Project for mba deepak desai.pdf

Embed Size (px)

Citation preview

  • 7/27/2019 Project for mba deepak desai.pdf

    1/48

    CHAPTER 1

    INTRODUCTION

  • 7/27/2019 Project for mba deepak desai.pdf

    2/48

    2

    1.1 BACKGROUND OF THE STUDYThe Indian foundry industry is the second largest in the world. There are more than

    6,000 foundries in India. Most foundries (nearly 90%) in India fall under the small and

    medium scale category and are located in clusters.

    The metal casting industry is naturally very energy intensive. Energy consumption

    in foundry mainly depends on electricity. The energy efficiency of any metal casting

    facility depends largely on the melting processes. Global warming is putting pressure on

    policy makers to formulate and adopt energy policies aimed at different sectors of the

    economy, industrial energy efficiency plays a central role in this regards.

    Foundry consumes huge amount of energy, and yields tons of wastes. Foundry

    industry is one of major energy consumption industry and exerts significant effect on

    environment. Energy accounting is necessary to determine where and how energy is

    being consumed and how efficient is the energy management system. Energy

    conservation and emission reduction is related tightly with the survival and development

    of the industry, and it is also a key point of sustainable development Foundry consumes

    huge amount of energy, and yields tons of wastes.

    Foundry uses two main forms of energy: coke and electricity. In a foundry usinginduction furnace for melting, electricity accounts for about 8595% of the total energy

    consumption of the unit. Induction furnace is major electricity consuming equipment, it

    consumes about 7085% of total electrical energy consumption. If the foundry units are

    heat treating the castings then diesel consumption comes out to around 1525% of the

    total energy consumption of the unit. In cupola-based units, coke typically accounts for

    8590% of the total energy consumption of the unit.

    The energy efficiency of foundry largely rides on the efficiency of the melting

    process a multi-step operation where the metal is heated, treated, alloyed, and

    transported into die or mold cavities to form a casting. The melting process is not only

    responsible for the energy consumption and cost-effectiveness of producing the castings

    but it is also critical to the control of quality, composition, and the physical and chemical

    properties of the final product.

  • 7/27/2019 Project for mba deepak desai.pdf

    3/48

    3

    1.2 COMPANY PROFILE

    Soundcasting is a world class manufacturer of Grey Cast Iron and Ductile Iron

    Machined Castings. With a built-up manufacturing area of 39,000 Sq. Meter, we have

    fully integrated casting and machining operations run in environmentally friendly

    foundries and machine shops. Our specialization is in supplying intricate, cored and fully

    machined cast components in the weight range of 10-125 kg and in the volume range of

    1,000-15,000 quantities per month to OEMs and system manufacturers. The installed

    casting capacity is 5000 tons per month, including a capacity of 1800 tons via High

    Pressure Moulding Line (DISAFLEX 70) installed in March 2010.

    1.2.1 BOARD OF DIRECTORS

    S.No Name of the Directors Designation1 Mr. V.N. Deshpande Executive Chairman2 Mr. N.S. Wagh Non-Executive Vice Chairman

    3 Mr. U.K. Deshpande Executive Vice Chairman

    4 Mr. Anand V. Deshpande Managing Director

    5 Mr. Ravindra K. Kalkundri Joint Managing Director

    6 Mr. Abhijeet V. Deshpande Joint Managing Director

    Table 1.01: Board of Directors

  • 7/27/2019 Project for mba deepak desai.pdf

    4/48

    4

    1 V.N. Deshpande(Executive Chairman and founder Director)

    Mr. VN Deshpande, VN, as he is referred by his friends, is also

    Chairman of Deshpande Automech Pvt. Ltd. Kolhapur, a company engaged

    in manufacture of Engine and bar components. He is BE (Mech) and

    PGDBM. He has past work experience in various industrial organizations in

    the area of materials management, oversees technical collaboration, planning

    and general management. While he has developed the organization through

    various roles, he now takes interest in long term strategic planning, expansion

    projects and key stake-holder relations.

    2 N.S. Wagh(Non-Executive Vice-Chairman and founder Director)

    Mr. Wagh is a BE Mech and BE Met and has a vast experience in the

    foundry industry. He has headed various areas in the company including

    HRD, marketing and operations. Currently he mentors the management team

    on a monthly basis and is on certain board appointed committees.

    3 U.K. Deshpande(Executive Vice Chairman and founder Director)

    Mr. UK Deshpande has a mechanical engineering background and has

    extensive experience in the areas of machining, ferrous casting and foundry

    project implementation. He is the Chief Technical Officer and a sensi to the

    technical team throughout the organization. Mr. UK Deshpande has led the

    successful plant installation and commissioning of our recent HPML line.

    4 Anand V. Deshpande(Managing Director)

    Mr. Anand has a B Tech in Mechanical Engineering from IIT

    Powai, MS in Industrial and Systems Engineering from The Ohio State

    University and MBA from University of Akron USA. Anand has worked in

    the USA for world class aerospace component manufacturer PPC airfoils

    and automotive company Mascotech, a leader in forgings. After working in

    the areas of product design and manufacturing he took over manufacturing

    of the company in 2000.

    He is responsible for creating the quality brand that Sound Castings

    is known for today. The ISO 9000, QS 9000 and TS 16949 were taken in a

  • 7/27/2019 Project for mba deepak desai.pdf

    5/48

    5

    short period of time and quality systems were strengthened over the decade

    to provide PPM levels at customer end. Anand is a hands-on leader and his

    primary focus area is Operations and Human Resource Development.

    5 Ravindra K. Kalkundri(Joint Managing Director)

    Mr. Ravi is a Chartered Accounted and in his previous career has

    practised in several organization including EOU companies. He joined the

    company full time in 1993. His acute financial acumen and discipline have

    helped the company progress in a systematic and planned manner without

    getting unduly leveraged. Ravi leads the finance, accounts and IT area within

    the company.

    6 Abhijeet V. Deshpande(Joint Managing Director)

    Mr. Abhijeet is a Metallurgist and has MS in Net Shape

    Manufacturing Systems from The Ohio State University. He also has an

    MBA from University of Pittsburgh. Abhijeet has worked for Tier 1, world

    class Die casting companies such as Ryobi and SPX Corporation in the USA.

    He has experience in the area of customer service, product quality/

    engineering and operations management. He is a certified Six Sigma Black

    Belt. Abhijeet leads the product development and marketing functions in the

    company.

  • 7/27/2019 Project for mba deepak desai.pdf

    6/48

    6

    1.2.2 MANUFACTURINGFoundries

    Soundcasting have State of the Art Foundries & Machine Shop at Kagal, Tardal and

    Shiroli in Kolhapur.

    MIDC Kagal KATP Ind Estate Tardal MIDC Shiroli

    Plot area -

    44,600 sq m.

    Plot area101,171 sq

    m.

    Plot area7,965 sq m.

    Built up area

    25,000 sq m.

    Built up area8,800 sq

    m.

    Built up area5,000 sq m.

    Power

    Connection

    -7500 KVA

    Power Connection -

    5435 KVA

    Power Connection -1500 KVA

    Table 1.02: Foundry Detail

    Present Total Capacity is 5000 MT/month

    Fully Automated DISA Make High Pressure Moulding Line Foundry

    Box size: 1000 mm x 700mm x 325/325 mm. 2.2 MVA, 750 Kg- 4 nos induction melting furnaces from Inductotherm India DISA make fully automated sand plants with 48MT / hour capacity Draft angles within 1 degree and mis-match within 0.5 mm PLC controlled Cold Box Core Shooters from 5 Kg to 100 Kg single piece

    core

    Cores dried in conveyor type ovens with appropriate temperature controls Automatic Core sand plants of 5MT/ hour to dry and process core sand Capability of casting modelling, gating design and access to simulation Environmental compliance via use of dust collectors, cyclones, scrubbers and

    other pollution control equipments

    In-mould cooling of 2 hours followed by 2 hours of air-cooling for largecastings

    Spinner hanger type shot blasting machines for good shot coverage

  • 7/27/2019 Project for mba deepak desai.pdf

    7/48

    7

    Mechanised conveyor type paint booth for uniform casting painting

    Fully mechanized APRA 900 and ARPA 450 Foundry from DISA India

    at Tardal

    Box Size of ARPA 900 - 800 mm x 650mm x 225/350 mm. Box Size of ARPA 450 - 650 mm x 650mm x 200/275 mm. 3750 KVA , 2000 Kg3 nos induction melting furnaces from Inductotherm

    India

    Vibratory chargers and magnetic cranes for feeding furnaces Automatic Core sand plants of 3MT/ hour to dry and process core sand PLC controlled Cold Box Core Shooters from 5 Kg to 18 Kg single piece core

    and 3 ton/hr. core oven, more are planned

    DISA make fully automated sand plants with 40 MT / hour capacity Automated mould handling system with auto punch-out (knockout) system Spinner hanger type shot blasting machines for good shot coverage

    Fully mechanized APRA 450 Foundry from DISA India at Kagal

    Box Size of line 1 - 650 mm x 650mm x 175/300 mm. Box Size of line 2 - 650 mm x 650mm x 225/250 mm. 550 KVA , 500 Kg 3 nos induction melting Furnaces from Inductotherm

    India

    DISA make fully automated sand plants with 36 MT / hour capacity

    Mechanized APRA 450/ 300 Foundry at Shiroli

    Box Size of line 1 - 650 mm x 650mm x 150/325 mm. Box Size of line 2500mm x 500mm x 150/300 mm. 550 KVA , 500 Kg 3 nos induction melting Furnaces from Inductotherm

    India

    Sand Plant capacity of 24 MT/ hour

  • 7/27/2019 Project for mba deepak desai.pdf

    8/48

    8

    Core Shops: Equipped with Core Sand plants, Cold Box core shooters

    and Core drying ovens

    Cold Box Core Shooters

    (2)- 100 Kg core shooter (1)- 80 Kg horizontal core shooter (1)- 65 Kg core shooter (1)- 30 Kg core shooter (1)- 25 Kg horizontal core shooter (1)- 20 Kg core shooter (5)-18Kg core shooter (2)-15 Kg horizontal core shooter (6)- 5 Kg core shooter

    Shot blasting & fettling / painting in-house facilities

    Facilities in Machine Shop

    Machine-shop space is available in all three locations and cumulative covered area is 8200 sq

    mts.

    A] Machining Centers

    Horizontal Machining Centres14 nos From maximum pallet Size 800x600 mm (Mazak 6800) to minimum pallet Size

    450x450 (Makino A 51)

    Vertical Machining Centres- 9 Nos Vertical CNC Turning centres- 6Nos Horizontal CNC Turning centres- 2 Nos

    B] Special Purpuse Machines (SPM's)- over 75 nos

    C] General Purpose machines

    Radial Drilling M/cs: RM 62, BVR 3 Milling M/cs: FN2, FN3 Tapping M/cs Vertical Balancing M/c

    D]Common Facilities for Foundry & Machine shop

    Electrical Power Connection7500 + 1500 + 5435 KVA

    Diesel Generator250 KVA- 3 Nos

  • 7/27/2019 Project for mba deepak desai.pdf

    9/48

    9

    1.2.3 QUALITY & TESTINGSoundcasting have a robust quality system certified to TS 16949 and ISO 9000 by

    TUV Nord, an independent IATF approved body.

    QC in Foundry:

    Spectro-lab make spectrometer (2 nos) Tensile testing machine Microscope with image analyser Chemical testing (wet analysis) Hardness testing Casting sectioning and layout marking

    Access to nationally certified labs for radiography, Dye-penetrant, and othertests

    QC in Machine shops

    3-D CNC controlled CMM (700x1000x600mm- Mitutoyo and Brown &Sharpe make),

    1-D electronic height gauges- make Trimos and Tesa Optical profile projector Surface testers, various bore dial gauges, air and water leakage testing etc. All critical characteristics (process and product) monitored by run charts/ SPC PDCA cycle effectively used for root cause analysis of non-conformance Mistake proofing, frugal engineering, cross-functional team working and

    continuous improvement are core to our manufacturing

    Our goal is to surpass customer ppm target

  • 7/27/2019 Project for mba deepak desai.pdf

    10/48

    10

    1.2.4 PRODUCTS

    Figure 1.01: Engine Appilcation

    Figure 1.02: Gearbox & Transmission

  • 7/27/2019 Project for mba deepak desai.pdf

    11/48

    11

    Figure 1.03: Axle, chassis and Brake Systems

    Figure1.04: Pump, Hydraulic Systems

  • 7/27/2019 Project for mba deepak desai.pdf

    12/48

    12

    1.2.5 CUSTOMERS

    Figure 1.05: Customers

    Table 1.03: Customer Specific

    1 Mahindra & MahindraLtd.- Automotive Sector

    2 Mahindra & Mahindra Ltd.-Farm Equipment Sector

    3 Mahindra Navy StarAutomotives Ltd

    4 Ashok Leyland Ltd

    5 John Deere Equipment PvtLtd

    6 Kirloskar Oil Engines Ltd7 New Holland Tractors 8 Brakes India Ltd.9 ZF India Pvt Ltd. 10 Windals Precision11 Eicher tractors 12 Tafe

  • 7/27/2019 Project for mba deepak desai.pdf

    13/48

    13

    1.2.6 MILESTONES1988:

    Established as a foundry making only 50T per month by Mr. VN Deshpande,

    UK Deshpande and Mr. NS Wagh.

    1993:

    Started Induction furnace melting by adding Inductotherm make furnace.

    1998:

    Merged Deshpande Industries, an independent machine shop with itself and

    expanded the machining set-up.

    2000-2006 :

    Started various new process improvement and six-sigma initiatives, added

    several new customers including Ashok Leyland, John Deere, Kirloskar Oil

    Engines and Brakes India.

    2007-2009:

    Added a plant in Kagal MIDC, added several investments in foundry and

    machining, added customers such as ZF and Case New Holland. Capacity

    increased to 2200 MT per month.

    2010:

    Added High Pressure Moulding Line. New customers such as TAFE and Tata

    Cummins limited were added, in addition to strengthening relations with

    existing customers. Capacity added to 4000 MT/month

    2011:

    Added new machining Centers including those from MAKINO and MAZAK,

    Japan.

  • 7/27/2019 Project for mba deepak desai.pdf

    14/48

    14

    1.2.7 CONTACTSOUND CASTINGS PVT. LTD.

    E-2, M.I.D.C., Shiroli, Kolhapur 416122

    Maharashatra State, India

    Phone +91-9623262099

    Fax 91-230-2468219

    [email protected]

    Figure 1.06: Location Map

    mailto:[email protected]:[email protected]:[email protected]:[email protected]
  • 7/27/2019 Project for mba deepak desai.pdf

    15/48

    15

    1.3 STATEMENT OF THE PROBLEMUntil recently, in most industries energy costs were regarded simply as a cost

    of doing business, and little attention was paid to them. The level of interest in efficient

    energy use had been moderated by continuing low electricity and fuel prices that

    prevailed until 2000.After 2000 due to price of electricity hike its added urgency to the

    need to examine the effectiveness of energy use in Soundcasting.

    1.4 NEED OF THE STUDYThe need of this study is to explore Grand Challenge or breakthrough

    opportunities that might dramatically reduce energy consumptions and Identification to

    potentially energy-saving based on the findings.

    1.5 SCOPE OF THE STUDYThe scope of the study includes energy consumptions and identification to

    potentially energy-saving applications in the metal casting industry in domestic markets.

    Although, the report focuses on foundry applications, the energy management programs

    discussed in this report are in general applicable to all casting industry and other

    industries.

    1.6 OBJECTIVES OF THE STUDY Determination of the energy consumption pattern. Helps to control energy cost by identifying areas where waste can occur and

    where scope for improvement may be possible.

    Finding energy management programs further.

  • 7/27/2019 Project for mba deepak desai.pdf

    16/48

    CHAPTER 2

    LITERATURE REVIEW

  • 7/27/2019 Project for mba deepak desai.pdf

    17/48

    17

    2.1 POWER DISTRIBUTION TREE OF FOUNDRYIn figure the main processes of foundry energy consumption is shown so that one

    can understand the whole system step by step with power consumptions in different

    departments and also the losses

    Figure 2.01: Power distribution tree of FoundryThe foundry industry is one of the most energy-intensive industries accounting for

    one-eighth of all the energy supplied to industries. Main foundry classes are Gray- and

    ductile-iron foundries (Standard Industrial Classification code 3321), malleable-iron

    foundries (SIC 3322), and steel foundries (SIC 3325)these represent more than 95 percent

    of the total foundry energy consumption in Wisconsin.

    The American Foundry mens Society Cast Iron Directory 1995-1996 lists 191

    foundries in Wisconsin, of which about 154 fall into the three ferrous iron categories listed

    above. Gray- and ductile-iron foundries account for more than half of this total, followed

    closely by steel foundries. There are only three malleable-iron foundries listed. Although

    many of Wisconsins ferrous foundries are relatively small, some high-volume plants are in

  • 7/27/2019 Project for mba deepak desai.pdf

    18/48

    18

    production. One Wisconsin plant, for example, melts approximately 700 tons of metal per

    day, and total daily energy consumption can reach 1000 kWh.

    This study was designed to provide information that could be used to help identify

    ways to improve process energy efficiency at foundries. To do this we performed an

    extensive review of the literature to develop the consistent foundry information resource

    presented through this report. This information is designed to provide utilities, government

    agencies, and energy-service providers with the data they need to design and deliver

    effective energy-saving programs for Wisconsin foundries.

    2.2 CURRENT INFORMATION ON PROCESS ENERGYUSE

    Among major processes, the melting process consumes the most energy in a foundry,

    representing about 50 to 80 percent of the total energy required to produce a casting. Typical

    energy-consumption values found in the literature for the three primary melting processes

    for Gray iron are shown in Table

    Figure 2.02: Energy consumption of melting processes (kWh per ton of casting sold)

    These figures depend on casting efficiency. All castings have risers and runners that

    are needed to produce a shrinkage-free product. Depending on how the casting is designed,

    the quantity of returns can vary between 30 and 95 percent. This material is melted but does

    not become a part of the finished casting. Hence, the energy used per ton of finished casting

    can vary substantially with the efficiency of the foundry, the intricacy of the mold, and the

    ability to reduce the quantity of metal returned.

    Although foundry processes may appear to be relatively homogeneous when

    compared with processes of other industries, significant variations between plants and

    processes exist. The great diversity of thermal operations in a foundryresulting from the

    different types of energy used, the working procedures used, production capacity, the nature

    of alloys produced, the dimensions of castings heat treated, and the effective castings yield

  • 7/27/2019 Project for mba deepak desai.pdf

    19/48

    19

    makes it difficult to establish an overall ratio of foundry energy consumption per ton of good

    casting that would be significant to all foundries.

    It has been difficult to develop average, typical, and best practice energy balances

    for Wisconsin foundries because of a lack of published information on energy consumption

    in specific foundry processes. Literature data tends to focus on the melting process; little or

    no data are available on energy consumption in the other foundry processes. The bulk of the

    information available is for Gray iron foundries, with limited data for ductile-iron,

    malleable-iron, and steel foundries. Most data are for production prior to 1983. Since that

    time, some foundries have taken steps to improve efficiency in the areas of yield

    improvement, oxygen melting assistance, furnace and ladle insulation, and recovery of heat

    previously discharged to atmosphere. As a result, Wisconsin foundries may be operating

    more efficiently than indicated by most information sources.

    2.3 INFORMATION DATABASE2.3.1 Developing Process Baselines

    We collected information on the major melting processes common to

    foundries. These data were often from highly detailed studies of foundry practicesand represent comprehensive information on foundry melting process energy

    consumption. Energy consumption figures collected for processes other than melting

    were less complete. The energy consumption data for melting processes were

    obtained from compilations available in the literature.

    2.3.2 Cupola Melting ProcessA major problem with comparing the coke consumption in cupolas is that

    some of the coke input is used for adjusting the metallurgical composition of the

    casting and is not combusted. Also, energy content of coke is variable and rarely

    reported in the literature. We used an energy content of 22.72 million BTUs person

    to convert coke consumption in cupolas reported in tons to energy units. We assumed

    that all of the data reported are for coke consumption in conventional coke cupolas.

    Coke less cupolas which use natural gas or oil as their primary fuel a re also

    available. These newer types of technology are often used in duplexing operations

  • 7/27/2019 Project for mba deepak desai.pdf

    20/48

    20

    combining coke less gas furnaces with electric induction holding furnaces. Many of

    the literature sources do not specifically list the type of cupola or the fuel consumed.

    About two-thirds of the data reported for cupola energy consumption are from

    Canadian and British studies of cupola energy consumption. The Canadian study

    (Warda et al, 1981) presents data from a detailed engineering study of thirty cupolas

    conducted by the Canada Centre for Mineral and Energy Technology in the late

    1970s. The British study (Energy Technology Support Unit, 1990a) draws on two

    main sources of data; a recent questionnaire survey of the British foundry industry

    conducted in 1989-90 and information from a British Cast Iron Research Association

    study conducted in 1979.

    We obtained only two data points for cupola melting energy in ductile-iron

    foundries. One was from the British foundry survey (Energy Technology Support

    Unit, 1991), and the other was from a Wisconsin foundry taken from a survey of

    Wisconsin foundries (Leadon, 1984).We obtained only three data points for cupola

    melting energy in malleable iron foundries (Energy Technology Support Unit,

    1990a).

    2.3.3 Induction Melting ProcessOne difficulty in comparing data for induction furnaces is the issue of

    holding. Often medium frequency furnaces are installed as a pair, so that the melting

    furnace can also perform the role of holding/pouring of molten iron after completing

    each melt. Unlike the cupola and the mains induction furnace, the quoted energy

    consumption would therefore include both the melting and holding/pouring

    processes. Holding of molten iron following the mains and cupola melting processes

    is most often accomplished by a channel induction furnace and energy consumption

    data are often reported separately. According to data collected as part of the British

    Energy Efficiency Office survey of coreless induction melting furnaces, (Energy

    Technology Support Unit,1991), average energy consumption by mains frequency

    induction furnaces was751 kWh/metric ton (681 kWh/US ton) of metal melted while

    energy consumption in medium frequency installations was 818 kWh/metric ton

    (742kWh/US ton). For reference, the theoretical electrical energy needed to melt cast-

    iron and raise its temperature to 1450 C (2650 F) is about 419 kWh/metric ton(380

    kWh/US ton). Considering coil and heat losses at about 20 to 25 percent, the

    minimum energy consumption for highly efficient induction furnaces would-be about

  • 7/27/2019 Project for mba deepak desai.pdf

    21/48

    21

    459 kWh/metric ton (416 kWh/US ton).More than half the data collected on induction

    melting process energy consumption for this study comes from the British Energy

    Efficiency Office survey. Data were obtained for only Gray-iron foundries and steel-

    foundries. Figures for yield were not available; nor were overall energy intensity

    figures for total foundry operations using induction melting processes. The majority

    of the data for steel foundries were taken from the International Cast Metals Journal

    (American Foundry mens Society, 1980), which gave only ranges of expected

    energy intensities for steel induction melting processes rather than empirical data.

    The one real data point (fora Wisconsin steel foundry) taken from the survey of

    Wisconsin foundries (Leedom, 1984), is within 95percent of the theoretical minimum

    energy intensity.

    2.3.4 Duplex Melting ProcessThe most detailed data reported for duplex melting are from Leedom (1984)

    fora foundry using a cupola and duplex process in two plants. There are two data

    points each for ductile-iron and Gray-iron castings.

    2.3.5 Electric-Arc Melting ProcessWe collected data for the arc melting process for Gray iron and steel. Most

    of these data points were taken from Leedom (1984). All of the data for Gray ironis

    10 to 15 years old. Data for arc melting for steel production contains both recent data

    for state-of-the-art operations and older data from the early 1980s.

    2.3.6 Induction Holding ProcessEnergy consumption data for induction holding processes was collected on

    the basis of energy consumption per unit of metal throughput. Many variables

    influence the energy intensity of holding a molten charge including technology,

    continuous vs. intermittent operations, length of time required for holding, and

    superheating as in a duplex/holding furnace. Information on these other important

    variables was not provided in the literature along with the energy consumption

    figure. We collected data for three different holding processes: duplex furnace,

    channel induction furnace, and crucible furnace. The majority of the data collected

    was for Gray iron, although we found two data points for ductile iron. All of the data

    are between 10 and 15 years old. A few data points are from a Wisconsin foundry.

  • 7/27/2019 Project for mba deepak desai.pdf

    22/48

    22

    2.4 INTERPRETING PROCESS ENERGY CONSUMPTIONESTIMATES

    The figures presented in this report may overestimate energy consumption becausemany estimates were based on pre-1983 data. With the fall of real energy prices, energy

    consumption in foundries has not been featured prominently in foundry literature. Since the

    early 1970s, some foundries have taken steps to improve energy efficiency. The major

    improvements have been in the areas of yield improvement, oxygen melting assistance,

    furnace and ladle insulation, and recovery of heat previously discharged to atmosphere. On

    the other hand, increases in pollution control apparatus have resulted in increased energy

    consumption. Even so, Wisconsin foundries are probably operating more efficiently than

    indicated by the outdated energy intensities available in the literature. We estimate that they

    are as much as 25 percent more efficient than indicated by the pre-1983 figures. The data

    shown for duplex process energy consumption must be viewed with extra caution. The data

    were highly aggregated, and thus may not accurately represent actual energy consumption.

  • 7/27/2019 Project for mba deepak desai.pdf

    23/48

    CHAPTER 3

    RESEARCH METHODOLOGY

  • 7/27/2019 Project for mba deepak desai.pdf

    24/48

    24

    3.1 PROBLEM RECOGNITIONThis study is focused on determining the practical potential for reducing energy

    requirements in the Soundcasting industry by looking at industry best practices, which

    are referred to as best practice minimums. Both equipment design efficiencies and

    operating procedures related to reduced-energy consumption are discussed in detail. The

    highest energy consuming processes within each casting alloy family were investigated

    to determine the potential for energy reduction measures.

    The theoretical minimum energy requirements are also calculated for the major

    energy consuming processes. The theoretical minimum energy requirements are

    calculated by ignoring all energy losses and therefore are not achievable in practice. A

    baseline of current foundry energy usage was also determined from the best available

    information and is referred to as the industry average. The industry average energy

    usage was then compared to the best practice to determine the potential for energy

    reduction using existing and proven technologies and procedures.

    Material and energy losses during process steps represent inefficiencies that waste

    energy and increase the costs of melting operations. Modifying the design and/or

    operation of any step in the melting process may affect the subsequent steps. It is,

    therefore, important to examine the impact of all proposed modifications over the entire

    melting process to ensure that energy improvement in one step is not translating to

    energy burden in another step.

    3.2 RESEARCH APPROACHAn energy management program follows the same principles that apply to

    any purposeful undertaking (e.g., to quality and environmental management systems)

    principles that Dr. Deming formulated as the four-step cycle, PlanDoCheckAct,

    PDCA, shown below.

  • 7/27/2019 Project for mba deepak desai.pdf

    25/48

    25

    .

    Figure 3.01: Four key steps

    The four stages of the PDSA cycle:

    Plan - The change to be tested or implemented.

    Do - Carry out the test or change.

    Check- Data before and after the change and reflect on what was learned.

    Act - Plan the next change cycle or full implementation.

    To realize opportunities, foundry management must successfully integrate

    organizational and behavioural (cultural) change and new energy use technology. The

    energy efficiency effort must have a defined focus, accountability and responsibility.

    The points in Figure are generic and given for information only. Their application will

    vary with the size and complexity of a foundrys operations and will be determined by

    site-specific conditions of a particular energy efficiency improvement program.

    3.3 DATA COLLECTION METHODS3.4.3 Primary data

    Primary data is the data that is collected for the first time i.e. the data did not

    exist before the collection. In this report primary data has been produced by for

    example finding energy usage across different utilities in company.

    3.4.4 Secondary DataSecondary data consist of data which has been collected in another

    context. In this report the data is collected from literature searches were

    conducted to obtain available information on energy conservation in the

    metal casting industry and from company annual report.

  • 7/27/2019 Project for mba deepak desai.pdf

    26/48

    26

    Literature searches conducted for this study provided many

    documents written by the metal casting industry and federal government

    agencies. The specific documents referred to for relevant casting energy data

    are listed in the reference section of this report. A significant study that

    yielded very accurate energy data for a specific number of facilities is the

    Energy Use in Select Metal casting Facilities, which was a quantitative

    study that performed onsite measurement of energy use. The study gives

    energy profiles for a cross section of casting facilities and was used along

    with other foundry-specific studies.

  • 7/27/2019 Project for mba deepak desai.pdf

    27/48

    CHAPTER4

    DATA PROCESSING AND ANALYSIS

  • 7/27/2019 Project for mba deepak desai.pdf

    28/48

    28

    4.1 FOUNDRY TECHNOLOGIESThere are several types of equipment and technologies that are widely used in the

    foundry process. Some of the major ones include:

    Melting furnaces Sand mullers Intensive mixers Pneumatic grinders Shell moulding machine Core oven Shell core shooters

    Knockout machine Shot blast machine

    The major equipments are described below.

    4.1.1Major equipment used in foundry units(a) Melting furnaces

    Two types of melting furnaces are commonly used in a foundry cupola and induction furnace. While cupola uses coke to melt the metallic charge

    materials, an induction furnace uses electrical energy. Although the energy cost

    per tonne of molten metal is lower in a cupola, other advantages of induction

    furnaces, viz., faster start-up, lower manpower requirement, and lower emissions

    have contributed to their increasing popularity among foundry units in Kolhapur

    cluster.

    (b) Sand mullers

    These are used for green sand preparation. Fresh sand is mixed with

    bentonite and other additives and mixed in Muller to make green sand. These

    usually come in small size of around 300 kg per batch, with typical connected

    drive of 10 kW and cycle time come about 710 minutes.

    (c) Intensive mixers

    Cores are forms that are placed into the mold to create the interior

    contours of the casting. They are typically made of clay-free silica sand mixture.

    The sand is thoroughly mixed with suitable binders, water, and other ingredients

  • 7/27/2019 Project for mba deepak desai.pdf

    29/48

    29

    in intensive mixers. This equipment basically has two motor drives, used to rotate

    the blades and perform mixing. A typical 10 tonne per hour, 500 kg batch-

    intensive mixture has a total connected load of around 70 kW.

    (d) Shell-moulding machine

    This is usually located below the sand mixer. Sand from a hopper falls

    into the moulding box and then pneumatically or hydraulically pressed to make

    the final mould. High pressure moulding machines can use moulding sand having

    lower moisture contents and hence higher mould densities can be achieved. The

    castings have better dimensional accuracy and better surface finish.

    (e) Knock-out machine

    The knock-out machine has grated base, and it has two vibrators one

    on either side or a single vibrator.

    (f) Shot blasting

    There are different types of shot-blasting machines available; the

    most common ones in Kolhapur foundry cluster are double door, two shooters

    type. It has four drives, two for shooters, one of bucket rotating, and one for dust

    collection. Typical 1 tonne per batch shot blast machine has total connected load

    of around 25 kW.

    4.2 FOUNDRY PROCESS DESCRIPTIONDifferent stages in manufacturing of a casting include the following:

    4.2.1 Preparation of moulds and charge materialThis involves preparation of (i) moulding sand, (ii) casting moulds, and (iii)

    charge (metals and alloys). Fresh sand is mixed with bentonite and other additives

    and processed to prepare green sand, which is the most commonly used moulding

    sand in Soundcasting, typical batch size varies between 200500 kg. The green sand

    is then used to prepare moulds for the castings. Simultaneously, metal scrap, pig iron,

    and other alloys are loaded in the furnace for melting. The ratio between raw

    materials depends on final casting properties. A typical cast iron casting has raw

    material in following percentage: metal scrap (25%), boring (60%), pig iron (10%),

    and others (5%).

  • 7/27/2019 Project for mba deepak desai.pdf

    30/48

    30

    4.2.2 Melting stageThe metal is then melted in either a cupola furnaceconventional or divided

    blastor induction furnace. The typical temperature requirement for CI casting is

    around 1500C, steel casting is around 1650C, and for aluminium casting 750C.Once the melting is completed, the molten metal is poured into the sand moulds using

    a ladle operated either manually, automatically, or semi-automatically, that were

    prepared in the first stage and allowed to cool down and harden.

    4.2.3 Finishing stageOnce the metal has taken shape of the mould, it is removed, shot blasted, and

    cleaned. It also goes through some machining, if required. The final product is tested

    using spectrometer and packed for dispatch. Meanwhile, the sand from the mouldsis either disposed or treated in a sand reclamation plant for reuse. Units using sand

    reclamation in Soundcasting are generally able to reuse about 80% of the sand. A

    more technical illustration of the manufacturing process of a typical foundry unit in

    the Soundcasting is presented in Figure.

    Figure 4.01: Manufacturing process of a typical foundry unit in Soundcasting

  • 7/27/2019 Project for mba deepak desai.pdf

    31/48

    31

    4.3 TYPES OF FUEL AND USAGE IN MSMES4.3.1Fuel types and quantity used in typical MSME units

    Foundry uses two main forms of energy: coke and electricity. In a foundry

    using induction furnace for melting, electricity accounts for about 8595% of the total

    energy consumption of the unit. Induction furnace is major electricity consuming

    equipment, it consumes about 7085% of total electrical energy consumption. If the

    foundry units are heat treating the castings then diesel consumption comes out to around

    1525% of the total energy consumption of the unit. In cupola-based units, coke

    typically accounts for 8590% of the total energy consumption of the unit.

    4.3.2Specifications and characteristicsCoke is used in foundries where the melting process is done in a cupola furnace

    (conventional or divided blast) and electricity is used in units where melting is done in

    an induction furnace. Other processes in a foundry such as sand preparation, machining,

    shot blasting, etc., are all operated using electricity, irrespective of whether the foundry

    is cupola based or induction based. Metallurgical coke is being used as fuel in cupola

    based units in the cluster. The calorific value of the coke varies between 55006500

    kcal/kg.

    4.3.3Price/Tariff ElectricityThe price of electricity has increased from INR 5.90 per unit to INR 8.50 per unit in

    Kolhapur. Figure 7 shows the trend over the last four years. The price shows an

    increment of over 15% during this period.

    Figure 4.02: Energy price (20092012)

  • 7/27/2019 Project for mba deepak desai.pdf

    32/48

    32

    4.3.4CokeThe price of coke has increased over the last year and is presently about INR 30,000

    per tonne.

    4.3.5SourcesElectricity to Kolhapur is supplied from the Maharashtra State Electricity

    Distribution Company Limited (MSEDCL). MSEDCL supplies electricity to 3.63 lakh

    industrial consumers sourcing its power from thermal, hydro, gas, and non-conventional

    sources like solar, wind, bagasse, etc. Coke is being supplied from various sources

    which include Sesa-Kembla Goa, Gujarat NRE, and also from some suppliers in

    Nagpur.

    4.4 ENERGY CONSUMPTION PATTERN4.4.1 Utility-wise energy share

    The share of energy usage across different utilities in Soundcasting foundry

    is given. As shown, the majority of energy is consumed for the melting process

    (about 70%). Moulding, core making, and sand preparation are also significant

    consumers in the process.

    Table 4.01: Utility-wise energy share in Soundcasting

    It is observed that melting consumes a major portion of total energy consumed.

    4.4.2 Energy consumption in melting furnacesA foundry had two medium frequency induction furnaces. The unit had fair

    energy metering and reporting systems. Every melting furnace was connected to an

    individual energy meter (average type). Every day the consumption and production

  • 7/27/2019 Project for mba deepak desai.pdf

    33/48

    33

    of each furnace was recorded and monitored. The furnace details are presented in

    table

    Furnace

    #

    No of

    crucibles

    Crucible

    Capacity,

    kg.

    Rated kW Rated

    frequency,

    Hz

    Average

    specific

    consumption,

    kWh/Mt

    # 1 2 1000 &

    1000

    1000 500 674

    # 2 3 500,500&

    1000

    550 100 777

    Table 4.02:Furnace details with specific energy consumption

    4.4.3 Energy consumption in CompressorsAir compressors were used in the machine shop for pneumatic equipment

    and machine tools. While visited the foundry compressor system had found some

    issues were presented below in table

    Present system of Air compressor system

    Location of the compressor was near

    by the heat source that shown the

    reason of rise in inlet temperature may

    reduce power saving.

    Measured temperature of inlet air is

    about 45C by contact thermometer.

    Regular checking of leak were not

    taken place that cause pressure drops

    that adversely affect the operation of

    air-using equipment and tools,

    reducing production efficiency.

    Table 4.03:Present system of Air compressor system

  • 7/27/2019 Project for mba deepak desai.pdf

    34/48

    34

    4.4.4 Present system of electrical distribution in foundryIt was found during visit that present electrical distribution system was not

    proper with respect to timing and capacitor as presented in table

    Present system of electrical distribution in

    foundry.

    No load is being shifted to Night

    timing when the electricity is at low

    cost.

    There are no any capacitors using in

    electrical system to maintain or

    improve the power factor.

    Table 4.04: Present system of electrical distribution

    4.5 Energy management planTo start, a few major components must be put in place:

    1. Firm commitment of top management2. Clearly defined program objectives

    3. Organizational structure and definition of responsibilities

    4. Provision of resourcespeople and money

    5. Measures and tracking procedures

    6. Regular progress review

    Table 4.05: Energy management plan

    Plan -Predict and prevent troubles beforehand.

    Do -Educate and train employees.

    -Implement the plans.

    Check - Compare the results against the targets.

    - When the results fall short, examine the causes.

    - Take immediate measures.

    - Analyze the process and identify the root causes and develop

    Act -Revise the standards.

  • 7/27/2019 Project for mba deepak desai.pdf

    35/48

    35

    4.5.1 Energy Saving Guideline Turn off lights (and other equipment) when not in use. High utility costs often

    include paying for energy that is completely wasted.

    Replace incandescent light bulbs with ENERGY STAR qualified compactfluorescent lamps (CFLs), wherever appropriate. CFLs cost about 75 percent

    less to operate, and last about 10 times longer.

    Adjust lighting to your actual needs; use free "daylight" during the day.

    Turning off machines when they are not in use can result in enormous energysavings. There is a common misconception that screen savers reduce energy

    use by monitors; they do not. Automatic switching to sleep mode or manually

    turning monitors off is always the better energy-saving strategy.

    To maximize savings with a laptop, put the AC adapter on a power strip thatcan be turned off (or will turn off automatically); the transformer in the AC

    adapter draws power continuously, even when the laptop is not plugged into

    the adapter.

    Fix leaks of water. Small leaks add up to many gallons

    Unplug battery chargers when the batteries are fully charged or the chargersare not in use.

    Air ingress into the furnace (heat treatment furnace) causes significant lossof energy. All that extra air needs to be heated to maintain the proper furnace

    chamber temperature. Air ingress may reduce cold spots and quality

    problems as well.

  • 7/27/2019 Project for mba deepak desai.pdf

    36/48

    36

    Figure 4.03: Radiation losses

    The radiation losses are serious in melting furnaces (e.g., induction furnaces)where they occur through open lids, open dross removing or slagging doors,

    from ladles with no or inadequate covers during heating, and especially

    during molten metal transfer.

    For thermal losses and conductive heat sinks, it is a question of adequateinsulation and furnace or ladle lining with the right type of refractory

    materials. If dense firebrick is used for lining the furnace, it needs to be

    installed in adequate thickness to limit the heat conductive losses.

    Energy management is an ongoing concern in any foundry. Its success

    depends on a team effort starting with a firm commitment from the top executive and

    his or her management team. Managements demonstration of unwavering, solid and

    visible support filters through the organization to each employee. Everybody will

    take heed and will follow the example. Once the decision to manage energy has been

    reached, it should be supported by a board-level energy policy, which will regard

    energy and the cost of utilities as direct costs on par with other operational costs,

    such as labour, raw materials, etc.

    A build-up of general awareness about energy issues through

    communication, education and training of employees at all relevant levels will

    contribute to a cultural change within the organization. Education and training must

    be sustained in order to achieve lasting energy efficiency improvements. Sometimes,

    even when the opportunities for energy savings are great, they are not utilized.

  • 7/27/2019 Project for mba deepak desai.pdf

    37/48

    37

    The reasons fall into the familiar:

    Was not aware of opportunities that exist;

    Did not know what to do;

    Top management not supportive;

    Energy issues not a priority;

    No money and/or staff and/or time; and

    No defined accountability.

    Since the primary business goal is financial savings, managers must

    understand the principle of economics and run their department as if it were their

    own business. In doing so, improving energy efficiency should get proper attention.

    This will require some education. Even if the financial gains from energy efficiency

    improvements were to seem modest compared to the value of sales or to the overall

    budget, they can contribute considerably to the foundrys net profit.

    4.6 ENERGY EFFICIENCYThe energy efficiency of the melting process is calculated by dividing the

    amount of theoretical energy needed to melt a metal and raise it to its pouring

    temperature by the actual amount of energy consumed in melting, treating, holding

    and handling the material.

    4.6.1 Energy Savings in Induction Furnaces The heat cycle that is pouring to pouring, recorded about 25-40% of the specified

    standard time.

  • 7/27/2019 Project for mba deepak desai.pdf

    38/48

    38

    The power to the furnace was varied very frequently due to empty space in thecrucible, excess charge, and sample analysis delay.

    The recorded electrical parameters indicate that about 35-40% of the heat timethe furnace was operated at 70-80% of rated power.

    About 80% metal is charged before taking the sample for the analysis. Theremaining 20% of crucible volume is loaded after obtaining the sample analysis.

    The first batch sample analysis indicates the short fall of different elements,based on this the additional material is added to achieve the required composition

    and quantity.

    Furnace # 1 Furnace # 2 Furnace Total

    Possible reduction in time (min) 6 8 -

    Reduction in energy (kW) 24 23.4 47.4

    Operating days per year 330 330 -

    Operating hours per day 22 17 -

    Energy savings (Lakh

    kWh/year)

    1.95 1.33 3.88

    Annual cost savings (Rs. Lakh) 6.30 4.06 10.36

    Investment required (Rs. Lakh) 1 1 2

    Payback period (Months) 2 3 2

    Table 4.06: Details of Saving

  • 7/27/2019 Project for mba deepak desai.pdf

    39/48

    39

    4.6.2 Energy Savings in the Compressed Air SystemThe relation between inlet temperature and relative air delivery and due to

    that power consumption can be analysed and it can be seen that lower inlet

    temperature can save more power.

    Foundry had found inlet temperature about 45C. So from table it consumes morepower. While extending the air intake from the outside of the building, minimize

    excess pressure drop in the suction line by selecting a duct of large diameter with

    the smallest number of bends that gave air at 32C temperature.

    Locate the compressor away from heat sources such as kilns, dryers and otheritems of equipment that radiate heat.

    Inlet Temperature (C) Relative Air Delivery

    (%)

    Power Saved (%)

    10.0 102.0 + 1.4

    15.5 100.0 Nil

    21.1 98.1 1.3

    26.6 96.3 2.5

    32.2 94.1 4.0

    37.7 92.8 5.0

    43.3 91.2 5.8

    Table 4.07: Effect of intake air temperature on power consumption

    4.6.3 Proposed energy Savings in the Electrical Distribution System Stagger the non-critical load according to the electricity tariff to reduce the

    energy bill. The benefits of load staggering are shown in Table 8.

    Maintain a high power factor, which will lead to reduced demand, better voltage,high system efficiency as well as rebates from the electricity supplying company.

    The power factor can be improved by installing capacitors in the electrical

  • 7/27/2019 Project for mba deepak desai.pdf

    40/48

    40

    system. Table shows the benefits of power factor improvements from the point

    of view of costs.

    Control the maximum demand by tripping non-critical loads through a demandcontroller. This will avoid the penalty levied when usage is greater than the

    sanctioned load.

    Balance the system voltage to reduce the distribution losses in the system. Forevery 1% increase in voltage imbalance, the efficiency of the motors decreases

    by 1%.

    Load to be shifted to night shift (10 PM - 6 AM) 15 kW

    Assumed working hours per shift 8 hours

    Monthly power consumption (30 days/month) 3000 kWh

    Electrical cost for night shift operations

    ( assuming Rs 3.5/kWh during 10 PM - 6 AM)

    Rs 1,0500

    Electrical cost for general shift operations (assuming Rs.

    5/kWh)

    Rs 1,5000

    Savings per month Rs 4500

    Annual savings Rs 54,000

    Table 4.08:Benefits of load staggering

  • 7/27/2019 Project for mba deepak desai.pdf

    41/48

    CHAPTER 5

    FINDINGS

  • 7/27/2019 Project for mba deepak desai.pdf

    42/48

    42

    From the collected data it is found that the major energy consumption department is

    melting department and to save energy from that must carried to save energy from furnaces.

    As shown from power distribution tree that accordingly air compressors and electrical

    distribution systems are also found major energy consumption areas in foundry after

    furnaces. Savings in each department can be accomplished as per choosing best energy

    management procedure.

    For proper energy management system it would be necessary to choose an efficient

    furnace that must be satisfy demand of foundry. Although high energy expenses are a

    significant concern for metal casters, many foundries are using melting technologies with

    poor energy efficiency. The amount of heat put into the furnace, the thermal efficiency refers

    to the percentage of that heat that actually melts the metal. The remaining heat is lost,

    through for example, inefficient combustion, the furnaces housing and flue

    Supply of the full power during the melting (most of the time) is being practiced.

    To lower the specific energy consumption, Reduction in time taken for sampleanalysis & communication was significantly reduced the heat time. Use of intercoms

    and alarms, pneumatic conveying and advanced logistical preparations helped to

    reduce the time for sample analysis.

    In addition to above, use of recently introduced energy optimizer for meltingoperation created a benchmark and enforced conscious practice to complete the job

    within the set goal. This energy optimizer senses the inverter output power and

    integrates into energy delivered to the furnace. It is possible to set a predetermined

    energy requirement value for melting the material to the desired temperature.

    For proper energy management, Setting of energy parameter was based on lowestachieved energy consumption figure during the past fortnight. Close monitoring of

    set goal and analysis of the reasons for not being able to comply with the

    benchmarking if any, shall ensure reaching the optimum level of energy

    consumption.

  • 7/27/2019 Project for mba deepak desai.pdf

    43/48

    CHAPTER 6

    CONCLUSIONS

  • 7/27/2019 Project for mba deepak desai.pdf

    44/48

    44

    There is a large scope of energy management in foundry industry sector in Indian

    small and medium scale foundry industries considering the fact that the large amount of

    power is being wasted by many ways. As majority of these foundries are not aware of

    these facts.

    From above we conclude that the better energy management program may save not

    only in terms of energy but also it may save money. Savings of at least 10% and up to

    40 % may be realized by implementing some useful energy management techniques.

    The key to achieving savings is to take a strategic approach to managing energy use and

    giving importance to energy management techniques. While energy efficient

    technologies have a significant role to play in reducing energy use in foundry industry.

    Most of the small-scale foundry units are family owned and managed. The general

    level of awareness among them about energy conservation and new technologies is low.

    Although some of the entrepreneurs are interested in energy efficiency and technological

    improvements they are constrained by lack of technical know-how and finances.

    Looking into todays scenario, it becomes very essential for Foundry men to look for

    means which can bring down the energy consumption in melting operation significantly

    by efficient methods and techniques

    Success of Energy management depends on a team effort starting with a firm

    commitment from the top executive and management team. The first assignment in

    energy saving activity must be the initial energy audit. It is a key step that establishes

    the baseline from which the future energy efficiency improvements can be measured.

    One of the main results of energy audit is the possibility of determination of the energy

    consumption pattern. The energy pattern is the key in understanding the way energy is

    used in a foundry and helps to control energy cost by identifying areas where waste can

    occur and where scope for improvement may be possible.

    The best available energy management techniques needs to be used in order to

    optimise the production. It is expected that there will be ample scope for Indian foundry

    operators in energy management

  • 7/27/2019 Project for mba deepak desai.pdf

    45/48

    CHAPTER 7

    RECOMMENDATIONS

  • 7/27/2019 Project for mba deepak desai.pdf

    46/48

    46

    This would break new ground in energy-efficiency studies of the foundry industry;

    it would produce the first process-oriented energy consumption database that considers

    more than just melting energy; and it would generate Energy balances describing

    foundry-process energy consumption that reflects the current state of the foundry

    industry.

    Specifically, the recommended survey project would

    Survey all foundries with a written questionnaire. Conduct in-depth energy audits and energy analyses at six to eight foundries. Assimilate and analyse survey and audit data to develop a process-level energy

    balance for foundry energy consumption.

    Develop a utility tool that field representatives could use to conduct foundrycustomer energy-efficiency analyses at the process end-use level.

    If appropriate, determine the energy use that goes into each process step bymonitoring actual energy input and material throughput as part of the energy audits.

    Develop a baseline from which foundry utilities can offer a service to quantifyfoundry customer energy consumption as compared to the baseline.

    Involve utilities in the study so they can follow-up with specific performanceoptimization proposals. The proposals could lead to case-study examples of foundry

    efficiency improvements with before and after results.

  • 7/27/2019 Project for mba deepak desai.pdf

    47/48

    BIBLIOGRAPHY

  • 7/27/2019 Project for mba deepak desai.pdf

    48/48

    1 Barney L. Cape Hart, Wayne C. Turner and William J. Kennedy, Guide to energymanagement.

    2 Energy conservation measures in the Foundry sector, Published by: WinrockInternational India, 2010.

    3 Chapman, L. R. and Stark, R. 1990. How to Organize an Energy ManagementEffort. Iron and Steel Engineer.

    4 Cluster Profile Report Kolhapur Foundry Industry.5 Manufacturing Energy Consumption Survey, Office of Industrial Technology,

    Department of Energy, 1998.

    Website:

    1 Foundry informatics centre. (http://www.foundryinfo-india.org).2 The institute of Indian foundry men (http://www.indianfoundry.org.).3 www.soundcasting.com.4 http://www.energymanagertraining.com/Journal/latesttrend%20greenbusinessc

    entre.pdf.

    http://www.foundryinfo-india.org/http://www.indianfoundry.org/http://www.indianfoundry.org/http://www.foundryinfo-india.org/