Project Appraisal – Capital Budgeting Methods

Embed Size (px)

Citation preview

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    1/55

    Project Appraisal CapitalBudgeting Methods

    Dr. Janardhan G NaikM.com, LL.B, AICWA,Ph.D

    Cost Accountant and

    Professor, Head Dept of Accountancy

    Gogte College of Commerce,Belgaum 590 006 Karnataka State, INDIA

    Cell : (0091) 9448578089 Email:[email protected]

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    2/55

    Project Appraisal

    Based on the Techno-Economic Analysis,

    and other factors of detailed project report

    a Project Appraisal or capital budgeting orcapital expenditure or investment

    decisions are arrived.

    The decision is to select a particular

    project or not or which alternate project is

    the best to be selected

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    3/55

    Types of Investment Decisions

    Public SectorInvestment Decisions

    Private SectorInvestment Decisions

    Expansion of existing business

    Expansion of new business

    Replacement and modernisation

    Research & Development project

    Independent (accept or reject) investments Contingent investments

    Mutually exclusive investments

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    4/55

    Public Sector Investment Decisions

    1. By Administrative Ministry:

    1. If the project is within the ceiling of approvedbudget and plan provisions

    2. For Railway, Defense, Dept. of AtomicEnergy, Dept of Space, & Dept. ofElectronics, no budget ceiling.

    2. By Committee for Public InvestmentBoard (CPIB) if the project is above theceiling of approve budget and planprovisions

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    5/55

    Procedure

    Pre-Feasibility Report (PFR) evaluation (clearance orobjection) by Project Appraisal Division of the PlanningCommission, Dept. of Public Enterprises, Dept. ofEnvironment & Forest, Dept. of Plan Finance from

    different angles Techno-Economic Feasibility Report (TEFR) preparation

    if PFR is cleared, and submitted to Public InvestmentBoard through secretary of the Administrative Ministry forsecond stage clearance

    Detailed Project Report (DPR) prepared, if TEFR iscleared and submitted for clearance for PIB and also byCabinet Committee on Economic Affairs (CCEA)

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    6/55

    Private Sector Investment

    Evaluation Criteria In private Sector Board of

    Directors or Top management

    takes project decisions. Procedure ofInvestment Decisions:

    1. Estimation of cash flows

    2. Estimation of the required rate ofreturn (the opportunity cost of capital)

    3. Evaluation Criteria i.e. Application ofdecision rules to choose

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    7/55

    Investment Decision Rule

    Consider all cash flows to determine the true profitabilityof the project.

    Maximise the shareholders wealth.

    Choose among mutually exclusive projects whichmaximises the shareholders wealth.

    Rank projects according to their true profitability.

    Bigger cash flows are preferable to smaller ones andearly cash flows are preferable to later ones.

    Provide for an objective and unambiguous way ofseparating good projects from bad projects.

    Decision rules must be capable of application to anyinvestment project.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    8/55

    Components of Cash Flows

    Initial Investment

    Net Cash Flows

    Revenues and Expenses Depreciation and Taxes

    Change in Net Working Capital Change in accounts receivable

    Change in inventory Change in accounts payable

    Change in Capital Expenditure

    Free Cash Flows

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    9/55

    Components of Cash Flows

    Terminal Cash Flows

    Salvage Value Salvage value of the new asset

    Salvage value of the existing asset now

    Salvage value of the existing asset at the end of its

    normal

    Tax effect of salvage value

    Release of Net Working Capital

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    10/55

    Cash Flows - Types

    Conventional Cash flow has initial cash outlay

    followed by cash inflows. Conventional projects

    produce initial negative and subsequent positive

    cash flows, i.e. the initial outflow followed byinflows, i.e., + + + + +.

    Non-conventional cash flow has cash outlays

    mingled with cash inflows throughout the life ofthe project. Non-conventional investments

    produce cash flows of the pattern like,

    + + + + + + + + .

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    11/55

    Estimation of the Required Rate

    of Return (RRR) RRR may be cost of capital (after tax) or

    the opportunity cost of capital (after tax)

    After Tax because cash flows are takenpost tax.

    RRR would be used as the Discounting

    rate for cash flow.

    RRR is considered as cut off rate for

    project selection

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    12/55

    Evaluation Criteria

    1. Traditional or Non-discounted Cash Flow

    Criteria

    1. Payback Period (PB)a. Post pay back Cash flow / Profitability

    b. Bailout payback periodc. Discounted Payback Period (DPB)

    2. Payback reciprocal3. Accounting Rate of Return (ARR)

    2. Discounted Cash Flow (DCF) Criteria1. Net Present Value (NPV)2. Internal Rate of Return (IRR)

    3. Profitability Index (PI)

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    13/55

    Payback Period (PBP)

    Payback is the number of years

    required to recover the original cash

    outlay invested in a project. Calculation of payback is different

    for:

    Annual cash inflows are uniform or constant Annual cash inflows are unequal or varying

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    14/55

    Payback Period- constant annual

    cash inflows i.e. annuity The payback period canbe computed by dividing

    cash outlay by the

    constant annual cash

    inflow ie (annuity).

    E.g. A project requires

    an outlay of Rs 50,000

    and yields annual cash

    inflow of Rs 12,500 for 7years. What is the

    payback period ?

    0Initial InvestmentPayback = =Annual Cash Inflow

    C

    C

    Rs 50000PBP = -----------------

    Rs 12500PBP = 4 years

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    15/55

    Payback Period- Varying annual

    cash inflows Payback period can be foundout by adding up (cumulate)the cash inflows until the totalis equal to initial cash outlay.

    I) Project X requires a cashoutflow of Rs 20,000, &generates cash inflows of Rs8,000; 7,000; 5,000; and 4,000during the next 4 years. What isthe payback?

    Answer: At 3 yrs Rs 20000 = 20000

    II) If in 2nd year cash flow is6000, What is the new payback?

    Answer: At 3 yrs Rs 1900020000,

    3 years + 12 (1,000/4,000)months

    = 3 years + 3 months

    (I) Years Cash flow Cum Flow

    Cash out 0 -20000

    Cash inflow 1 8000 8000

    2 7000 150003 5000 20000

    4 4000 24000

    (II) Years Cash flow Cum Flow

    Cash out 0 -20000

    Cash inflow 1 8000 8000

    2 6000 14000

    3 5000 19000

    4 4000 23000

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    16/55

    Payback - Acceptance Rule

    Accept project if its payback period is

    less than the maximum orstandard

    payback period set by management. While in ranking alternate projects,

    highest rank for shortest payback period

    and lowest rank for highest payback

    period.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    17/55

    Payback Period Evaluation

    Merits:

    1. Simplicity

    2. Cost effective

    3. Short-term effects4. Risk shield

    5. Liquidity

    Demerits:

    1. Post payback Cash flows

    ignored

    2. Cash flow patterns (timing)irrelevant

    3. Terminal or scrap value

    ignored

    4. Inconsistent with shareholder

    value creation5. Aggregation of payback periods of

    all projects of the firm not possible

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    18/55

    Post Payback Cash flow/Profitability

    Project X has payback of 3 years when cash out =cash in, But postcash flow is just 4000 extra. Select on payback basis, but reject on

    post pay back cash flow. Project Y has payback of 3years + 12 x (2000/8000)months

    PBP = 3Yrs + 3 months. But post cash flow is Rs 6000 extra. Selecton post payback basis, although rejected on payback baisi

    Years Project X Project Y

    Cash flow Cum Flow Cash flow Cum Flow

    Cash outflow 0 -20000 -20000

    Cash inflow 1 8000 8000 5000 5000

    2 7000 15000 6000 11000

    3 5000 20000 7000 18000

    4 4000 24000 8000 26000

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    19/55

    Bailout Payback Period

    1. Consider salvage value at every years onassumption of termination of project

    2. Cumulate cash inflow along with salvage

    3. Payback period is that when cumulated cashinflow equal to cash outflow, Here below 3 yrs.

    Years Project M

    Cash flow Cum Flow Scrap Value Cum Flow +Scrap

    Cash outflow 0 -20000

    Cash inflow 1 6000 6000 8000 14000

    2 7000 13000 5000 18000

    PBP3 5000 18000 2000 20000

    4 4000 22000 1000 23000

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    20/55

    Discounted Payback Period (DPBP)

    Project N out flow Rs 4000, life 4 yr, K =10%

    YearCashinflow PVF10% DistdVal

    Cum DistdVal

    1 3000 0.909 2727 2727

    2 1000 0.827 827 3554

    3 1000 0.751 751 4305

    4 1000 0.683 683 4988

    Total PV Cash Inflow 4988

    Less Total PV Cash Outflow 4000

    NPV 988

    PBP (simple) = 2yrs

    Distd PBP = 2yr + 12(446/751) = 2yr 7 months

    Project M out flow Rs 4000, life 4 yr, K =10%

    YearCashinflow PVF10% DistdVal

    Cum DistdVal

    1 0 0.909 0 0

    2 4000 0.827 3308 3308

    3 1000 0.751 751 4059

    4 2000 0.683 1366 5425

    Total PV Cash Inflow 5425

    Less Total PV Cash Outflow 4000

    NPV 1425

    PBP (simple) = 2yrs

    Distd PBP = 1yr + 12(692/751) = 2yr 11 months

    The discounted payback period is the number of periods taken inrecovering the investment outlay on the present value basis.

    The discounted payback period still fails to consider the cash flowsoccurring after the payback period.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    21/55

    Reciprocal Payback (RP)

    Timing of cash flow and rate of return may be

    accommodated by taking reciprocal of payback

    Reciprocal payback = 1/Payack x 100

    = 1/3yrs x 100 = 33.3%

    RP is approximation of the internal rate of return

    (IRR) if the following two conditions are satisfied:

    The life of the project is large or at least twice the paybackperiod.

    The project generates equal annual cash inflows.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    22/55

    Accounting Rate of Return Method

    ARR is the ratio of theaverage after-taxprofit divided by the

    investment.1) ARR on average

    investment. Theaverage investment isequal to half of theoriginal investment.

    2) ARR on InitialInvestment

    2)

    Average After Tax Profit ARR = ---------------------------------

    Initial Investment

    1)Average After Tax Profit

    ARR = ---------------------------------Average Investment

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    23/55

    ARR Acceptance Rule

    Accept all those projects with ARRhigherthan the minimum rateestablished by the management

    Reject those projects which have ARRless than the minimum rate.

    Ranking a project as number one if it

    has highestARR and lowest rankwould be assigned to the project withlowest ARR.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    24/55

    Evaluation of ARR Method

    Merits:

    1. Simplicity

    2. Accounting data

    3. Accounting

    profitability

    Limitations:

    1. Cash flows ignored

    2. Time value ignored

    3. Arbitrary cut-off

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    25/55

    Net Present Value Method

    Based on realistic assumptions forecastproject cash flows.

    Select appropriate discount rate todiscount the forecasted cash flows.

    The appropriate discount rate is theprojects opportunity cost of capital.

    Present value of cash flows is found bymultiplying cash flow with PVF of theopportunity cost of capital, the discountrate.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    26/55

    NPV Formula

    Take sum of PV of cash inflow and cashout flow

    Difference between PV of Cash inflow andPV of Cash out flow is Net Present Value(NPV)

    The formula is :

    31 202 3

    0

    1

    NPV(1 ) (1 ) (1 ) (1 )

    NPV(1 )

    n

    n

    n

    t

    t

    t

    k k k k

    k!

    !

    !

    L

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    27/55

    Calculating Net Present Value

    ProjectXcosts Rs 2,500 now and is

    expected to generate year-end cash

    inflows of Rs 900, 800, 700, 600

    and 500 in 1 to 5 years of project

    life. The opportunity cost of the

    capital is 10%.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    28/55

    Calculating NPV(1.Formula method & 2.Table method)

    Project X out flow Rs 2500,

    life 5 yrs, K =10%

    Year Cash inflow PVF 10% Distd Val

    1 900 0.909 818

    2 800 0.827 662

    3 700 0.751 526

    4 600 0.683 410

    5 500 0.621 311

    Total PV Cash Inflow 2726

    Less Total PV Cash Outflow 2500

    NPV 226

    2 3 4 5

    1,0.10 2,0.10 3,0.10

    4,0.10 5,0.

    Rs 900 Rs 800 Rs 700 Rs 600 Rs500NPV Rs2,500

    (1+0.10) (1+0.10) (1+0.10) (1+0.10) (1+0.10)

    NPV [Rs 900(PVF )+Rs 800(PVF )+Rs 700(PVF )

    +Rs 600(PVF )+Rs500(PVF

    !

    !

    10)] Rs2,500

    NPV [Rs 900 0.909+Rs 800 0.826+Rs 700 0.751+Rs 600 0.683

    +Rs500 0.620] Rs2,500

    NPV Rs2,725 Rs2,500 +Rs225

    ! v v v v

    v

    !

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    29/55

    NPV Acceptance Rule

    Accept the project when

    NPV is positive NPV > 0

    Reject the project when

    NPV is negative NPV < 0

    May accept the project when

    NPV is zero NPV = 0

    Suitablitiy: For selecting one amongmutually exclusive projects; the one with the

    higher NPV should be selected.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    30/55

    Evaluation of the NPV Method

    Merits of NPV :Most acceptable investmentrule as it has below merits:

    1. Time value

    2. Suited for constant &even cash flows

    3. Measure of trueprofitability

    4. Considers flow overentire life

    5. Value-additivity6. Shareholder value7. Assumed to be reinvested

    at cost of capital

    Limitations:1. Not easy to find

    Discount rate

    2. Difficulties Cash flow

    estimation3. Ranking of projects

    1. Projects with unevenlife decisions

    2. Projects with uneven

    investment3. Mutually exclusive

    projects

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    31/55

    Internal Rate of Return (IRR)

    IRR is the rate that equates the present value of investment

    outlay with the present value of cash inflows over life of project.

    IRR implies that the rate of return is equal to the discount rate

    which makes NPV = 0. It is Discounted Rate of Return

    In the following equation, r is IRR when NPV= 0

    31 20 2 3

    01

    0

    1

    (1 ) (1 ) (1 ) (1 )

    (1 )

    0(1 )

    n

    n

    n

    t

    tt

    n

    t

    t

    t

    C CC CC

    r r r r

    CC

    r

    CC

    r

    !

    !

    !

    !

    !

    L

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    32/55

    Calculation of IRR

    a) When constant (annuity) cash flows

    b) When unequal cash inflow

    a) Constant (annuity) Cash Flows When annual cash inflows are constant IRR is equal to

    r of present value annuity factor (PVAF) for the life ofthe project (n) of mean cash flow.

    IRR = PVAF(n,r) {Cash outlay/Constant cash inflow)

    By referring to PVAF table for given n life of project,find r which is IRR, that produces zero NPV

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    33/55

    Constant (annuity) Cash Flows

    Project X outlay is Rs 18,000 and its annual cashinflow is Rs 6,000 for 5 years. What is IRR of X ?

    The IRR of the investment can be found out asfollows:

    NPV = Cash outflow Annuity cash inflow(PVAFn,,r)

    NPV = 18000 6000(PVAF 5,r) = 0

    PVAF 5,r = (18000/6000)= 3

    From PVAF table we find PVAF 5,r= 3, For 5 years, at

    20% from PVAF table it is 2.991, is nearer to 3. So thatis r = IRR.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    34/55

    Uneven Cash Flows

    IRR is found by Trial and Error Select any discount rate to compute the present value of

    cash inflows.

    If the present value of inflows is higher than the presentvalue of outflows, ie NPV is positive, a higher rate shouldbe tried.

    If the calculated present value of the expected cash inflowis lower than the present value of cash outflows, ie NPV isnegative, a lower rate should be tried.

    Repeat until net present value becomes zero or elseinterpolate between two rate causing positive and negativeNPV to find IRR when NPV = 0

    C

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    35/55

    Uneven Cash Flows(IRR is found by Trial and Error)

    Project Z needs Rs 60000 outlay and produces cashflow of Rs15000, 20000,30000 & 20000 in 4 years of life.Find IRR?

    IRR determination by Trial & Error (trial started with 14%, then 15% )

    Years Cash Inflow PVF 14% PV Cash flow PVF 15% PV Cash flow

    1 15000 0.877 13155 0.870 13050

    2 20000 0.769 15380 0.756 15120

    3 30000 0.675 20250 0.658 19740

    4 20000 0.592 11840 0.572 11440

    85000 60625 59350

    Less Cash ouflow -start of 1st year 60000 60000

    NPV = PV inflow - PV outflow 625 -650

    At 14% NPV is 625 and at 15% NPV is -650 So r lies between 14 - 15%

    By Interpolation r = 14% + 625/(625+650) x (15% - 14%)

    r = IRR = 14.50%

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    36/55

    Uneven Cash Flows(modified annuity method)

    IRR is found by modifying annuity method

    using average cash inflow

    Average cash inflow =(15000+20000+30000+20000)/4 =

    21250 NPV = Cash outflow Average cash inflow(PVAFn,,r) = 0

    NPV = 60000 - 21250(PVAF 4,r) = 0

    PVAF 4,r = (60000/21250)= 2.82

    From PVAF table we find PVAF 4,r= 2.82, For 4 years, at15% from PVAF table it is 2.85, is nearer to 2.82. So try

    with 15% to get IRR.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    37/55

    NPV Profile Graph to find IRR

    Cash inflow

    Annuity

    PVAF(6,r) NPV

    5430 1% 11472

    5430 5% 75615430 10% 3649

    5430 15% 550

    5430 16%IRR 0

    5430 20% (1942)

    5430 25% (3974)

    Initial outlay Rs 20000, life 6 Yrs

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    38/55

    Acceptance Rule of IRR

    Accept the project when r> k.

    Reject the project when r< k.

    May accept the project when r= k.

    Kis cost of capital (WACC)

    Ranking based on highest IRR first, and last

    for lower IRR

    In case of independent projects, IRR and NPVrules will give the same results if the firm has

    no shortage of funds.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    39/55

    Evaluation of IRR Method

    Merits: Time value of money

    Profitability measure forentire life

    Determination ofopportunity cost ofcapital not prerequisite

    Uniform ranking as IRRis in %

    Acceptance rule

    Shareholder valuemaximised

    Limitations:

    1. Multiple rates

    2. Mutually exclusiveprojects

    3. Different projects IRRcant be added

    4. Assumed to be reinvestedat IRR which may notmatch cost of capital

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    40/55

    NPV Versus IRR

    1. Reinvestment Assumption

    2. Varying Opportunity Cost of Capital

    3. Conventional Independent Projects Ranking

    4. Lending and borrowing-type projects

    5. Problem of Multiple IRRs (non-conventional)

    6. Ranking of Mutually Exclusive Projects

    7. Timing of Cash Flows8. Scale of Investment

    9. Project Life Span

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    41/55

    Reinvestment Assumption

    The IRR method assumes that the cash

    flows generated by the project can be

    reinvested at its internal rate of return,

    The NPV method assumes that the cash

    flows are reinvested at the opportunity

    cost of capital.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    42/55

    Varying Opportunity Cost of

    Capital There is no problem in using NPVmethod when the opportunity cost of

    capital varies over time.

    If the opportunity cost of capital varies

    over time, the use of the IRR rule

    creates problems, as there is not a

    unique benchmark opportunity cost ofcapital to compare with IRR.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    43/55

    Conventional Independent Projects

    Conventional Independent Projects which

    are economically independentof each

    other, NPV and IRR methods result in

    same accept-or-reject decision if the firm

    is not constrained for funds in accepting

    allprofitable projects.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    44/55

    Lending or borrowing-type projects

    (Both are conventional projects)

    Project R is a lending type, which involves initial outflow Rs 1000,followed by inflow of Rs 1200 over one year life.

    This has NPV 91 positive, Accepted. But IRR = 20%

    Project Q is a borrowing type, where there is initial inflow of Rs 1000,followed by outflow of Rs 1200 at first year end of life.

    This has NPV -91, Rejected.

    But IRR = 20% for both Q and R. Choose any project on IRR basis.

    Borrowing type Project Q yr end outflow Rs 1200, life 1 yr, K =10%

    Year Cash outflow PVF 10% Distd Val

    1 1200 0.909 1091

    Total PV Cash outflow 1091

    Total PV Cash inflow yr0 1000

    NPV -91

    IRR comes to 20%

    Lending type Project R out flow Rs 1000, life 1 yr, K =10%

    Year Cash inflow PVF 10% Distd Val

    1 1200 0.909 1091

    Total PV Cash Inflow 1091

    Less Total PV Cash Outflow 1000

    NPV 91

    IRR comes to 20%

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    45/55

    Problem of Multiple IRRs

    (non-conventional)

    A project may have

    both lending and

    borrowing features

    together (non-conventional).

    IRR method can yield

    multiple internal rates

    of return because of more than one change

    of signs in cash flows is

    possible here.

    P Rs

    -

    -

    -

    iscount Rate ( )

    P (Rs)

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    46/55

    Ranking of Mutually Exclusive Projects

    The NPV and IRR rules give conflicting rankingto the projects under the following conditions: The cash flow pattern of the projects may differ. That is,

    the cash flows of one project may increase over time,while those of others may decrease orvice-versa.

    The cash outlays of the projects may differ.

    The projects may have different expected lives.

    Investment projects are said to be mutually exclusive

    when only one investment could be accepted andothers would have to be excluded.

    Two independent projects may also be mutuallyexclusive if a financial constraint is imposed.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    47/55

    Timing of Cash Flows

    Cash Flows (Rs) NPV

    Project C0 C1 C2 C3 at 9% IRR

    M 1,680 1,400 700 140 301 23%

    N 1,680 140 840 1,510 321 17%

    Both projects are lending type, with initial outlay

    of Rs 1680, with life of 3 yrs, and K at 9%.

    But their NPV at 9% are different, Select N

    But their too IRR differ. On IRR basis accept M

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    48/55

    Scale of Investment

    Ca sh Flo w (Rs) NPV

    Projec t C0 C1 at 10% IRR

    A -1,000 1,500 364 50%

    B -100,000 120,000 9,080 20%

    Both projects are lending type. But initial outlayof A is Rs 1000, while B is Rs 100000. But life of

    both is 1 yr, and K at 10%. But their NPV at 10% are different, Select B

    But their IRR too differ. On IRR basis accept A

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    49/55

    Project Life Span

    Cas lo s( s)

    Project C0 C1 C2 C3 C4 C5 PV at 10% I

    X

    10,000 12,000 908 20Y 10,000 0 0 0 0 20,120 2,495 15%

    Both projects are lending type with same initialoutlay of Rs 10000. But life of X is 1 yr and of Y

    is 5yrs. K at 10%. But their NPV at 10% are different, Select Y

    But their IRR too differ. On IRR basis accept X

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    50/55

    Modified Internal Rate of

    Return (MIRR) The modified internal rate of return (MIRR)

    is the compound average annual rate that is

    calculated with a reinvestment rate different

    than the projects IRR.

    Modified internal rate of return is the

    compound average annual rate that is

    calculated with a reinvestment rate different

    than the projects IRR.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    51/55

    Profitability Index

    Profitability index is the ratio of the

    present value of cash inflows, at the

    required rate of return, to the initial cash

    outflow of the investment.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    52/55

    Profitability Index

    It is time adjusted method, also known asbenefit-cost ratio

    Sum ofPresentValue ofCash inflows

    PI = ----------------------------------------------------Sum ofPresentValue ofCash outflows

    Net Present Value PI (Net) = ----------------------------------------------------

    Sum of Present Value of Cash outflows

    PI (Net) = (PI - 1)

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    53/55

    Profitability Index

    The initial cash outlay of M project is Rs 1,00,000 and itcan generate cash inflow of Rs 40000, 30000, 50000and 20000 in year 1 through 4. Opportunity cost ofcapital is10%. Calculate PI.

    .1235.11,00,000Rs

    1,12,350RsPI

    12,350Rs100,000Rs112,350RsNPV

    0.6820,000Rs+0.75150,000Rs+0.82630,000Rs+0.90940,000Rs

    )20,000(PVFRs+)50,000(PVFRs+)30,000(PVFRs+)40,000(PVFRsPV 0.104,0.103,0.102,0.101,

    !!

    !

    vvvv

    !

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    54/55

    Acceptance Rule

    The following are the PI acceptancerules: Accept when PI > 1 or PI (net) is +Ve

    Reject when PI < 1 or PI (net) is -Ve May accept PI = 1 or PI (net) is 0

    The project with positive NPV will havePI greater than one. PI less than meansthat the projects NPV is negative.

  • 8/6/2019 Project Appraisal Capital Budgeting Methods

    55/55

    Evaluation of PI Method

    Merits

    Time value of money.

    Shareholder valuemaximisation.. A project

    with PI > 1 will havepositive NPV and ifaccepted, it will increaseshareholders wealth.

    Relative measure of aprojects profitability - as

    the present value of cashinflows is divided by theinitial cash outflow

    Limitations:

    PI criterion requirescalculation of cash flowsand

    Estimate of the discountrate.

    In practice both are poseproblems in estimation.