Upload
masgraha
View
220
Download
0
Embed Size (px)
Citation preview
8/11/2019 Project Life Cycle Analysis
1/21
George Currie
George is based in Black & Veatchs Singapore officeand leads its Management Consulting Division teamin Asia. He has been working across the Middle Eastand Asia for the past 30 years in projectdevelopment, finance and construction, bridging thedivide between technology, finance and thecomplex legal framework within which major capitalprojects are brought to fruition. His experienceencompasses various private participation models inall types of infrastructure projects, including not
only power generation plants but also high speedrail, urban rail, toll roads, ports, airports, and waterand wastewater treatment projects.
A civil engineer by profession, George spent theearly part of his career in project management inthe energy, transportation and water sectors, and is
skilled in the technical aspects of project design anddelivery. In 1992, as part of his Masters degree inConstruction Management specializing in ValueManagement (with an emphasis on whole-life costsof assets), he graduated the very first Society of
Office LocationSingapore
EducationB.Sc. (Honors) CivilEngineering M.Sc. ConstructionManagement
Managing Director Asia
Pacific ManagementConsulting
8/11/2019 Project Life Cycle Analysis
2/21
GEORGE CURRIE
POWER PLANT LIFE CYCLE COST ANALYSIS: REVIEWING BASIC POWER PLANT BID EVALUATION TECHNIQUES
2 5 N o v e m b e r 2 0 1 3
8/11/2019 Project Life Cycle Analysis
3/21
Power plant bid evaluation will determine the makeup of the PLN system for the next 30+ years
To review the power plant lifecycle cost evaluation technique for screening power plant proposals
Explain why this approach is preferred over focusing on a single cost component such as capital cost only
Explain why bids must be evaluated and compared on an apples to apples basis in order to make valid resource selection decisions
PURPOSE OF PRESENTATION
25 November 2013BVI |
2
8/11/2019 Project Life Cycle Analysis
4/21
Consist of the total fixed and variable costs over the lifetime of a power plant
Must evaluate all power plant costs on a present value basis to identify lowest cost option: this is the power plant lifecycle cost approach
Utility and developer trend of focusing on direct capital cost to the exclusion of life cycle costs and the EPC contractors record This is not in the interest of utilities,
off takers or national economies
POWER PLANT LIFE CYCLE COSTS DEFINITION AND TRENDS
25 November 2013BVI |
3
8/11/2019 Project Life Cycle Analysis
5/21
A utility has issued an RFP for a 500 MW coal fired power plant
Two bids are received having different capital cost and performance
characteristics Lets evaluate by comparing capital
costs only and then by comparing life cycle costs
UTILITY & POWER CONSUMER PERSPECTIVE EXAMPLE
25 November 2013BVI |
4
8/11/2019 Project Life Cycle Analysis
6/21
SAMPLE BID INFORMATION FOR TWO IPP PROPOSALS
25 November 2013
5
BVI |
Bid 1
is
20%
lower
in
capital
cost,
but
what
about power plant life cycle costs?
Bid Information Bid 1 Bid 2Total Capital Cost, $/kW 2,000$ 2,400$Total Capital Cost $ 1,000,000,000$ 1,200,000,000$Net Plant Output, MW 500 500Expected / Guranteed Availability (%) 90 / 86 90 / 90
Full Load Net Plant Heat Rate (kJ/kWh) 10,867 10,550 Fixed O&M, 1st Year, $/kW-year 25.00$ 22.00$Variable O&M, 1st Year, $/MWh 2.10$ 2.00$Escalation of O&M 3.0% 2.5%Fuel Cost $/GJ $3.80 $3.70
Fuel Escalation 3.0% 2.5%
8/11/2019 Project Life Cycle Analysis
7/21
Step 1: Develop annual cost streams for all cost components: capital costs, FOM, VOM, fuel costs
FOM, VOM, and fuel costs: begin with the 1st year bid price and escalate according to a bid escalation index (or a RFPspecified escalation rate) RFP often will ask for evidence that the fuel cost rate bid is
achievable RFPs often ask for an O&M plan and evidence that the O&M costs
are achievable for the technology, as demonstrated in other existing plants
Future value
formula:
Present
value
* (1+i)^n Where i is the escalation rate and n is the number of periods
into the future (1+i)^n is called the future value factor
TO DEVELOP A POWER PLANT LIFE CYCLE COST ANALYSIS:
25 November 2013
6
BVI |
8/11/2019 Project Life Cycle Analysis
8/21
Capital costs include the EPC cost and many indirect or owners costs (legal fees, permitting, land costs, owners engineer, financing costs, interest during construction, etc.)
All should be considered
Convert capital costs to an annual capacity cost stream by developing a levelized fixed charge rate (FCR) that is applied to the total capital cost
The FCR is the singe rate that, when applied to the initial capital cost, produces a revenue stream adequate to offset all capital
related costs on present worth basis Developed through a FCR spreadsheet program
CONVERTING CAPITAL COSTS TO AN ANNUAL CAPACITY CHARGE / COST
25 November 2013
7
BVI |
8/11/2019 Project Life Cycle Analysis
9/21
POWER PLANT LIFE CYCLE COSTS: BID 2
25 November 2013
8
BVI |
Illustration of
each
cost
component
column:
annual capital, FOM, VOM, fuel cost
8/11/2019 Project Life Cycle Analysis
10/21
Developing the annual cost of each component and summing these yields a total annual cost ($304,012 for year 1 in the example)
To compare life cycle costs among bids, we must also account for the time value of money
Done by discounting the future total costs to the present by applying the following formula to the total year cost: 1/(1+i)^n , which is called the present value factor Where i is the discount rate (usually the utility weighted cost of
capital), and n is the year of operation
In our example, the discount rate is 9.5% and when applied to the 1styear total capital cost of $304,012 it gives a present value cost of $277,636 (in thousands of US$)
This process of discounting is followed for each year
ACCOUNTING FOR THE TIME VALUE OF MONEY
25 November 2013
9
BVI |
8/11/2019 Project Life Cycle Analysis
11/21
Summing the present value of annual costs yields the total life cycle cost of a power plant bid
Often, these life cycle costs are stated on a levelized cost / kWh basis
Levelization refers to the process of converting the variable, year by year costs in to a single cost that has the same present value (and therefore makes the comparison among bids much simpler than comparing entire cost streams)
Levelization is done by taking the sum of the present worth costs divided by the sum of the present worth factors
In our example, the levelized cent/kWh cost is 8.82 cents/kWh
DEVELOPING COSTS / KWH AND LEVELIZING COSTS
25 November 2013
10
BVI |
8/11/2019 Project Life Cycle Analysis
12/21
This levelized cost assumes a single capacity factor each year
By developing levelized costs at various capacity factors, a levelized total cost curve is produced for screening bids
If the cost curve for 1 option is above the cost curve for another option at all capacity factors, then the higher cost option can be safely eliminated
If there is a cross over at realistic capacity factor ranges, more detailed (production costing models that simulate operation of the entire power system) are required (provided by utility planning
departments or consultants such as Black & Veatch planning personnel)
USE OF LEVELIZED COST CURVES
25 November 2013
11
BVI |
8/11/2019 Project Life Cycle Analysis
13/21
CENT/KWH COST COMPARISON: BID 1 VS. BID 2
25 November 2013
12
BVI |
Bid 2
becomes
lower
in
cost
at
80%
capacity
factor and higher
8.6
9.1
9.6
10.1
10.6
60% 70% 80% 86% 90%
C e n t
/ k W h L e v e l i z e d C o s t
Levelized Life Cycle CostsBid 1 vs. Bid 2
Bid 1Levelizedc/kWh Cost
Bid 2Levelizedc/kWh Cost
8/11/2019 Project Life Cycle Analysis
14/21
OTHER LIFE CYCLE COST RESULTS: BID 1 VS. BID 2
25 November 2013
13
BVI |
Distribution of Total Life Cycle Costs
(Bid 2, Nominal Costs)
CapitalFixed O&MVar. O&MFuel
$200,000,000
$250,000,000
$300,000,000
$350,000,000
$400,000,000
$450,000,000
$500,000,000
$550,000,000
$600,000,000
1 4 7 10 13 16 19 22 25 28
D o l l a r C o s t s
Year of Operation
Annual Costs: Bid 1 vs Bid 2at 90% Capacity Factor
Bid 1 Yearly Costs Bid 2 Yearly Costs
Distribution of
Total Life
Cycle
Costs
(Bid 1, Nominal Costs)
CapitalFixed O&M
Var. O&MFuel
8/11/2019 Project Life Cycle Analysis
15/21
OTHER LIFE CYCLE COST RESULTS: BID 1 VS. BID 2
25 November 2013
14
BVI |
Bid 2 has significant cost advantages over Bid 1
$100,000,000
$0
$100,000,000
$200,000,000
$300,000,000
$400,000,000
$500,000,000
$600,000,000
1 4 7 10 13 16 19 22 25 28
D o
l l a r C o s t s
Year of Operation
Cumulative Savings
of Bid 2
$(40,000,000)
$(30,000,000)
$(20,000,000)
$(10,000,000)
$
$10,000,000
$20,000,000
$30,000,000
$40,000,000
1 4 7 10 13 16 19 22 25 28
Present Value Cost Savings of
Bid 2(9.5% Discount Rate)
8/11/2019 Project Life Cycle Analysis
16/21
To fairly compare options, need to consider the potential power replacement cost
to achieve
an
equivalent
of 90% availability guaranteed for Bid 2
$85 to $140 million (nominal) in this case, depending on replacement power cost
OTHER CONSIDERATIONS: RECALL THE BID 1 GUARANTEED AVAILABILITY OF 86% VS. 90% FOR BID 2
25 November 2013
15
BVI |
$60,000,000
$70,000,000
$80,000,000
$90,000,000
$100,000,000
$110,000,000
$120,000,000
$130,000,000
$140,000,000
$150,000,000
10 12 14 16
First Year US cent/kWh Cost of Replacement Power
(then 3%
escalation)
30Year Replacement Power Cost, 4%
Difference in Availability (Nominal US$)
8/11/2019 Project Life Cycle Analysis
17/21
Added investment in capital cost can significantly improve long term performance, plant availability, and plant life
This benefit can be difficult to assess, but the RFP should require sufficient in formation and guarantees such that the cost / benefit of bids can be assessed by qualified experts
For example, require guaranteed availability with PPA penalty, require design / spares information in bid, require guaranteed NPHR with PPA penalty, require maintenance schedule to be submitted as part of bid
Bidder must be willing to transfer all performance and guarantees
to the PPA Bidder experience is a key: Have they done it before? What EPC contractor is the developer using?
OTHER CONSIDERATIONS
25 November 2013
16
BVI |
8/11/2019 Project Life Cycle Analysis
18/21
Black & Veatch is well qualified to help in this bid evaluation function
The example of guaranteed availability differences (86% vs 90%) underscores the need to fairly compare different bid options on an apples to apples basis
Done by designing a performance RFP in which bidders are required to meet a specified performance level (for example, the RFP may specify the required minimum output, COD schedule, availability, NPHR, etc.)
In the evaluation period, adjustments are made to bids to fairly evaluate differences in performance, usually by bringing deviations back to the performance specifications
Requires a team of qualified specialists in power plant design and utility economics
OTHER CONSIDERATIONS
25 November 2013
17
BVI |
8/11/2019 Project Life Cycle Analysis
19/21
Departing from
these
principles
is
not
in
the
interest
of utilities, off takers or national economies
Choosing based only on lowest capital cost per kW rather than on life cycle cost and the ability to deliver performance guarantees can be
very costly Only by evaluating the life cycle cost of competing options can
proper economic decisions be made for the benefit of power customers and national economies
Evaluating competing options can be difficult because bids will have different features in terms of performance, schedule, and cost
Nevertheless, it is very important to evaluate bids on a fair or apples to apples basis and this can require specialists who are experienced at making such assessments / comparisons
Black & Veatch can assist PLN in evaluating competing power plant bids; let us know how we can help
CONCLUSIONS
25 November 2013
18
BVI |
8/11/2019 Project Life Cycle Analysis
20/21
Q&A
25 November 2013
19
BVI |
8/11/2019 Project Life Cycle Analysis
21/21
www.bv.com