Upload
dobao
View
216
Download
3
Embed Size (px)
Citation preview
1
Project Delivery
Baumgartner Axel Hofer Daniel
Pölzleitner Anton
2
Introduction • After Project planned and initiated, manager has to ensure
remaining on track • Plan reveals what needs to be done and by whom • Management Team must know how well the team is
performing (time, cost, quality, benefit expectations) • Reports needed for corrective action where necessary • Only on completion of control step the plan can be updated
with the step taken and the cycle repeated • Anyone who has to manage an aspect of the project has to
know this cycle and follow it to keep control
3
Control Cycle
Control
Report Monitor
Delegate
Plan
4
Plan
• Road map • Identifies the deliverables • Shows to whom the work will be delegated
5
Delegate
• Portfolio management team delegates to project steering group – Commercially or strategically beneficial
outcome • Project steering group delegates to project
manager – Products on time, on budget and specification
• Project manager delegates to teams working on the project
6
Delegate • When delegating both sides have to know what
is required and in which constraints • To ensure that, both parties have to agree on:
– Product description – Planned start/finish – Planned effort/cost – Dependencies – Prerequisite products
• Focus on outcome expected from delegatee
7
Delegate
• Further set of terms for controlling the delegated work: – Timesheet code – Skills/experience required – Roles – Reporting arrangements – Escalation conditions – Techniques, processes, procedures
8
Monitor and Report
• Monitoring: observation and supervision to know the condition of the project
• Tool: Reports – Show current completion expectations,
Reforecast of originally expectations – Satisfy each tier of management for timely
and accurate information for decision making or corrective action
9
Portfolio management team
• Meets every month • Also process for dealing with exceptional
matter in short term • Agenda at regular meetings:
– Prospects – Initiated projects – Notifications – Completions – Realizations
10
Project First Project Second Project Background ID 1 2 Last assessment date Jan 12th 06 Assessor Pete Robbins Maggie Jones Project start date Dec 10th 05 Sep 10th 05 PSG Sponsor Brad Somerville Mark Knowles Customer representative(s) Kevin Quinn Helen Smith Developer representative(s) Mark Johnson Bupinda Patel PM Project manager Will Stevens Harry King Time Baseline end date May 31st 06 Jun 10th 06 Forecast end date May 31st 06 Sep 30th 06 Variance (weeks) 0 -16 Escalation conditions (weeks) 2 2 Within escalation conditions? Yes No Cost Baseline budget $2,026,971 $101,923 Forecast budget $2,026,971 $115,000 Variance $0 -$13,077 Escalation conditions % 10 10 Within escalation conditions? Yes No Benefits Baseline benefits $2,703,836 $200,101 Forecast benefits $2,703,836 $200,101 Variance $0 $0 Escalation conditions % 10 10 Within escalation conditions? Yes Yes Business case Baseline profit $676,865 $98,178 Forecast profit $676,865 $85,101 Variance $0 -$13,077 Escalation conditions % 10 10 Within escalation conditions? Yes No
11
Corporate Dashboard • Detail of the project register can be summarized
to a corporate dashboard • Giving an overview of the portfolio • Indicating where escalation conditions have
been breached – further information in project register
12
Project steering group • Each group directs individual project • Ensure something exceptional happens the
project manager alerts PSG • PSG can intervene trough:
– Project initiation and closure – Holding meetings at the different stages of the
project – Holding unscheduled meetings – Holding scheduled meetings – Project forecast reports
13
Stage meetings
• At the beginning of every stage • To confirm the project remains viable (cost
– benefits) • Consider performance of the previous
stage • Review and approve plan for the next
stage
14
Stage meetings
• Agenda: – Review of previous stage – Review of project plan – Review of business case – Review of next stage plan – Approval of controls – Approval of proceed
15
Unscheduled meetings
• Necessary only if a breach of escalation condition is forecast
• Agenda: – What has happened to require notifying PSG – The effect on the plan – The options available to correct or
accommodate the matter – The recommended solution and its effect on
plan
16
Scheduled meetings
• Some managers are uncomfortable with management by exception
• Solution: regular PSG meetings • Frequency depends on duration of the
project • Agenda:
– Review and approval of the latest project forecast report from the project manager
17
Monitoring and reporting: Project manager
• Plans, monitors and controls: – Time – Cost – Quality
• Has to: – live up to stakeholders’ expectations – identify risks and problems – motivate team
18
Monitoring and reporting: Essential tools
• Progress meetings • Project forecast reports:
– Time forecast – Budget forecast – Quality forecast – Product quality log – Benefits forecast – Risk register
• Timesheet • Earned value analysis
19
Project team progress meetings
• Weekly meetings to assess progress data from team
• Required for reporting to the project steering group
20
Progress meetings: Agenda
• Delivery highlights: identify products started or completed, in previous or next period
• Scrutinise progress and identify variances and their reasons: – Timescales – Budgets – Quality
21
Progress meetings: Agenda
• Risks and issues: – Dependencies with other projects – Risk mitigation progress: monitor mitigations – Risk closure: low risks may be considered
closed – New risks
• Actions and decisions: review and assign
22
Project forecast report • Communication tools between project manager
and: – Stakeholders – Project steering group – Portfolio management
• Regular and frequent snapshots of the project status
• Summary PFR: overview for project steering group
• Detailed PFR: fine granularity, base for summary
23
Project forecast report: Terms • Baseline:
– Data agreed by a recognised authority at project initiation stage
– used to track variances • Actual to date (ATD): range of measures that
increase over time • Estimate to complete (ETC): what is expected • Forecast at completion (FAC): ATD + FAC • Variance: difference between baseline and
forecast
24
Project forecast report: time forecast
• Lists all products or milestones • Shows progress made in achieving
targets
25
Project forecast report: cost forecast
• Lists all resource types or milestones • Shows cost
26
Project forecast report: cost forecast
• Lists all resource types or milestones • Shows cost • Required for earned value analysis
27
Project forecast report: project quality forecast
• Lists the intended success criteria • Shows whether the project meets
expectations
28
Project forecast report: product quality log
• Lists key deliverables or milestones • Shows status
29
Project forecast report: benefits forecast
• Although benefits cannot be delivered before project completion, benefit forecasts can be helpful if the benefits: – change (under- / overestimation) – have already been delivered – have to be compared
• Lists benefits • Shows completion as percentage
30
Project forecast report: risk register
• Lists risks • Shows:
– Likelihood (0-10) – Impact (0-10) – Factor (likelihood * impact) – Mitigation
31
Timesheet
• Delegates report status (timescale, cost) of milestones / products: – Actual to date – Estimate to complete
• Base data for project forecasts
32
Earned value analysis
• Measures a project’s accomplishment against the time, cost and quality targets
• Tracks: – Planned value: budgeted cost of work
scheduled – Earned value: budgeted cost of work
completed – Actual cost: actual cost of work performed
33
Earned value analysis
• Measures a project’s accomplishment against the time, cost and quality targets
Cost variance (under budget)
Schedule variance (behind schedule)
34
Quality reviews
• Compare draft product and product description
• Different forms of quality reviews: – Testing – Inspection – Demonstration – Formal quality review – Informal quality review
35
Quality review process Describe the product's quality criteria
Product description
Build or rework the draft product
Draft product
Does product meet quality criteria? Quality review (prepare, review, follow-up)
Yes No
Baselined product
36
Quality review: preparation
• Roles in the review group: – Chair – Scribe – Author – Reviewers – Project manager
• What they need: error list, product description, draft product
37
Quality review: review
• Conducting a review: – participants should be prepared – product should be reviewed, not the author – compare product with product description – identify errors, not solutions – annotate trivial errors – avoid irrelevant debate
38
Quality review: review
• Conclusion of a review: – approved – revise and reschedule
product not ready product needs significant change insufficient reviewers unqualified reviewers unprepared reviewers
39
Quality review: follow up • Enough time and budget for necessary
changes? • Release revised version to reviewers
Informal Quality Review:
• Via mail or email → cheaper, (faster), quality
• Set deadline
40
Control
41
Control
• Change request or issue: Anyone
• Analysis: What are the reasons for the issue or CR?
• Impact assessment: – What are the time and money implications oft the issue or CR? – How will this issue or CR affect the robustness of the design – How will this issue or CR affect the operability of the solution
42
Control • Solution proposal: • Any solution will be a compromise • Fixed deadline - more resources - faster resources
• Fixed budget - cheaper resources - fewer resources
• Original quality - more resources - “better” resources
43
Control
• Decision:
• Who should decide
• Red amber and green escalation conditions • Amend plan:
• Change significant – additional changes to project plan and/or business case
• Change requests earlier or more often
44
Control
• Importance of effective control: • Many small changes – significant effect on
project • Effective control mitigates the risk of a
project failing.
45
Danke