Project Management

HNC Computing 2000

Unit 8 Quality Management

Prepared by S Hargrave

Page 2: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Time

CostQuality Features

Project manager must negotiate for more time, more people or fewer features

Page 3: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Project Management

Planning identifying activities determining order estimating length deciding on resources

Control ongoing reallocating resources

Page 4: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Documentation

Requirements specification Purchase requisition forms Manpower budget Change control documents Work plan/task list

Page 5: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Techniques

Gantt Charts Project Evaluation and Review

Techniques (PERT) Critical Path Analysis (CPA)

Page 6: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Project Management Tool : Network Analysis Critical Path Diagrams

Planned activities Dependencies

Page 7: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Case Study

Installing a network

Page 8: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Identify Activities Carry out initial study of

needs Invite tenders from

suppliers appoint suppliers obtain computer

equipment convert classroom advertise for technician shortlist candidates and

invite to interview

Interview candidates test computer hardware procure office furniture install furniture and

network system procure network software prepare documentation for

users test network correct system faults train staff

Page 9: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Activity dependence

Page 10: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Network Analysis (1)

1 2 3A B

Activity B starts when Activity A ends

Page 11: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Network Analysis (2)

3

4

5 6

C

D

E

E begins when both C and D have finished

Page 12: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Network Analysis (3)

3

4

21A

B

C

Page 13: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Rules for Network Drawing

There must be only one start node and one finish node

No activities are allowed to have the same start and finish node

Arrows should go from left to right

Page 14: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Network Analysis (4)A

B

WRONG

Dummy Activity RIGHT

Page 15: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Activity PrecedingActivity

Duration(Days)

LatestStartTime

EarliestStart Time(of nextactivity)

SlackTime

A Initialsurvey

None 15 0

B InviteTenders

A 19 15

C AppointSuppliers

B 5 34

D ObtainComputerEquipment

C 10 39

E ConvertClassroom

C 40 39

Page 16: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Latest Starting Time

Page 17: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Slack Time

E LD

Slack Time =

EST of following activity minus no of days for current activity minus LST of current activity

Page 18: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

Slack Time continuedActivity Preceding

ActivityDuration(Days)

LatestStartTime

EarliestStartTime(of nextactivity)

SlackTime

A Initial survey None 15 0 15 0

B Invite Tenders A 19 15 34 0

C AppointSuppliers

B 5 34 39 0

D ObtainComputerEquipment

C 10 39 79 30

E ConvertClassroom

C 40 39 79 0

Page 19: Project Management HNC Computing 2000 Unit 8 Quality Management Prepared by S Hargrave

CriticalPath

Resource Scheduling