35
AFRICAN DEVELOPMENT BANK GROUP PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION DELIVERY PROJECT COUNTRY: UNITED REPUBLIC OF TANZANIA APPRAISAL REPORT September 2015 OWAS Public Disclosure authorized Public Disclosure authorized

PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

AFRICAN DEVELOPMENT BANK GROUP

PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND

SANITATION DELIVERY PROJECT

COUNTRY: UNITED REPUBLIC OF TANZANIA

APPRAISAL REPORT

September 2015

OWAS

Pu

bli

c D

iscl

osu

re a

uth

ori

zed

Pu

bli

c D

iscl

osu

re a

uth

ori

zed

Page 2: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

TABLE OF CONTENTS

Loan Information ........................................................................................................................... ii

Project Summary ........................................................................................................................... iii

Results Based Logical Framework ................................................................................................ iv

Project Time Frame ....................................................................................................................... vi

I – STRATEGIC THRUST & RATIONALE ....................................................................... 1

1.1 Project linkages with country strategy and objectives ............................................... 1

1.2 Project linkages with Bank’s Strategy and operational priorities .............................. 1

1.3 Rationale for Bank’s involvement in the Project ....................................................... 2

1.4 Donor coordination in Tanzania ................................................................................ 2

II – PROJECT DESCRIPTION ............................................................................................. 3

2.1 Sector goal, development objectives, Project description and components .............. 3

2.2 Technical solutions retained and other alternatives explored .................................... 5

2.3 Project type ................................................................................................................ 5

2.4 Project cost and financing arrangements ................................................................... 5

2.5 Project’s target area and population ........................................................................... 7

2.6 Participatory process for Project identification, design and implementation ............ 8

2.7 Bank Group experience and lessons reflected in Project design ............................... 9

2.8 Key performance indicators and monitoring of targets ............................................. 9

III – PROJECT FEASIBILITY ........................................................................................... 10

3.1 Financial and Economic analysis ............................................................................. 10

3.2 Environmental impacts and social safeguards ......................................................... 11

3.3 Climate Change ........................................................................................................ 12

3.4 Gender and social ..................................................................................................... 12

IV – IMPLEMENTATION ................................................................................................... 14

4.1 Implementation arrangements .................................................................................. 14

4.2 Procurement arrangements....................................................................................... 14

4.3 Financial management and disbursement arrangements .......................................... 15

4.4 Monitoring of Project implementation activities and progress ................................ 16

4.5 Governance .............................................................................................................. 16

4.6 Sustainability............................................................................................................ 17

4.7 Risk management ..................................................................................................... 18

4.8 Knowledge building ................................................................................................. 19

V – LEGAL INSTRUMENTS AND AUTHORITY ........................................................... 19

5.1 Legal instruments ..................................................................................................... 19

5.2 Conditions associated with Bank’s intervention ...................................................... 19

5.3 Compliance with Bank Policies and Strategies ....................................................... 20

VI – CONCLUSION AND RECOMMENDATION ........................................................... 20

Appendix I: Tanzania - Comparative Socio-Economic Indicators – May 2015 ........................... I

Appendix II. Table of AfDB’s Country Portfolio ....................................................................... II

Appendix III. Key Related Projects in the Country ................................................................... IV

Appendix IV. Map of the Project Area ....................................................................................... V

Appendix V. Justification for ADB financing of more than 50% of the Project cost. ............... VI

Page 3: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

i

Currency Equivalents

May 2015

1 UA = TZS 2,555.19

1 UA = USD 1.40642

1 UA = EURO 1.25405

Fiscal Year 1 July – 30 June

Weights and Measures 1 metric tonne = 2204 pounds (lbs)

1 kilogramme (kg) = 2.200 lbs

1 metre (m) = 3.28 feet (ft.)

1 millimetre (mm) = 0.03937 inch (“)

1 kilometre (km) = 0.62 mile

1 hectare (ha) = 2.471 acres

List of Acronyms

ADB African Development Bank KfW Kreditanstaltfuer Wiederaufbau

ADF African Development Fund M&E Monitoring & Evaluation

AGTF Africa Growing Together Fund MDGs Millennium Development

ACC Arusha City Council Goals

AUWSA Arusha Urban Water Supply and MoEVT Ministry of Education and Vocational

Sanitation Authority Training

CAG Controller and Auditor General MoF Ministry of Finance

CFRA Country Fiduciary Risk MoW Ministry of Water

Assessment MTS Medium Term Strategy

CIFA Country Integrated Fiduciary NAO National Audit Office

Assessment NGO Non-Governmental Organization

CSP Country Strategy Paper NSGRP National Strategy for Growth

DAWASA Dar es Salaam Water and and Reduction of Poverty

Sewerage Authority NRW Non- Revenue Water

DoE Department of Environment OCGS Office of Chief Government Statistician

DP Development Partner PER Public Expenditure Review

EA Executing Agency PEFA Public Expenditure and Financial

ESAP Environmental and Social Accountability

Assessment Procedure PIU Project Implementation Unit

ESIA Environmental and Social PFM Public Financial Management

Impact Assessment RWSSP Rural Water and Sanitation Program

ESMP Environmental and Social O&M Operation and Maintenance

Management Plan Department

GEF Global Environmental Facility PRSP Poverty Reduction Strategy Paper

GoT Government of the United QPR Quarterly Progress Report

Republic of Tanzania RWSSI Rural Water Supply and Sanitation Initiative

HBS Household Budget Survey RMC Regional Member Countries

IA Implementing Agency TZFO Tanzania Field Office

IFIMS Integrated Financial Mgmt. System UA Unit of Account

IWRM Integrated Water Resources WSDP Water Sector Development Program

Management WSS Water Supply and Sanitation

Page 4: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

ii

Loan Information

Client’s Information

BORROWER: United Republic of Tanzania

EXECUTING AGENCY: Arusha Urban Water Supply and Sanitation Authority (AUWSA)

Financing Plan

Source USD’ 000 UA’ 000 Instrument

ADB 143,647 102,137 Loan

ADF 25,316 18,000 Loan

AGTF 42,000 29,863 Loan

GOV. OF TANZANIA 22,953 16,320 Counterpart

TOTAL COST 233,916 166,320

ADB’s / AGTF Key Financing Information

Interest Type Enhanced Variable Spread Loan

Interest Rate Spread Floating Base Rate+ Funding Cost Margin + Lending

Spread

Funding Cost Margin 1 Refer footnote 1

Lending Margin 60 basis points (0.60 %)

Commitment fee None

Repayment Semi-Annual

Tenor Up to 20 years inclusive of grace period

Grace Period Up to 5 years

ADF key financing information

Interest rate spread None

Commitment fee 0.5% per annum

Service charge 0.75% per annum

Duration 40 years

Grace period 10 years

Key financial and economic analysis information

FIRR 6.11% and NPV TZS 117.7 billion (at 4% base case)

EIRR 17.6% and NPV TZS 287.1 billion (at 10% base case)

Timeframe - Main Milestones (expected)

Project approval September 2015

Signing of Loan Agreement November 2015

Project completion / closing December 2019

Project Last Disbursement June 2020

Last repayment ADB Dec 2037; ADF Dec 2057

1 The six months adjusted average of the difference between: (i) the refinancing rate of the Bank as to the borrowings linked to 6- month LIBOR

and allocated to all its floating interest loans denominated in USD and (ii) 6-month LIBOR ending on 30 June and on 31 December. This spread

shall apply to the 6-month LIBOR which resets on 1 February and on 1 August. The Funding Cost Margin shall be determined twice per year on 1

January for the semester ending on 31 December and on 1 July for the semester ending on 30 June.

Page 5: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

iii

Project Summary

Project Overview: The objective of the Project is to provide safe, reliable and sustainable water and

sanitation services in Arusha city, Tanzania and thereby contribute to improvement in health, social

well-being and living standards of the beneficiaries. The Project will improve existing infrastructure and

enhance the operational, commercial and service delivery efficiency of the Arusha Urban Water Supply

and Sanitation Authority (AUWSA). The total cost of the Project is USD 233.92 (equivalent to UA 166.32

million) and will be implemented over a period of four years from 2016 to 2019. AUWSA currently meets

all its costs from internally generated revenue and has been rated as the best performer, in cost recovery,

among all the 23 regional water utilities in Tanzania. As shown in the Project need below, the water access

coverage in Arusha city is low, while its only existing sewage treatment plant is critically overloaded posing

a major environmental and health hazard. Thus, the operation is of high priority to the Government. The

Project is technically feasible, environmentally sustainable and economically and socially viable and

justifiable.

Project Beneficiaries and Impact: At completion, the Project will benefit a resident population of

more than 600,000 people in Arusha city and 250,000 additional people, who commute to the city,

at daytime, for business purposes. Over the Project horizon, about one million people will benefit.

Improved access to water and sanitation services will complement other social services and boost socio-

economic activities in the city, while providing a conducive business environment. The Project will also

provide climate adaptation benefits in relation to water sources management and it will lead to reduction

of water borne diseases and associated health-care costs. It is estimated that water borne diseases in the

Project area account for about 40% of per capita health expenditure. Furthermore, there will be

employment opportunities during construction. The Project will provide capacity building to AUWSA

and will support the Utility in adopting the National Gender Policy and in addressing the needs of

vulnerable groups.

Project Rationale: The Project is consistent with the Country’s Development Framework as laid

out in the National Vision 2025, which aims to improve the living standards through sustainable

development, including investment in basic infrastructure, such as water and sanitation facilities. It is

also aligned with the National Strategy for Growth and Reduction of Poverty NSGRP (2011-2015), the

Tanzania 5 years Development Plan (2011/12 – 2015/16), the Tanzania National Water Policy 2002

and the Bank’s Tanzania CSP (2011-2015). The Project is consistent with the Bank Group Strategy

(2013-2022), the Bank’s Integrated Water Resources Management Policy (2000) and the Gender

Strategy “Investing in Gender Equality for Africa Transformation” 2014 – 2018.

Project Need: In spite of the strategic importance of Arusha city, as a major business, diplomatic

and tourism hub, its water coverage is currently less than 44%. Its sewerage network caters to

less than 7.6% of the city’s inhabitants, and the treatment plant is critically overloaded. Significant

capital investment is required to address the current challenges and to avoid potential negative health

and environmental problems. The Project will lead to transformative improvement of water and

sanitation services in the city which is a pressing requirement at this point in time, and a key sector

priority.

Bank Value Added: Consistent with its operational priorities, the Bank has an important role in

the provision of resources to support Government development Projects. The Bank financing in

the Water Sector Development Program (WSDP) has to date been dedicated to the rural water and

sanitation subsector, and with this Project the Bank’s support is expanded to the urban subsector,

contributing much needed financial resources and bringing its vast experience in the urban subsector.

The Bank has vast experience in supporting water utilities, in water supply, sanitation and water

resources management, which are among its core competencies. The Bank field office will continue to

play an active role in the implementation of the Project and policy dialogue with the Government of

Tanzania, Development Partners and other key stakeholders.

Knowledge Management: The operation shall enhance Bank’s knowledge in the sector and it shall

impart knowledge to the beneficiaries through sensitization activities. This knowledge will be

captured through systematic monitoring and evaluation of the Project outputs and outcomes, Project

reports, supervision missions, a mid-term review, findings of stakeholder consultations and a Project

completion report at the end of the operation.

Page 6: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

iv

Results Based Logical Framework

COUNTRY AND PROJECT NAME: Tanzania – Arusha Sustainable Urban Water and Sanitation Delivery Project PROJECT PURPOSE: To provide safe, reliable and sustainable water and sanitation services and contribute to improvement in health, social well-being and living standards of the beneficiaries.

RESULTS CHAIN PERFORMANCE INDICATORS MEANS OF

VERIFICATION RISKS/MITIGATING

MEASURES Indicators Baseline (2014) Target

IMP

AC

TS

Improve health and social well-being through reliable water and sanitation services

Access to water and sanitation services in urban regional centres

65%

100% in 2025 EWURA, WSDP

reports, NBS & HBS

surveys

RISK 1: Non - Compliance with counterpart funding obligations Mitigation: The General Condition requiring the Borrower to meet its counterpart contribution will be strictly applied during Project implementation. The country macro-economic situation and water budgetary allocation as well as the relatively good financial performance and position of AUWSA, limits this risk. RISK 2: Unwillingness of the consumers to pay increased tariff for water and sanitation services Mitigation: Detailed tariff and affordability study supported by sensitization campaigns and undertaking to implement recommended tariff, in line with the regulatory process. RISK 3: Catchment deterioration Mitigation: The Project includes a water resources management component, under which catchment management plans will be developed and implemented. RISK 4: Financial management risk: Details and mitigation measures are given in Annex B4 (sections B4.3, B4.13 and B4.14)

Under five mortality rate 81/1000 in 2012 54/1000 in 2025

Target in 2020

OU

TC

OM

ES

Improved access to sanitation services

Sewerage service coverage 7.6% 30% (main infrastructure)

AUWSA reports/ Project quarterly reports

People with improved on-site sanitation 142,000 (52% female)

300,000 (52 % female)

Sewerage services functionality

Sewerage effluent vs Tanzania effluent standard

Standard not met Standard met

Sewer blockage incidents 230 per month 100 per month Improved access to water services

Water supply service coverage 44% 100 % Population with reliable piped water services

325,000 (52% female)

600,000 (52% female)

Water services functionality

Quality of water vs Tanzania quality standard

- Standard met

NRW management (% of NRW) 48% 25%

OU

TP

UT

S

COMPONENT 1: SANITATION INFRASTRUCTURE AND SERVICES

IMPROVEMENT

AUWSA reports / Project quarterly reports

Sewerage infrastructure Length of sewerage pipelines laid 45 km (existing) 135 km (new) Sewerage connections 3,300 20,000 New treatment ponds system built 1 (existing) 1 (new)

Onsite sanitation New facilities constructed - 100 School sanitation blocks New sanitation blocks constructed - 100 Sanitation and hygiene campaign/sensitization and awareness in HIV/AIDS, cholera etc.

People engaged in campaign (male, female)

0 50,000 (52% female)

Sex disaggregated on-site public sanitation facilities, which are user friendly to physically challenged users

0 100 (segregated by gender / physically challenged users)

COMPONENT 2: WATER SUPPLY INFRASTRUCTURE AND SERVICES

IMPROVEMENT

Water sources capacity Intake/spring rehabilitated / constructed + m3

- 4 (33,000 m3)

Water boreholes (number and capacity in m3)

19 (existing) 30 (57,600 m3) - new

Water storage capacity Water storage tanks + capacity m3 15 (existing) 17 (19,045 m3) – new

Water distribution Length of rehabilitated and new pipelines laid

289 km (existing) 355km (new) 55km (rehab.)

District /bulk metering No. of district/bulk meters installed 0 38/ 50 Water sources management

Gender informed catchment mgmt. plans

None Developed and adopted

COMPONENT 3: INSTITUTIONAL SUPPORT AND PROGRAM

DELIVERY SUPPORT

Tariff study Tariff and affordability study conducted

None 1 Detailed Tariff Study

Page 7: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

v

Environmental / gender plan

Environmental / gender mgmt. plan None Developed and adopted

Staff training Staff trained in key identified areas .. Training in 7 key areas

IFMS Integrated financial mgmt. information system

.. Operational

Organisation review study Institutional and organizational review study

None Carried out and adopted

KE

Y

AC

TIV

ITIE

S ACTIVITIES INPUTS

Component 1-Sanitation Infrastructure and Services Improvement: consultancy services; contract works for the supply of equipment and working tools to enhance smooth operations and carrying out measures to promote use of improved and environmentally safe on-site sanitation facilities in areas not covered by the sewerage system; Component 2-Water Supply Infrastructure and Services Improvement: consultancy services for studies, detailed designs and supervision; contract works for water sources and water infrastructure and conservation of water sources: Component 3-Institutional Support and Program Delivery Support: Capacity building of AUWSA staff; supply of Project equipment; Project management; Project auditing; compensation; studies and other support activities. More details are given in section 2.1 and the Technical Annexes sections A2 and B2.

Total Project Cost - UA 233,916, 000

ADB - UA 102,137,000

ADF – UA 18,000,000

AGTF – UA 29,863,000

United Republic of Tanzania – UA

16,320,000

Page 8: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

vi

Project Timeframe

Page 9: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

1

Report and Recommendation of the Management of the AfDB Group

to the Boards of Directors on a Proposed Loan to Tanzania for the Arusha

Sustainable Urban Water and Sanitation Delivery Project

Management submits the following report and recommendation on a proposed ADB loan of

USD 143.65 million, an ADF Loan of USD 25.32 million and an AGTF Loan of USD 42 million

to finance the Arusha Sustainable Urban Water and Sanitation Delivery Project in the United

Republic of Tanzania.

I – STRATEGIC THRUST & RATIONALE

1.1 Project linkages with country strategy and objectives

1.1.1 Alignment with Country Development Agenda: The overarching focus of the

country development agenda includes growth, reduced poverty and improvement of social

well-being. The Project objective is consistent with the country’s development framework and

long-term socio-economic development goals as laid out in: (a) Tanzania’s Vision 2025, which

aims to reduce poverty and improve living standards through sustainable development,

including investment in basic economic and social infrastructure, such as water and sanitation

facilities (b) the medium-term national growth and poverty reduction strategy 2011-2015, which

focuses on three broad clusters, namely: growth and reduction of income poverty; improvement

of quality of life and social well-being, and governance and accountability, and (c) the 5 years

Development Plan 2011/12 – 2015/16.

1.1.2 The Project will be carried out under the umbrella of the water sector development

program (WSDP) which was developed following policy reforms and enactment of an

enabling legal and regulatory framework in the water sector, including: (a) the National Water

Policy 2002 (b) the Water Sector Strategy 2006 and (c) Water Resources Management Act No.

11 of 2009 and Water Supply and Sanitation Acts No. 12 of 2009. Details are given in section

A1.2 of the Technical Annexes.

1.2 Project linkages with Bank’s Strategy and operational priorities

1.2.1 The Project is in line with the Bank Integrated Water Resources Management

Policy (2000) and the Bank Group Strategy (2013-2022) core operational priorities which

include supporting Africa’s transformation by promoting sustainable economic growth through

investment in infrastructure, while enhancing inclusive growth, community participation and

gender parity which are all addressed by the Project. The Project is further supported by the

Bank’s Urban Development Strategy (2011) and the Bank Gender Strategy 2014 – 2018, since

gender equality is an important aspect of Africa’s transition to green growth.

1.2.2 The Project is consistent with Pillar 1 of the Tanzania Country Strategy Paper

(CSP) 2011-2015 which focuses on infrastructure, including water supply and sanitation, as an

enabling factor to boost economic growth and improve the quality of life and social well-being.

The Project will also promote pillar 2 of the CSP through the institutional support sub-

component including use of applicable country systems. The Bank is a key development partner

in supporting the Government to address water and sanitation infrastructure and service delivery

needs in the country and the Government of Tanzania (GoT) is keen on continuing with its

cooperation with the Bank in the sector.

1.2.3 Inclusive Growth: The Project will support GoT efforts towards inclusive growth

by improving the sustainability and access to water and sanitation services to 66% of the

population of Arusha city that is currently unserved. Supporting inclusive economic growth

is a key development priority for Tanzania, to enable social well-being and poverty reduction

to the population as a whole. The Project will complement other social services and boost economic

activities in the Project area.

Page 10: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

2

Inclusiveness: The Project will respond, with targeted solutions, to the needs of all groups

including the economically disadvantaged, and will complement and enhance AUWSA’s

current pro-poor strategy. It will ensure that the urban poor are adequately protected; on-site

sanitation and promotional activities will be carried out in areas not covered by the sewerage

system; public kiosks will be installed in designated areas; and Project interventions will include

gender considerations. AUWSA’s current pro-poor strategy is further discussed in section B9

of the Technical Annexes. The Project will also offer employment opportunities during

construction.

1.2.4 Green growth: The Project will support green growth by promoting sustainable

development of the investment, by ensuring reduction / mitigation of environmental risks,

including avoidance of environmental degradation through water sources and catchment

management.

1.3 Rationale for Bank’s involvement in the Project

1.3.1 Arusha city is the headquarters of the East African Community (EAC) and other

international institutions. It is a major diplomatic and business centre and the country’s most

important tourist hub (tourism is the country’s biggest export earner). Responsibility for the

water and sanitation services in the city, is vested in the AUWSA. The Authority’s goals and

business approach are covered in its Strategic and Business Plans, under which investments

have been made in the improvement of its operational systems including metering all its

customers, recruitment of qualified staff and rehabilitation of water and sewerage pipes.

1.3.2 Following upgrading from a municipality to a city in 2010, the service area of

AUWSA has more than doubled, to 208 km2, while the service coverage has remained low

(44% for water and 7.6% for sewerage). AUWSA has thus commissioned studies and detailed

designs, to improve its infrastructure, but has not been able to access financing for the required

investment. Hence the GoT has submitted to the Bank a request for financing of the proposed

Water and Sanitation Service Delivery Improvement Project. The objective of the investment

is consistent with the country’s development framework and the Bank Group Strategy 2013 –

2022.

1.3.3 Accordingly, this strategic Project has been prepared to enable transformative

improvement of water and sanitation services in Arusha city, as detailed in subsequent

sections of this report. The Project is aligned with the sector objectives and WSDP

implementation arrangements and targets. Currently the Bank is supporting transport and

financial sectors in the city through regional integration initiatives namely the Arusha-Holili

and the EAC transport Projects and the EAC Payments and Settlement Systems Integration

Project. With the new Project the Banks support will be expanded to the water and sanitation

sector. The Project investment has sound potential for sustainability.

1.3.4 The Project will be under the umbrella of component 3 of the WSDP, which covers

regional urban centres, district headquarters and small towns and areas serviced by national

Projects. It will support the WSDP targets in the urban sub-sector, which are to serve, by 2019,

some 8.1 million beneficiaries in Dar es Salaam and the 23 regional urban centres, 109 district

headquarters and small towns and areas served by 7 national Projects.

1.4 Donor coordination in Tanzania

1.4.1 The country’s development cooperation landscape includes 4 multilateral

organizations, 16 United Nations agencies and 18 bilateral Development Partners (DPs).

There is a well-established structure for dialogue with the Government and Donor coordination

is carried out at both national and sector levels. The Bank is active in all key sectors, with a

strong presence in infrastructure development, including the water sector. Water sector

Page 11: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

3

coordination is conducted through the Development Partners Group for Water (DPG-W). A

Memorandum of Understanding (MOU) sets out the roles and responsibilities in supporting the

sector, particularly the WSDP, which is jointly financed by DPs and the Government, as shown

in the table below.

1.4.2 The Bank Group financing in the WSDP has to date been dedicated to the rural

water and sanitation subsector, and with the Project the Bank’s support is expanded to

the urban subsector. The Bank is a key member of the water sector dialogue with the

Government, which comprises: (i) annual joint water sector reviews, involving GoT, DPs and

stakeholders to review institutional, policy, financing and sector performance (ii) steering

committee meetings; (iii) thematic and water sector working group meetings; (iv) DPG-W

meetings; and (v) thematic working group meetings.

1.4.3 Sector financing is shown in Table 1.4 while additional information on donor support

is given Annex A1.

Table 1.1: Sector financing

II – PROJECT DESCRIPTION

2.1 Sector goal, development objectives, Project description and components

2.1.1 Sector Goal and Project Development Objective

The sector goal is to improve quality of life and social wellbeing of the population and

enhance the performance of the national economy by ensuring equitable provision of

adequate, reliable and sustainable water and sanitation services. The Project is a constituent

part of the national WSDP. The Project shall contribute to the national effort towards

improvement of public health and quality of life, hence poverty alleviation among the urban

population. The Project objective is to improve water supply and sanitation services within the

service area of AUWSA.

2.1.2 Project Description

The Project will improve quality of water supply and sewerage services in the service area

under AUWSA, and comprises the following three main components: (a) Sanitation

Infrastructure and Services Improvement; (b) Water Supply Infrastructure and Services

Improvement and (c) Institutional Support and Project Delivery. A description of the Project

components is given in section 2.1.2, while detailed activities, quantities and costs are given in

the Technical Annexes section A2 and B2.

Water Sector Development Financing from July 2007 - June 2014

Total Government Basket Donors Earmarked Donors 970 mill UA

(100%) 173 mill UA

(17%)

413 mill UA

(43%)

384 mill UA

(40%)

Level of Donor Coordination

Existence of Thematic Working Groups [Yes]

Existence of SWAPs or Integrated Sector Approaches [Yes]

ADB's Involvement in donors coordination [Member]

Key DPs

include:

WB

KfW

DfID

AFD

AfDB

MCC

JICA

Page 12: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

4

2.1.3 Project Components

Table 2.1: Project Components (detailed activities, quantities and costs are given in Technical Annexes)

Component (UA)

mill

Component Description

Sanitation

Infrastructure

and Services

Improvement

74.1

(69.0)

This component focuses on rehabilitating and expanding the sewerage network and

sewerage treatment facilities and will support decentralized sanitation systems including

sanitation marketing for on-site sanitation technologies and gender sensitive community

sensitizations in order to address sanitation challenges in the areas not covered by the

sewerage system. Activities include:

Consultancy services for design review (including review of both technical aspects and

non-technical, covering financing, management and PPP options), preparation of tender

documentation and supervision of the works.

Construction of new sewerage treatment facilities, design of which takes into account

latest technology as well as financing and management options, including PPP options.

Expansion of the sewerage network (by 135 km) to improve coverage from 7.6% to

30%; and rehabilitating the existing network.

Construction of a workshop and installation of operational facilities/equipment;

together with supply of equipment and working tools to enhance smooth operations.

Carrying out measures to promote use of improved and environmentally safe on-site

sanitation facilities in areas not covered by the sewerage system including construction

of public sanitation facilities.

Construction of decentralized sanitation facilities.

Construction of sanitation blocks for schools.

Water Supply

Infrastructure

and Services

Improvement

79.65

(74.1)

This component focuses on increasing water production capacity and improving the

transmission and distribution network; and enhancing the Utility’s operational efficiency.

Due consideration will be given to water quality of sources as groundwater in the area

generally contains high fluoride from its geological content. Activities include:

Consultancy services for studies and review of water sources plus design, tender

documentation and supervision of works; to assure protection of sources, the

consultancy ToR will include provision to ensure that communities around water

sources have access to pipe-borne water. Peri-urban areas and adjacent rural

communities to be also addressed

Improving water operations and reducing NRW from 48% to 25%;

Increasing water production capacity from 40,000m3/d to 109,000 m3/d;

Construction of 3 new conventional water treatment plants (33,000 m3/d);

Rehabilitating and expanding the transmission and distribution network (about 355 km)

to improve water supply coverage from 44% to 100%;

Construction of 17 water storage tanks (19,045 m3),

Construction of a new water quality and testing laboratory;

Supply & installation of 5 new fluoride removal units, one nitrate removal unit and

chlorination units and refurbishment of chlorination units;

Water resources management including catchment and water sources conservation;

Installation of water kiosks;

Institutional

Support and

Project

Delivery

12.48

(6.6)

This component will enhance AUWSA institutional capacity in water and sanitation

services delivery and provide Project management support.

Activities include:

Implementation of environmental and social / gender management plans;

Institutional and organizational review study

Training and capacity building of AUWSA staff

Support to AUWSA Corporate Social Responsibility Program (CSR)

Support to AUWSA to adopt and implement the national gender strategy

Implementation of integrated financial management information system

Tariff and affordability study and awareness

Supply of Project equipment; construction of new office building;

Project management support; Project auditing; compensation,

Communication and media coverage;

Total 166.32

(150)

The amount in parenthesis ( ) is financed by ADB and AGTF. The amount not in parenthesis is the total. All are in UA

Page 13: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

5

2.2 Technical solutions retained and other alternatives explored

Technical solutions retained are based on international best practice, while taking into

account appropriate technology, and lifetime cost consideration, including investment

needs and operation costs. Reduction of non-revenue water as well as refurbishment and

upgrading of the existing systems and improvement of the operational efficiency of the Utility

are major features of the proposed solutions in order to enhance service delivery and improve

revenue generation. Technical deficiencies in the existing system will be corrected, including

pressure and water balance zoning. District metering areas will be established to enable water

demand management based on reliable flow measurements. Due consideration will be given to

water quality of sources and treatment options, since water in the area has high fluoride levels.

Alternative Project systems considered are given below.

Table 2.2: Project Alternatives Considered

Alternative Brief Description Outcome/reason for rejection

Solar

powered

pumping

systems

Drilled production

boreholes using solar

powered

submersible pumps

Solar pumping is not considered cost effective for the proposed large

borehole systems in Arusha which will require high peak power

requirements.

Sewerage

treatment

options

Use of biological

treatment systems

involving

mechanical elements

(such as trickling

filters, activated

sludge, or aerated

lagoons) vs. waste

stabilization pond

systems.

Biological (mechanized options) such as trickling filters, will need

power for operation in addition to regular maintenance, unlike

biological (waste stabilization) options which do not require energy

for their operation. Based on the current status of Arusha and the

Projected situation over the planning period, the current Project

design has recommended use of waste stabilization ponds, as the

most cost effective solution, considering that sufficient uninhabited

land has been acquired by AUWSA for their construction at an

optimal location, based on gravity sewer flows. Waste stabilization

ponds are suitable in areas where the intensity of sunlight and

temperature are sufficient to facilitate the treatment process. They

are used for municipal sewage treatment in many tropical and sub-

tropical regions and are highly effective in the treatment of

pathogens. Nonetheless, technical options for the sewerage treatment

as well as financing and management including PPP options, will be

further re-examined as part of the engineering services prior to

construction of the infrastructure.

Recycling Reuse of sewage

effluent

Current Project studies consider this option to be limited however it

will be further explored under the Project engineering services.

2.3 Project type

The Project is part of the national Water Sector Development Program (WSDP) which the GoT

is implementing with the aim of improving water supply and sanitation services and

strengthening sector institutions throughout the country. It is one of the projects under the urban

water supply and sanitation component of the WSDP, which addresses management support for

utilities and investment for urban water supply and sanitation systems. The urban component

of the WSDP is being implemented in partnership with different DPs supporting urban water

supply Projects in different regions. Improvement of water supply and sanitation services in

Arusha city is urgently needed, and is one of the priority Projects in the GoT’s investment plan

of the sector. The Project will be financed through the earmarked window of WSDP, using Bank

disbursement modalities to transfer funds for Project activities.

2.4 Project cost and financing arrangements

2.4.1 Background: The GoT in partnership with Development Partners is implementing the

WSDP Phase II, covering the period 2014/15 to 2018/19, estimated to cost USD 3.27 billion,

Page 14: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

6

of which the urban water and sanitation sub-sector would require an estimated budget of USD

1.32 billion. Table 2.3 below provides a summary of urban sub-sector financing needs.

Table 2.3: Cost Estimates for Urban Water and Sanitation Sub-sector/Component of the WSDP

Yearly Financing Requirement USD’ 000 Total

Urban area Intervention Area 2014/15 2015/16 2016/17 2017/18 2018/19 USD ‘000

DAWASA

Management Support 1,261 3,391 2,826 1,696 1,130 10,304.34

Priority Investments 56,340 168,520 114,601 68,760 47,545 455,766.00

Regional WSSAs

Management Support 1,925 2,902 2,419 1,451 967 9,664.00

Priority Investments 35,077 129,847 122,539 54,923 36,616 379,002.00

National Projects

and Small Towns

Management Support 1,449 3,673 3,065 1,837 1,334 11,358.00

Priority Investments 43,853 147,497 114,581 99,748 45,336 451,015.00

Ministry of Water Management Support 199 298 249 149 99 994.00

Total 140,104 456,128 360,280 228,564 133,027

1,318,103.

34

2.4.2 The urban sub-sector will be financed by GoT and

DPs, including the Bank, through a combination of

earmarked and basket funding modalities. Table 2.4

herewith presents an indicative summary of funds

mobilized to date by DPs and GoT for the period 2014/15

to 2018/19. The AfDB/AGTF, will support in financing

the Project as part of the urban subsector of the WSPD for

the period 2015-2019, through an earmarked allocation of

USD 211 million (UA 150 million).

2.4.3 The total cost of the Project is estimated at USD

233.92 million (equivalent to UA 166.32 million), net of taxes and duties, of which USD 163.3

million (69.8%) are foreign costs and USD 70.6 million (30.2%) are local costs. These cost

estimates are derived from the Rapid Study Update of Arusha Water and Sanitation Feasibility

Study of March 2015 and other studies on the Project with details of estimated unit rates

obtained from suppliers and contractors, as well as from experience with similar ongoing

Projects in the country and in the region. A physical contingency of 10% and a price

contingency of 3% per annum have been allowed. A summary of the Project cost estimates by

components and categories of expenditure is shown in the table 2.5 and 2.6 below, while details

are provided in the Technical Annexes section B.2

Table 2.5 : Project Cost by Component

COMPONENT USD’ 000 UA’ 000

Foreign Local Total Foreign Local Total %

1) Sanitation Services

Improvement

60,904 29,416 90,320 43,304 20,915 64,219 45%

2) Water Supply Improvement 74,993 21,944 96,938 53,322 15,603 68,925 48%

3) Institutional Capacity

Building and Project

Management Support

5,505 9,824 15,330 3,914 6,985 10,900 8%

Total Base Cost 141,402 61,184 202,587 100,540 43,504 144,04

4

100%

Physical Contingency (10%) 14,140 6,118 20,259 10,054 4,350 14,404

Price Contingency (3% annually) 7,727 3,343 11,070 5,494 2,377 7,871

Total 163,269 70,646 233,916 116,089 50,231 166,32

0

Table 2.4: Indicative WSDP 2

commitment

DP USD million %

World Bank 229.0 31.0

USAID 60.0 8.1

JICA 44.5 6.0

KfW 24.0 3.2

EU 45.6 6.2

Other DPs 50.0 6.8

ADB 211.0 28.6

GoT 75.0 10.1

Total 739.1 100

Page 15: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

7

Table 2.6 : Project Cost by Category of Expenditure

CATEGORY OF

EXPENDITURE

USD’ 000 UA’ 000

Foreign Local Total Foreign Local Total %

1 A) Works 125,447 48,031 173,478 89,196 34,151 123,347 85.6%

2 B) Goods 3,864 1,041 4,905 2,747 740 3,487 2.4%

3 C) Services 9,632 3,493 13,125 6,848 2,484 9,332 6.5%

4 D) Operating Costs 784 3,136 3,920 557 2,230 2,787 1.9%

5 E) Miscellaneous 1,676 5,484 7,160 1,192 3,899 5,091 3.5%

Total Base Cost 141,402 61,184 202,587 100,540 43,504 144,044 100.0%

Physical Contingency 14,140 6,118 20,259 10,054 4,350 14,404

Price Contingency 7,727 3,343 11,070 5,494 2,377 7,871

Total Cost 163,269 70,646 233,916 116,089 50,231 166,320

2.4.4 The Project will be financed by AfDB, AGTF and GoT/AUWSA. The Bank Group will

provide an ADB loan of USD 143.65 million (equivalent to UA 102.14 million), an ADF loan

of USD 25.32 million (equivalent to UA 18.00 million), and an AGTF loan of USD 42 million

(equivalent to UA 29.863 million), representing 61%, 11% and 18%, respectively of the total

Project cost. GoT/AUWSA will fund the balance of USD 22.95 million, which represents 10%

of the total Project cost. The sources of financing and the expenditure schedule by component

are provided in table 2.7 and 2.8 below, while the Technical Annexes section B2 gives a

breakdown of Project cost components by source of funds as well as a breakdown of Project

cost by category of expenditure financed by different sources of funds.

Table 2.7 : Sources of financing

Sources of Finance USD’ 000 UA’000 %

ADB 143,647 102,137 61%

ADF1 25,316 18,000 11%

AGTF 42,000 29,863 18%

GoT/AUWSA 22,953 16,320 10%

Total 233,916 166,320 100% 1ADF will be used for part of component 3 and part of the sanitation activities in component 2 - component details are given

in the Annexes.

Table 2.8: Expenditure schedule by component

COMPONENT USD’000

2016 2017 2018 2019 Total

1) Sanitation Services Improvement 13,585 32,015 30,755 13,964 90,320

2) Water Supply Improvement 11,576 38,411 29,862 17,089 96,938

3) Institutional Capacity Building and

Project Management Support 6,307 5,163 2,410 1,450 15,330

Total Base Cost 31,468 75,589 63,027 32,502 202,587

Physical Contingencies (10%) 3,147 7,559 6,303 3,250 20,259

Price Contingencies (3%) 1,038 2,494 4,222 3,315 11,070

Total Costs 35,653 85,642 73,552 39,068 233,916

2.5 Project’s target area and population

The Project covers greater Arusha, comprising Arusha city and surrounding areas. Following the upgrading of Arusha from a municipality to a city in 2010, the service area of the

water Utility (i.e. AUWSA) has more than doubled from 93km2 to 208 km2. At completion, the

Project will benefit a resident population of more than 600,000 (288,000 male and 312,000

female) people in Arusha city and 250,000 additional people, who commute to the city for

business purposes, during daytime.

Over the Project horizon about one million people will benefit. The Project benefits include:

(a) improved reliability and sustainability of the water and sanitation services; (b) overall

improvement of the public health situation in the city as a result of a more reliable water supply

service and rehabilitation of waste water collection and treatment facilities (c) an increased

Page 16: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

8

implementation capacity of water and sanitation Projects by AUWSA. Sanitation and hygiene

promotion, including sensitization and awareness raising on water borne diseases and

HIV/AIDS, using information and communication technology material and radio programs will

also benefit the population in Arusha city and neighbouring districts.

2.6 Participatory process for Project identification, design and implementation

2.6.1 Participatory process for Project identification and design: The Bank’s

identification, preparation and appraisal missions consulted with key stakeholders including

senior central and local government officials, development partners, representatives of public

and private sector institutions and the beneficiaries. The missions were accompanied by

officials from the Directorate of Urban Water Supply in charge of Projects under the urban

component of WSDP. Extensive consultations were held with the AUWSA Management team

who provided significant support and Project information.

2.6.2 During Project appraisal the Bank mission had discussions with the Minister and

Permanent Secretary of the Ministry of Water on the challenges of Arusha, urgent need for the

Project, status of Project preparation and design. The mission also met the AUWSA Board,

which includes key stakeholders from industry and business, institutions, women

representatives, and consumers. The mission further held consultations with the Director of

Environment who is also the GEF Country Focal point, and experts from the Pangani water

basin (which encompasses the Arusha area) and visited the de-fluoridation research centre in

Ngurdoto.

2.6.3 The beneficiary consultation process which was supplemented with field visits to

Project sites provided valuable feedback for the Project. Beneficiaries expressed the need to

urgently address the challenges of the current level of water and sanitation services and stressed

their willingness and ability to pay for improved services. Women expressed a strong desire for

the Project, as it will improve general livelihood and reduce health hazards among children.

2.6.4 Public consultations were carried out during the preparation of the environmental impact

assessment report (ESIA) as discussed in detail in the Technical Annexes section B8.4

(Stakeholders). In addition an ESMP summary was disclosed to the public by posting on the

Bank website on 6th August 2015. The public participatory process will continue during Project

implementation. The AUWSA Gender Focal Person and the Customer Care / Outreach Officer

will ensure participation of women during the implementation of the ESMP including

monitoring of gender-related issues.

2.6.5 Participatory process during implementation: AUWAS will conduct stakeholder

consultative meetings and workshops during Project implementation to update stakeholders on

the progress of the Project, including customers, the beneficiary communities, DPs, key

Government Ministries, Non-Governmental Organisations (NGOs), the media, the Energy

Water Utility Regulatory Authority (EWURA), and Quality assurance regulators including

Tanzania Bureau of Standards (TBS), the Tanzania Occupational Safety and Health Authority

(OSHA) and the National Environmental Management Council (NEMC). The outcomes and

feedback from the stakeholder consultations will be duly taken into account to improve project

performance throughout the project implementation, including the review and detailed design

stage prior to construction. In addition, community groups and other beneficiaries will be

engaged through advocacy and community awareness programs included in the Project design.

Page 17: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

9

2.7 Bank Group experience and lessons reflected in Project design

2.7.1 The Bank Group’s active portfolio in Tanzania is rated as

satisfactory with a score of 2.38 (on a 0-3 scale). Water and sanitation

accounts for 12% of the portfolio value, as shown in the table 2.9. Details

of the portfolio and ratings are given in Appendix 2. The disbursement

rate for national public sector operations improved to 51.9% in 2014 from

47.3% in 2013 and 24.86% in 2011. The number of ageing projects

decreased from 6 projects in 2013 to 2 projects in 2014, with the average

age of the portfolio reducing from 4.1 years to 3.8 years. The average

national public sector project size has also increased from UA 32.4

million to UA 43.1 million. Over 96% of the projects have been supervised twice per year.

2.7.2 Lessons from Bank’s experience as reflected in Project Completion Reports

(PCRs), and IDEV post evaluation reports have been taken into account in the design and

formulation of the Project. Three Project Completion Reports (PCR) are available for the water

sector (Project details are given in the Annex 2) and there is no PCR backlog. Some key lessons

from Bank Group experience reflected in Project design are shown below, with detailed

information provided in Annex B1. These include:

(a) The need to adopt an integrated approach comprising water supply and sanitation, effective

community participation by involving the beneficiaries in Project design, Project

implementation using existing institutional arrangements, and the need to support the executing

agency. The Project design incorporates the integrated approach and has already taken into

consideration the views of beneficiaries.

(b) Integration of infrastructure improvements with capacity building and adequate strategic

planning enables Water Utilities to improve their performance and cost recovery and promotes

sustainability of water investments which depends on the strength of the institutions responsible

for their operations and maintenance. The Project will enhance AUWSA operational and

commercial efficiency, including water demand management and reduction of non-revenue

water to achieve higher cost recovery, above the current O&M recovery.

(c) Pro-poor service delivery and inclusive growth require adequate consideration; otherwise

poor communities may revert to unprotected water sources. The Project will support AUWSA

current efforts to ensure that, in addition to the target of achieving financial and economic

objectives, the urban poor are protected. Currently there are 138 vulnerable households which

are supported by AUWSA. Decentralized sanitation facilities catering for groups of households

will be implemented. Funds for social connections have been allocated, whereby AUWSA will

connect poor households, and will recover the cost in the long term from the water bills. This

arrangement will facilitate an affordable access to water and sanitation for poor households in

accordance with the pro-poor policy.

2.7.3 The project has also taken into account experiences gained under the WSDP plus sector

knowledge including case studies covering Tanzania, such as strengthening pro-poor targeting

of investments in urban water and sanitation utilities.

2.8 Key performance indicators and monitoring of targets

2.8.1 The Project will be monitored using Key Performance Indicators (KPIs) reflected

in the Project’s Results Based Matrix which are in-line with the Bank’s Core Sector

Indicators (CSIs). The Project’s Result Based Matrix reflects the KPI of the Project at input,

output, outcome and impact levels. At impact level these include the level of access to

sustainable water and sanitation services and the under-five mortality rate. The outcome

objectives will be measured through monitoring reliable and equitable water supply and

sanitation services. These include: water service coverage ratio, level of Non-Revenue Water,

and number of service connections within the Project area. For sanitation, this will be measured

Table 2.9: TZFO

Portfolio

Sector %

Transport 39

Multinational 16

Water 12

Social 12

Energy 8

Private

sector

7

Agriculture 5

Multi-sector 1

Page 18: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

10

by sewerage services coverage, gradual reduction of sewage blockage incidents, and improved

quality of sewage effluent. The output of the Project will mainly be measured through

production capacity for treated water and volume of wastewater removed and treated as well as

the key facilities constructed.

2.8.2 At the commencement of Project implementation, for the purpose of post-

evaluation of the Project, the baselines for all the indicators will be re-validated and

disaggregated including gender. The ToR for the post evaluation study will be developed in

preparation for the post evaluation process, after some years from the end of the Project.

2.8.3 The Project implementation schedule and procurement plan which provide

milestones for monitoring implementation progress, will be updated with actual status for

evaluation against planned targets on a regular basis. AUWSA through the Project Management

Team (PMT) will monitor and report the Project’s achievements against the identified

performance indicators. AUWSA management will assess the Project’s achievements through

analysis and interpretation of data collected. During implementation, necessary corrective

adjustments will be made to ensure that the Project remains on course and achieves its outputs

as well as its outcomes.

III – PROJECT FEASIBILITY

3.1 Financial and Economic analysis

Table 3.1: Key Economic Figures

FIRR 6.11% and NPV TZS 117.7 billion (at 4% base case)

EIRR 17.6% and NPV TZS 287.1 billion (at 10% base case)

NB: Detailed calculations are available in Annex B7

3.1.1 The financial and economic analysis of the Project have been undertaken by

comparing “with Project” and “without Project” scenarios of the various costs and

benefits that will accrue to the beneficiaries of improved and extended water supply and

sanitation services for the residents in Arusha City and surrounding areas. The Project will

improve access to reliable and clean water supply and sanitation services which will promote

environmental health. These will result in reduced water borne diseases for the populations

living in the Project areas, especially those with limited service and residents in the peri-urban

areas of Arusha city. These will also enhance the quality of livelihood and well-being of the

beneficiary population, and boost economic activities in the Project area. The returns are

measured in terms of benefits which accrue to residents in the form of clean, regular and

adequate drinking water supply, improved sanitation services, improved health and living

conditions of the beneficiary population.

3.1.2 The main assumptions are:

Benefits stream: (i) the level of non-revenue water is projected to be reduced from 48%

to 25% as a result of the Project. The NRW reduction activities, comprising of leak detection

and prevention activities, rehabilitation and expansion of metering systems, and promotion of

water demand management, and rehabilitation of the water supply system will enhance

operating efficiency in the delivery of water services, which is a major Project benefit; (ii)

Another major benefit is the incremental revenue from water supply and sanitation services

from the expanded services reaching out to the suppressed demand within the city as well as

extension of water services to unserved areas, especially to the peri-urban; and communities

located around water sources (iii) In addition the Project has health benefits which account for

the reduction in water borne diseases of populations living in the Project areas, leading to

savings in health expenditures;

Page 19: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

11

Costs stream: The costs side includes capital investments, periodic replacement costs,

and incremental operating and maintenance (O&M) costs, comprising of staff costs, energy,

chemicals and repairs and other overhead costs. The incremental O&M costs are estimated at

15% of incremental water and sanitation revenue. All costs and benefits are considered net of

duties and taxes. In addition, the economic life of the investment is estimated at 25 years.

3.1.3 The Project yields a financial internal rate of return (FIRR) of 6.11% and financial

NPV (at 4% discount rate) of TZS 117.7 billion. Sensitivity analysis to test the robustness of

the FIRR was carried out to determine the impact of adverse variations. The FIRR changes to

4.9% assuming that investment cost increases by 15%, and changes to 4.2% when the benefits

of the Project are decreased by 15%.

3.1.4 The Project’s rate of return is reasonable for water and sanitation sector operation,

especially taking into account the Project’s significant investment for sanitation, which

has major environmental and health benefits, and the social aspects of these services.

Furthermore, the Utility will be able to recover its incremental O & M costs from the revenues

generated over the Projection period. It would over time be able to fully recover its costs while

also contributing in expanding the population’s access to improved water supply and sanitation

services at affordable prices, thereby contributing towards achievement of the country water

sector goals.

3.1.5 The Project’s economic rate of return is estimated at 17.6%. The value is higher

than the opportunity cost of capital and thus the Project is considered economically viable.

Sensitivity analysis to test the robustness of the EIRR was carried out to determine the impact

of adverse variations. The EIRR changes to 15.6% assuming that investment cost increases by

15%, and changes to 15.1% when the benefits of the Project are decreased by 15%. The analysis

shows that the Project is economically viable and socially beneficial for Tanzania. Annex B7

shows the assumptions and the calculations of the Project cost benefit analysis.

3.2 Environmental impacts and social safeguards

3.2.1 The Arusha Sustainable Urban Water and Sanitation Delivery Project was

classified as a Category 2 Project – validated by ORQR on 19 February 2015 – in

accordance with the Bank’s Integrated Safeguards System (ISS) and Environmental and Social

Assessment Procedures (ESAP), mainly because impacts are site-specific, have no significant

and irreversible detrimental effects, and can be minimized by applying appropriate mitigation

measures. The Project’s environmental and social assessment process has been guided by the

policy and legal requirements of Tanzania in addition to the requirements of the African

Development Bank. National legislation in Tanzania does not have Project categorization

procedures but require that urban water supply and sanitation Projects undertake the ESIA

process and do not require stand-alone Environmental and Social Management Plans (ESMPs)

unless requested by lenders.

3.2.2 There are no significant negative environmental impacts anticipated for this

Project. The proposed works for pipe laying are along existing roads, the new boreholes are to

be drilled in specially selected areas, the existing Water Treatment Tanks and Lemara

Wastewater Treatment Ponds will undergo rehabilitation, and the new Wastewater Treatment

Ponds at Terrat will be on land that is purchased by AUWSA and currently uninhabited.

Potential adverse impacts are anticipated mainly during construction. Direct impacts such as

noise, dust, public safety, disruption of surface water drainage, interruption of utilities,

pollution, disposal of waste, and social impacts will be mitigated and generally eliminated.

Many of the impacts will only occur at active construction sites (trenching and pipe laying) and

therefore move with the works such that many locations will only be impacted for a couple of

weeks rather than the duration of the Project. At Lemara Wastewater Treatment Plant, de-

sludging will entail removal of silt and sludge and repairs to the WTP embankments. The site

for the WTP is fenced and there is a buffer zone, so limited social impacts may occur (if any).

Short-term impacts include disruption of road traffic and impaired access to property and

Page 20: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

12

livelihood for those trading alongside roads. No businesses will be permanently impacted but

informal traders may temporally be prevented from trading for those sections where traders

have encroached on the road reserve.

3.2.3 In order to address the Project’s potential adverse environmental and social impacts an

Environmental and Social Management Plan (ESMP) was developed as part of the ESIA.

Among the main mitigation measures proposed are identifying pipeline routes along existing

roads to avoid resettlement (the Project’s current design avoids any resettlement impacts) and

making compensation payments to affected people for land property losses, ensure coordination

with proper authorities (e.g. TANROADS, TANESCO) to address possible damage to local

infrastructure and disruption of public service utilities, ensure proper planning and management

of construction works, and enhance control of industrial effluent discharges into the municipal

sewerage system. Additionally, enhancement measures for positive impacts were also proposed

and include maximizing employment creation for local people (men and women) during

construction and operation phases, intensifying awareness and education campaigns on hygiene

and sanitation practices among local residents, and intensifying effluent quality monitoring to

ensure discharges meet required standards particularly for use in irrigation. The cost of

implementing environmental mitigation measures, including supervision and monitoring is

estimated to be about TZS 4 billion. A stand-alone ESMP, including budget for plan

implementation (comprising costs associated with awareness campaigns and enhancement

measures) and reflecting the final Project scope, was submitted to the Bank. A summary has

been prepared and was posted at the Bank website on 6th August 2015.

3.2.4 The environmental and social benefits of the Project include: (i) improvement in

water supply systems and a healthy environment; (ii) improvement of sanitation and sewerage

disposal (iii) significant enhancement in quantity and quality of supplied water to water

deficient areas; and (iv) proper accounting of water by metering of connections. Specifically,

benefits include improved health conditions among the urban residents and the surrounding

areas, particularly reduction of water borne (e.g. diarrhea, dysentery, and cholera) and water

wash diseases (e.g. skin infections); improved ground and surface water quality and abatement

of nuisance from overflow of sewer pipes and reduction of public health hazards in the serviced

areas; improved access to reliable and sustainable water and sanitation services; as well as

creation of employment opportunities during construction.

3.3 Climate Change

The Project has been classified as Category 2 on Climate Risk in accordance with the

Bank’s Climate Safeguards System. On climate change, the Project will deliver adaptation

benefits in relation to water resources management that is sustainable in the face of projected

climate change. The city of Arusha has experienced water shortages due to drought conditions

which AUWSA has been managing through water rationing. The proposed Project will

diversify water sources which will improve resilience against climate vulnerability. Key

approaches to ensure sustainability are: provision of sustainable and climate resilient water

sources, climate resilient infrastructure and development and implementation of community

driven catchment management plans to protect the watershed. Water sources are located outside

of the city, therefore, communities in the vicinity of water sources are not necessarily

beneficiaries of the city water services. The Project will engage with these communities to raise

awareness on importance of catchment management. In addition, the Project will also support

livelihood improvement of these communities to build resilience of the communities as well as

to reduce root cause of catchment deterioration. A climate change mitigation plan is reflected

in the ESMP.

3.4 Gender and social

3.4.1 Socio-economic and gender assessment were conducted, which were based on

stakeholders’ consultation, reviews of the relevant policies, and discussions with AUWSA

Page 21: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

13

management and staff, and the Ministry of Water. Socio-economic and gender information

which has been used in designing the Project interventions is given in Annex B9. The

information includes division of labor, women’s educational attainment, the health situation,

decision within households, income, policy governing gender empowerment and access to the

media. The water and sanitation situation in the city has resulted in a number of socio-economic

challenges affecting men and women differently. While women are found to be more active in

providing water and ensuring health and wellbeing for the households, competing demands

within the household makes hard for both men and women to agree on priority needs.

3.4.2 The National Gender Policy’s (2000) key objective is to provide guidelines that will

ensure that gender sensitive plans and strategies are developed in all sectors and institutions.

While the policy aims at establishing strategies to eradicate poverty, it puts emphasis on gender

quality and equal opportunity for both men and women to participate in development

undertakings and to value the role of each member in society. The WDSP has aligned its gender

consideration with the national policy. The Project shall support AUWSA to adopt and

implement the policy through providing equal opportunities to both men and women.

3.4.3 AUWSA will appoint a Gender Focal Point. He/she will be trained to design, undertake

and supervise all gender interventions in AUWSA, in consultation with the Ministry of Water

Gender Officer. Knowledge and sensitization on gender mainstreaming and gender specific

needs will be provided to the Project Management Team as part of the institutional capacity

building. Awareness raising of the Board members and communities on the importance of

gender mainstreaming is planned. Gender mainstreaming and gender informed interventions

for all activities will be observed. For instance, a gender sensitive hygiene promotion will be

developed and will benefit 50,000 people (24,000 / 26,000 male/female respectively).

Moreover, due to the low coverage of sanitation in schools, the Project will provide 100

sanitation blocks (segregated by gender and physically challenged users). A budget for gender

mainstreaming has been allocated under the institutional capacity building components.

3.4.4 Between January and March 2015, Arusha had 10697 (5208 female and 5489) cases of

water borne diseases based on the Arusha Health Data, details of which are given in Annex B9

including the types of diseases. The existing sanitation situation in schools is not adequate.

Over 50% of the primary schools have inadequate toilet facilities. The worst affected primary

schools have over 90 pupils sharing one toilet.

3.4.5 AUWSA has adopted a Pro-poor Policy in 2003. AUWSA is providing free water

service to 138 urban poor households in the city and the costs are subsidized by the Authority.

The total amount subsidized by AUWSA in 2013/2014 is Tshs 1,979,631.36. The provision of

water services to these households is part of the AUWSA Corporate Social Responsibility

(CSR) program started in the 2004.

3.4.6 AUWSA has developed a set of criteria for identification of urban poor households in

collaboration with the Arusha Regional Administration and the Arusha City Council, who

assisted in providing data on poverty status and level. Details are given in Annex B9. The

monitoring and evaluation (M&E) system will provide regular information of how many

vulnerable households benefited from the CRS (segregated by household profile). Gender and

social outputs indicators will be part of the consultants and contactors TORs as well as the

quarterly progress reports.

3.4.7 Overall Benefits: the Project will contribute to the regional and national effort for the

improvement of the wellbeing of the population. The Project will also contribute to the

enhancement of environmental public health, ensuring households have access to safe drinking

water, reducing household health expenditures, increasing productivity as result of reduction of

water borne diseases, which will lead to improvement of quality of life, hence poverty

alleviation among the urban and peri-urban population of Arusha. Furthermore, the Project will

Page 22: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

14

lessen women’s burden and enhance productivity for both men and women. Detailed gender

and social analysis is given in annex B9.

3.4.8 Involuntary resettlement: There is no involuntary resettlement foreseen.

IV – IMPLEMENTATION

4.1 Implementation arrangements

4.1.1 The Project will be implemented using existing structures and institutional

arrangements, incorporating lessons and experience gained from similar operations. The United

Republic of Tanzania is the Borrower of the ADB/AGTF loan, while AUWSA, under the

Ministry of Water (MoW), will be the Executing Agency (EA) of the Project. The EA has

constituted a Project Management Team (PMT) from its own staff, comprising of a Project

Coordinator, Water Engineer, Sanitation Engineer, Procurement Expert, Social/Community

Mobilization Expert, Environmentalist and Project Accountant, to be in charge of the

implementation of the Project. The overall coordination of the Project and reporting obligations

to the Bank will be the responsibility of AUWSA.

4.1.2 Under existing institutional arrangements, the Project falls within the framework of the

National Water Sector Development Program; the Permanent Secretary Ministry of Water will

be responsible for overall implementation, while the Urban Water and Sanitation Department

(UWSD) within the Ministry of Water will be in charge of coordination and oversight. The EA

(AUWSA) will operate within this framework, and will be responsible for the procurement,

financial management, monitoring and reporting and overall project management functions.

The PMT jointly with Arusha City Council (ACC) will be responsible for the implementation

of Sanitation and Hygiene Education component, especially in the peri-urban areas, using

Community Based Organizations and NGOs. AUWSA will also ensure implementation,

supervision and reporting of the ESMP. In addition, the consultants and the contractors will

have Environmental and Social Experts on board who will be supervised by the AUWSA’s

Environmentalist, Social Expert and Community Liaison Officer.

4.1.3 The overall coordination of the Project and reporting obligations to GoT and the Bank

will be the responsibility of the EA (AUWSA). The dedicated PMT within AUWSA will

implement and deliver the Project outputs within the agreed timeframe. The PMT will

coordinate and supervise the implementation of the Project, maintain the Project accounts and

financial records, process disbursement requests, and reports in accordance with the

requirements of GoT and ADB. The PMT shall also coordinate implementation of the ESMP,

oversee the implementation of the gender strategy, implementation of the cross-cutting issues

and awareness raising, promotional sanitation, and Hygiene Education sub-components in the

peri-urban areas using the existing institutional structures.

4.2 Procurement arrangements

4.2.1 Procurement of ICB contracts and Consulting services for the proposed Project will be

carried out in accordance with the Bank’s Rules and Procedures: “Rules and Procedures for

Procurement of Goods and Works”, dated May 2008, revised July 2012 as amended from time

to time; and “Rules and Procedures for the Use of Consultants”, dated May 2008, revised July

2012 as amended from time to time using the relevant Bank Standard Bidding Documents, and

the provisions stipulated in the Financing Agreement. Procurement of contracts for goods and

works using national competitive bidding (NCB) procedures will be carried out in accordance

with the national procurement law, the Public Procurement Act, 2011 of the United Republic

of Tanzania and the relevant national Standard Bidding Documents.

4.2.2 Assessment of the National Procurement Law, Rules and Procedures was carried out

and findings are given in section B5.1 of the Technical Annexes. The overall Project risk for

procurement is moderate. The Procurement Plan has been discussed and finalized. Related

Page 23: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

15

procurement documents have also been discussed. To expedite the smooth execution of the

Project, the government requested use of Advance Contracting (AC) procedures for the

following consultancy service contracts: Consultancy for Engineering Services for Review,

Preparation of Detailed Design, Tendering and Supervision of Work; Consultancy Services for

Additional Water Sources Investigation (including quantity, quality and treatment options) and

study on Lake Duluti and Consultancy Services for Demand and Non-Revenue Water

Management. Detailed procurement arrangements are provided in section B5 of the Technical

Annexes.

4.3 Financial management and disbursement arrangements

4.3.1 The Financial management Specialist conducted an assessment of the adequacy of the

AUWSA financial management system, based on the Bank’s financial management (FM)

Implementation Guidelines (2014) and concluded that the overall financial management risk is

“Substantial”. However if the Proposed mitigation measures as per the Risk table in Annex 1,

are implemented, the Project will be able to: (i) use the funds for the intended purposes in an

efficient and economical way; (ii) prepare accurate, reliable and timely periodic financial

reports, and (iii) safeguard the entities’ assets.

4.3.2 In line with the Paris Declaration on Aid Effectiveness and Accra Agenda for Action, the

Project will substantially make use of the AUWSA’s financial management system, for which

enhancement measures are included in the Project design. The day to day financial management

will be as per AUWSA Financial rules and procedures, which are being updated. AUWSA Finance

Manager will be responsible for the Financial Management function of the Project. A designated

Project Accountant (under the supervision of the Finance Manager) with relevant knowledge and

experience acceptable by the Bank will be part of the Project team. The Project will prepare

quarterly physical and financial reports, in line with AUWSA reporting requirements and submit

to the Bank within 45 days after the end of each quarter.

4.3.3 AUWSA Internal Audit Department will audit the Project at least once annually and share

internal audit reports with the Bank during supervision missions. To enhance the financial

management functions, AUWSA is in the process of upgrading the computerized accounting

system from PASTEL PARTNER to PASTEL EVOLUTION which is expected to integrate all systems

including billing and will be able to accommodate Project functions.

4.3.4 Although the Authority has no previous experience in managing Bank financed Projects, a

dedicated and experienced Project management team (PMT), supported by capacity building under

the Project, will enable AUWSA to execute the Project. The dedicated PMT will be constituted as

per the implementation arrangements in section 4.4 and the conditions in section 5.2 of this report.

Further support will also be provided by the Bank during Project launching and implementation

support / supervision missions. Detailed financial management and disbursement arrangements are

given in Annex B4. Analysis of the financial performance of AUWSA based on its previous

audited financial statements is given in section B7.2.4 of the Technical Annexes.

4.3.5 Audit arrangements: The Project financial statements will be prepared within three (3)

months after the closure of every financial year and presented to external auditors. The Project

audit will be conducted by the Controller and Auditor General (CAG) or a Private Audit firm

appointed by CAG and agreed with the Bank based on the Bank’s audit terms of reference. The

audit report, complete with a Management Letter, will be submitted to the Bank not later than

six months after the end of the financial year. The Project will also be subjected to a Value for

Money audit once at Mid Term or when substantial work has been done. The cost of the audit

will be borne by the Project if undertaken by the Private Audit Firm.

4.3.6 Disbursement arrangements: The Project will mainly use the Direct Payment method

to pay contractors/consultants/suppliers whereas the Special Account method will be used for

financing all eligible operation and capacity building costs. The Reimbursement methods can

Page 24: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

16

be used where the need arises after consultation with Bank and obtaining prior approval. The

four disbursement methods are prescribed in the Disbursement Handbook available in the

Bank’s website. AUWSA will open two (2) Special Accounts (SAs), one denominated in

foreign currency at the Bank of Tanzania and the other in Tanzania Shillings (TZS) at a bank

acceptable to the Bank. The opening of the special accounts will be a condition to first

disbursement. The Bank will issue a disbursement letter, which will provide specific guidelines

on key disbursement procedures and practices. The content of the disbursement letter will be

discussed during negotiations.

4.4 Monitoring of Project implementation activities and progress

4.4.1 The Executing Agency (AUWSA) will be responsible for the overall monitoring

and supervision of the Project activities including ESMP implementation. It will produce

monthly, quarterly and annual progress reports on the status of the various Project activities,

financial and procurement status, asset management, stakeholder participation, safeguard, risks

and mitigation measures. Besides submission of the reports to the Bank, these will also be

shared with the relevant government’s bodies, especially the Ministry of Water, Ministry of

Finance, and Ministry of Planning so that the results can feed into the country’s National Data

System. The Project mid-term review will enable AUWSA, the Government and Bank to re-

examine the implementation arrangements and further strengthen the system if necessary. Once

the Project approaches substantial completion, a completion report will be prepared by AUWSA

that includes details of Project implementation, financial management, procurement, asset,

safeguard and measures of the achievements of the Project against the indicators in the log

frame. The Project completion report will also provide lessons learnt for future operations. All

reports will be prepared and submitted according to the Bank’s requirements. The data will be

entered into Implementation Progress and Results Report (IPR) in timely manner.

4.4.2 The Bank shall also conduct regular Project monitoring through supervision missions.

The Project implementation schedule is presented in Annex A1. A summary of the main

milestones is presented table 4.1 below:

Table 4.1 : Key Milestones

Timeframe Milestone Monitoring process / feedback loop

September 2015 Loan Approval Bank

October 2015 Procurement (Consultant) Procurement and contract documents; Bank’s “No objection”

November 2015 Loan Agreement Signed Sign Loan Agreement between the Bank and GoT

December 2015 Loan effectiveness Launching mission; Loan conditions fulfilled

February 2016 Procurement (Works) Procurement and contract documents; Bank’s “No objection”

June 2016 Construction Starts Supervision; progress monitoring and reporting

June 2017 Mid-term review Reporting informed by review of progress, supervision and

audit reports, and field visits

December 2019 Project completion All Project activities completed and Project Completion

Report prepared.

4.5 Governance

The design of the Project has taken into account the governance environment at Project level

and at country level, as discussed below.

Governance at Project level:

4.5.1 The overall Project risk for procurement is moderate. Mitigation measures to

address fiduciary risks, at Project level, including procurement and financial

management, are discussed in section 4.2 and 4.3 of this report and the Technical Annexes

sections B4 and B5. These will include using the standard Bank bidding/contracting procedures

and guidelines in addition to the Government’s systemized procurement procedure, which shall

reinforce transparency and accountability during tendering and award of contracts. In addition,

Page 25: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

17

an internationally recognized engineering firm will be recruited to assist with review, detailed

design, procurement and supervision of major construction works.

4.5.2 The governance and organization structure of AUWSA (the Executing Agency) is

discussed in Annex B7.2. The Bank appraisal assessment concluded that AUWSA is well

managed. The Managing Director of AUWSA shall thus be the Principal Accounting Officer

for the resources entrusted to the Project and shall designate the Project Team to undertake the

day-to-day management of the Project. The Internal audit department of AUWSA and the

Ministry of Water will supplement oversight of Project Management. Robust governance

arrangements have been put in place to ensure successful implementation, monitoring and audit

of the Project, as highlighted in the procurement and financial management sections and the

Technical Annexes.

Governance at Country Level:

4.5.3 Tanzania has made progress in public accountability, particularly through the

strengthening of oversight institutions such as the Controller and Auditor General’s

(CAG) Office, the Prevention and Combating of Corruption Bureau (PCCB) and

Parliament. The autonomy of both the Combatting and Control of Corruption Bureau (PCCB)

and the office of the Control and Auditor General (CAG) has increased substantially. For

instance, the PCCB and CAG in 2014 led investigations into the allegations of irregularities in

payments to the Independent Power Tanzania Limited (IPTL). The independence of PCCB and

CAG were observed during the investigations which also included public disclosure of

information, parliamentary debates and subsequent Government follow up.

4.5.4 The GOT, in 2011, amended the Public Procurement Act of 2004, to strengthen the

Public Procurement Regulatory Authority’s functions. Tanzania is also implementing the

National Framework on Good Governance to improve the capacity of all representative bodies

and strengthening local level governance institutions, in addition to core reform programs in

financial management, public service, the legal sector and the local government sector. The

Government has prepared an Action Plan to implement the Open Government Partnerships

(OGP), from July 2012, starting with three sectors of water, health and education. OGP is a

global initiative to promote transparency, empower citizens, fight corruption and encourage use

of new technologies to improve governance. Government anti-corruption efforts are led by the

PCCB, which was set up in 1991. The Bank is currently supporting the Government’s

governance agenda through the Institutional Support for Good Governance Project.

4.5.5 Tanzania Governance and CPIA information: According to Transparency

International’s 2014 Corruption Perception Index, Tanzania ranked 119 out of 175 countries

compared to 111 out of 177 countries in 2013. Tanzania ranked 15 out of 52 countries in the

Mo-Ibrahim Index of African Governance with an overall score of 58.2 (out of 100) in 2014,

which is higher than the East Africa and sub-Saharan Africa averages of 48.5 and 51.7

respectively. The World Bank’s Worldwide Governance Indicators show that in all dimensions

of governance, Tanzania was between the 22 to 42 percentile rank amongst the 200 countries

surveyed in 2013. Tanzania had the best percentile rank in voice and accountability and political

stability and absence of violence (percentile rank 41) and the lowest score in control of

corruption (percentile rank 22).

4.6 Sustainability

4.6.1 The Government’s commitment to the development of the water and sanitation

sector in the country is demonstrated by the renewed commitment to continue to implement

the WSDP 2006-2025, which is currently under implementation. The Government encourages

full ownership and participation by the beneficiaries in the provision of water and sanitation

services, taking into account gender sensitivity and environmental & social safeguard in the

process, in order to ensure their effectiveness and sustainability. The Project will promote the

Page 26: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

18

sustainability of the investment through appropriate cost recovery mechanisms from the

beneficiaries / customers, as discussed further in the sections below.

4.6.2 The Executing agency, AUWSA is a well-managed and functioning Utility with a

good performance, as reported by the national regulator (EWURA). The Utility has

policies, systems and procedures in place to ensure effective sustainability of the facilities

constructed under the Project. The design of the Project has taken into consideration the

technology used in the existing systems. Furthermore, the Project incorporates training and

capacity building of AUWSA staff to further enhance their capacity to plan, operate and

maintain the system effectively and efficiently. As part of the Project, the Utility will undertake

Institutional and Organizational study to reassess and adjust its structure to enable to provide

efficient water supply and sanitation services to the growing number of water supply and

sewerage consumers, including those in the greater Arusha area. The conduct of the institutional

and organization study and implementation of the recommendations is one of the conditions of

the loan.

4.6.3 Current AUWSA’ tariff for sewerage services is not fully reflective of economic

cost of service provision. There is need to review and update the tariff structure for both water

and sanitation services to reflect efficient cost of service and to take into account the proportion

of water supply and waste water services so that tariffs commensurate the cost of these services.

In this regard, the Project will finance a detailed tariff study which takes into account the social

nature of these services and affordability especially for the poor, and make recommendations.

This is one condition of ADB loan.

4.6.4 The current water supply and sanitation tariff enables the Utility to generate

adequate funds to operate and maintain the water supply and sewerage system. The

provision and enhancement of the water supply and sanitation infrastructure in Arusha and

surrounding areas will increase the water and sanitation revenue of AUWSA. The current tariff

level, average of TZS 831/m3 for water and TZS 450/m3 for sewer services is higher than the

operations and maintenance cost recovery, estimated average of TZS 600/m3 and TZS 330/m3

for water and sewer services, respectively. At completion of the Project, the incremental

revenue (TZS 38 billion) generated from the Project will more than offset the incremental

recurrent costs (TZS 13 billion). Consequently, there will not be any need for budgetary support

or subsidies from GOT for operations and maintenance of the Project.

4.7 Risk management

4.7.1 Payment for increased tariff: One of the challenges the Project may face is

unwillingness by the beneficiaries to pay increased tariff for services. This is particularly so for

the majority who hitherto have not been benefiting from any public water supply and sewerage

services. This risk will be mitigated by the tariff and affordability study and enhanced public

awareness campaign to be conducted as part of the Project. The tariff setting will take into

account affordability by different categories of beneficiaries, which will allow for social tariffs

affordable to the poor. In addition, the Project will include public awareness and extensive

sensitization campaigns to get beneficiaries on board.

4.7.2 Potential for delayed service connections: The Project could also run the risk of

delayed connections to the extended water supply and sewerage system. This is common with

new water and sewerage Projects which can take a long time before attaining a critical mass of

household/premises connections. To ensure that delays in house connections do not occur,

customers will be connected as the water supply and sewers are laid under the Project.

Connection works will be built into and carried out as part of the overall water supply and

sewerage laying contract, and connection charges gradually recovered from water and sanitation

bills. In addition well-targeted sensitization campaigns together with health and hygiene

education will be carried out to further minimize the risk.

Page 27: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

19

4.7.3 Government contribution: The GoT has been implementing the WSDP to support

provision of water supply and sanitation services to the majority of its people. The target is to

reach the entire population by 2025. This calls for timely allocation of adequate resources for

the sector. There is therefore a risk of the Government failing to make this timely allocation of

enough resources especially taking into account the fact that some of the older systems also

require rehabilitation and upgrading. To minimize the risk, constant dialogue between the

government and development partners including the Bank will be maintained together with

efforts to mobilize adequate resources.

4.7.4 Fiduciary (financial management and procurement) assessment, including risk

mitigation measures are discussed in sections 4.2, 4.3 and 4.5.1 of this report and details are

given in the Technical Annexes sections B4 and B5.

4.8 Knowledge building

4.8.1 The Project is expected to generate considerable knowledge and experiences that

will add value and build up lessons for the design and management of similar Projects, to

be replicated throughout the country as well as to other RMC. The lessons learnt will be

documented including gender mainstreaming, as well as lessons in addressing fluoride content

in water sources. Bank supervision missions, quarterly and annual progress reports, mid-term

review, audit and completion reports will also provide an opportunity to capture knowledge on

relevant aspects of Project. This will include its design, implementation modalities,

procurement and disbursement processes, as well as Government response, which will be

available for internal analysis and sharing.

4.8.2 The Executing Agency will learn the Bank’s procedures and safeguards to ensure

adequate preparation and successful implementation of development Projects, and be able to

replicate the same in its future development work. The Bank will also share with other RMCs

as well as internally, the lessons learnt from the experience of implementing this Project in

Tanzania.

V – LEGAL INSTRUMENTS AND AUTHORITY

5.1 Legal instruments

5.1.1 The Project will be financed by an ADB Loan, ADF Loan and an Africa Growing

Together Fund Loan (AGTF). Hence, three loan agreements: ADB Loan Agreement, ADF Loan

Agreement and AGTF loan Agreement will be executed with the Borrower.

5.2 Conditions associated with Bank’s intervention

5.2.1 Conditions Precedent to Entry into Force of the Loan Agreements:

The Loan Agreements shall enter into force subject to the fulfilment by the Borrower of the

provisions of section12.01 of the General Conditions Applicable to Loan Agreements and

Guarantee Agreements of the African Development Bank. The Conditions for the AGTF loan

will be similar to those for the ADB loan.

5.2.2 Conditions Precedent to First Disbursement for the Loans: Evidence acceptable to

the Bank of:

(i) Having opened two special accounts, one denominated in foreign currency at the Bank

of Tanzania and the other in Tanzania Shillings at a bank acceptable to the ADB into

which Bank funds will be deposited; and

(ii) A Subsidiary Financing Agreement between the Government of the Republic of

Tanzania and AUWSA, prepared in due consultations with the AfDB, on the transfer of

the AfDB loan proceeds.

Page 28: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

20

5.2.3 Undertakings that:

(i) Counterpart funds by GoT/AUWSA will be available during Project implementation;

(ii) AUWSA maintains a current ratio (current assets to current liabilities) of more than 1.5

by 2018 and decrease AUWSA’s debt to employed capital ratio to less than 50% by

2019;

(iii) AUWSA carries out by 30 December 2016, a detailed tariff and affordability study;

(iv) AUWSA in consultation with the Regulator (EWURA) implements the

recommendations of the tariff and affordability study by 30 June 2017; and

(v) AUWSA carries out by 30 December 2016, Institutional and Organizational Study; and

(vi) AUWSA implements the recommendations of the Institutional and organizational study,

by 30 June 2017.

5.3 Compliance with Bank Policies and Strategies

This Project complies with all applicable Bank policies and strategies including the Bank

Integrated Water Resources Management Policy (2000), the Bank Group Strategy (2013-2022),

the Bank Urban Development Strategy (2011), the Bank Gender Strategy (2014 – 2018), the

Bank Climate Risk Management and Adaptation Strategy (2009), the Bank Group Eligible

Expenditure Policy and the Bank Group Credit Policy.

VI – CONCLUSION AND RECOMMENDATION

6.1 Conclusion

The proposed Project is in line with the priorities of the Government of the United Republic of

Tanzania, the Bank’s CSP for Tanzania and sector priorities as per the WSDP. It will have a

positive impact to the country’s economy and to the health and well-being of the population and

will provide climate adaptation benefits in relation to water resources management.

The investment has high economic returns and reasonable commercial return and is primarily

geared towards improving the quality of services, with significant investment for sanitation, to

address environment and health standards. Furthermore, the project will enhance the financial

sustainability of the Utility, while ensuring social inclusiveness. Further justification of the

investment is given in Appendix V.

6.2 Recommendation

Management recommends that the Boards of Directors approve the proposed ADB loan of USD

143.647 million (equivalent to UA 102.14 million), an ADF loan of USD 25.316 million

(equivalent to UA 18.00 million) and an AGTF loan of USD 42 million (equivalent to UA

29.863 million) to the United Republic of Tanzania, for the purposes of the Project and subject

to the conditions stipulated in this report.

Page 29: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

I

Appendix I: Tanzania - Comparative Socio-Economic Indicators – May 2015

Page 30: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

II

Appendix II. Table of AfDB’s Country Portfolio

The overall performance of the national public sector portfolio is rated satisfactory with an assessment score

of 2.38 (on a scale of 0 to 3). Details for ongoing operations are given below. Closed operations in the water sector are Monduli

Water and Sanitation Project, Dar es Salaam Water Supply and Sanitation Project and the Rural Water Supply & Sanitation Program 1.

PROJECT/OPERATION

APPROVAL

DATE

CLOSING

DATE

APPROVED

(UA MIL)

DISBURSED

( UA

MIL)

DISBURSE

MENT

RATE (%)

OVERALL

ASSESSME

NT

IP

DO AGE

YRS

AGRICULTURE 104.7 10.98 27.45% 2.25 2

Marketing Infrastructure, Value Addition and Rural Finance Programme

29 June 2011 31 Dec 2016 40.0 10.98 27.45% NPPP 3.0 3.0 3.5

TRANSPORT 352 172.88 49.11% 2.63 5.0

Singida – Babati- Mijingu Road 17 Sep 2007 31 Dec 2014 60.0 55.34 92.23% 2.88 2.85 3.0 7.25 Road Sector Project I 2 Dec 2009 31 Dec 2015 152.0 92.94 61.14% 2.76 2.86 2.7

5 5.08

Road Sector Project II* 5 April 2012 30 Sep 2017 140.0 24.61 17.58% NPPP 3.0 3.0 2.67

ENERGY 75.86 24.32 32.1% 2.37 4.06

Electricity V Project - ADF Loan

14 Dec 2007 30 June 2015 28.68 14.1 49.18% 2.59 2.5 3.0 7.0

- ADF Grant 14 Dec 2007 30 June 2015 1.32 1.01 76.21% 2.59 2.5 3.0 7.0 Iringa-Shinyanga Transmission Line* 26 Oct 2010 31 Dec 2015 45.36 9.21 20.3% NPPP 2.71 3.0 4.17 Scaling up Renewable Energy 20 Dec 2013 0.5 0.0 0% na na na 1.0

WATER 106.59 86.05 80.73% 2.48 3.14

Zanzibar Water & Sanitation - ADF Loan 11 Nov 2008 30 June 2015 25.0 23.59 94.35% 2.48 2.43 2.7

5 6.70

AWF Grant 11 Nov 2008 30 June 2015 2.78 2.75 98.91% 2.48 2.43 2.75

6.70

Rural Water Supply and Sanitation II - ADF Loan 15 Sep 2010 31 Dec 2015 59.0 53.5 90.67% 2.72 2.71 3.0 4.33 AWF Grant 15 Sep 2010 31 Dec 2015 5.8 5.8 100% 2.72 2.71 3.0 4.33

Zanzibar Urban Water & Sanitation 19 Dec 2012 31 Dec 2017 14.0 0.41 2.9% NPPP 3.0 3.0 2.50

SOCIAL SECTOR 109.0 58.09 53.29% 2.34 4.25

Support to Maternal Mortality Reduction

11 Oct 2006 30 Apr 2015 40.0 37.72 94.3% 2.25 2.93 2.25

8.17

Small Entrepreneurs Loan Facility II 10 May 2010 31 Dec 2015 20.0 18.75 93.77% 2.52 2.5 3.0 4.58 Alternative Learning Skills and Development

29 June 2011 31 Dec 2016 15.0 1.62 10.79% NPPP 3.0 3.0 3.5

Support to Technical Vocational and Training and Teachers Education

2 April 2014 31 Dec 2019 34 0 0% na na na 0.75

MULTI SECTOR 5.82 5.12 88% 2.18 4.42

Institutional Support for Good Governance

20 Sep 2010 31 Dec 2014 5.2 4.7 90.41% 2.18 2.07 2.25

5.25

EFC- Tanzanie Fund for Africa Private Sector Assistance

1 June 2012 31 Mar 2016 0.62 0.42 68.26 na na na 2.58

PRIVATE SECTOR 66.09 1.37 2.07% na na na

Bagamoyo Sugar Project – ADB Loan

23 April 2014

32.35 0 0.0% na na na 0.75

CRDB SME Partial Credit Guarantee 22 Jul 2008 31 Mar 2016 1.39 1.37 98.6% na na na 6.42

MULTINATIONAL OPERATIONS

147.83 11.91 8.1% 2.37 4.08

Dsm-Isaka-Kigali/Keza-Musongati Railway

17 Nov 2009 31 Mar 2016 1.66 1.02 61.43 2.50 2.36 3.0 5.17

Arusha –Namanga ADF - Grant ADF- Loan

13 Dec 2006 28 Feb 2014 0.54 0.19 35.8% 8.0 13 Dec 2006 28 Feb 2014 3.5 2.07 59.1% 2.73 2.83 3.0 8.0

East Africa Transport & Trade 29 Nov 2009 30 Nov 2015 6.2 3.37 54.33% 2.27 2.08 3.0 8.17 Transit Transport Facilitation 22 Dec 2010 31 Dec 2015 0.32 0.19 58.96% na na na 4.0 Arusha-Holili/Taveta-Voi Road 16 April

2013 31 Dec 2018 79.9 0 0.0% NPPP 3.0 3.0 1.67

EAC Payments &Settlement System 5 Dec 2012 31 Jan 2017 15 0.89 5.96% NPPP 3.0 3.0 2.08 Lake Victoria Water & Sanitation 17 Dec 2010 31 Dec 2015 17.48 3.95 1.3% 2.22 1.71 3.0 4.0 Regional Rusumo Hydropower 27 Nov 2013 31 Aug 2019 22.41 0 0% na na na 1.08 EAC Railway Sector Enhancement 29 June 2012 31 Dec 2015 0.82 0.28 0% na na na 2.5

(a) Public Sector Only 689.27 357.44 51.9% 2.38 3.97 (b) Public + Private Sectors 755.36 358.81 47.5% 3.78 (c) Public + Private + MNO 903.19 368.63 44% 3.88

OTHER MULTINATIONAL OPERATIONS

33.59 26.26 78.18% 2.58 6.93

SADC: Shared Watercourses Support 31 May 2006 na 9.38 8.28 88.29% 2.47 2.46 3.0 9.16

Page 31: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

III

PROJECT/OPERATION

APPROVAL

DATE

CLOSING

DATE

APPROVED

(UA MIL)

DISBURSED

( UA

MIL)

DISBURSE

MENT

RATE (%)

OVERALL

ASSESSME

NT

IP

DO AGE

YRS

SADC: Control of communicable diseases

31 may 2006

na 20.00 15.35 76.75% 2.69 2.73 3.0 8.83

Songwe River Basin AWF Development Programme AWF (Tanzania/Malawi) NEPAD-IPPF)

25 May 2010 an 0.49 0.26 51.83% na 4.83 25 May 2010 na 2.65 1.75 65.82% na 4.83

28 April 2010

na 1.07 0.62 57.92% na 4.92

(c) Public + Private + ROs+ other multinational Operations

936.78 385.07 41.1%

Page 32: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

IV

Appendix III: Key Related Projects in the Country

COUNTRY / AGENCY

SECTOR PROJECT

French Development

Agency (AFD)

Small Towns WSS

Small Towns Water Supply and Sanitation (WSS)

Project

Word Bank

Urban, rural and

water resources

Water Sector Support Program

Zanzibar Urban Services Project

Marine and Coastal Environment Project

UK Department for

International Dvp (DFID)

Water resources Rufiji Basin Rural WSS

Rural Water Supply and Sanitation (RWSS) Program

European Union Small Towns WSS Water Supply Programme Regional Centres

German Dvp Agencies

(GTZ& GIZ)

Policy WSS Development Ass. Policy & planning

Japan

Rural WSS

Study WS improvement Coastal Region

RWS in Lindi & Mtwara

Study RWS Mwanza & Mtwara

Expert in groundwater dev RWS Urban WSS Zanzibar WS Dev. Project

German Development

Bank (KfW)

Urban WSS Urban Investment Program

Songea Water and Sanitation Project

Regional Centres

Rural WSS East Kilimanjaro Project

Moshi Rural District Projects Belgium Small Towns WSS Kigoma Water Supply and Sanitation Project China National Project Chalinze WSS UNICEF Water and

Sanitation Rural and urban water supply and sanitation

including school WASH and technical assistance India Urban WSS Dar es Salaam Water Supply – Upper Ruvu BADEA Rural/small towns Same – Mwanga – Korogwe Project

African Development

Bank

Rural /urban WSS Rural Water Supply and Sanitation Program

Zanzibar Water Supply and Sanitation Project Urban - Zanzibar Zanzibar Urban Water and Sanitation Project Multinational and

Water Resources Lake Victoria Water Supply and Sanitation Progr.

SADC Shared Water Basin

Songwe River Basin Dev. Program - Design Others including Ireland, S.Korea, Sweden,

Denmark, Norway, OPEC, Egypt, UNDP, UN

HABITAT, CIDA, DANIDA, Water Aid,

CARE, SNV, Plan.

Various earmarked Projects

Page 33: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

V

Appendix IV. Map of the Project Area

Page 34: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

VI

Appendix V: Justification for ADB financing of more than 50% of the Project cost.

1. Country context

1.1 Country Commitment to Implement its Overall Development Program:

Tanzania’s current development strategy, the “Five Year Development Plan” FYDP I (2011/12

– 2015/16), has the overarching theme of ‘Unleashing Tanzania’s Growth Potential’. The

Government is committed to implementing the FYDP and continues to mobilize domestic

resources for the purpose and to strengthen the linkage between the plan and the national

budget. The FYDP thus features fundable and implementable activities, which eventually

translate into annual development plans as part of the national budget implementation. The

Government has ensured alignment of policies, strategies and programs as well as plans of

Ministries, Departments and Agencies (MDAs), Regions and Local Government Authorities

(LGAs) with the FYDP, and harmonization with the national budget. The Government formally

launched the Big Results Now! (BRN) initiative in 2013, to establish a strong and effective

system to oversee, monitor, and evaluate the implementation of plans, policies and strategies.

The BRN priorities are: transport infrastructure in the central corridor; energy; agriculture;

water; education; domestic resource mobilization; and business environment. Under the BRN

initiative, a Presidential Delivery Bureau (PDB) has been established to assess implementation

progress of performance indicators for line Ministries.

1.2 Financing Allocated by the Country to Sectors Targeted by Bank Assistance: The

Government continues to prioritize water and sanitation in line with its poverty reduction

objectives. The share of water sector budget in the planned government spending has averaged

4% over the past three years. The share of Government funding in the water sector increased

from 51% in the 2013/14 budget to 66% in the 2014/15 budget. The Government has

consistently honoured its commitment in the funding of the Water Sector Development

Program by allocating requisite funding through annual budget allocations as indicated in Table

1 below:

TABLE 1: FINANCING OF WATER SECTOR IN TANZANIA

2013/2014 Budget 2014/15 Budget

Financing allocated to water sector UA 285 million UA 260 million Share of water sector in the budget 4% 4%

Source: Ministry of Finance

1.3 Country Budget Situation and Debt Level: The current budget situation is

summarized in Table 2 below, which portrays decline in the country’s dependence on external

financing of its budget. Over the past decade, about a third of the Government Budget was

dependent on foreign aid, in form of concessional loans and grants. However, the trend has

significantly reversed, and based on the recently released budget frame, concessional loans and

grants account for only about 12% of the total budget. Public debt stands at around 37% of

GDP and, based on the recent Debt Sustainability Analysis (DSA), both by the Government

and (Joint) IMF/World Bank, Tanzania’s debt remains sustainable, with low risk of debt

distress.

Page 35: PROJECT: ARUSHA SUSTAINABLE URBAN WATER AND SANITATION … · 2019-06-29 · iii Project Summary Project Overview: The objective of the Project is to provide safe, reliable and sustainable

VII

TABLE 2: BUDGET SITUATION

2014/15

Budget 2014/15

Current/Likely 2015/16

Budget Total Expenditure as % of GDP 23.4% 21.5% 23.9% Domestic Revenues as % of GDP 14.4% 12.8% 14.1% Share of Foreign Loans and Grants in total Budget 21% 15% 12% Share of General Budget Support in total Budget 7% 4% 4% Foreign Loans and Grants as % of GDP 7% 7% 6%

Source: Ministry of Finance

1.4 Country Initiatives: Interventions in the water sector are carried out under the WSDP,

which is jointly funded by the Government and Development Partners. The Government has

demonstrated commitment by allocating about a quarter of the resources for implementation of

the interventions under WSDP. The Government has allocated about UA 167.3 million for the

Program, and demonstrated leadership in the implementation of the program by disbursing the

full committed amount (121% of the commitment) – which was higher than disbursement of

foreign funds for the program.

Table 3: Disbursement status of WSDP 1 as of June 2014

Source Original commitment

USD

Revised commitment

-USD

Disbursement -

USD %

Tanzania Government 251,000,000 251,000,000 304,017,973 121%

Basket DPs 330,000,000 612,379,117 593,450,525 97%

Earmarked Donors 370,000,000 569,849,433 340,436,905 60%

Own Source 0 5,385,324 5,385,324 100%

Total 951,000,000 1,438,613,874 1,243,290,727 86%

2. Justification and conclusion

The Country’s fiscal outlook and debt sustainability is stable. The GOT has demonstrated its

commitment through its national and sector development programs and spending in critical

sectors such as infrastructure development in water and sanitation. Despite progress made to

date in increasing access and use in water and sanitation, investment in physical infrastructure

is not at a level to guarantee reliable and efficient delivery of services to the population. As

highlighted in the “Policy on Expenditure for Bank Group Financing”, the country’s

commitment should not only be measured by Government’s counterpart contribution but also

by the ownership and commitment to the overall development program as presented above.

Therefore, it is reasonable and justifiable to raise the Bank financing up to 90% of the total

Project costs.