12
PROJECT CRASHING 1

Project Life Cycle

Embed Size (px)

DESCRIPTION

About how a project is made,How it advances to the next stage and how it is finally implemented on a large scale.

Citation preview

  • PROJECT CRASHING

    *

    Wiley 2010

  • PROJECT MANAGEMENT What is a project?Any unique endeavor with specific objectivesWith multiple activitiesWith defined precedent relationshipsWith a specific time period for completionExamples?A major event like a weddingAny construction projectDesigning a political campaign

    *

    Wiley 2010

  • PROJECT LIFE CYCLE

    ConceptDevelopmentImplementationTermination

    *

    Wiley 2010

  • NETWORK PLANNING TECHNIQUESProgram Evaluation & Review Technique (PERT):Developed to manage the Polaris missile projectMany tasks pushed the boundaries of science & engineering (tasks duration = probabilistic)

    Critical Path Method (CPM):Developed to coordinate maintenance projects in the industryA complex undertaking, but individual tasks are routine (tasks duration = deterministic)

    *

    Wiley 2010

  • REDUCING PROJECT COMPLETION TIMEProject completion times may need to be shortened because:Different deadlinesPenalty clausesNeed to put resources on a new projectPromised completion datesReduced project completion time is crashing*

    Wiley 2010

  • REDUCING PROJECT COMPLETION TIME CONT

    Crashing a project needs to balanceShorten a project durationCost to shorten the project durationCrashing a project requires you to knowCrash time of each activityCrash cost of each activityCrash cost/duration = (crash cost-normal cost)/(normal time crash time)*

    Wiley 2010

  • REDUCING THE TIME OF A PROJECT (CRASHING)*

    ActivityNormal Time (wk)Normal Cost ($)Crash TimeCrash Cost ($)Max. weeks of reductionReduce cost per weekA48,000311,00013,000B630,000535,00015,000C36,00036,00000D624,000428,00022,000E1460,0001272,00026,000F55,00046,50011500G26,00026,00000H24,00024,00000I34,00025,00011,000J44,00026,40021,200K25,00025,00000

  • CRASHING EXAMPLE: SUPPOSE THE NETSOL PROJECT MANAGER WANTS TO REDUCE THE NEW PRODUCT PROJECT FROM 41 TO 36 WEEKS. Crashing Costs are considered to be linearLook to crash activities on the critical pathCrash the least expensive activities on the critical path first (based on cost per week)Crash activity I from 3 weeks to 2 weeks Rs 1000Crash activity J from 4 weeks to 2 weeks Rs 2400Crash activity D from 6 weeks to 4 weeks Rs 4000Recommend Crash Cost Rs 7400

    Question: Will crashing 5 weeks return more in benefits than it costs?*

    Wiley 2010

  • CRASHED NETWORK DIAGRAM *

  • SUMMARYA project is a unique, one time event of some duration that consumes resources and is designed to achieve an objective in a given time period.Each project goes through a four-phase life cycle: concept, Development, Implementation and termination.Two network planning techniques are PERT and CPM. PERT uses probabilistic time estimates. CPM uses deterministic time estimates.PERT and CPM determine the critical path of the project and the estimated completion time. On large projects, software programs are available to identify the critical path. *

    Wiley 2010

  • To reduce the length of the project (crashing), we need to know the critical path of the project and the cost of reducing individual activity times. Crashing activities that are not on the critical path typically do not reduce project completion time.*

    Wiley 2010

  • DISCUSSION*

    Wiley 2010

    ***********