Project Implementation: Project Implementation: Procurement & Contract Procurement & Contract Management Management April 2012

Project Implementation: Procurement & Contract Management April 2012

Embed Size (px)

Citation preview

Page 1: Project Implementation: Procurement & Contract Management April 2012

Project Implementation: Procurement & Project Implementation: Procurement & Contract ManagementContract Management

April 2012

Page 2: Project Implementation: Procurement & Contract Management April 2012

We would like to acknowledge the contribution of the Programme Management Department in the

preparation of this presentation that will introduce some concepts and guiding principles for

Procurement & Contract Management

For more information on the topic please refer to the supervision training material of February 2012

Project Implementation: Procurement & Contract ManagementProject Implementation: Procurement & Contract ManagementProject Implementation: Procurement & Contract ManagementProject Implementation: Procurement & Contract Management

Page 3: Project Implementation: Procurement & Contract Management April 2012

3

What are IFAD’s role and responsibility in procurement for projects?

What are the tasks involved in procurement supervision?

How is procurement supervision conducted?

How are contracts managed?

Project Implementation: ProcurementProject Implementation: ProcurementLearning ObjectivesLearning Objectives

Project Implementation: ProcurementProject Implementation: ProcurementLearning ObjectivesLearning Objectives

Page 4: Project Implementation: Procurement & Contract Management April 2012

4

• Inefficient or ineffective procurement may have serious consequences:

expected project results and impacts not achieved delays in project implementation higher cost of implementation

• Procurement is a sensitive activity:

can be conducive to corruption and fraud complexity of certain procurement actions combined use of national & IFAD regulations / guidelines

Project Implementation: ProcurementProject Implementation: ProcurementIntroductionIntroduction

Project Implementation: ProcurementProject Implementation: ProcurementIntroductionIntroduction

Purchasing goods, services and works (procurement) is a critical element of project implementation. . .

Page 5: Project Implementation: Procurement & Contract Management April 2012

5

• Different methods (ranging from International Competitive Bidding to Direct Contracting) are used for the different categories of procurement depending on nature, amount and other criteria - guiding principle being economy and efficiency

Project Implementation: ProcurementProject Implementation: ProcurementProcurement MethodsProcurement Methods

Project Implementation: ProcurementProject Implementation: ProcurementProcurement MethodsProcurement Methods

Page 6: Project Implementation: Procurement & Contract Management April 2012

6

Project Implementation: ProcurementProject Implementation: ProcurementTendering ProcessTendering Process

Project Implementation: ProcurementProject Implementation: ProcurementTendering ProcessTendering Process

Formation of Bid Evaluation Committee; N-O by I FAD

Prepare Specifications and tender documents (Advertisement/ I TBs/ RFPs/ RFQs as applicable) and No-Objection (if required)

Key

I TB –Invitation to Bid

RFP – Request for Proposal

RFQ –Request for Quotation

Bid Evaluation and draft contractI FAD Prior Review and No-Objection (if

required)

Contract Award to best evaluated bid

Page 7: Project Implementation: Procurement & Contract Management April 2012

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

• International Competitive Bidding (ICB): for high value requirements (1)

Advertise in widely circulated newspapers, local representatives, Embassies, UN Development Forum

Pre-qualification Public bid opening Bid evaluation based on

point scoring system (technical + financial)

• National Competitive Bidding (NCB): for public procurement in Borrower’s country (2)

Advertise in local newspapers (note: foreign suppliers may bid)

Same

Same Same

7

Page 8: Project Implementation: Procurement & Contract Management April 2012

8

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

International Shopping (3): short-list at least three

reputable suppliers in at least two member countries of IFAD

issue ITB to the short-listed suppliers

receive bids in original form (not faxed)

bid evaluation based on lowest cost for compliant offers

sign contract

Local Shopping (4): prepare specifications and

request for quotations short-list at least three reputable

suppliers

issue request for quotations to the short-listed suppliers

Same

Same

Same

Page 9: Project Implementation: Procurement & Contract Management April 2012

Direct Contracting (5): Extension of/ addition to an existing contract Standardisation of goods with existing project assets

Note: Competitive process is not required

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

Project Implementation: ProcurementProject Implementation: ProcurementCommon Procurement MethodsCommon Procurement Methods

9

Page 10: Project Implementation: Procurement & Contract Management April 2012

10

Difference Between Procuring Goods and Works and Selecting Consulting Services . . .

GOODS, WORKS AND TECHNICAL SERVICES

CONSULTING SERVICES

Product based Knowledge based

Open competition Selective competition

Public bid opening Non-public bid opening of technical offers

Public opening of financial proposals

Price is a major factor Quality is a major factor

Detailed specification Terms of Reference

(general work program)

Single-stage procedure Two-stage procedure

Negotiations rarely Negotiations usual

Project Implementation: ProcurementProject Implementation: ProcurementGoods & Works vs. Consulting ServicesGoods & Works vs. Consulting Services

Project Implementation: ProcurementProject Implementation: ProcurementGoods & Works vs. Consulting ServicesGoods & Works vs. Consulting Services

Page 11: Project Implementation: Procurement & Contract Management April 2012

11

• Procurement rules and procedures applicable to a particular project come from different sources:

national procurement rules and regulations

IFAD Procurement Guidelines project appraisal report loan agreement

• Applicable rules, methods and procedures are specified in the Letter to the Borrower, as well as IFAD procurement review requirements

Project Implementation: ProcurementProject Implementation: ProcurementRegulatory FrameworkRegulatory Framework

Project Implementation: ProcurementProject Implementation: ProcurementRegulatory FrameworkRegulatory Framework

Must adhere to regulatory framework . . .

Page 12: Project Implementation: Procurement & Contract Management April 2012

12

• Procurement planning (in line with project objectives and AWPB)

• Preparation and issuance of bidding documents and invitation to bid

• Opening and evaluation of offers

• Negotiation, award and signature of contract

• Monitoring of contract execution (technical and financial/administrative)

• Delivery of goods/works/services

• Payment

Project Implementation: ProcurementProject Implementation: ProcurementRole of Borrower/PMU in Procurement Role of Borrower/PMU in Procurement Project Implementation: ProcurementProject Implementation: Procurement

Role of Borrower/PMU in Procurement Role of Borrower/PMU in Procurement

PMU has overall responsibility forProcurement

Page 13: Project Implementation: Procurement & Contract Management April 2012

13

IFAD’s Fiduciary responsibility:

• Proper use of loan funds: IFAD must ensure loan proceeds are used only for intended purpose: while FM responsibilities lie with CFS-Finance Officers, procurement related activities are in PMD, specifically CPM and Support Staff

• Economy and efficiency requirements in project implementation in general and procurement in particular: IFAD must ensure contract awards result from a competitive process

• IFAD must ensure equity, integrity, transparency and good governance in procurement process

• Concept of “no objection”

Project Implementation: ProcurementProject Implementation: ProcurementImportance of Procurement – IFAD GuidelinesImportance of Procurement – IFAD Guidelines

Project Implementation: ProcurementProject Implementation: ProcurementImportance of Procurement – IFAD GuidelinesImportance of Procurement – IFAD Guidelines

Page 14: Project Implementation: Procurement & Contract Management April 2012

14

CPM must ensure:

• coherence of procurement actions with project objectives, AWPB and procurement plan, and timing within project implementation period

• funds availability: cost of procurement must not exceed funds allocated in loan agreement and annual budget

• transparency and equity: procurement must be conducted in compliance with applicable rules and procedures

• best value for money: procurement must be the result of a competitive process

- IFAD staff must maintain neutrality and impartiality

- Flexibility is a must – but know rules and regulations

Project Implementation: ProcurementProject Implementation: ProcurementRole of IFAD in ProcurementRole of IFAD in Procurement

Project Implementation: ProcurementProject Implementation: ProcurementRole of IFAD in ProcurementRole of IFAD in Procurement

Page 15: Project Implementation: Procurement & Contract Management April 2012

15

• A complete financial and administrative procedures manual (Implementation/ Operations Manual)

• A well-prepared start-up workshop with a technical sessionThe technical session should include discussions about the importance of quality submissions, frequent causes of delays, timing issues …

• A ‘procurement plan’ summarizing procurement methods, applicable rules and prior review requirements as provided in the financing agreement

Project Implementation: ProcurementProject Implementation: ProcurementKey Tools for Successful Procurement (1)Key Tools for Successful Procurement (1)

Project Implementation: ProcurementProject Implementation: ProcurementKey Tools for Successful Procurement (1)Key Tools for Successful Procurement (1)

Page 16: Project Implementation: Procurement & Contract Management April 2012

16

• Assessment of procurement capacity at the national/project level

• Training of relevant PMU and national partners in all aspects of procurement

• Procurement expertise at national/project level (complemented by on-going capacity building)

• Procurement expertise at IFAD level (procurement specialist to assist CPM in supervision)

Project Implementation: ProcurementProject Implementation: ProcurementKey Tools for Successful Procurement (2)Key Tools for Successful Procurement (2)

Project Implementation: ProcurementProject Implementation: ProcurementKey Tools for Successful Procurement (2)Key Tools for Successful Procurement (2)

Page 17: Project Implementation: Procurement & Contract Management April 2012

17

Under the responsibility of the CPM (assisted by a procurement expert)

Prior review procedures: HQ supervision reviews:

Procurement plans Pre-qualification of bidders Bidding documents Procurement progress reports No objection as required

Ex-post review procedures: - As part of the review of WA’s

- Field supervision (during supervision missions)

Review of procurement progress and processes (technical, financial/administrative)

Identification of issues and constraints Coaching of national and/or PMU staff Issuance of recommendations for improvement

Project Implementation: ProcurementProject Implementation: ProcurementDifferent Levels of ProcurementDifferent Levels of Procurement

Project Implementation: ProcurementProject Implementation: ProcurementDifferent Levels of ProcurementDifferent Levels of Procurement

Page 18: Project Implementation: Procurement & Contract Management April 2012

18

I. Review of pre-qualification of bidders (for large/complex works or expected significant time/cost savings => need advanced procurement skills)

Prior to issuance of invitations to pre-qualify, IFAD reviews: draft advertisement and invitation to pre-qualify draft pre-qualification documents, including pre-qualification

questionnaire and evaluation criteria and methodology

After borrower’s evaluation of bidders’ submissions, IFAD reviews: draft evaluation report list of pre-qualified bidders and statement of their qualifications reasons for excluding any applicant from pre-qualification

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (1) Prior Review Procedures (1)

(refer to workflow 1 & checklists)(refer to workflow 1 & checklists)

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (1) Prior Review Procedures (1)

(refer to workflow 1 & checklists)(refer to workflow 1 & checklists)

Page 19: Project Implementation: Procurement & Contract Management April 2012

19

II. Review of procurement of goods and works

Prior to issuance of invitations to bid, IFAD reviews: conformity of procurement with applicable rules/procedures,

approved AWPB/procurement plan and funds availability draft bidding documents, including invitation to bid, instructions to

bidders, technical specifications, evaluation criteria, contractual conditions

proposed composition of the bid evaluation committee (for comments)

After borrower’s evaluation of bidders’ submissions, IFAD reviews: minutes of public bid opening bid evaluation report, including evaluation and comparison of bids

and award recommendation evidence of individual evaluations by each committee member draft contract

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (2) Prior Review Procedures (2)

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (2) Prior Review Procedures (2)

Page 20: Project Implementation: Procurement & Contract Management April 2012

20

III. Review of procurement of consulting services

Prior to issuance of request for proposal (RFP), IFAD reviews: conformity of procurement with applicable rules/procedures, approved

AWPB/procurement plan and funds availability draft RFP, including instructions to consultants, terms of reference,

selection method and evaluation criteria, shortlist of consultants, cost estimate, contractual conditions

After borrower’s evaluation of technical proposals, IFAD reviews: technical evaluation report, including description of the process,

summary of scores and award recommendation technical scores/ranking given to each consultant on each evaluation

criterion scores given by each evaluation committee member copy of proposals, if requested by IFAD

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (3) Prior Review Procedures (3)

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (3) Prior Review Procedures (3)

Page 21: Project Implementation: Procurement & Contract Management April 2012

21

III. Review of procurement of consulting services using the following methods:

Quality and cost-based selection Selection under a fixed budget Least-cost selection

After borrower’s evaluation of financial proposals, IFAD reviews: minutes of public bid opening account of adjustments made to prices of the proposals and

determination of the evaluated price final evaluation report and award recommendation

(The above review step is not applicable for quality-based selection, selection based on consultants’ qualifications, single source selection or individual consultant selection)

In all cases, IFAD reviews and provides No-Objection to the negotiated draft contract

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (4) Prior Review Procedures (4)

Project Implementation: ProcurementProject Implementation: ProcurementPrior Review Procedures (4) Prior Review Procedures (4)

Page 22: Project Implementation: Procurement & Contract Management April 2012

22

Project Implementation: ProcurementProject Implementation: ProcurementExample of Weights for Consultant Evaluation CriterionExample of Weights for Consultant Evaluation Criterion

Project Implementation: ProcurementProject Implementation: ProcurementExample of Weights for Consultant Evaluation CriterionExample of Weights for Consultant Evaluation Criterion

EVALUATION CRITERION: POINTSConsultants / firms specific experience 5 - 10Methodology 20 - 50Key personnel (general qualificationsadequacy for the assignment) 30 - 60Transfer of knowledge 0 - 10Participation by nationals 0 - 10

TOTAL 100

– Could be divided into sub-criteria, but should be kept to the essential

– For training - high points on key Personnel– Points may be adjusted for specific circumstances

Page 23: Project Implementation: Procurement & Contract Management April 2012

23

At HQPost-award review of procurement actions as part of the withdrawal applications approval process

Documents submitted by PMU must include bidding documents, evaluation reports, award recommendations, signed contracts and updated contract record

IFAD reviews conformity of procurement with applicable rules/procedures, project objectives, approved AWPB/procurement plan and funds availability

Project Implementation: ProcurementProject Implementation: ProcurementEx-Post Review Procedures (1) Ex-Post Review Procedures (1)

Project Implementation: ProcurementProject Implementation: ProcurementEx-Post Review Procedures (1) Ex-Post Review Procedures (1)

Page 24: Project Implementation: Procurement & Contract Management April 2012

24

Project Implementation: ProcurementProject Implementation: ProcurementEx-Post Review Procedures (2) Ex-Post Review Procedures (2)

Project Implementation: ProcurementProject Implementation: ProcurementEx-Post Review Procedures (2) Ex-Post Review Procedures (2)

During IFAD supervision/Implementation support missions

Post-award review of procurement actions based on selection of a sample of transactions

PMU makes available to the supervision review team all procurement and payments files, updated contract record and individual contract monitoring forms

Focus of supervision mission review is conformity of procurement with applicable rules/procedures, project objectives, approved AWPB/procurement plan, and funds availability

Page 25: Project Implementation: Procurement & Contract Management April 2012

25

Project Implementation: ProcurementProject Implementation: ProcurementEx-Ex-Post Review ProceduresPost Review Procedures (3) (3)

Project Implementation: ProcurementProject Implementation: ProcurementEx-Ex-Post Review ProceduresPost Review Procedures (3) (3)

The IFAD supervision/Implementation mission team also:

assesses the physical and financial progress of procurement actions and the quality of final products (through site visits for works, review of consultants’ reports, review of the contract monitoring forms, etc.)

identifies procurement issues and constraints

briefs/coaches borrower and/or PMU staff on procurement issues

issues recommendations for improvement (e.g. training of staff, fielding of implementation support missions, streamlining of workflows, …)

Page 26: Project Implementation: Procurement & Contract Management April 2012

26

Project Implementation: ProcurementProject Implementation: ProcurementHow to avoid delays in procurement (1)How to avoid delays in procurement (1)Project Implementation: ProcurementProject Implementation: Procurement

How to avoid delays in procurement (1)How to avoid delays in procurement (1)

Lack of procurement plan or inadequate/incomplete procurement plan

Poorly designed and/or unrealistic AWPB

Imprecise and ambiguous terms or documents for the bid evaluation method and selection criteria

Absence of confidentiality at various stages of the bid evaluation process and/or selection of winning bid

Failure to justify rejection of bids or non-selection of a competitive bid

Political interference in the procurement process

Corruption, fraud, conflicts of interest and miss-procurement

Page 27: Project Implementation: Procurement & Contract Management April 2012

27

Project Implementation: ProcurementProject Implementation: Procurement How to avoid delays in procurement (2) How to avoid delays in procurement (2)

Project Implementation: ProcurementProject Implementation: Procurement How to avoid delays in procurement (2) How to avoid delays in procurement (2)

Poor qualification of evaluation committee members

Lack of procurement capacity at borrower and/or project level

Poor understanding of IFAD procedures at borrower and/or project level

Confusion between national procedures and IFAD guidelines/loan agreement procedures

Cumbersome procedures and bureaucracy for approval of procurement documents at borrower level

Long delays in issuance of no-objections by IFAD

Long response time by IFAD to queries from PMU

Page 28: Project Implementation: Procurement & Contract Management April 2012

28

Project Implementation: ProcurementProject Implementation: ProcurementMonitoring of Procurement at HQ Monitoring of Procurement at HQ

Project Implementation: ProcurementProject Implementation: ProcurementMonitoring of Procurement at HQ Monitoring of Procurement at HQ

Several source documents for monitoring procurement . . .

AWPB and updated procurement plan

Results of prior reviews and ex-post reviews at HQ

Supervision mission reports

Progress reports

Based on monitoring results, follow-up on issues and problems identified

Page 29: Project Implementation: Procurement & Contract Management April 2012

29

Project Implementation: ProcurementProject Implementation: ProcurementProcurement in Project Completion ProcessProcurement in Project Completion Process

Project Implementation: ProcurementProject Implementation: ProcurementProcurement in Project Completion ProcessProcurement in Project Completion Process

• To ensure that all goods are delivered/works completed/services rendered by the project completion date: Closely review and monitor the final procurement plan

and progress reports during the last year of the project Take measures to facilitate completion of physical

execution of contracts Cancel contracts that cannot be executed within the

completion date

• Ensure that only contracts executed by project completion date are paid

• Ensure that procurement files are complete and obtain missing documents from project

• Report on lessons learned and make recommendations for future projects

Page 30: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementProject implementation: Contract ManagementProject implementation: Contract Management• IntroductionIntroduction

Contract contents – all pertinent deliverables,

timing, deadlines, results-oriented reporting &

expected outcomes, with measurable indicators

Contract management – monitoring &

supervision is crucial

Contract execution – procurement is complete

only when contracted product of satisfactory

quality is delivered at appointed time

30

Page 31: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementFive Stages of Contract ManagementFive Stages of Contract Management

Project implementation: Contract ManagementProject implementation: Contract ManagementFive Stages of Contract ManagementFive Stages of Contract Management

Monitoring & Control of performance

Change Management

Dispute Resolution

Financial Management & Payment

Contract Administration

31

Page 32: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract Performance (1)Monitoring & Control of Contract Performance (1)

Project implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract Performance (1)Monitoring & Control of Contract Performance (1)

Establishment of Contracts Register

Establishment of Contract Monitoring Register

Establishment of Individual Contract Monitoring Sheet

Establishment of Contract Monitoring Form

Key tipKey tip

Contract management Guidelines- Service providerContract management Guidelines- Service provider

Contract Register

Contract Monitoring Register

ICM Register

32

Page 33: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract PerformanceMonitoring & Control of Contract PerformanceProject implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract PerformanceMonitoring & Control of Contract Performance

Key Indicators

Consulting Services

Goods

Works

Timely delivery of key outputs Responsiveness to reasonable requests The quality services of services provided

The timeliness of delivery Quantity delivered Compliance with specifications

Timeliness of each stage of the works Compliance with the bill of works The quality of the works

33

Page 34: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract PerformanceMonitoring & Control of Contract PerformanceProject implementation: Contract ManagementProject implementation: Contract ManagementMonitoring & Control of Contract PerformanceMonitoring & Control of Contract Performance

Tips

• indicate actual delivery date of goods/ works/ services (or agreed milestones)

• written reminders to contractors/ consultants where there is a default (including penalties)

• file response from contractors/ consultants• record agreed changes in delivery dates & penalties exactedInspection

As necessary, especially for works, it is necessary to ensure that qualified independent oversight is provided to ensure that works are constructed according to industry standards

34

Page 35: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementAcceptanceAcceptance

Project implementation: Contract ManagementProject implementation: Contract ManagementAcceptanceAcceptance

Service

Goods

Works

written confirmation that the required services have been delivered on time & of an acceptable quality

completion of the Receipt and Inspection Report (RIR). It may be necessary for the supply of goods to ensure that suitably qualified staff or consultants are involved in the RIR

engineer’s report that timely construction of acceptable standard has been completed

35

Page 36: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementChange ManagementChange Management

Project implementation: Contract ManagementProject implementation: Contract ManagementChange ManagementChange Management

Includes avoiding unnecessary changes as well as

incorporating necessary changes into contract

It is important is ensure necessary prior approval is

obtained including a no objection from IFAD if the value

of cumulative change exceeds 15% of contract value

36

Page 37: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementRemediesRemedies

Project implementation: Contract ManagementProject implementation: Contract ManagementRemediesRemedies

Termination

Dispute resolution

seek legal advice

determine if liquidated damages should apply in

accordance with contract

negotiation

arbitration

37

Page 38: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementFinancial Management and PaymentsFinancial Management and Payments

Project implementation: Contract ManagementProject implementation: Contract ManagementFinancial Management and PaymentsFinancial Management and Payments

Payments need to be made in line with the contract terms (normally

within 30 days of submission of a valid invoice)

It is important to maintain an expected payment schedule as part

milestone of the Contract Monitoring Register to ensure that there is

sufficient liquidity in the Special Designated Account or to promptly

process request for direct payment

Delayed payments negatively affect the cost of future contracts – where

delayed payments are a regular feature, suppliers & contractors build in

margins to cover anticipated delays in payment or refuse to tender

38

Page 39: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract Management

Performance SecuritiesPerformance Securities

Project implementation: Contract ManagementProject implementation: Contract Management

Performance SecuritiesPerformance Securities

Where required these should be provided by the supplier/contractor in a timely manner. These should be returned within 30 days of final acceptance (contract completion as per contract terms), including any warranty or maintenance period

39

Page 40: Project Implementation: Procurement & Contract Management April 2012

Project implementation: Contract ManagementProject implementation: Contract ManagementContract Completion Contract Completion

Project implementation: Contract ManagementProject implementation: Contract ManagementContract Completion Contract Completion

All products/ services have been provided

Documentation in the contract file shows receipt & formal acceptance of all contract terms

There are no claims or investigations pending

Any property provided by the Project is returned & discrepancies resolved

All actions regarding contract amendments have been attended to

All sub-contracting issues have been attended to

Warranty matters are resolved and defect period elapsed

Any necessary audit has been satisfactorily finalised

The final invoice has been submitted & paid

Procurement Staff with necessary technical support should verify: