Project experiences “Slag Rec”A new process for recycling slag from
electric-arc furnaces (EAF):experiences with project management
and delivering results
M. Svanera, R. RobertiR&D ASO Siderurgica (Italy)
Eco-Innovation European Info Day - Brussels, 13 April 2010
Eco-Innovation European Info Day - Brussels, 13 April 2010
General coordination experiences
The SLAG-REC project in a nutshell Launching and managing the projectDaily coordinationDelivering results and maximising the impactMarket uptake and replication strategy Experiences with the EACI
Eco-Innovation European Info Day - Brussels, 13 April 2010
The SLAG-REC project in a nutshell
Market need:Nowadays in the EU 60% of EAF slag is addressed to dumps (about 12 million t/year!), with strong environmental effects. All this slag quantity could be re-used in road constructions saving up the same quantity of natural resources (sand and gravel) which nowadays is extracted.
Eco-Innovation European Info Day - Brussels, 13 April 2010
The SLAG-REC project in a nutshell (cont…)
This proposal introduces to the market an innovative solution for 100% recycling of EAF slag.
Project objectives: - to introduce an innovative dry granulation system into the target market of European EAF operators through a first application in ASO
Eco-Innovation European Info Day - Brussels, 13 April 2010
The SLAG-REC project in a nutshell (cont…)
Project objectives: -to provide driving forces to encourage its diffusion and market uptake.
Combination of environmental benefits and business!Implementation: June 2009 – May 2011
Eco-Innovation European Info Day - Brussels, 13 April 2010
A small but strategic consortium:
3 partners:ASO Siderurgica (Italy) – steelmaker, inventor of the innovative technologyMFL – Maschinenfabrik Liezen (Austria) –machinery and plant producerCabra Engineering (Italy) – engineering company
Eco-Innovation European Info Day - Brussels, 13 April 2010
A small but strategic consortium: (cont…)
3 partners:Previous collaborations, well-known reliabilityAll required skills are coveredPartners have the necessary complementary competencesAll 3 partners are strongly motivated: a new business opportunity for all!
Eco-Innovation European Info Day - Brussels, 13 April 2010
SLAG-REC project activities
The first trials………… the patent………the designed Slag-Rec
Eco-Innovation European Info Day - Brussels, 13 April 2010
November 2009 executive drawings
June 2010 assembling and installation of the SLAG-REC machine
Eco-Innovation European Info Day - Brussels, 13 April 2010
Launching and managing the project
Very important: All partners must have a common understanding of the project goals and activities. Use the kick-off meeting not only to discuss the technical to-do’s but also to: - clear the last doubts of any kind- define the internal monitoring procedure
(schedule of short internal progress reports)
Eco-Innovation European Info Day - Brussels, 13 April 2010
Launching and managing the project (cont…)
Use the kick-off meeting also to: - define the internal communication rules and practices- ensure everyone has read and understood the project and their exact role- get everyone tuned on the common objectives
Eco-Innovation European Info Day - Brussels, 13 April 2010
Daily coordination
Good project coordination includes:- keep regular internal monitoring to ensure everybody is working on their tasks and to discover eventual problems asap;- send out regular reminders on upcoming deadlines well in advance;- discuss and confirm well in advance dates and venues for all meetings;
Eco-Innovation European Info Day - Brussels, 13 April 2010
Daily coordination (cont…)
- confirm the expected contribution from partners (e.g. during the meetings);- communicate regularly about project develop-ments (e.g. partners have to inform the consortium members about their dissemination activities);- monitor regularly the performance indicators and check if the project is on the right track.
Eco-Innovation European Info Day - Brussels, 13 April 2010
Delivering results and maximising the impact
Make sure the project results will really reach the target groups:- keep your marketing and disseminating strategy flexible and actualise them if necessary;- the project website is important but it is a passive tool, not enough;
Eco-Innovation European Info Day - Brussels, 13 April 2010
Delivering results (cont…)
- include active market approaching tools in your market uptake strategy (e.g. direct mails to target group representatives with tailor-made information, a business model to calculate payback in different circumstances, etc.);
Eco-Innovation European Info Day - Brussels, 13 April 2010
Delivering results (cont…)
- identify carefully the decision-making persons to ensure your information will be really evaluated;- the EACI gives your project additional visibility via its project databases, publications, etc.
Eco-Innovation European Info Day - Brussels, 13 April 2010
November 2009: GLOBAL SLAG CONFERENCE
(Brussels)
October 2010 EUROSLAG (Madrid)
October 2009: EMO 2009
(Milan)
Eco-Innovation European Info Day - Brussels, 13 April 2010
- Difficulties in slag managements by steelwork;- Increasing the price of slag disposal;- More restrective legislation.
We are developing a marketing plan combining different scenarios with these assumptions
Market possibilities:
Eco-Innovation European Info Day - Brussels, 13 April 2010
Experiences with the EACI
• Positive, both during the application and negotiation phases• Make good use of the pre-proposal service!• Clear definition of program priorities and supporting material on the program website are of good help
Eco-Innovation European Info Day - Brussels, 13 April 2010
Experiences with the EACI (cont…)
• Brochure of selected projects is also very useful to understand the expected kind of actions• The project evaluation report is very constructive and provides valuable suggestions for improvement
Eco-Innovation European Info Day - Brussels, 13 April 2010
Experiences with the EACI (cont…)
• The contract negotiation process helps to improve the quality of the project: the more coherent your project is, the less problems will occur during its implementation!
Eco-Innovation European Info Day - Brussels, 13 April 2010
THANK YOU ALL
FOR YOUR KIND ATTENTION
Contact: Eng. Massimo SVANERAASO [email protected]