Upload
others
View
4
Download
0
Embed Size (px)
Citation preview
Project Description:Completion of the existing partial diamond interchange at I-77 and Miller Rd by adding a NB exit ramp and a SB entrance ramp including an auxiliary lane between the new SB entrance ramp and
the I-80 exit ramp. The project also includes widening I-77 to add a third lane from the Ohio Turnpike Interchange to the SR 21 (Brecksville Rd) Interchange, and the widening of Miller Rd to
provide left turn lanes including structure widening and dual WB right turn lanes onto the I-77 NB entrance ramp.
What is the requested TRAC Tier Tier II - Development
Please identify the project mode (roadway, transit or freight):
Roadway
ODOT District District 12 County Cuyahoga
ODOT PID 104983 Project Mode Roadway
Project Information
Application ID 2019-D12-01 Date Submitted 5/31/2019
Project Name I-77-Miller Road Interchange / SUM-77-32.30
What is the current TRAC Tier New Project
Processed: 6/6/2019 2019 TRAC Funding Application 1 of 13
What Type of Application Are you Submitting?New project - that demonstrates significant
impact to jobs, regional economic impact and has significant non-ODOT funding
Address 9069 Brecksville Road
City Brecksville
State Ohio Zip Code: 44141
Project Contact Alan R. Piatak, P.E.
Phone (440) 260-1555
Email [email protected]
Project Sponsor Information
Project Name I-77-Miller Road Interchange / SUM-77-32.30
Sponsoring Agency City of Brecksville
Processed: 6/6/2019 2019 TRAC Funding Application 2 of 13
Utility Relocation Not Started 3/1/2023
Detailed Design Not Started 3/1/2022
Right-of-way Acquisition Not Started 6/1/2022
Preliminary Engineering Studies Not Started 6/1/2021
Environmental / NEPA Approval Not Started 4/15/2021
Planning Studies In Progress 6/1/2020
Interchange Modification Study (IMS) / Interchange Justification Studies (IJS)
In Progress 7/15/2019
Project ScheduleNew projects are required to supply project milestone information. Please select the status of each milestone below as either Not Yet Started, In Progress or Completed. Additionally please enter the corresponding date for the milestone and status.
Status Date
Processed: 6/6/2019 2019 TRAC Funding Application 3 of 13
41.259056 -81.632914 41.269625 -81.636403
0 0 0
New Roadways / New Alignment 0
Begin Latitude Begin longitude End Latitude End longitude
0 0 0
0 0 0
Secondary Roadway Segments
SCUYIR00077**C 0.42 0.82
0 0 0
0 0 0
ODOT NLFID Begin Point End PointPrimary Roadway
SegmentSSUMIR00077**C 32.3 33.1
Transportation InformationIn an effort to understand the complex issues associated with the project TRAC collects a variety of transportation related data and information in the evaluation process including: congestion data, safety data, truck traffic, and model derived transportation values; such as, cost/benefit analysis and air quality. The roadway segments associated with the application is the basis of this analysis. Transit and Freight related projects should identify the roadway segments that will receive the benefit from projects implementation.
New project applications must identify the primary roadway segment that will be improved by the project and ancillary roadways that will be improved as part of the project.
Processed: 6/6/2019 2019 TRAC Funding Application 4 of 13
Truck Miles Traveled (TMT) Reduction Not Applicable
Existing Freight Capacity Not Applicable
Existing Freight Volume / Existing Freight Capacity Ratio
Not Applicable
Freight Capacity Increase Not Applicable
Freight Multi-Modal Project Information
Freight Type Not Applicable
Route/Number Not Applicable
Existing Freight Volume Not Applicable
Existing Peak Hour Ridership / Capacity Ratio Not Applicable
Added Peak Hour Capacity Not Applicable
Vehicle Miles Traveled (VMT) Reduction Not Applicable
Route/Number Not Applicable
Peak Hour Ridership Not Applicable
Existing Capacity Not Applicable
Transit Multi-Modal Project Information
Transit Type Not Applicable
Processed: 6/6/2019 2019 TRAC Funding Application 5 of 13
Please provide a brief explanation as to how this project will connect an STS resource with a local freight or transit facility or resource
The project will provide an alternative route between I-77 and the Ohio Turnpike in the event of a ramp incident at the existing interchange. FedEx, Yellow Freight, and House of LaRose are all
within the project area.
Will the project facilitate a connection between two or more corridors or modal hubs identified on the STS?
Yes
Please provide a brief explanation as to how this project will facilitate a connection between two or more STS resources.
Completing the Miller Road Interchange and widening I-77 within the project limits will facilitate the I-77 connection with the Ohio Turnpike by reducing congestion.
Will the project connect an STS resource with a local freight or transit facility or resource?
Yes
Strategic Transportation System (STS) Connections
The Strategic Transportation System (STS), identified as part of Access Ohio 2040 - ODOT’s long range transportation plan - stratifies Ohio’s significant transportation corridors and inter-modal hubs across Ohio. Additional information about the STS and Access Ohio 2040 can be view at the Access Ohio 2040 Website
Is the project part of an STS corridor? Yes
Processed: 6/6/2019 2019 TRAC Funding Application 6 of 13
Warehouse 1,599,000
Commercial 2,192,000
Institutional 1,219,000
Water and Sewer Service 95%
What is the estimated square footage for the following building types within the calculated project area?
Light Industrial 369,000
Heavy Industrial 111,000
Estimated Project Area Acreage 5,568
What is the estimated percentage of acres being served by the local services within the estimated project area calculated above?
Local Streets and Roadways 74%
Electrical Service 0%
Local Investment FactorsBuilt Out Local Attributes
Local Investment factors analysis and evaluation of the dollar value of existing, local built-out attributes such as streets, water, and land use. For this analysis TRAC has standardized the project area as a one-mile "rectangular" buffer around the primary roadway segment. Additionally TRAC also considers percentage of acres served by local services within the rectangular buffer with the following formula: (Length of the primary roadway segment in miles + 2 miles) x 2 miles x 640 acres)
What is the length of the primary roadway segment being improved by the project?
2.35
Processed: 6/6/2019 2019 TRAC Funding Application 7 of 13
Poverty Rate Data SourceSub-County Unemployment RateUnemployment Rate Data Source
0
00
Do you want to enter distress values for a sub-county area to be used in the evaluation of this
application?
No - I want to use the information collected by ODOT.
County 0Sub-County Poverty Rate 0
What is the dollar value of committed or recent public investment in new, non-project
infrastructure within the project area? (Millions) $ 47
What is the present value of private investment in existing facilities within the project area? (Millions)
$ 39
Economic Distress - Poverty & Unemployment RatesAs part of the application scoring process, ODOT collects county level information as the standard measurement for poverty and unemployment factors; however, if a project sponsor provides defensible data at a sub-county or census tract level, TRAC can consider that level of geographic analysis for scoring and evaluation.
What is the estimated percentage of road route miles served by transit routes (excluding ADA/Para
Transit) within the project area?25%
What is the estimated percentage of existing building square footage that is currently vacant?
5%
New Local InvestmentsTRAC will consider the monetized value of public investments or commitments for new, non-project infrastructure and private investments within 5-year time horizon prior to and after the date of this TRAC Application.
Processed: 6/6/2019 2019 TRAC Funding Application 8 of 13
-$ -$ -$ 9.95$
Will additional TRAC funds be needed for future phases of development or construction? Yes
PE DD RW CO
PE DD RW CO-$ -$ -$ -$
CO Funding Request -$ 0
Total New TRAC Funding Request 2.45$
Has TRAC previously committed funding for the development or construction of this project?
No
DD Funding Request 0.38$ 2021
RW Funding Request 0.55$ 2021
Which phase(s) you are requesting new TRAC funding for as part of this application?
PE - Preliminary EngineeringDD - Detailed Design
RW - Right-of-way
Amount (Millions) Requested Fiscal YearPE Funding Request 1.52$ 2020
Project Funding PlanTRAC Funding Request
Please indicate the amount of funding being requested by phase and fiscal year. Funding requests should consider the funding that will be needed with the next two fiscal years.
Processed: 6/6/2019 2019 TRAC Funding Application 9 of 13
Local Funding TotalsPE DD RW CO
1.52$ 0.38$ 0.55$ 1.76$
PE DD RW CO-$ -$ -$ -$
-$ -$ -$ -$
Local funding Source (5) 0
Local funding Source (4) 0
PE DD RW CO
PE DD RW CO-$ -$ -$ -$
-$ -$ -$ -$
Local funding Source (3) 0
Local funding Source (2) 0
PE DD RW CO
PE DD RW CO1.52$ 0.38$ 0.55$ 1.76$
Will local funding sources be used in the development or construction of this project? Yes
What is the total number of local funding sources for the development and construction of this project? 1
Local funding Source (1) City of Brecksville TIFF Funds and General Funds
Local Funding CommitmentsProject Development and construction can be funded with multiple local funding sources. The questions below will help identify the funding sources for this project.
Processed: 6/6/2019 2019 TRAC Funding Application 10 of 13
% Local % ODOT % OTIC % TRAC25.3% 0.0% 0.0% 74.7%
Total Local Total ODOT Total OTIC Total TRAC4.21$ -$ -$ 12.40$
Funding Totals 3.04$ 0.76$ 1.10$ 11.71$
Total Project Cost 16.61$
New TRAC Funding 1.52$ 0.38$ 0.55$ -$
Future TRAC Funding -$ -$ -$ 9.95$
OTIC Bond Funding -$ -$ -$ -$
Previous TRAC Funding -$ -$ -$ -$
Local Funding 1.52$ 0.38$ 0.55$ 1.76$
ODOT / Earmark Funding -$ -$ -$ -$
Funding Summary
PE DD RW CO
PE DD RW CO-$ -$ -$ -$
-$ -$ -$ -$
OTIC Turnpike Bond Revenue Funding
Have Ohio Turnpike and Infrastructure Commission (OTIC) Revenue Bonds been committed for the No
ODOT Program or Earmark Funding Commitments
Will funding from another ODOT program or legislative earmarks be used in the development or No
PE DD RW CO
Processed: 6/6/2019 2019 TRAC Funding Application 11 of 13
Date of Inflated Estimate 1/0/1900
Year of Inflation Estimate $ -
Railroad $ -
Contingency $ -
Total Estimate $ -
Traffic Control $ -
Structures $ -
Retaining Walls $ -
Tier I Construction Estimate
Projects requesting Tier I status are required to submit a budgetary construction estimate. Additionally estimates must be inflated to the anticipated year of construction.
Roadway $ -
Drainage $ -
Processed: 6/6/2019 2019 TRAC Funding Application 12 of 13
District Acknowledgement
Has the appropriate ODOT District Planning Office been contacted about the development and construction of this project?
Yes
Has the ODOT District Office provided a letter or support or acknowledgment for this project? Yes
Attachments
Is this project within the boundaries of a Metropolitan Planning Organization (MPO)? Yes
Please identify the respective MPO. NOACA
Has the MPO provided a letter or support or acknowledgment for this project? Yes
MPO & District AcknowledgementMPO Acknowledgement
Processed: 6/6/2019 2019 TRAC Funding Application 13 of 13
I-77/MILLER ROAD INTERCHANGE CUY-77-00.82, PID 104983
Location Maps
PROJECT LIMITS
PROJECT INTERCHANGE
0°52'53"
Δ
Θ
COMMERCIAL
& INDUSTRISAL
PARCELS ADJACENT
TO LOCAL STREETS
PARCELS ADJACENT TO
NON-LOCAL STREETS
N
SCALE IN FEET
2000 0 2000 4000
O
H
I
O
T
U
R
N
P
I
K
E
O
H
I
O
T
U
R
N
P
I
K
E
I-77
I-77
I
-
7
7
MILLER RD.
R
T
.
8
2
R
T
.
2
1
RT
. 21
RT
. 21
PROJECT
AREA
S
W E
ROAD NETWORK
AND LAND USE
MAP
LEGEND
PROJECT AREA
CUYAHOGA COUNTY
SUMMIT COUNTY
CUYAHOGA COUNTY
SUMMIT COUNTY
1
Lastovka, David
From: Picuri, John
Sent: Thursday, May 23, 2019 12:25 PM
To: Lastovka, David
Cc: Benesh, Gary; Kallio, Eric
Subject: RE: Brecksville - TRAC Application - District 12 Acknowledgement
Dave,
Please move forward on our end with this application. Thank-you.
Sincerely,
John P. Picuri, P.E.
District Deputy Director
District 12
5500 Transportation Blvd., Garfield Heights, Ohio 44125
216.584.2000
transportation.ohio.gov
From: Lastovka, David
Sent: Thursday, May 23, 2019 11:35 AM
To: Picuri, John <[email protected]>
Cc: Benesh, Gary <[email protected]>; Kallio, Eric <[email protected]>
Subject: FW: Brecksville - TRAC Application - District 12 Acknowledgement
John,
Gary and I have been meeting regularly with the City of Brecksville over the past few weeks to assist the City with a TRAC
funding application to complete the I77 interchange at Miller Road, and to widen I77 from the Ohio Turnpike to SR 21
(Brecksville) Road I77 interchange in Richfield. (CUY-77-Miller Road IMS; PID 104983)
The TRAC application process requires District acknowledgement of the application. Your formal response to this email
is requested to serve as the District acknowledgement to this project in this funding cycle.
Dave
David Lastovka, P.E. Acting Capital Programs Administrator
Cleveland Innerbelt Corridor Project Manager
ODOT District 12 Capital Programs
5500 Transportation Blvd, Garfield Heights, Ohio 44125
216-584-2115
transportation.ohio.gov
2
From: Gerry Wise <[email protected]>
Sent: Thursday, May 23, 2019 10:40 AM
To: Benesh, Gary <[email protected]>; Lastovka, David <[email protected]>
Cc: Mayor Hruby <[email protected]>
Subject: Brecksville - TRAC Application - District 12 Acknowledgement
Dave & Gary:
On behalf of the City of Brecksville, please accept this email as a request for a letter of support from ODOT D-12 for our
TRAC application to complete the I-77 interchange at Miller Road and widen I-77 from the Ohio Turnpike to the
Brecksville Road/I-77 ramps in Richfield.
As you are aware, the City of Brecksville has been working with the District for years on the completion of this
Interchange and it is vital to development within the south end of Brecksville including the recently acquired VA
property.
Thank you for your anticipated support.
Gerry
Gerald M. Wise
City of Brecksville, Engineer
Donald Bohning & Associates
7979 Hub Parkway
Valley View, OH 44125
T 216.642.1130 x110