Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Project Journey
Quarterly Update to MWAA Board of Directors July 2018
1. Program Overview
2. Project Status
3. Safety
4. Community Benefits Plan
Program Overview
Secure National Hall
New North Concourse
Package 2A Demolition
Package 2B Apron Package 1 Enabling
PROGRAM OVERVIEW
Project Status
Design Reviews
Constructability
Reviews
Estimating
Scheduling
Value Engineering
Development of Firm
Fixed Price
% Complete 100%
PRECONSTRUCTION
NTP
Before
Construction Completed STATUS:
Actual Completion September 22, 2017
Task Order Schedule
Construction
% Complete 100%
Relocation of
American Airlines
Commuter Ramp
Operations Facilities
Airfield Ramp
Pavement Extension
Utility Work
After
PACKAGE 1- LOT K / AIRFIELD AREA A PAVING
Actual Completion January 3, 2018
Construction
Completed
STATUS:
NTP
Construction
% Complete 100%
Demolition of
Hangars 11/12 and
MWAA COB
Relocation of
American Airlines
Commuter Aircraft
Parking
Air Operations Area
(AOA) Fence
modifications
Before
After
Demolition
Task Order Schedule
PACKAGE 2A – DEMOLITION OF HANGARS & MWAA COB
In Construction STATUS:
NTP
Construction of new
Blast Wall – Complete
Phase 1 Hydrant
Fueling System
ongoing
Phase 1 Glycol
Recovery System
ongoing
Phase 1 Storm Drain
System ongoing
Construction
% Complete 15%
Blast Wall Temporary Light Tower
Current Schedule May 2021
PACKAGE 2B – APRON
Storm Drain System
PACKAGE 3 – NEW CONCOURSE
In Construction STATUS:
Construction
% Complete 3%
Processing Administrative
and Construction Submittals
Performing Existing
Conditions Surveys and
Utility Locating – Complete
Relocation of Chiller and
Generator at Loading Dock
Sequence 1, 2 & 3 Paving
Removal
Current Schedule July 2021
NTP
Pavement Removal Sequence 1 & 2 Prep for Chiller Relocation
N. Substation 3D
Scanning & Survey
In Construction STATUS: Ticket Counters and
TSA Equipment
relocations completed
Temporary partition
construction continues
Thomas Avenue
crossovers completed
Pile Testing completed
Security Identification
Display Area (SIDA)
Wall Mock-up
underway
Construction
% Complete 8%
11
North Test Pile Drill Rig Ticket Counter Relocations
South Test Pile
Thomas Avenue
Excavation Terminal C X-Ray
Current Schedule Feb 2021
NTP
SECURE NATIONAL HALL
Safety
As of June 1, 2018
Man Hours …………………………………………..……................... 201,191
Recordable Incident Rate (RIR)…………………............................. 0
Lost Time Incident Rate (LTIR) ………………………….................. 0
Safety Orientation (Total Employees Trained)……………………... 1220
Safety
Community
Benefits Plan
Update
1. Training and Apprenticeship Program
2. Veterans Program
3. LDBE Subcontracting Programs
4. LDBE Training Program: Turner School of Construction Management (TSCM)
5. LDBE Mentor/Protégé Program
6. Career Outreach Program
7. Summer Youth Program
8. Community Hotline / Website / Other
Training and Apprenticeship Program
On-Going Engagement REQUIREMENT:
Working with union shops to ensure placement of apprenticeship interests on the New Concourse
(NC) and Secure National Hall (SNH)
Firm Trade/Services
Kalkreuth Roofing and Sheet Metal
Schindler Elevators
NFP Fire Suppression and Sprinklers
RM Thornton Mechanical and Plumbing
AIW, Inc. Misc. and Ornamental Metals
Jervis Webb Baggage Handling
Boatman & Magnani Terrazzo
Gelberg Signage
ISEC, Inc Millwork and Interior Wall Panels
Berlin Steel Construction Co. Structural Steel Framing
Universal Builders Supply Scaffolding
Apprenticeship Activity Jan 1, 2017- May 31, 2018
Task Order Journeyman
Hours Apprenticeship
Hours Total Craftsman
Hours % Apprenticeship
Hours
NC Package 1 40,265 2,603 42,868 6.1
NC Package 2A 28,157 2,113 30,270 7.0
NC Package 2B 22,426 1,303 23,729 5.5
NC Package 3 1,697 0 1,697 0
SNH 24,467 264 24,731 1.0
On-Going Engagement REQUIREMENT:
Continuous Focus for Internal Hiring
Military Recruitment Fairs
Quarterly Recruiting in Gulfport, MS
Hire our Heroes Intern Program
Veterans on MWAA Project
Veterans Program
Chris Robinson Quality Control/Superintendent
Greg Trojan Safety Manager
On-Going Engagement REQUIREMENT:
Community Engagement – partnership with
VA
Painting of USO Offices
Partnership with VA – Homes for the formerly
homeless
Veterans Program
LDBE Subcontracting Programs
1 Event/Package REQUIREMENT: 18 EVENTS
INVITES TO 3K-8K/EVENT
OVER 1600 ATTENDEES
Activity Date Attendance
SHL Open House Aug. 22, 2016 100
SHL Walk Through Sept. 15, 2016 111
NNC #1 Open House Sept. 29, 2016 38
NNC #1 Pre Bid, Site Walk Thru Oct. 17, 2016 25
NNC #2A Open House Dec. 8, 2016 70
DSLDB Open House Jan 13, 2017 60
NNC #2A Pre Bid, Site Walk Thru Feb. 1, 2017 100?
Secure NH Open House Feb. 16, 2017 77
Informational Open House with
HCA
March 4, 2017 50
NNC #2B Open House April 20, 2017 155
Secure NH Pre Bid, Site Walk Thru April 25, 2017 216
Secure NH MEP Walk Thru May 11, 2017 30
NNC #2B Pre Bid, Site Walk Thru June 15, 2017 63
How to Business with MWAA June 23, 2017 50
NNC #3 Open House Sept. 7, 2017 118
How to Business with MWAA Oct. 20, 2017 120
MWMCA Economic Summit Nov. 7, 2017 100
NNC #3 Pre Bid, Site Walk Thru Nov. 16, 2017 185
TOTAL 1,668
ADDITIONAL
OUTREACH EVENTS /
ACTIVITIES:
Over 3,000 phone &
email inquires fielded
Over 2,000 firms
invited to bid
MWMCA Events
MEP work sessions
2 DOT events
COMTO panel
AMAC panel
Misc. Trade Shows
Partnered with MWAA and Other
Minority and Small Business
Organizations
18 events since August 2016,
including Open Houses, Site
Visits, Panel Discussions, MEP
Work Sessions, Matchmaking
Over 1,600 attendees to
date
Over 2,000 firms invited
to bid
LDBE Subcontracting Programs
18 EVENTS
INVITES TO 3K-8K/EVENT
OVER 1600 ATTENDEES
ADDITIONAL
OUTREACH EVENTS /
ACTIVITIES:
Over 3,000 phone &
email inquires fielded
Over 2,000 firms
invited to bid
MWMCA Events
MEP work sessions
2 DOT events
COMTO panel
AMAC panel
Misc. Trade Shows
Gallaudet Event – Panel Discussion
Business with MWAA/Graduation Event
150 Attendees, LDBE Engagement Focus
Two Speakers – Tom Dvorak, Charles Mann
Notable Attendees
MWAA Board Members:
Warner Session, Walter Tejada
MWAA Executive Team:
Roger Natsuhara, Julia Hodge, Darren Durbin
Wande Leintu, Monica Hargrove
District DM Courtney Snowden
Contracts Overview
Task Order Total
Subcontracts
Total Subcontracts
with LDBE Status
NC Package 1 22 15 Executed TO
NC Package 2A 26 16 Executed TO
NC Package 2B 19 12 Executed TO
NC Package 3 77 46 Executed TO
SNH 67 36 Executed TO
LDBE Subcontracting Programs
25% REQUIREMENT:
28% AWARDED TO DATE:
*
*
LDBE-AWARDED
Task Orders
CURRENT INDICATED
REVENUE ($) WIP (%) $ %
1 - Pre Construction Secure National Hall $1,569,811 100% $105,177 5%
2 - Pre Construction New Concourse $2,071,1494 100% $124,290 6%
4 - New Concourse Package 1 (Temp Pavement/Utilities)
$10,368,481 100% $3,317,914 32%
5 - New Concourse Package 2A (Demolition Of Hangars 11/12 and COB)
$10,017,006 100% $3,205,442 28%
6 - Secure National Hall $199,796,834 8%
$47,152,053
24%
7 - New Concourse - Package 2B $73,386,151 15% $21,281,984 29%
8 - New Concourse - Package 3 $195,127,253 3% $62,440,721 33%
TOTAL $492,337,030 $137,627,580 28%
Labor by Race/Ethnicity
African American Asian Caucasian Hispanic Other
Task Orders
Total Hours Hours % Hours % Hours % Hours % Hours %
NC 1 42,867 8,098 18.9% 626 1.5% 15,518 36.2% 16,830 39.3% 1,796 4.2%
NC 2A 30,271 4,621 15.3% 0 0.0% 12,347 40.8% 12,665 41.8% 637 2.1%
NC 2B 23,730 2,646 11.2% 32 0.1% 6,618 27.9% 12,505 52.7% 1,929 8.1%
NC 3 1,697 251 14.8% 0 0.0% 555 32.7% 891 52.5% 0 0.0%
SNH 24,731 3,035 0.0% 0 0.0% 4,310 17.4% 12,269 49.6% 5,117 20.7%
TOTAL 123,296 18,651 15.1% 658 0.5% 39,348 31.9% 55,160 44.7% 9,479 7.7%
* Labor from outside of the DMV area
Labor by State
Virginia Maryland Washington, DC Other*
Task Order Total Hours
Hours % Hours % Hours % Hours %
NC 1 42,867 10,926 25.5% 25,111 58.6% 4,721 11.0% 2,109 4.9%
NC 2A 30,271 15,415 50.9% 13,748 45.4% 502 1.6% 605 2.0%
NC 2B 23,730 12,594 53.1% 8,580 36.2% 255 1.1% 2,301 9.7%
NC 3 1,697 1,290 76.0% 285 16.8% 0 0 122 7.2%
SNH 24,731 12,451 50.3% 9,146 37.0% 2,198 8.9% 936 3.8%
TOTAL 123,296 52,676 42.7% 56,870 46.1% 7,676 6.2% 6,073 4.9%
LDBE Training Program: Turner School (TSCM)
1 School / Year REQUIREMENT:
CORE PROGRAMMING WASHINGTON, DC: Most recent class: April 26 – June 1, 2018
partnered with MWAA for LDBE/graduation/event
Spanish Offering: Fall 2018, Rosario School
MARYLAND: October 2018
Two Relationships, One General Contractor (GC) & One Additional REQUIREMENT:
ACHIEVEMENT: 3 in place
Focus on building GC Capabilities
Focus on building Financial Competency
LDBE Mentor/Protégé Program
Focus on building Overall Volume
2 college interns every summer of project REQUIREMENT:
ACHIEVEMENT:
Career Outreach
Parker Wilson • North Carolina A&T • Construction Management
6 college interns /summer of 2018
Ashley Lucas • Virginia Tech • Civil Engineering
Cheriece Davidson • Howard University • Civil Engineering
Brian Johnson • VA Military
Institute • Civil Engineering
Liam McCrann • Catholic University • Civil Engineering
Yoali Tchuenbou • New York University • Civil Engineering
Participation in District Summer Program REQUIREMENT:
ACHIEVEMENT: 4 Phelps ACE High School interns for summer 2018
SUMMER YOUTH PROGRAM
STARTED JUNE 25
MWAA PROJECT
ANALYSIS OF MBE, WBE VOLUME
TURNER SCHOOL OF CONSTRUCTION MANAGEMENT ALUM, LDBE ENGAGEMENT
OTHER
INTERVIEW SKILLS / WORKSHOP
VISIT PROJECT SITES
MWAA, CONRAD, COOLIDGE
WEEKLY VOLUNTEER WITH S.O.M.E. (VETERANS), COVENANT HOUSE
Youth Development
LDBE Database review project – determine
“viability” of contacted LDBEs to consider
participating
Project Website / Community Hotline
Implementation of a Project Website (Core communication point for subcontractor information and project status)
REQUIREMENT:
ACHIEVEMENT: www.Turner-DCAProjects.COM
Implementation of a
Hotline: Alternative
communication point for
subcontractor information
and questions
ACHIEVEMENT: (571) 260-0440