Project Management - CPI SPI EAC (1)

Embed Size (px)

DESCRIPTION

PMAN 639 Final Exam

Citation preview

  • 5/26/2018 Project Management - CPI SPI EAC (1)

    1/4

    a. At the end of week 1:

    i. What is your SPI?

    ii. What is your CPI?

    iii. What is your EAC?

    In this project we developed the project budget and schedule as follows:

    Activity Duration Budgeted Cost

    Mobilize the team 1 $3,000

    Lay the Cable (15 miles) 3 $45,000

    Terminate & test the cable 1 $5,000

    Total 5 $53,000

    At the end of 1 week

    ActivityScheduled

    Completion

    Actual

    Completion

    Budgeted Cost of

    Work Scheduled

    Budgeted Cost of

    Work Performed

    BCWS BCWP

    Mobilize the Team 100% 100% $3,000 $3,000Lay the cable (15 miles) 0% 0% $0 $0

    Terminate & test the cable 0% 0% $0 $0

    Total $3,000 $3,000

    b. At the end of week 1:

    i. What is your SPI?

    ii. What is your CPI?

    iii. What is your EAC?

    At the end of 3 week

    ActivityScheduled

    Completion

    Actual

    Completion

    Budgeted Cost of

    Work Scheduled

    Budgeted Cost of

    Work Performed

    BCWS BCWP

    Mobilize the Team 100% 100% $3,000 $3,000

    Lay the cable (15 miles) 67% 33% $30,000 $15,000

    Terminate & test the cable 0% 0% $0 $0

    Total $33,000 $18,000

    c. At the end of the project:

    i. What is your SPI?

    ii. What is your CPI?

    iii. What is your EAC?

    At the end of the project

    EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP

    EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP

  • 5/26/2018 Project Management - CPI SPI EAC (1)

    2/4

    ActivityScheduled

    Completion

    Actual

    Completion

    Budgeted Cost of

    Work Scheduled

    Budgeted Cost of

    Work Performed

    BCWS BCWP

    Mobilize the Team 100% 100% $3,000 $3,000

    Lay the cable (15 miles) 100% 100% $45,000 $45,000

    Terminate & test the cable 100% 100% $5,000 $5,000Total $53,000 $53,000

    EAC: Sum for all tasks: + ACWP (if task is complete) + Budgeted cost (if task is not started) + (ACWP/BCWP

  • 5/26/2018 Project Management - CPI SPI EAC (1)

    3/4

    Actual Cost of

    Work PerformedCPI SPI EAC

    ACWP = BCWP/ACWP = BCWP/BCWS

    $4,500$0

    $0

    $4,500 0.667 1.000 $54,500

    Actual Cost of

    Work PerformedCPI SPI EAC

    ACWP = BCWP/ACWP = BCWP/BCWS

    $4,500

    $28,000

    $0

    $32,500 0.554 0.545 $93,500

    * Task Budget) if task is underway

    * Task Budget) if task is underway

  • 5/26/2018 Project Management - CPI SPI EAC (1)

    4/4

    Actual Cost of

    Work PerformedCPI SPI EAC

    ACWP = BCWP/ACWP = BCWP/BCWS

    $65,000 0.815 1.000 $65,000

    * Task Budget) if task is underway