6-1 Allocating Resources to the Project

Project Management in Practice

  • Upload
    fathi

  • View
    45

  • Download
    3

Embed Size (px)

DESCRIPTION

Project Management in Practice. Allocating Resources to the Project. Outline:. Expediting or Crashing a project Resource Loading Resource Leveling. Homework: 20 (omit e) using MSP 21 (an AOA diagram may help!) by hand and Excel. Expediting A Project:. - PowerPoint PPT Presentation

Citation preview

Page 1: Project Management in  Practice

6-1

Allocating Resources to the Project

Page 2: Project Management in  Practice

6-2

Homework: 20 (omit e) using MSP 21 (an AOA diagram may help!) by hand and Excel

Expediting or Crashing a project Resource Loading Resource Leveling

Page 3: Project Management in  Practice

6-3

Table 6-1, Example

Project completion time = 21 days, cost $400, critical path = a-c-f

Page 4: Project Management in  Practice

6-4

Table 6-1, Example (21 days, baseline)

a6

a6

e5

e5

c6

c6

b7

b7

f9f9

d7

d7

g7

g7

0 6

13 20

6 13

12 21

0 7

6 12

0 6

7 14

9 14

7 12

2 9

5 7 12 21

14 21

6 or 4 days only

Page 5: Project Management in  Practice

6-5

Table 6-1, Example (20 days)

a5

a5

e5

e5

c6

c6

b7

b7

f9f9

d7

d7

g7

g7

0 5

12 19

5 12

11 20

0 7

5 11

0 5

6 13

8 13

7 12

1 8

5 7 11 20

6 or 4 days only

13 20

Page 6: Project Management in  Practice

6-6

Table 6-1, Example (19 days)

6 or 4 days only

a6

a6

e5

e5

c6

c6

b7

b7

f9f9

d7

d7

g7

g7

0 6

13 20

6 13

12 21

0 7

6 12

0 6

7 14

9 14

7 12

2 9

5 7 12 21

14 21

Page 7: Project Management in  Practice

6-7

Table 6-1, Example (19 days)

6 or 4 days only

a5

a5

e5

e5

c6

c6

b7

b7

f8f8

d7

d7

g7

g7

0 5

12 19

5 12

11 19

0 7

5 11

0 5

7 12

0 7

5 7 11 19

12 19

5 12

7 12

Page 8: Project Management in  Practice

6-8

Table 6-1, Example (18 days)

6 or 4 days only

a5

a5

e5

e5

c4

c4

b7

b7

f9f9

d7

d7

g6

g6

a (-1)

g (-1)

c (-2)

Page 9: Project Management in  Practice

6-9

Table 6-1, Example (max)

a5

a5

e5

e5

c4

c4

b7

b7

f9f9

d7

d7

g6

g6

Fully crashed.

Fully crashed.

Crashed by 1.

Page 10: Project Management in  Practice

6-10

Table 6-1, Example (max=16)

a5

a5

e5

e5

c4

c4

b7

b7

f9f9

d7

d7

g6

g6

Fully crashed.

Fully crashed.

Crashed by 1.

f7

g4

Page 11: Project Management in  Practice

Project Cost versus Project DurationExample Table 6.1

$400$430

$470

$550

$650

$750

Page 12: Project Management in  Practice

6-12

Table 6-1, Example (21 days, baseline) AOA

11

22

55

44

33

66

May be crashed 1 day at a time

a6

b7

c6

d7

e5

f9

g7

Page 13: Project Management in  Practice

6-13

Table 6-1, Example (21 days, baseline) AOA

May be crashed 1 day at a time

11

22

55

44

33

66

a6

b7

c6

d7

e5

f9

g7

Page 14: Project Management in  Practice

Amount of specific resources that are scheduled for use on specific activities or projects at specific times.

Usually a list or table.

6-14

Page 15: Project Management in  Practice

6-15

Page 16: Project Management in  Practice

6-16

Page 17: Project Management in  Practice

6-17

No Resource Loading7 Day Work WeekFormat Gantt Chart Wizard

a5

a5

c5

c5

e2

e2

b3

b3

f6f6

d4

d4

g2

g2

0 5

9 11

5 9

7 13

0 3

5 7

3 8

Activity Resourcesa Timb Joec Gusd Amye Amy,Joef Sueg Tim

0 5

7 11

6 11

11 13

3 6

5 7 7 13

d,e

Page 18: Project Management in  Practice

6-18

Added ResourcesAdded Resource Names to GanttTools, Level Resources Clear Leveling (button)

a5

a5

c5

c5

e2

e2

b3

b3

f6f6

d4

d4

g2

g2

0 5

9 11

5 9

7 13

0 3

5 7

3 8

Activity Resourcesa Timb Joec Gusd Amye Amy,Joef Sueg Tim

0 5

7 11

6 11

11 13

3 6

5 7 7 13

Page 19: Project Management in  Practice

6-19

ViewResource Usage

ViewResource Graph

Activity Resourcesa Timb Joec Gusd Amye Amy,Joef Sueg Tim

Page 20: Project Management in  Practice

6-20

Tools, Level Resources Level Now (button)

Used d’s (LS/LF) slackto avoid overloading of Amy

a5

a5

c5

c5

e2

e2

b3

b3

f6f6

d4

d4

g2

g2

0 5

11 13

7 11

7 13

0 3

5 7

3 8

Activity Resourcesa Timb Joec Gusd Amye Amy,Joef Sueg Tim

0 5

7 11

6 11

11 13

3 6

5 7 7 13

Page 21: Project Management in  Practice

6-21

View Resource Usage

Activity Resourcesa Timb Joec Gusd Amye Amy,Joef Sueg Tim

Page 22: Project Management in  Practice

6-22

Unleveled

Page 23: Project Management in  Practice

6-23

Leveled

e finishes at 7, but f cannot startSue is still busy on c

a5

a5

c5

c5

e2

e2

b3

b3

f6f6

d4

d4

g2

g2

0 3 3 80 5

7 11 12 14

5 7 7 138 14

Activity Resourcesa Timb Joec Sued Amye Amy,Joef Sueg Tim

d cannot start until time 7because Amy is not free

11 13

7 12

0 5

5 7 8 14

e cannot start at time 6 and finish at 8because Amy is needed on task d at time 7

8 12

3 6

b cannot LF at time 7because Joe is needed on e at time 6

Page 24: Project Management in  Practice

6-24

LeveledActivity Resources

a Timb Joec Sued Amye Amy,Joef Sueg Tim