Project Life Cycle Analysis

Embed Size (px)

Citation preview

  • 8/11/2019 Project Life Cycle Analysis

    1/21

    George Currie

    George is based in Black & Veatchs Singapore officeand leads its Management Consulting Division teamin Asia. He has been working across the Middle Eastand Asia for the past 30 years in projectdevelopment, finance and construction, bridging thedivide between technology, finance and thecomplex legal framework within which major capitalprojects are brought to fruition. His experienceencompasses various private participation models inall types of infrastructure projects, including not

    only power generation plants but also high speedrail, urban rail, toll roads, ports, airports, and waterand wastewater treatment projects.

    A civil engineer by profession, George spent theearly part of his career in project management inthe energy, transportation and water sectors, and is

    skilled in the technical aspects of project design anddelivery. In 1992, as part of his Masters degree inConstruction Management specializing in ValueManagement (with an emphasis on whole-life costsof assets), he graduated the very first Society of

    Office LocationSingapore

    EducationB.Sc. (Honors) CivilEngineering M.Sc. ConstructionManagement

    Managing Director Asia

    Pacific ManagementConsulting

  • 8/11/2019 Project Life Cycle Analysis

    2/21

    GEORGE CURRIE

    POWER PLANT LIFE CYCLE COST ANALYSIS: REVIEWING BASIC POWER PLANT BID EVALUATION TECHNIQUES

    2 5 N o v e m b e r 2 0 1 3

  • 8/11/2019 Project Life Cycle Analysis

    3/21

    Power plant bid evaluation will determine the makeup of the PLN system for the next 30+ years

    To review the power plant lifecycle cost evaluation technique for screening power plant proposals

    Explain why this approach is preferred over focusing on a single cost component such as capital cost only

    Explain why bids must be evaluated and compared on an apples to apples basis in order to make valid resource selection decisions

    PURPOSE OF PRESENTATION

    25 November 2013BVI |

    2

  • 8/11/2019 Project Life Cycle Analysis

    4/21

    Consist of the total fixed and variable costs over the lifetime of a power plant

    Must evaluate all power plant costs on a present value basis to identify lowest cost option: this is the power plant lifecycle cost approach

    Utility and developer trend of focusing on direct capital cost to the exclusion of life cycle costs and the EPC contractors record This is not in the interest of utilities,

    off takers or national economies

    POWER PLANT LIFE CYCLE COSTS DEFINITION AND TRENDS

    25 November 2013BVI |

    3

  • 8/11/2019 Project Life Cycle Analysis

    5/21

    A utility has issued an RFP for a 500 MW coal fired power plant

    Two bids are received having different capital cost and performance

    characteristics Lets evaluate by comparing capital

    costs only and then by comparing life cycle costs

    UTILITY & POWER CONSUMER PERSPECTIVE EXAMPLE

    25 November 2013BVI |

    4

  • 8/11/2019 Project Life Cycle Analysis

    6/21

    SAMPLE BID INFORMATION FOR TWO IPP PROPOSALS

    25 November 2013

    5

    BVI |

    Bid 1

    is

    20%

    lower

    in

    capital

    cost,

    but

    what

    about power plant life cycle costs?

    Bid Information Bid 1 Bid 2Total Capital Cost, $/kW 2,000$ 2,400$Total Capital Cost $ 1,000,000,000$ 1,200,000,000$Net Plant Output, MW 500 500Expected / Guranteed Availability (%) 90 / 86 90 / 90

    Full Load Net Plant Heat Rate (kJ/kWh) 10,867 10,550 Fixed O&M, 1st Year, $/kW-year 25.00$ 22.00$Variable O&M, 1st Year, $/MWh 2.10$ 2.00$Escalation of O&M 3.0% 2.5%Fuel Cost $/GJ $3.80 $3.70

    Fuel Escalation 3.0% 2.5%

  • 8/11/2019 Project Life Cycle Analysis

    7/21

    Step 1: Develop annual cost streams for all cost components: capital costs, FOM, VOM, fuel costs

    FOM, VOM, and fuel costs: begin with the 1st year bid price and escalate according to a bid escalation index (or a RFPspecified escalation rate) RFP often will ask for evidence that the fuel cost rate bid is

    achievable RFPs often ask for an O&M plan and evidence that the O&M costs

    are achievable for the technology, as demonstrated in other existing plants

    Future value

    formula:

    Present

    value

    * (1+i)^n Where i is the escalation rate and n is the number of periods

    into the future (1+i)^n is called the future value factor

    TO DEVELOP A POWER PLANT LIFE CYCLE COST ANALYSIS:

    25 November 2013

    6

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    8/21

    Capital costs include the EPC cost and many indirect or owners costs (legal fees, permitting, land costs, owners engineer, financing costs, interest during construction, etc.)

    All should be considered

    Convert capital costs to an annual capacity cost stream by developing a levelized fixed charge rate (FCR) that is applied to the total capital cost

    The FCR is the singe rate that, when applied to the initial capital cost, produces a revenue stream adequate to offset all capital

    related costs on present worth basis Developed through a FCR spreadsheet program

    CONVERTING CAPITAL COSTS TO AN ANNUAL CAPACITY CHARGE / COST

    25 November 2013

    7

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    9/21

    POWER PLANT LIFE CYCLE COSTS: BID 2

    25 November 2013

    8

    BVI |

    Illustration of

    each

    cost

    component

    column:

    annual capital, FOM, VOM, fuel cost

  • 8/11/2019 Project Life Cycle Analysis

    10/21

    Developing the annual cost of each component and summing these yields a total annual cost ($304,012 for year 1 in the example)

    To compare life cycle costs among bids, we must also account for the time value of money

    Done by discounting the future total costs to the present by applying the following formula to the total year cost: 1/(1+i)^n , which is called the present value factor Where i is the discount rate (usually the utility weighted cost of

    capital), and n is the year of operation

    In our example, the discount rate is 9.5% and when applied to the 1styear total capital cost of $304,012 it gives a present value cost of $277,636 (in thousands of US$)

    This process of discounting is followed for each year

    ACCOUNTING FOR THE TIME VALUE OF MONEY

    25 November 2013

    9

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    11/21

    Summing the present value of annual costs yields the total life cycle cost of a power plant bid

    Often, these life cycle costs are stated on a levelized cost / kWh basis

    Levelization refers to the process of converting the variable, year by year costs in to a single cost that has the same present value (and therefore makes the comparison among bids much simpler than comparing entire cost streams)

    Levelization is done by taking the sum of the present worth costs divided by the sum of the present worth factors

    In our example, the levelized cent/kWh cost is 8.82 cents/kWh

    DEVELOPING COSTS / KWH AND LEVELIZING COSTS

    25 November 2013

    10

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    12/21

    This levelized cost assumes a single capacity factor each year

    By developing levelized costs at various capacity factors, a levelized total cost curve is produced for screening bids

    If the cost curve for 1 option is above the cost curve for another option at all capacity factors, then the higher cost option can be safely eliminated

    If there is a cross over at realistic capacity factor ranges, more detailed (production costing models that simulate operation of the entire power system) are required (provided by utility planning

    departments or consultants such as Black & Veatch planning personnel)

    USE OF LEVELIZED COST CURVES

    25 November 2013

    11

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    13/21

    CENT/KWH COST COMPARISON: BID 1 VS. BID 2

    25 November 2013

    12

    BVI |

    Bid 2

    becomes

    lower

    in

    cost

    at

    80%

    capacity

    factor and higher

    8.6

    9.1

    9.6

    10.1

    10.6

    60% 70% 80% 86% 90%

    C e n t

    / k W h L e v e l i z e d C o s t

    Levelized Life Cycle CostsBid 1 vs. Bid 2

    Bid 1Levelizedc/kWh Cost

    Bid 2Levelizedc/kWh Cost

  • 8/11/2019 Project Life Cycle Analysis

    14/21

    OTHER LIFE CYCLE COST RESULTS: BID 1 VS. BID 2

    25 November 2013

    13

    BVI |

    Distribution of Total Life Cycle Costs

    (Bid 2, Nominal Costs)

    CapitalFixed O&MVar. O&MFuel

    $200,000,000

    $250,000,000

    $300,000,000

    $350,000,000

    $400,000,000

    $450,000,000

    $500,000,000

    $550,000,000

    $600,000,000

    1 4 7 10 13 16 19 22 25 28

    D o l l a r C o s t s

    Year of Operation

    Annual Costs: Bid 1 vs Bid 2at 90% Capacity Factor

    Bid 1 Yearly Costs Bid 2 Yearly Costs

    Distribution of

    Total Life

    Cycle

    Costs

    (Bid 1, Nominal Costs)

    CapitalFixed O&M

    Var. O&MFuel

  • 8/11/2019 Project Life Cycle Analysis

    15/21

    OTHER LIFE CYCLE COST RESULTS: BID 1 VS. BID 2

    25 November 2013

    14

    BVI |

    Bid 2 has significant cost advantages over Bid 1

    $100,000,000

    $0

    $100,000,000

    $200,000,000

    $300,000,000

    $400,000,000

    $500,000,000

    $600,000,000

    1 4 7 10 13 16 19 22 25 28

    D o

    l l a r C o s t s

    Year of Operation

    Cumulative Savings

    of Bid 2

    $(40,000,000)

    $(30,000,000)

    $(20,000,000)

    $(10,000,000)

    $

    $10,000,000

    $20,000,000

    $30,000,000

    $40,000,000

    1 4 7 10 13 16 19 22 25 28

    Present Value Cost Savings of

    Bid 2(9.5% Discount Rate)

  • 8/11/2019 Project Life Cycle Analysis

    16/21

    To fairly compare options, need to consider the potential power replacement cost

    to achieve

    an

    equivalent

    of 90% availability guaranteed for Bid 2

    $85 to $140 million (nominal) in this case, depending on replacement power cost

    OTHER CONSIDERATIONS: RECALL THE BID 1 GUARANTEED AVAILABILITY OF 86% VS. 90% FOR BID 2

    25 November 2013

    15

    BVI |

    $60,000,000

    $70,000,000

    $80,000,000

    $90,000,000

    $100,000,000

    $110,000,000

    $120,000,000

    $130,000,000

    $140,000,000

    $150,000,000

    10 12 14 16

    First Year US cent/kWh Cost of Replacement Power

    (then 3%

    escalation)

    30Year Replacement Power Cost, 4%

    Difference in Availability (Nominal US$)

  • 8/11/2019 Project Life Cycle Analysis

    17/21

    Added investment in capital cost can significantly improve long term performance, plant availability, and plant life

    This benefit can be difficult to assess, but the RFP should require sufficient in formation and guarantees such that the cost / benefit of bids can be assessed by qualified experts

    For example, require guaranteed availability with PPA penalty, require design / spares information in bid, require guaranteed NPHR with PPA penalty, require maintenance schedule to be submitted as part of bid

    Bidder must be willing to transfer all performance and guarantees

    to the PPA Bidder experience is a key: Have they done it before? What EPC contractor is the developer using?

    OTHER CONSIDERATIONS

    25 November 2013

    16

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    18/21

    Black & Veatch is well qualified to help in this bid evaluation function

    The example of guaranteed availability differences (86% vs 90%) underscores the need to fairly compare different bid options on an apples to apples basis

    Done by designing a performance RFP in which bidders are required to meet a specified performance level (for example, the RFP may specify the required minimum output, COD schedule, availability, NPHR, etc.)

    In the evaluation period, adjustments are made to bids to fairly evaluate differences in performance, usually by bringing deviations back to the performance specifications

    Requires a team of qualified specialists in power plant design and utility economics

    OTHER CONSIDERATIONS

    25 November 2013

    17

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    19/21

    Departing from

    these

    principles

    is

    not

    in

    the

    interest

    of utilities, off takers or national economies

    Choosing based only on lowest capital cost per kW rather than on life cycle cost and the ability to deliver performance guarantees can be

    very costly Only by evaluating the life cycle cost of competing options can

    proper economic decisions be made for the benefit of power customers and national economies

    Evaluating competing options can be difficult because bids will have different features in terms of performance, schedule, and cost

    Nevertheless, it is very important to evaluate bids on a fair or apples to apples basis and this can require specialists who are experienced at making such assessments / comparisons

    Black & Veatch can assist PLN in evaluating competing power plant bids; let us know how we can help

    CONCLUSIONS

    25 November 2013

    18

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    20/21

    Q&A

    25 November 2013

    19

    BVI |

  • 8/11/2019 Project Life Cycle Analysis

    21/21

    www.bv.com