Upload
others
View
6
Download
0
Embed Size (px)
Citation preview
1 PCR Template Version 28/08/2019
I BASIC DATA
A Report data
Report date Date of report: 16 September 2019
Mission date (if field m From: 24th June 2019 To: 28th June 2019
B Responsible Bank staff
Positions At approval At completion
Director General (*)
F. BLACK, ORSA Kapil Kapoor, RDGS Gabriel Negatu, RDGE(*) El Azizi Mohamed, RGDN Dore Ousmane,RDGC
Deputy Director General Nwabufo, Nnenna, RDGE
Country Manager N/A M.Monyau,COZM
M. Phiri, CORW
Sector Directors G. Mbesherubusa, OITC
A.Oumarou,PICU
Sector Manager A. Oumarou,ONRI1(appraisal at Appraisal)
J.K.Kabanguka, PICU.1
Task Manager A. Oumarou, Transport Engineer(at the
appraisal stage )
P. Munyaruyenzi, Infrastructure Specialist
Alternate Task Manager Romain Ekoto, Chief Aviation expert, PICU1
PCR Team Leader Philippe Munyaruyenzi, Infrastructure Specialist
PCR Team Members Romain Ekoto, Chief Aviation expert, PICU1
(*) it is “Multi-Regions”, and the management of the project was in HQ and CORW since the PIU was based in Rwanda, in the RDGE region.
C Project data
Project name: COMESA Airspace Integration Project
Project code: P-Z1-DA0-003 Instrument number(s):ADF- Regional Envelope : ADF Grant No2100155019666
Project type: Technical Assistance Sector: Transport( Air)
Country: Multinational Environmental categorization (1-3): N/A
Processing milestones – Bank approved
financing only (add/delete rows depending
on the number of financing sources)
Key Events (Bank approved financing
only)
Disbursement and closing dates (Bank
approved financing only)
Financing source/ instrument1: ADF
Grant
Financing source/ instrument ADF grant: Financing source/ instrument1: ADF Grant
Date approved: 15/9/2010 Cancelled amounts: UA 1,758,606 should
be cancelled,
Date signed: 04.11.2013 Supplementary financing: 0.00 Original closing date:30/06/2016
Date of entry into force: 5/8/2011 Restructuring (specify date & amount
PROJECT COMPLETION REPORT FOR COMESA AISPACE INTEGRATION PROJECT (P-Z1-DA0-003).
AFRICAN
DEVELOPMENT BANK GROUP
2 PCR Template Version 28/08/2019
involved): n/a
Date effective for 1st disbursement:
26/12/2012
Extensions (specify dates): 30/06/2016 -
30/06/2017; 30/06/2017 – 30/03/2018;
30/03/2018 -30/06/2019
Revised (if applicable) closing date:
30/06/2019
Date of actual 1st disbursement: xxx
Financing source/instrument (add/delete
rows depending on the number of financing
sources):
Disbursed amount
(amount, UA):
Percentage
disbursed (%):
Undisbursed
amount (UA million
):
Percentage
undisbursed (%):
Financing source/ instrument1: ADF Grant 5.75 69.4% 1.92 31.7%
Financing source/ instrument2:
Other (eg. co-financiers). COMESA 0.30 0% 0.30 100%
TOTAL 6.05 70.9% 2.22 29.1
Co-financiers and other external partners: None
Executing and implementing agency (ies): Comesa Secretriat
D Management review and comments
Report reviewed by Name Date reviewed Comments
Country Manager M. MONYAU
M.PHIRI (**)
Sector Manager J.K.KABANGUKA,PICU1
Regional Director (as chair of Country Team) Covering 4 Regions (***) : RDGE,RDGS,RDGC,RDGN
Sector Director A. OUMAROU
(**)While the project was a multi-region project, the implementation was carried out in Rwanda,’’CORW” where the PIU is located
and all communications to the Execvution Agency by ‘’COZM’’.
(***) due to the fact that this is a “special project” it will be cleared only by Sector Director in conjunction with RDGE.
II Project performance assessment
A Relevance
1. Relevance of project development objective
Rating* Narrative assessment (max 250 words)
3 The Sector Goal of the project is to provide safe, efficient air navigation services in a unified airspace to
support trade, tourism and regional socio-economic integration in COMESA.
The objectives of the Technical Assistance (TA) are: (i) To determine suitable legal and institutional
requirements to establish a cooperative Regional Framework for a unified airspace in the COMESA region; (ii)
To Prepare detailed analysis of strategic technical, financial, and operational options for the provision of upper
airspace navigation services using CNS/ATM and make recommendation for implementation modalities; (iii)
To build the partnerships needed for implementing the project and promote private sector participation in
financing and operating regional air transport infrastructure and services.
The project is of a regional nature and spans over three of the Bank regions. As such it doesn’t reference a
specific Country Strategy or Regional Strategy Papers of the Bank. However its objectives are in line with
3 PCR Template Version 28/08/2019
Bank’s Transport Policy, and Regional Integration Strategy. The project is also aligned with the Bank’s Hi Five
focus areas, in particular “Integrate Africa”, which were adopted during the implementation of the prioejct.
The Project’s objectives are aligned with COMESA’s Article 87(3g) of the Treaty which mandates all
COMESA Member States to “consider ways to develop, maintain and co-ordinate in common, their
navigational, communications and meteorological facilities for the provision of safe air navigation and the joint
management of their air space.
The project is also a priority under the NEPAD short-term action plan theme of having , safe, secure and
efficient skies and airports. The project is also in line with NEPAD’s policy on promoting regional integration”.
The overall rating towards the development objective is satisfactory
* For all ratings in the PCR use the following scale: 4 (Highly satisfactory), 3 (Satisfactory), 2 (Unsatisfactory), 1 (Highly unsatisfactory)
2. Relevance of project design
Rating* Narrative assessment (max 250 words)
2 The project design was based on extensive consultations with COMESA, National Civil Aviation Authorities of
several member countries, and airline companies as well as Development Partners active in the sector including
the World Bank, the European Union, JICA, and USAID. International Civil Aviation stakeholders,
particularly ICAO, ASECNA, and EUROCONTROL were also consulted. The project design took into account
the lessons learned from previous interventions of the Bank in multinational operations, and project involving
regional entities and reflected these lessons by providing a dedicated and appropriately staffed project
implementation unit and designing a strong regional project coordination steering committee with appropriate
budgetary provisions.
The implementation arrangements were also designed to leverage the political leadership role entrusted to
Rwanda by the COMESA’s Heads of State to spearhead the CNS/ATM initiative.
The current management of the lower and upper airspaces are handled by the same Air Navigation Sevice
Provider (ANSP) in most COMESA States. Additionnally, regarding the implementation arrangements, the
chair of the Project Steering Committee (SC) was entrusted to one country throughout project rather than
envisaging a rotating mechanism. As a result the implementation oversight mandate of the SC was not
achieved consistently throughout the project life cycle.
The project objectives could be achieved at least partially with the given level of inputs. However, given the
complexity of having 19 countries , a sterring Committee composed by seven ( 7) countries and the need for
consensus building, the project timeframe was not sufficient to establish the ultimate needed Air Traffic control
( Though Public Private Partnership) for full achievement of project objectives. On some of the initiatives (e.g.,
ground infratructures ), more financial resources are required in order to deliver on the initial planned outputs of
the project.
The rating of relevance of project design is satisfactory
3. Lessons learned related to relevance
Key issues (max 5, add rows as needed)
Lessons learned Target audience
Complexity in design
of Multinational
Projects of such
magnitude and 19
Multinational projects design should incorporate country
specificities and ensure full understanding, consensus and ownership
by Member States to ensure effective implementation. The project
AfDB, COMESA and
Member States
4 PCR Template Version 28/08/2019
countries involved. has succeeded in achieving this and creating ownership through its
Steering Committee implementation mechanism, which allowed
countries to present their specific concerns and views. The example
should be replicated in similarly complex proejcts.
Sovereignty and
security of Airspace
Sovereignty of airspace remains a major challenge in airspace
management as countries are very sensitive on national security
issues when it comes to entrusting the operations of their airspaces
to foreigners.at the implementation,involvement of Senior Military
Officials in the project has helped to alleviate this challenge at the
conception stage of the project.
AfDB, COMESA and
Member States
Private Sector
Involvement in
Airspace Management
In cases where national security issues may be involved, Member
States can be strongly opposed to the involvement of foreign private
sector in the management of their airspace for national security
reasons.
AfDB, COMESA and
Member States
Implementation
arrangements / PIU
location
The location in Kigali is what helped push the project considering
Rwanda’s strong commitment expressed in availing facilities,
support from Chairman of Civil Aviation, etc. This location was
agreed upong from day one, including by COMESA Countries
themselves. However, significant challenges in the project
coordination and monitoring by the COMESA Infrastructure
Directorate were noticed. The colocation of the PIU and the grantee
approach for such projects was not an issue rather the Comesa
Secretraiat (EA) performance due to limited time in focusing of
project management. The nature of their staff mandate require more
missions in member states countries.
COMESA
Stakeholder
Participation
Consistent participation by the same experts from Member States
helps to improve project understanding, reduces delays in the project
implementation and enhances cooperation among experts and
together have a better understanding of the critical issues on the
subject matter.
AfDB, COMESA and
Member States
B Effectiveness
1. Progress towards the project’s development objective (project purpose)
Comments
Provide a brief description of the Project (components) and the context in which it was designed and implemented. State the project
development objective (usually the project purpose as set out in the RLF) and assess progress. Unanticipated outcomes should also be
accounted for, as well as specific reference of gender equality in the project . The consistency of the assumptions that link the different
levels of the results chain in the RLF should also be considered. Indicative max length: 400 words.
The project sector goal was to provide safe and efficient air navigation services in a unified airspace to support
trade, tourism and regional socio-economic integration in COMESA. The project’s specific objectives were (i) to
establish a cooperative Legal and institutional Regional Framework for a unified airspace in the COMESA region,
(ii) to prepare detailed analysis of strategic options for the provision of upper airspace navigation services using
CNS/ATM and (iii) to promote private sector participation in financing and operating regional air transport
infrastructure and services.
In order to achieve these objectives, the following activities were planned :
5 PCR Template Version 28/08/2019
i. Prepration of Legal and Institutional Arrangements
ii. Technical and Financial Feasibility
iii. Transaction Advisory Services
iv. Establishment of Regulatory Framework & Agency
At the beginning of the Project implementation, some Member States cautioned against the idea of pursuing the
project objectives, i.e. to establish an unified upper airspace and to conclude PPP arrangements to finance, build and
operate the regional CNS/ATM infrastructure. Accordingly, out of the four studies listed above, three were
succesfuly conducted after a revision of the TORs by Member States as follows :
i) Establishment of a Cooperative Legal and Institutional Framework (Sept. 2016). In addition to a report, the
study also produced a set of Regulations establishing the COMESA Seamless Upper Airspace,
ii) Establishment of a Regulatory Framework and Agency (Oct. 2016). In addition to a report, the following
deliverables were produced: ;
(1) Draft Agreement for the setting up of the COMESA Regulatory aviation Agency,
(2) Civil-Military Interface Framework and Model MoU for the establishment of National
Civil/Military Committees,
(3) Model Air Navigation Safety and Economic Regulations and Guidelines, and
(4) Framework for the Business and Strategic Plan of the Agency.
iii) Technical and Financial Feasibility study (June 2017) In addition to a detailed gap analysis on the legal,
regulatory and equipement aspects, the study Report proposed a phased approach towards a Unified Upper Air
Space in the COMESA region sequenced as follows;
(a) Phase 1 : Establishing a Seamless Upper Airspace; time frame : from 2018 to 2027;
(b) Phase 2: Establishing sub-regional Clusters; from 2028 to 2037; and
(c) Phase 3 : Establishing the Unified Upper Airspace; from 2038 to 2047.
The fourth Study on Transaction Advisory Services was not undertaken because Member States were opposed to
private sector’s involvement in the management of their airspace.
In addition to the above, the project also contributed to capacity development by providing Training on CNS/ATM,
Civil-Military Cooperation, Cost Benefit Analysis and Safety Management Systems;
The overall rating towards the development objective is satisfactory
2. Outcome reporting
Outcome indicators (as per RLF; add more rows as needed)
Baseline value (Year) (2013)
Most recent value (2019)
End target (C)
(expected value at project
completion)
Progress towards target
(% realized) [(B-A)/(C-
A)]
Narrative assessment (indicative max length: 50 words per outcome)
Core Sector Indicator (Yes/No)
Outcome1:
COMESA
Unified Airspace
Agreement
N/A
Not signed Unified Airspace Agreement signed by
90 Member States were against the
establishment of a COMESA Unified
Airspace opting for a Seamless Upper
Airspace instead as the first step
Yes
6 PCR Template Version 28/08/2019
signed by several
member countries member countries by Oct. 2012.
torwards unification. The Technical and
Financial Feasibility Study
recommended a phased approach
starting with a seamless upper airspace
at ultimate phase3. Accordingly, a
Framework Regulation was developed
for adoption by the COMESA Council.
The Multilateral Agreement takes the
form of a Regulation which when
adopted by the Council of Ministers will
become automatically binding on the
COMESA Member States in accordance
with Article 10 of the COMESA Treaty
Outcome2:
COMESA
Airspace Control
Company and
Regulatory
Agency are
established.
N/A Not
established
( put on
hold due to
a Member
State
concerns
during the
Council of
Ministers) –
some
adjustments
required.
COMESA Airspace Regulatory Agency operational .
70 Draft Agreement establishing the
Agency and accompanying Regulations
were prepared and are due for review by
the DG CAA in October 2019 after
integration of comments from Egypt. It
will then go through the signing and
subsequent ratification process by
Member States. Its coming into force
will be subject to its ratification by 2/3
of Member States.
Yes
Outcome3:
Financial Close
and Concession
Agreement for
building and
operation of
regional
CNS/ATM and
Unified Upper
Space Control
Center
N/A No Financing mobilized
Financial Close and/or Concession Agreement signed by 09/14.
0 Due to the fact that the Unification of
the airspace and private sector
participation in the project were rejected
by Member States, no resource
mobilization efforts were initiated per
se. However the Technical and
Financial feasibility study estimated the
investment required for the
implementation of Phase 1 of the
Seamless Airspace (approx.. 310 M €)
over the ten year period.
Yes
Total Number of Outcomes :
3
Number of outcomes
achieved/likely to be
achieved
1
Number of outcomes likely to be achieved with
corrective measures
1
Number of expected
outcomes to be achieved2
Rating* (see IPR methodology)
Narrative assessment
2 The project outcomes performance can be rated as satisfactory. Just like with most multilateral
instruments, it would take time for the agreement and the regulatory agency to be established.
Nevertheless, the development of these instruments and the agreement and endorsement by the
Member States will generate the momentum towards realization of the these outcomes.
7 PCR Template Version 28/08/2019
3. Output reporting
Output indicators (as specified in the RLF; add more rows as needed)
Most recent value
(A)
End target (B) (expected value at project
completion)
Progress towards target
(% realized) (A/B)
Narrative assessment (indicative max length: 50 words per output)
Core Sector
Indicator
(Yes/No)
Draft Legal
Framework for a
Multilateral
Cooperative
Agreement for
Unified Airspace
Management in
COMESA
Region.
multilateral
agreement
delayed.
Draft
Multilateral
Agreement
and
institutional
framework
for Unified
Airspace
Management
adopted.
90 The Draft Legal and Institutional Agreement
developed for COMESA Seamless Upper
Airspace is going through COMESA
approval processes. Commencement of the
project was delayed as it only started in the
second half of 2014.
Yes
Draft Institutional
Framework for
implementing,
managing and
regulating the
Unified
COMESA
Airspace.
Drafts of
regulations
completed
n/d 100 The safety, economic and performance
regulations; Guidelines were prepared and
when implemented would create
harmonization amongst Member States:
i) Regulations establishing the
COMESA Seamless Upper Airspace,
(1) Draft Agreement for the setting up
of the COMESA Regulatory aviation
Agency,
(2) Civil-Military Interface Framework
and Model MoU for the establishment of
National Civil/Military Committees,
(3) Model Air Navigation Safety and
Economic Regulations and Guidelines, and
(4) Framework for the Business and
Strategic Plan of the Agency.
The Structure and funding mechanism of the
Multilateral Regulatory Agency to oversight
the provision of air navigation services in the
Upper Airspace of COMESA Member States
was developed.
yes
Technical
Reports,
Specifications and
Cost Estimates for
CNS/ATM. Cost
Benefit Analysis
for alternative
options.
Technical
report with
cost estimates
Technical
Reports,
Specifications
and Cost
Estimates for
CNS/ATM.
validated by
stakeholders.
100 All technical reports for CNS/ATM were
developed and validated by stakeholders.
The Study provided a cost estimate (total of
Euro 1,593 million) and investment plan for
the implementation of the project in a phased
manner over 30 years
yes
8 PCR Template Version 28/08/2019
Advisory Services
for Private Sector
Participation
(PPP/BOT)
PPP Advisory
Services
completed
RFQ, RFP for BOT
concession completed.
0 PPP Advisory Services were not done because
COMESA Member States were against the
involvement of the private sector in the project.
The study on Transaction Advisory Services was
not undertaken. Member States originally they
were with it, but later changed, and this happened
due to political changes in the region.
yes
Audit Reports Audit reports Audit Reports
submitted
yearly
100 Compliance with the obligation to conduct
annual audits. All audits report approved by
the Bank
No
Total Number of Outcomes :
5
Number of Outputs
Achieved/On-track
4
Number of Outputs Off-track
1
% On-track
Outputs 80
Rating* (see IPR methodology)
Narrative assessment
3 The performance is satisfactory. Four out 5 indicators achieved ( (80% rate of achievement).
4. Development Objective (DO) rating
DO rating (derived from updated IPR)*
Narrative assessment (indicative max length: 250 words
3 Although there was a shift in the approach, i.e. rather than establishing a unified upper
airspace directly with the involvement of the private sector to cover the capital intensive
requirement, the project maintained the same ultimate objective but identified intermediary
phases/activities consisting of the establishment of a seamless upper airspace first.The
unification was envisaged as the third phase within 30 years. Accordingly, the Project’s
outcomes and outputs as reviewed above are considered satisfactory.
5. Beneficiaries (add rows as needed)
Actual (A) Planned (B) Progress towards target (% realized) (A/B)
% of women
Category (eg. farmers, students)
Airlines, Airport
Agencies,
Ministries in charge
of Air Transport.
Air Travelers, Air
Freight Shippers,
Business
community,
Airlines, Airport
Agencies,
Ministries in charge
of Air Transport
50% n/a Airlines, Airport Agencies, Ministries
in charge of Air Transport
6. Gender equality
Assessment on the performance of gender equality in the operation (indicative max length: 250 words)
Women will naturally benefit from the project considering their involvement in area of air transport industry. A
9 PCR Template Version 28/08/2019
total of 139 people including women from 17 countries were trained under the project. The training was in the
following fields : CNS/ATM (51) , COSECNA and ASECNA Case Studies (15); Tour of EUROCONTROL
and Maastricht Upper Airspace Control Centre (15); Cost Benefit Analysis (CBA) (15) Flexible Use of
Airspace (FUA) (14); Safety Management Systems (SMS) (29). Women constitute 8 % of the total number of
people trained under the project.
7. Unanticipated or additional outcomes (add rows as needed)
Description Type (eg. gender, climate change, social, other)
Positive or negative
Impact on project (High, Medium,
Low)
n/a n/a n/a n/a
n/a n/a n/a n/a
8. Lessons learned related to effectiveness (add rows as needed)
Key issues (max 5, add rows as needed) Lessons learned Target audience
Output delivery
Some outputs were not according to project design due
to Member States interests. For instance the project
ended up delivering on the COMESA Seamless Upper
Airspace as opposed to COMESA Unified Airspace
envisaged in the design. Member States also opposed
involvement of the private sector in the project which
rendered the study on Transaction Advisory Services
irrelevant.
AfDB/COMESA
Readiness for execution
• Political changes can have an impact on such
regional high level project.
• For multinational projects that encompass a
large number of countries, the risk of changes to
the project design is high. Accordingly project
components and outcomes that should be kept at
a manageable risk level, e.g. producing reports,
NOT producing report and establishing Agency,
for example.
• Ensuring quality at entry and during
implementation through proper planning and
focused execution will eliminate unnecessary
delays to the project.
COMESA
Staffing. Competences of PIU staff have a
bearing on the implementation success of
the project
Shortage in the specialized types of skills affected the
quality of PIU staff who were hired (leading the Bank,
based on COMESA’s own assessment, not to concur
with the renewal of the contract of the Project
Coordinator),
Ensuring timely recruitment of skilled and
knowledgeable staff helps in executing the project
COMESA,
Member States
10 PCR Template Version 28/08/2019
efficiently.
Consultation and Participatory Approach.
Involvement of all concerned Member
States at every stage of the project
contributed positively towards
advancement of project objectives.
Extensive consultation and involvement of all concerned
Member States in the execution of the project assisted in
securing stakeholder buy-in and avoiding pitfalls of
related past studies. However, Member States interests
may in some cases militate against effectiveness as they
may override decisions of implementers.
AfDB, COMESA
The nature of the project involved discussions and
consultation on new technologies and concepts such as
PPPs that were new to a large number of Government
officials participating in the project. This led to
comments and feedback that were not comprehensive
enough, and also led to major decision taken by the
Steering Committee countries on aspects the team were
not fully familiar with. The project offered the option for
the COMESA to obtain experts from the target countries
as the need arose. This plan presented a good approach
but was not utilized (for different reasons).
Location of PIU office
Effective coordination and monitoring will be achieved
if the PIU Office is located within the implementing
agency’s offices.
AfDB, COMESA
C Efficiency
1. Timeliness
Planned project duration – years (A) (as per PAR)
Actual implementation time – years (B) (from effectiveness for 1st
disb.)
Ratio of planned and actual implementation time (A/B)
Rating*
5 years 7.17 years 0.70 2
Narrative assessment (indicative max length: 250 words)
Commencement of the project delayed. From the signing of the Grant Agreement in February 2011, effectiveness of first
dirsbursment by August 2011, recruitment of the full staff compliment of the PIU was completed in August 2014 although
the Project Manager was recruited in May 2013. The procurement process for consultants to carry out the studies was
finalized in 2015.
2. Resource use efficiency
Median % physical implementation of RLF outputs financed by all
financiers (A) (see II.B.3)
Commitment rate (%) (B) (See table 1.C – Total commitment
rate of all financiers)
Ratio of the median percentage physical implementation and
commitment rate (A/B)
Rating*
100% 95% 105% 4
Narrative assessment (indicative max length: 250 words)
The Bank’s resources were used efficiently as they were spent on activities as indicated by the appraisal. At the closing
date, ADF disbursement stood at 69.42% against the project budget of UA5.75million.
11 PCR Template Version 28/08/2019
N° Categoryof
expenditure
Ammount allocated Actual Cost (dirsbursed) Variation
UA million UA million UA million
1 Goods 0.16 0.03 -0.13
3 Services 3.6 3.22 -0.38
4 Operating cost 1.61 0.57 -1.04
7 Unallocated 0.38 0 -0.38
7 Total 5.75 3.82 -1.93
3. Cost benefit analysis
Economic Rate of Return (at appraisal) (A)
Updated Economic Rate of Return (at completion) (B)
Ratio of the Economic Rate of Return at completion and at
appraisal (B/A)
Rating*
N/A N/A N/A
Narrative assessment (indicative max length: 250 words)
N/A
4. Implementation Progress (IP)
IP Rating (derived
from updated IPR)
*
Narrative comments (commenting specifically on those IP items that were rated Unsatisfactory or Highly Unsatisfactory, as per last IPR). (indicative max length: 500 words)
3 For most activities, schedules were not adhered to. Setting up PIU, and equipping the offices was not
adhered to. Some appointments of the PIU staff was not done on time, and affected overall project
progress. although the project had to be extended due to late start after technical launching.
Compliance with commitments: The project complied with project covenants, environmental and social
safeguards and audit. Adherence and compliance with Grant agreements and clauses are satisfactory. The
project complied with applicable Bank policies. This project was classified as Category 3 under the Bank's
Environmental and Social Assessment procedures. According to the Bank's policy, an Environment and
Social Management Plan (ESMP) was not required during the implementation of the project. As the project
was on studies with no adverse impacts recorded.
Project systems and procedures: (procurement, financial management and monitoring and evaluation)
strictly followed Bank rules set at the appraisal. As the bulk of the acquisition was related to consultancies
and goods and all the procurements were subjected to the bank's pre-approval for awarding the contract, no
significant problem was recorded during the implementation.
The Executing Agency achieved acceptable performance in the overall coordination of the project. At the
closing date, disbursement stood at 69.42% against the project budget of UA5.75 million,. A fruitful
partnership was also developed with and among Civil Aviation Authorities which is vital in improving
safety in the aviation sector.
12 PCR Template Version 28/08/2019
Two project objectives on the preparation of detailed analysis of strategic options for the provision of
upper airspace navigation services using CNS/ATM and promotion of private sector participation in
financing and operating regional air transport infrastructure and services were not achieved because
COMESA Member States were opposed to the unification of their airspace and involvement of the private
sector in its financing and management. The study on Transaction Advisory Services was therefore not
undertaken.
Achievement of project implementation based on “outputs delivered” against “resources used” based on
cumulative commitments at completion is fair at approximately 69%..
5. Lessons learned related to efficiency
Key issues (max 5, add rows as needed) Lessons learned Target audience
1. Delays in Project start which resulted in
the project being extended.
1.1 In developing project plans, adequate time is
required for mobilising for such complex projects (
multinational with 19 countries by then was accounted
for in the project plan-- even much more, now Somalia
and Tunisia joined the REC when project is completed).
The Steering Committee should be be involved at the
beginning of the project.
1.2 Procurement processes delayed project completion.
There is need to strictly adhere to project milestones and
timings as per project design.
The Bank
The Bank and Beneficiary.
2.Joint Hosting of Workshops and
Meeting
2.Careful planning and coordination resulted in joint
hosting of workshops and meetings for the three
completed studies which had a positive impact on costs.
Cost savings resulted from these arrangements as the
consulting firms were sharing ticket costs, per diem and
conference package as opposed to standalone workshops
and meetings for each study. Savings made from each of
the three contracts were used to support training in Safety
Management Systems, Flexible Use of Airspace (Civil-
Military Cooperation) and Cost Benefit Analysis for
ANSPs.
COMESA, AfDB
13 PCR Template Version 28/08/2019
3.Project Management
3.1 Weak follow-up by the PIU staff; inability to properly
hold responsibilities by the PIU in delivering their
mandate, led COMESA’s management occasionally to
take responsibilities for the activities that were meant to
be handled by the PIU unit. COMESA Secretariat had
strong positions in trying to rectify performance of PIU
staff, but its efforts was not consistent.
3.2 The project manager or PIU being in Kigali while
Executing Agency in Lusaka resulted into challenges in
implementation and coordination above mentionned. The
first coordination was not performing and after
assessment, the Bank team recommended of contract
termination. The acting coordinator was also poorly
evaluated in terms of performance.
The implementing
agency.
4. Comesa Secretariat count part
contribution
COMESA’s contributions designed to be originally and
have actually not disbursed 0%. Budgeting the contpart
funding for should be part a conditions for first
dirsbursment.
The Bank , and
Comesa
Secretariat
D Sustainability
1. Financial sustainability
Rating*
Narrative assessment (indicative max length: 250 words)
2 More resources will be required beyond the current project phase to finalise the draft Agreement establishing the
Regulatory Agency and its operationalization. Since COMESA members have rejected private sector
participation, resources will be coming from Government. However, government usually struggle to avail
resources given competing needs at their national level. Even though, a partnership with the Bank could continue
with new initiatives in line with the same objective, a COMESA will continue to secure necessary funds to
implement the project once agreement and regulations are signed and ratified.
There is a new program under development : Support to Air Transport Sector Development (SATSD) in the
Eastern Africa, Southern Africa and Indian Ocean region (EA-SA-IO), CRIS number: FED/2019/039-999
financed under European Development Fund and the programme will support activities aiming among others at:
Facilitating the provision of seamless operations in EA-SA-IO region to improve air navigation efficiency in a
liberalized and integrated air transport market. This new project was designed with one of its three objectives
being to ensure continuation of the current AfDB funded project. There is there synergy between the two
programs’ activities and objectives.
2. Institutional sustainability and strengthening of capacities
Rating*
Narrative assessment (indicative max length: 250 words)
14 PCR Template Version 28/08/2019
3 This will follow the signing of the Multilateral Agreement establishing the Agency and its setting up. Capacity
building workshops on CNS/ATM, Safatey Management System (SMS), Flexible Use of Airspace (FUA) and
Cost Benefit Analysis (CBA) for Air Navigation Service Providers (ANSPs) were conducted in the course of the
studies. All countries members regulary participated in the workshops/training conducted by the consultants.
3. Ownership and sustainability of partnerships
Rating*
Narrative assessment (indicative max length: 250 words)
3 The overall project underwent extensive consultation with all key stakeholders inclusive of government
ministries, the members of the civil aviation community in COMESA including Civil Aviation Authorities, Air
Traffic Service Providers, airport operators, and airline companies. The Project was guided by the Member States
through the Steering Committee comprising of Seven (7) countries and the validation workshops involving all
Member States.
4. Environmental and social sustainability
Rating*
Narrative assessment (indicative max length: 250 words)
4 This was not applicable to the component.
5. Lessons learned related to sustainability
Key issues (max 5, add rows as needed) Lessons learned Target audience
Funding : Dependency on donor funding for the
implementation of similar initiatives and heavily
relying on consultants to undertake the technical
work.
5.1. Member States are opposed to the
collection and use of their en route charges to
support the Agency. Additionally, member
States are more concerned of their sovereignity
at the expense of private sector involvement.
Member States/ COMESA /AfDB
5.2. it is important for programmes to also
incorporate aspects of building inhouse
technical capacity to ensure continued accrual
of benenfits. There is need to incorporate a
clear knowledge and skills transfer to the RECs
and Member countries.
5.3. there is need for Member countries to
consider establishing sustainable financing
mechanisms and resource mobilisation for
respective or shared regional initiatives. The
Bank may also provide assistance to Member
countries in this regards.
Capacity Building
There exists skills gap among member States
relating to current and future technology which
will necessitate training various aspects of
Aviation.
Member States/COMESA/A
fDB
Member States cooperation Cooperation among Member States and mutual
trust is critical for the sustainability and
effective implementation of the project
Member States/COMESA
15 PCR Template Version 28/08/2019
III Performance of stakeholders
1. Bank performance
Rating*
Narrative assessment by the Borrower on the Bank’s performance, as well as any other aspects of the project (both quantitative and qualitative). See guidance note on issues to cover. (indicative max length: 250 words)
3
The Bank had a close supervision of the project through regular supervision missions, meetings and guidance
helped a lot to reach the project purpose. The Bank disbursed funds as per project design. the Bank participated in
some Technical Committee meetings, and conducted scheduled supervisory missions. The project found these to
be helpful. When unanticipated events occurred, the Bank was helpful in resolving these issues, including
authorization of pre-financing to ensure a continuous flow of activities, Single external audit firm for all Bank’s
funded project and use of Comesa systems for the auditing report for the purpose of value for money.
Comments to be inserted by the Bank on its own performance (both quantitative and qualitative). See guidance note on issues to cover. (indicative max length: 250 words)
The Bank provided guidance to the project especially in ensuring that the project is implemented in line with
Bank rules as per the Grant agreement. The Bank carried out annual supervision missions. These helped in
ensuring that the project remains relevant to the Both the Bank’s and the Comesa strategies. An example is
whereby the Bank agreed to a request for extension of the project implementation three (3) times.
Key issues (related to Bank performance, max 5, add rows as needed)
Lessons learned
To develop a stronger and more structured
system for managing regional projects. The Bank should develop a stronger and more-structure system for managing
regional projects that are low in value of lending/ grant, but high in impact
and require extensive resources. Efficient use of decentralized staff and
Countrries offices will go a long way in addressing this.
2. Borrower performance
Rating*
Narrative assessment on the Borrower performance to be inserted by the Bank (both quantitative and qualitative, depending on available information). See guidance note. (indicative max length: 250 words)
2 The COMESA Secretariat has provided very effective oversight and also contributed resources to ensure
continuation of activities. Towards the end of the project , COMESA Secretariat has shown leadership qualities in
implementation of the project. However ,at the beginning there was coordination issues due to weaknesses in
COMESA Secretariat and the PIU. Although COMESA managed contracts of the PIU staff well and ensured the
delivery of good quality support to the Secretriat , the use of the Legal Expert in the PIU ended up being on a full
time basis acting in Project Manager capacity to ensure that the project deliverables are achieved. However the
performance of the Legal Expert was not properly assessed and resulted in relying on her own willingness to
provide reports when needed ( such as final report of the project, progress report) as the project was at the end.
Comments to be inserted by the Borrower on its own performance (both quantitative and qualitative). See guidance note on issues to cover. (indicative max length: 250 words)
Locating the PIU away from COMESA Secretariat partly contributed to coordination challenges. Short term
extensions of the project Grant Disbursement period made it difficult to recruit a replacement for the Project
Manager resulting in the Legal Expert (whose expertise was mainly of a legal nature) acting for an extended time
from September 2017 to 30 June 2019. There were also issues beyond the control of COMESA Secretariat
especially Member States decisions such as change in Government views/ stances on the PPP issue during
implementation.
Key issues (related to Borrower performance, max 5, add rows as needed)
Lessons learned
16 PCR Template Version 28/08/2019
1. Variation between planned project approach and the
actual approach at implementation.
1. It is important that these kinds of variations are spelt out
clearly at supervision so that all the necessary adjustments
could be made especially to the project scope.
Use of performance contracts and assessing performance more frequently.
The use of a consulting firm to supervise the project may have led to better results than the use of the individual consultants to staff the PIU. It would have provided more accountability, and would have availed better qualified PIU staff.
3. Performance of other stakeholders
Rating*
Narrative assessment on the performance of other stakeholders, including co-financiers, contractors and service providers. See guidance note on issues to cover. (indicative max length: 250 words)
2 There is not good performance considering lack of approval by the Council of Ministers ( superior policy organ in the REC) of the Draft Multilateral Agreement and institutional framework for Unified Airspace Management
adopted which was all the way approved by other stakeholders including Attoney generals from the Memebr Countries. This deliverable was not met and was very criticaly to determine the fate of other outcome such as The fourth study on Transaction Advisory study (PPP) and the Regulatory Agency was not setup within the
project timelines as invisaged
Key issues (related to performance of other stakeholders, max 5, add rows as needed)
Lessons learned (max 5) Target audience (for lessons learned)
For such complex and
innovative projects, include a
program focused short-term
capacity building activities to
bring the participating decision-
makers up to a minimum level
of appreciating and understand
the topics addressed.
For projects with such technical studies, there should be detailed
discussions with the concerned countries (not only with
COMESA) to understand the capacities of these countries in
dealing (understanding and analyzing) with the subjects
covered. In cases of deficiencies the Program should included
focused short-term capacity building activities to bring the
participating decision-makers up to a minimum level of
appreciating and understand the topics addressed. Also the use
of secondees of the Member countries should be detailed at the
appraisal stage and not be left for the decision of the PIU/
COMESA Secretariat during implementation.
Bank and
Beneficiaries
IV Summary of key lessons learned and recommendations
1. Key lessons learned
Key issues (max 5, add rows as needed) Key lessons learned Target audience
1. Project staffing in the PIU: while projects staff in
the PIU were recruited through competiveness, their
delivrery and capacity in project management was
poor and resulted into some changes.
Increase due diligence in hiring a strong Project
Manager of such complex and magnitude
project involving many countries.
Bank and
Beneficiaries
Some components of the project could not be
delivered because the sensitivity and the project
realised later that some activities that involved
This required the use Economic Sector Works
(ESWs) in informing the design of similar
projects. It will help for a sensitisition of a
Bank and
Beneficiaries
17 PCR Template Version 28/08/2019
private sector would require strong reaction from
some Member countries as touching on their
sovereignty .
group of Like-minded States may fast track the
process and establish a sub-regional area control
center for the upper airspace in line with the
concept of variable geometry as provided for in
the COMESA Treaty.
Decision making and obtaining consensus in RECs Decision making takes time due to national
interests preceding regional interests and
inclusion of the political dimension. These will
need to be addressed upfront otherwise they will
always delay projects.
2. Key recommendations (with particular emphasis on ensuring sustainability of project benefits)
Key issue (max 10, add rows as needed) Key recommendation Responsible Deadline
Provide provide shrt term training to ensure
that that skills gap in member States
relating to current and future technology are
reduced capacity building among Member
Staes in the REC
In conjunction with other specialized
organization , ensure that that skills gap in
member States relating to current and future
technology which will necessitate training
various aspects of Aviation. And enough
budget to be provided for such component.
Ban Bank and
Beneficiaries k,
RECs
Similar
futufutu
re
projects
projects
The project is an innovative and unique in
nature. This project presents a good example of a
regional project that only institutions like
AfDB and COMESA can cooperate to
deliver. The two institutions played a
remarkable role utilizing their comparative
advantage of being regional entities to bring
this project to realization. While the
outcomes were not fully achieved, the
experience should be replicated, taking into
considerations the lessons learnt, to yield
stronger results and higher impact for
regional integration.
Ban Bank and
Beneficiaries k,
RECs
Similar
futufutu
re
projects
projects
V Overall PCR rating
Dimensions and criteria Rating*
DIMENSION A: RELEVANCE 3
Relevance of project development objective (II.A.1) 3
Relevance of project design (II.A.2) 3
DIMENSION B: EFFECTIVENESS 3
Development Objective (DO) (II.B.4) 3
DIMENSION C: EFFICIENCY 2.67
Timeliness (II.C.1) 2
Resource use efficiency (II.C.2) 3
Cost-benefit analysis (II.C.3) N/A
Implementation Progress (IP) (II.C.4) 3
DIMENSION D: SUSTAINABILITY 3
18 PCR Template Version 28/08/2019
Financial sustainability (II.D.1) 2
Institutional sustainability and strengthening of capacities (II.D.2) 3
Ownership and sustainability of partnerships (II.D.3) 3
Environmental and social sustainability (II.D.4) 4
DIMENSION E: PERFORMANCE OF STAKEHOLDERS 2.3
Bank performance
3
Borrower performance
2
Performance of other stakeholders
2
AVERAGE OF THE DIMENSION RATINGS 2.8
OVERALL PROJECT COMPLETION RATING 3
VI Acronyms and abbreviations
ACC Area Control Centre AFI Africa - Indian ocean area ADF African Development Fund APIRG Planning and Implementation Regional Group ASECNA Agency for the Security of Aerial Navigation in Africa
and Madagascar ATC Air Traffic Control ATM Air Traffic Management ATS Air Traffic Services CNS/ATM Communications, Navigation, and Surveillance / Air
Traffic Management COMESA Common Market for Eastern and Southern Africa DME Distance Measuring Equipment ESIA Environmental and Social Impact Assessment FIR Flight Information Region GNSS Global Navigation Satellite System GPS Global Positioning System (United States) ICAO International Civil Aviation Organization IFR Instrument Flight Rules ILS Instrument Landing System NDB Non-directional beacon NEPAD New Partnership for Africa’s Development PIU Project Implementation Unit PPP Public Private Partnership RFP Request for Proposals TA Technical Assistance UACC Upper Airspace Control Center VHF Very High Frequency VOR VHF Omnidirectional Radio Range WGS-84 World Geodetic Reference System 1984
Required attachment: Updated Implementation Progress and Results Report (IPR)– the date should be the same as the PCR mission.
19 PCR Template Version 28/08/2019
The phases of the project towards the Upper Airspace Traffic Control Company (UACC)
20 PCR Template Version 28/08/2019