Upload
charity-whitford
View
213
Download
1
Tags:
Embed Size (px)
Citation preview
Project Management Fundamentals
Element K
Version: Apr-12
Kim AndrewsSenior Practice Partner
L&OD613-7612
2
Duke Course Objectives• Determine why projects fail• Describe the methodologies, tools,
and techniques to manage projects
• Plan and meet schedule deadlines and budget goals
3
Is It a Project?
Project Work and Ongoing Work Are DifferentOngoing Work Project WorkRepeating process One of a kind, temporary processNo clear beginning or ending Clear beginning and endingSame output created each time Output is created only onceEveryone in work group Requires multi-disciplined team performs similar functions
Project Management – Planning, organizing, scheduling, leading, communicating, and controlling work activities to achieve time and budget goals.
Workbook page 2
4
The Project Management Life Cycle
5
Progression of Risk
6
Role of the Project Manager
• Leader
• Planner
• Organizer
• Controller
• Communicator
• Negotiator
• Peace Maker
• Advocate
• Risk Manager
7
3 Factors of Success
8
Initiation Phase
9
Statement of Work
• Stakeholders and their responsibilities
• Purpose
• Objectives
• Scope
• Sign-off and review hierarchies
• Reporting and communication plans
• Assumptions or Constraints
10
Project CharterOfficial statement of support by the project’s sponsor
• Name, purpose, and objectives of project
• Name of project manager
• Authorization to use organizational
resources
11
The Project Team
12
Sources of Risk
13
Risk Assessment
14
Project Management LawsMurphy’s Law – Anything that can go wrong, will go wrong.Finagle’s Law of Dynamic Negatives or Finagle’s Corollary to Murphy’s Law - Anything that can go wrong, will – at the worst possible moment.Hofstadter’s Law – It always takes longer than you expect, even when you take into account Hofstadter’s law.Parkinson’s Law – Work expands so as to full the time available for its completion.
15
Risk Management Approaches• Avoid It
• work around so risk never occurs
• Accept It• live with the consequences
• Transfer It• share the risk
• Mitigate It• prepare through contingency planning
16
The Project Management Life Cycle
17
Work Breakdown Structure
18
Dependencies/Relationships
Finish-to-Start
Finish-to-Finish
Start-to-Start
Start-to-Finish
Preceding activity must finish before successor activity can start
Preceding activity must finish before successor activity can finish
Preceding activity must start before successor activity can start
Preceding activity must start before successor activity can finish
Relationship Description Gantt Chart
19
Dependency Table
20
Network Logic Diagram
21
The Project Schedule1. Estimate the duration and effort.2. Calculate the critical path.3. Calculate float.
22
The Project Schedule
23
Float
24
The Schedule. What if…The Gantt Chart
25
Project BudgetCost Element
Description Formula
Labor People costs, including overtime
• (regular hours x hourly rate) + (overtime hours x overtime rate)
• + pro-rated overhead and fringe benefits
Equipment Purchase, lease, or rental price and the cost of usage
• Purchase pricelease or rental price x time period
• Pro-rated usage fees
Facilities The cost of the space to house the team, utilities, and services
• Rental cost x time period• Organizational burden rate x
time period
Supplies Consumables • Estimated volume x cost + inflation adjustment
Special expenses
• Estimated cost
26
Balance the Budget and Schedule
• Shorten the schedule• Lengthen the schedule• Increase the budget• Change the scope• Change the expected quality
27
The Project Management Life Cycle
28
Identifying Variances
29
Identifying Variances
30
Earned Value Analysis Cost Variance Percentage (CVP)
Schedule Variance Percentage (SVP)
Estimate at Completion (EAC)
31
Variables UsedBudgeted versus Actual
Work Scheduled versus Work Performed
Budgeted Cost for Work Scheduled (BCWS) – the amount you budget for a task between its start date and today (not the end of the project!)
Budgeted Cost for Work Performed (BCWP) – the % of the task budget that corresponds to the task’s completion status
Actual Cost for Work Performed (ACWP) – The actual cost of the task so far
32
Cost Variance Percentage(BCWP – ACWP) / BCWP = CVP
Divides cost variance by budgeted cost.
A negative value means a cost overrun.
33
Schedule Variance Percentage
(BCWP – BCWS) / BCWS = SVP
Divides schedule variance by cost to date.
A negative value means the work is behind schedule.
34
Estimate at Completion(Original cost x ACWP) / BCWP =
EAC
Recalculates the cost or completion date based on performance to date.
35
Dealing with Variances1. Find the cause.2. Plan corrective action.3. Determine overall project impact.4. Present the information to
stakeholders.
36
Project ReportsType of Information
Key Questions And…
Status Is the project on target? What are you, the PM, doing to fix the situation?
Are there problems or variances that need to be addressed?
Progress What has the project team accomplished since the last update?
Why? Or Why not?
What work packages are complete, which partially complete, etc.?
What are you, the PM, doing to fix the situation?
Project Forecast
What is the outlook for ongoing status and progress?
Are there scope and goal changes that must be made in order to complete the project successfully?
What support do you need from others to make it happen?
37
Report Formats
38
Report Formats
39
Report Formats
40
Report Formats
41
Change Request• Change
• Requested By• Reason for Change
• Method of Change
• Affected Parties• Affect on Success Criteria
• Backup Information
• Sign-Offs• Date of Approval
42
The Project Management Life Cycle
43
Duke Course Objectives• Determine why projects fail• Describe the methodologies, tools,
and techniques to manage projects
• Plan and meet schedule deadlines and budget goals
Project Management Fundamentals
Element K
Version: Apr-12
Kim AndrewsSenior Practice Partner
L&OD613-7612