reynolds, Smith & Hills, Inc. (RS&H)

• Rummel, Klepper & Kahl, LLC (RK&K)

• Whitman Requardt & Associates (WRA)

• Wilson T. Ballard Co., The

• WSP

Page 24: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

In accordance with VDOT’s IIM APD 2.2, each Offeror shall conduct an internal review of its

current affiliations and shall require its team members to identify potential Conflict of Interest,

or a real or perceived competitive advantage relative to the anticipated procurement.

o This includes, but is not limited to, potential conflict presented by working for (MDOT) and/or

(MSHA) on the I-495 project.

o Should a potential conflict exist, the firm shall obtain a written Conflict of Interest determination

from VDOT prior to submitting an Expression of Interest (EOI).

o VDOT will require a minimum of three (3) business days for issuing a determination

o The request for determination must include sufficient details including, but not limited to, the

firm’s role, scope, prime/sub-consultant information, and work performed on the project to date.

VDOTs COI policy is available at http://www.virginiadot.org/business/resources/APD_Docs/APD_Office_Page/IIM-APD-2.2_Final_11-9-

2017.pdf

24

Conflict of Interest

Page 25: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

• Information/Records available to the consultants working on existing VDOT contracts for this

Project are considered proprietary, confidential and not public. As such, the consultants are

prohibited from using such data and information to compete for this RFP.

• In the event of any unauthorized disclosure of such confidential information, VDOT reserves

the right to take any necessary actions including but not limited to terminating the subject team

from further competing on this procurement.

25

Conflict of Interest (Cont’d.)

Page 26: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

• Must be submitted in two separate volumes

• EOI submittals required through VDOT’s ProjectWise system – All information must be uploaded

and received prior to 2:00pm on 04/05/2019

• All items shall be on 8 ½” X 11” and printed one side with single spaced type no smaller that 10

point where applicable

Expression of Interest

Virginia Department of Transportation

Page 27: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Carefully Review the instructions when preparing EOI

KEY PERSONNEL Resumes in SF 330 Part I, Section E (Item 4) - Each resume shall be

limited to two (2) pages with a font no less than 10 point.

• The number of relevant projects should be limited to no more than five (5). If more than five projects are

provided, only the first five (5) projects will be considered for evaluations.

• Provide scope, size and cost for each of the relevant projects.

• Clearly identify the Key Personnel’s role, state its duration, indicate whether it was part-time or full-time,

and describe the tasks performed on these projects.

• Identify if the tasks were performed as an owner representative or as part of the Contractor’s team.

• Contracts and Projects cannot be interchangeably used with the exception of Contract Manager’s resume

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 28: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

KEY PERSONNEL Resumes in SF 330 Part I, Section E (Item 4) Cont. -

Provide the following items in Section 18 of Key Personnel Resume :

a) Chronologically list:

1) employment history

2) position held

3) duration of employment for the last fifteen (15) years.

b) List all current active assignments (contracts/projects) including but not limited to VDOT and other

assignments along with associated roles and responsibilities. Also, clearly identify tasks performed to

date on these assignments along with the start and end date of these assignments.

c) Provide a list of pursuits for which SOQs/EOIs have been submitted and also the ones that you intend to

pursue. Provide associated roles and responsibilities.

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 29: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

SF 330 Part I, Section F (Example Projects Which Best Illustrate Proposed Team’s

Qualifications for this Contract) (Item 5) - Provide the scope, size and cost of projects and

describe how they are relevant to the subject contract. Projects and Contracts cannot be used

interchangeably.

SF 330 Part I, Section H (Additional Information) (Item 7) – This section is limited to a

maximum of five (5) pages.

Item 11 -

In two (2) pages or less, provide your contract administration approach for the subject contract.

The approach shall provide the anticipated staffing plan to meet the schedule. Your approach

should also highlight measurable commitments to deliver the contract in a fiscally responsible

manner.

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 30: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Item 12 -

In five (5) pages or less, please provide your approach in the management of the following for the

I-495 NEXT project:

a. Engineering management

b. Construction Management

c. Agency Coordination

d. Environmental Management

e. Traffic/ TMP Management

Item 13 -

In three (3) pages or less, identify five (5) key challenges likely to be encountered on this project.

Using specific examples from experience of the individuals listed on the organizational chart,

provide your approach in managing these challenges.

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 31: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Item 14 -

Provide a list of all projects, contracts, task orders, or any other work being performed by the

Offeror, including its team members, on the I-495 project on behalf of MDOT and/or MSHA.

The information shall provide sufficient details including, but not limited to, each firm’s role and

scope of work performed on the project to date. Also, identify the Contract/ Project number,

whether the work was performed as a prime or sub-consultant, and provide a list of all team

members on the Contract/Project.

There is no page limit for this information submittal.

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 32: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

DBE – The DBE contract goal for this procurement is 12%

Expression of Interest (Cont’d.)

Virginia Department of Transportation

Page 33: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

33

SCORING CRITERIA & PRESENT WORKLOAD

Page 34: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Consistent with 23 CFR172.11 requirements, VDOT will conduct negotiations

with the selected firm.

• The classification rates will be negotiated based on the fair and reasonable market rates in Virginia for

the position and associated responsibilities. The classifications rates will not solely be based on

Individual’s salary.

• Principals, partners, directors, vice presidents, officers and those with similar duties and titles those with

similar titles are considered to have administrative and/or management functions whose costs have been

included in the overhead. If the Consultant choses to propose these individuals for any classifications, the

individual’s salary will be removed from the computations of Pre-Award submittal used for negotiations. In

any case, the hourly rate established for the classification will be established without considering his/her

salary.

• All firms will be required to have field and home office overhead rates.

Negotiations

Virginia Department of Transportation

Page 35: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Keeping Team Intact

• VDOT expects all Key Personnel identified on the Organizational chart to remain on the Consultant’s

Team for the duration of the procurement process and, if the consultant is awarded a contract, the

duration of the contract unless otherwise approved by VDOT.

Negotiations (Cont’d.)

Virginia Department of Transportation

Page 36: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

• For AWP 1, from the execution of the contract to June 30, 2020, an escalation of 1.5% will be

allowed.

• For AWP 2 beginning July 1, 2020 through June 30, 2021, the escalation rate of 3% will be

allowed.

• AWP 3 onwards the escalation rate will be based on the annual VDOT published rate for that

year.

Escalation

Virginia Department of Transportation

Page 37: Project Management Support Services for the...Project Management Support Services for the 495 Express Lanes Northern Extension Pre-Proposal Conference March 26, 2019 Ken Connors, P.E

Thank You

37

QUESTIONS??