133
PROJECT ANAYSIS AND PROJECT ANAYSIS AND PLANNING PLANNING

Project Analysis and Planning

Embed Size (px)

Citation preview

Page 1: Project Analysis and Planning

PROJECT ANAYSIS AND PROJECT ANAYSIS AND PLANNINGPLANNING

Page 2: Project Analysis and Planning

ObjectivesObjectivesMain Objective: • To deepen participants’ knowledge and skills in the Analysis,

design & management of development projects.

Learning Outcomes:At the end of the course, participants will be able to:• Use the Logical Framework as a tool for project planning and

monitoring• Undertake stakeholder analysis• Undertake investment analysis • Undertake technical analysis of projects• Undertake environmental impact assessment

Page 3: Project Analysis and Planning

Achieving the Intended OutcomeAchieving the Intended Outcome• To achieve the learning outcomes, there will

be a combination of lectures, case studies and group discussions

• Class assignments are a very important component of the learning package

• The lectures provide the basic framework for the module and should be supplemented by further reading of the professional literature.

Page 4: Project Analysis and Planning

ReferencesReferences• Rory Burke: Project Management-Planning

and Control Techniques

• P. Belli, J.R. Anderson, H.N. Barnum, J.A. Dixon and Jee-Peng Tan, Economic Analysis of Investment Operations, First Published 2001, World Bank Institute, ISBN0821348507.

• D. Potts, Project Planning and Analysis for Development, First Published 2002, Lynne Reinner Publishers, ISBN1555876560.

Page 5: Project Analysis and Planning

What is a Project?What is a Project?• A project is any series of interrelated activities or

tasks that have to be accomplished within a specified time frame to achieve well defined objectives.

• Specific package of investments, policies, institutional reforms and other actions designed to designed to achieve a specific development objective or set of objectives within a designated period of time (W. B)

• A project can vary in size & complexity from a simple intervention like drilling a borehole, to a complex endeavour like design & production of a new aircraft.

Page 6: Project Analysis and Planning

Development projectsDevelopment projects

• A dev’t. project can be described as a specific task or set of activities designed to take place within a specified timeframe in order to improve the living standards or socio-economic life of a people.

• A development project may consist of investments in the following:– construction or civil works,– Provision of socio-economic services– Institutional strengthening

• Focus will be on social & construction projects

Page 7: Project Analysis and Planning

Characteristics of a ProjectCharacteristics of a Project

• Set of activities or tasks

• Has time-frame (defined start & end time)

• Has well defined objective (s)

• Has cost constraints

• Unique (may never be repeated the same way by the same group of people.)

Page 8: Project Analysis and Planning

Projects and OperationsProjects and Operations• Organizations perform work, which generally

involves operations or projects.• Operations & projects have similar

characteristics:– Performed by people,– Constrained by limited resources– Planned executed and controlled

• Although the two may overlap, the main difference is that operations are ongoing (permanent) & repetitive activities to deliver products & services, whilst projects are temporary and unique.

Page 9: Project Analysis and Planning

Projects and Operations Cont’d.Projects and Operations Cont’d.

• The temporary nature of projects stands in contrast with business as usual (or operations)

• Once a project is completed, it is either dissolve or turned into a normal on-going organization

Page 10: Project Analysis and Planning

Why Undertake Projects?Why Undertake Projects?

• To meet some development need or problem, such as lack of potable drinking water, deforestation etc.

• To take advantage of some opportunities.• To satisfy an interest.• Note: Projects can generate innovative, locally

adjusted solutions that can be up-scaled to accelerate development process.

Page 11: Project Analysis and Planning

What is Project PlanningWhat is Project Planning• Project planning is concerned with making rational

decisions or choices among alternative projects or interventions that would optimize the benefits to a society or group.

• It involves identifying priority needs & opportunities, setting clear objectives and the most appropriate interventions to accomplish those objectives as well as working out the human and material resources needed.

• The various stages of planning may be linked to the project cycle as captured in the next slide.

Page 12: Project Analysis and Planning

EVALUATION

FORMULATION(design)

IMPLEMENTATION(Scheduling, control, monitoring etc)

IDENTIFICATION (Conception)(Assessment of needs & opportunities)

The Traditional Project Cycle

APPRAISAL

Page 13: Project Analysis and Planning

Project Identification PhaseProject Identification Phase

• At this stage, an idea to address some problem or take advantage of some potential is identified.

• This idea is usually hatched through discussions with specialists and local community leaders

• Projects can be conceived based on the following:– Needs, such as basic materials and services to a

community that should be fulfilled– Market demand- domestic or overseas that should be

taken advantage of– Resource availability– Political consideration

Page 14: Project Analysis and Planning

Project Formulation (design)Project Formulation (design)

• At this stage, project objectives are defined and alternative solutions described.

• The alternative solutions are assessed to ascertain their feasibility in relation to technical, economic, social & environmental dimensions, & best options selected

• This requires collection and analysis of relevant data (information)

• For complex projects details feasibility studies are done, which may involve technical surveys, drawings, etc.

Page 15: Project Analysis and Planning

Project Cycle Contd.Project Cycle Contd.– Appraisal: For complex projects, or projects with high

investments, further feasibility studies are done. – This involves critical review & verification of all aspects of

the project to guarantee success. Usually done by third party (funding agency). May be followed by negotiations & approval of the Project

– Implementation: Executing the project to realize its objectives: preparing work plans; physical construction, procurement, recruitment, setting up institutions, managing people, monitoring activities.

An aspect of implementation is the project control, which seeks to keep the project on-track, on-time and within budget

Page 16: Project Analysis and Planning

Project cycle cont’d.Project cycle cont’d.

– Evaluation: Assessment of project effectiveness, efficiency, relevance and impact, so as to draw lessons to guide the way forward.

• Note: The breakdown and terminology of these phases differ, depending on type of project

Page 17: Project Analysis and Planning

PROJEC PLANNING-USING THE PROJEC PLANNING-USING THE LOGICAL FRAMEWORK APPROACHLOGICAL FRAMEWORK APPROACH

• The logical framework (Logframe) is an analytical tool used for the design, execution and evaluation of projects

• It derives its name from the Logical linkages set out by the planner(s) to connect a project’s means with its ends

• The key features of the project is summarized in a matrix highlighting the cause –effect logic or “If/Then” (If we supply farmers with improved seeds and assume there is adequate rainfall, then production will be increased.

Page 18: Project Analysis and Planning

Logical Framework MatrixLogical Framework Matrix

NARRATIVE SUMMARY

PERFORMANCE INDICATOR

MEANS OF VERIFICATION

ASSUMPTION

GOAL:

PURPOSE:

OUTPUT:

ACTIVITY: INPUTS

Page 19: Project Analysis and Planning

The Logical Framework Matrix Cont’d.The Logical Framework Matrix Cont’d.

• The Logical Framework Matrix provides answers to the following questions of a project: – WHY: a project is carried out– WHAT: the project is expected to achieve?– HOW: the project is going to achieve these

results?– WHICH: external factors are crucial for its success?– HOW: we can assess project success?– WHERE: we can find data required to assess its

success– WHAT: the project will cost

Page 20: Project Analysis and Planning

LogframeLogframeNARRATIVE SUMMARY

PERFORMANCE INDICATOR

MEANS OF VERIFICATION

ASSUMPTION

GOAL:Health Status of Rural Population Improved

PURPOSE:Health Services Expanded and Utilized by rural population

OUTPUT:1.Clinics Constructed

2. Primary Health Staff Trained and Posted

ACTIVITY:1.1 Locate site for the construction

1.2 Clearing of site

Page 21: Project Analysis and Planning

Logframe - GoalLogframe - Goal

• The Goal is the strategic or development objective, that the project combined with others will achieve

• This is the sector goal or broad objective to which the project contributes

• It is fairly broad in scope like ‘increased annual income of farmers’.

• It is usually stated in a positively achieved future condition.

Page 22: Project Analysis and Planning

Purpose or Immediate ObjectivePurpose or Immediate Objective• The Purpose is the result expected at the end of the

project execution period. • It is the change that the project will foster or what

would occur after producing & utilizing the outputs? • It is often the change in behaviour of project

beneficiaries or their response to the project. E.g what will farmers do differently if improved seeds are provide? This will be stated as: “Food production increased”

•  The Purpose is rationale for the project & an important cause of the Goal.

• The title of the project should come directly from the statement of the Purpose

Page 23: Project Analysis and Planning

Project Purpose Cont’d.Project Purpose Cont’d.• The logical framework requires that each project

have only one Purpose, so as to ensure clarity • If there is more than one Purpose there is ambiguity,

and trade-offs can arise • Furthermore, experience shows that it is easier to

focus project outputs on a single Purpose since multiple Purposes diffuse project efforts & weaken the design

• In practice, however, the logframe of a complex programme may have different sub-projects each with a purpose and outputs

Page 24: Project Analysis and Planning

Project OutputsProject Outputs

• These are the specific products and services generated from the project activities

• These are the desired results generated from the project activities

• The outputs should bring about the project purpose • Examples of Outputs:

– “ Clinics Constructed”– “50 farmers acquired knowledge and skills in

improved farming methods” • Project implementers are held accountable for

achievement of project outputs.

Page 25: Project Analysis and Planning

OutputOutput Purpose Goal Purpose Goal

GOAL: Health Status of Rural Population Improved”

PURPOSE: Health Services Expanded and Utilized by Rural Population”

OUTPUTS:• Clinics Constructed

• Primary Health Care Staff Trained and Posted” 

Page 26: Project Analysis and Planning

THE OBJECTIVE PYRAMIDTHE OBJECTIVE PYRAMID

INCREASED INCOME

IIMPROVED AGRICULTURAL

PRODUCTION

SEED CREDIT EXTENSION

Page 27: Project Analysis and Planning

The ActivitiesThe Activities

• The activities describe what the implementers will do or how they will carry out the project to achieve the outputs.

• Example: For the output – “50 Farmers trained in modern farming practices”,

• the activities will include:– Develop training materials– Conduct training– Evaluate training.

Page 28: Project Analysis and Planning

Performance IndicatorsPerformance Indicators• Indicators define in measurable detail the

performance levels or evidence that a goal, purpose or output is achieved.(How much, how well, timeframe etc.)

• Indicators tell us how to recognize successful accomplishment of results (outputs, purpose & goal)

• The basic principle of the column is ‘if you can measure it, you can manage it?’.

Page 29: Project Analysis and Planning

Means or Sources of VerificationMeans or Sources of Verification

• These describe the sources of information that will demonstrate what has been accomplished. They tell us:– Where to get the evidence that the objectives have

been met– Where we can find the data necessary to verify the

indicator • Important questions include:

– How available are the means of verification?– How reliable are the sources?– Is special data gathering required? If so what will it

cost?

Page 30: Project Analysis and Planning

Assumptions/RisksAssumptions/Risks• Assumptions are the external conditions that must exist if

the project is to succeed.• They are statements about the uncertain or risky factors

between each of the levels in the Hierarchy of Results. • They may describe important natural conditions, such as

– “25 millimeters of rain falls between May and October,” or factors such as

– “No labor strikes during start up of project,” – “Community transportation systems can handle weekly

shipments,” – “Timely release of budget,” – “Crop prices remain stable,” – “Farmers willing to try new methods, “etc.

Page 31: Project Analysis and Planning

Assumptions cont’d.Assumptions cont’d.

• Assumptions complete the if/then logic (describing the necessary conditions between each level) by adding the if/and/then logic (describing the necessary and sufficient conditions between each level).

• Determine the Assumptions by asking; what conditions must exist in addition to my Purpose (or Activities, Output, Purpose, Goal) in order to achieve the next level?

Page 32: Project Analysis and Planning

ExerciseExercise

• Indicate the cause and effect relationship with each set of statements by labeling them with ‘’1,2,3,4’’ beginning with ‘’1’’ as the first cause.

• ______ Increased small farmer income.• ______ Distribute the seeds.• ______ Standard of living in the rural areas raised

• ______ Potable water available to 60% of the villages in the southern region

• ______ Sickness due to water impurities decreased in the southern region

• ______ Choose the sites for the water purification systems.• ______ Water purification systems in operation.

Page 33: Project Analysis and Planning

____Recruit extension personnel.

• ______ Total cereals production increased.• ______ Extension program operational.• ______ Rice production increased.

4______ Design refresher course for health personnel.______ Health units meet medical needs of local

population.______ Rates of morbidity and mortality decreased.______ Medical skills of health personnel upgraded

Page 34: Project Analysis and Planning

Processes that precede LogframeProcesses that precede Logframe

• A Situational Analysis is carried out which comprises of:– Problem Analysis– Objective Analysis and – Stakeholder Analysis

Page 35: Project Analysis and Planning

Problem AnalysisProblem Analysis• Planners often use problem tree analysis technique

to identify all the problems surrounding a given problem and arranging these in a cause-effect relationship

• A problem tree approach can also be used to diagnose root-causes of various problem including organizational ones

• The problem analysis begins by identifying a core problem ( the trunk). The tree is then expanded upwards and downwards by continousily asking the following questions;– What is the cause of this problem?– What is th e effect of the problem?

Page 36: Project Analysis and Planning

• To enrich the discussions and analysis, it is desirable to identify major interest groups ( those affected or involved) in the project and involve them

• Capture the diverse perspectives as to the causes and effects of each identified problem

• Arrange the problems & their effects in logical cause –effect manner as shown in the next slide

Page 37: Project Analysis and Planning

Example of problem treeExample of problem tree

DecliningCoconut

Production

Coconut palms increasingly

affected by virus diseases

Farmers do not plant new coconuts

Farmers rarely apply plant protection measures

Traditional varieties

susceptible to virus

Farmers do not have access to more resistant

varieties

Farmers lack capital to buy

inputs

Farmers don’t know how to apply new varieties and

related inputs

Producer prices not attractive for

farmers

No localnurseries

Resistant varieties not available on

local markets

Mobility of extension

service severely restricted

Extension service

concentrates only on food

crops

Effective protection

measures very complex

Traditional protection rather

ineffective

Declining income of farmers

Declining national supply of fresh coconut

oil

No more exports of coconut products

Page 38: Project Analysis and Planning

Objective tree analysisObjective tree analysis

• The problem tree so constructed can be converted into an objective tree by rephrasing the problems into future desired states

• This is captured in the next slide

Page 39: Project Analysis and Planning

Example of objective treeExample of objective tree

IncreasedCoconut

Production

Reduced occurrence of

pests and diseases

Farmers increasingly plant new coconuts

Effective pest and disease

control system in place

Access to needed inputs

guaranteed

Farmers‘knowledge on improved coconut

cultivation practices enhanced

Government price policy favorable

for coconut production

Credit facilities for input

procurement by farmers

Import restrictions for

essential inputs removed

Capable extension staff

Effective extension

strategies for coconuts

Effective input supply system in

place

Increased income of farmers

Increased national supply of fresh

coconut oil

Exports of coconut products resumed

Sufficient capacities of

extension service

Page 40: Project Analysis and Planning

STAKEHOLDER ANALYSIS (SA)STAKEHOLDER ANALYSIS (SA)• Stakeholders are persons, groups or

institutions with interests in a project or programme.

• Primary stakeholders are those ultimately affected, either positively (beneficiaries) or negatively

• Secondary stakeholders are the intermediaries in the aid delivery process.

• This definition of stakeholders includes both winners and losers, and those involved or excluded from decision-making processes.

Page 41: Project Analysis and Planning

STAKEHOLDER ANALYSIS (SA)STAKEHOLDER ANALYSIS (SA)• This is the identification of key stakeholders of a

project and their interests and power differentials to influence the outcome of the project

• stakeholder analysis can:– draw out the interests of stakeholders in relation to

the problems which the project is seeking to address– identify conflicts of interests between stakeholders,

which will inform assessment of a project‘s– help to identify relations between stakeholders which

can be built upon, and may enable "coalitions" of project sponsorship, ownership and cooperation

– help to assess the appropriate type of participation by different stakeholders, at successive stages of the project cycle.

Page 42: Project Analysis and Planning

Stakeholder matrixStakeholder matrix

STAKEHOLDERS INTERESTS (expectations & fears)

Power or influence on Project 1) Primary

a) Beneficiaries

b) Negatively affected groups

c) Implementing agencies

2) Secondary

a) Policy makers

b) Donor

c)

Page 43: Project Analysis and Planning

Stakeholders Interests and Power Stakeholders Interests and Power Differentials.Differentials.

Keep Satisfied Engage Closely & Influence Actively

INTEREST HighLow

High

POWER

Monitor (Minimum effort)

Keep Informed

Page 44: Project Analysis and Planning

ASSIGNMENTASSIGNMENT

• Your situational analysis revealed that the rampant violent conflicts in districts X and Y are due to the following underlying causes, as shown in the next slide

Page 45: Project Analysis and Planning

Assignment cont’dAssignment cont’d

Rampant violent conflicts

Poor natural resource management

Poor democratic culture

Unfair benefit sharing

OverlappingLand

ownership

Weak Admin. system

Non-transparent

Electoral process

Political opponents as enemies

Page 46: Project Analysis and Planning

Assignment cont’d.Assignment cont’d.

• TASK:– Undertake further analysis development of the

problem tree on conflicts in the two districts and outline project proposal to address this problem. The proposal should capture the goal, intermediary objective (s), short term objectives and their indicators as well as the proposed activities.

– Summarize the proposal in a logframe.

Page 47: Project Analysis and Planning

Techniques in Project AnalysisTechniques in Project Analysis

• Various appraisal techniques are usually employed in project planning to decide on the merit of a project and to enhance its effectiveness, efficiency and sustainability

• The various dimensions of project analyse include: – Technical Analysis– Economic Analysis– Social Analysis– Environmental Impact Assessment

Page 48: Project Analysis and Planning

Technical Analysis of ProjectsTechnical Analysis of Projects• Technical Analysis involves two things:

i. Determination (measurement) of some technical parameters that are fundamental to effective project design & implementation e.g yield of crop or capacity of machinery. Based on these measurements, determine soundness of the project.

ii. Examination of the linkages and inter-relationship between various technical components of a project. E.g linkages between animal breed, feeding, health & housing.

Page 49: Project Analysis and Planning

4949

Why Undertake Technical Analysis? Why Undertake Technical Analysis?

• To establish project technical feasibility

• To provide a basis for making tentative choices among technological alternatives.

• To ensure that technical estimates or projections are realistic.

• To align technical design with project requirements or objectives (e.g meeting budgetary and socio-cultural requirements)

• To improve efficiency of operations.

Page 50: Project Analysis and Planning

5050

Why Technical Analysis (2)Why Technical Analysis (2)

• To provide a basis for monitoring project performance. E.g technical estimates and projections on crop yields can serve as indicators to monitor project performance

• To minimize risk by providing knowledge and visibility of some critical issues that would influence project viability. E.g some missing linkages made visible.

Page 51: Project Analysis and Planning

5151

ELEMENTS OF TECHNICAL ELEMENTS OF TECHNICAL ANALYSISANALYSIS

• Elements of technical analysis will vary from project to project.

• For example, an agricultural project will tend to focus on issues like soils, vegetation & climate, while an industrial project will focus on quality of machinery and equipments, costs, building plans and technology, etc.

Page 52: Project Analysis and Planning

5252

Elements of T.A ContinuedElements of T.A Continued

• However, there are common elements of technical analysis relevant to most projects. These are:

– Appropriateness of technology.

– Scale of operation,

– Location and layout of the project.

Page 53: Project Analysis and Planning

5353

Common Elements of T.ACommon Elements of T.A

i. Choosing the Right Technology

• Technological analysis is done by generating technological alternatives that are evaluated based on some critical factors or questions:

– Is the technology suitable for the realization of the specific objectives of the project?

Page 54: Project Analysis and Planning

5454

Elements of T.A Cont’d.Elements of T.A Cont’d.

– Is the technology feasible within the physical limitations of the site? For example, small power tillers may not be able to till heavy soils.

– Is the technology consistent with the general socio-economic conditions of the area?

– Is the cost of the technology within budget constraints?

Page 55: Project Analysis and Planning

5555

Elements of T.A Cont’dElements of T.A Cont’d

– Is there local capacity to operate and maintain the technology effectively? If not is it possible to build such capacity in the short run?

– Is the quality of machinery and equipment reflecting value for money?

– Is the technology environmentally sound?

Page 56: Project Analysis and Planning

5656

ii Scale of Operationii Scale of Operation• This is analysed with reference to the

following issues, among others:– Are there sufficient raw materials or other vital

inputs to justify the scale of operation?– Is the scale of operation consistent with the

technological choice?– Will the prevailing physical limitations allow for

the proposed scale of operation? – Is there market for the level of output?

Page 57: Project Analysis and Planning

5757

iii. iii. Location & layout of the projectLocation & layout of the project• Project location analysis may consider:

– Availability of raw materials– Access to labour– Transportation problems– Access to markets– Available government concessions for locating

projects in some places– Environmental & geo-physical constraints– Availability of basic infrastructure or utility

services

Page 58: Project Analysis and Planning

5858

Note:

• choice of project location will be determined by type of project. E.g a project for agro-forestry will consider different parameter than a pastoral project.

• The selection of site may involve a trade- off among various considerations like proximity to source of raw materials, market, infrastructure facility and access to labour.

Page 59: Project Analysis and Planning

5959

LayoutLayout

• For industrial projects, the lay out of the plant facilities is also critical so as to improve operational process (way of doing things) and cost efficiency.

• ( See Flow Chart on Technical Analysis)

Page 60: Project Analysis and Planning

6060

Analysis of Technical Feasibility.Analysis of Technical Feasibility.

• The following methods may be used:

i. Technical Surveys: Depending on the project, different types of surveys may be conducted to evaluate some parameters:

• Soils survey: to determine soil structure, nutrients and suitability.

• Topographic surveys: to design drainage system or for irrigation dev’t.

• Hydro-geological surveys to evaluate rock types & ground water.

Page 61: Project Analysis and Planning

6161

ii. Use of Historical Records: Historical records may be used to evaluate environmental factors, incidence of pests and diseases etc.

iii. Field Trails: This may be necessary to verify yields and other information. Some machinery or equipment may also be tried to ascertain their suitability.

iv. Field Interviews: Knowledge about the socio-cultural realities of people in the project area may be assessed through field interviews and direct observations

Page 62: Project Analysis and Planning

Investment AnalysisInvestment Analysis• Investment analysis is about choosing among

various investment options that are competing for our limited resources

• Projects require initial investments of scarce resources & the project will yield a stream of benefits over a period called the project life.

• A the same time, in order to sustain the benefits, a stream of costs called the operating costs will be generated.

• These project costs and benefits must be identified and valued (cost –benefit analysis), based on which the most beneficial project is selected from others

Page 63: Project Analysis and Planning

Investment Analysis Cont’d.Investment Analysis Cont’d.

• In Assessing the worth of a project or investments (be it public, private or business concerns) consideration is given to: – the size of the outflows and inflows of funds– the lifespan of the investment, – the degree of risks attached and – cost of obtaining funds.

Page 64: Project Analysis and Planning

Investment Analysis cont’d.Investment Analysis cont’d.

• Careful project analysis will point out unrealistic or questionable assumptions and indicate ways to modify the project so as to enhance the benefits

• A project carefully analysed has better chances of being implemented on time and yield the desired benefits

Page 65: Project Analysis and Planning

Financial Vrs Economic analysisFinancial Vrs Economic analysis• Projects can be appraised from the viewpoint of the

project’s beneficiary or loser ( financial analysis) or from the viewpoint of the whole society (economic analysis)

• Financial analysis seeks to answer the question: “Is the project financially profitable to a given individual, group or business?”

• Here costs & benefits are valued at market prices• Financial analysis is important to check if project is

financially sustainable whether cash flow will be sufficient to meet commitments

Page 66: Project Analysis and Planning

Financial Vrs Economic analysis Cont’dFinancial Vrs Economic analysis Cont’d

• Economic Analysis seeks to answer the question: “Is the project profitable to the society or the target population as a whole? What is its impact in areas like job creation & linkages with other sectors?”

• In Economic Analysis, costs and benefits are valued at shadow (efficiency or accounting) prices

Page 67: Project Analysis and Planning

Financial Vrs Economic analysis Cont’dFinancial Vrs Economic analysis Cont’d

• The main sources of the difference between financial and economic analysis are:

i. Market imperfections: market values are equivalent to social values only under conditions of perfect competition

ii. Externalities: A project may have benficial or detrimental external effects beyopund the project environment. E.g A road benefits not only the project target group but also neighboring area

iii.Taxes & Subsidies: In financial analysis, ( private point of view) taxes are costs and subsidies are finacial gains, but in economic naluysis ( social point of view), taxes and subsidies are only transfer payments, without any relevance to the projects outcome

Page 68: Project Analysis and Planning

Financial Vrs Economic analysis Cont’dFinancial Vrs Economic analysis Cont’d

iv. Concerns for savings: From the private point of vie (financial analysis) consumption & savings are treated equally, but in capital-scarce developing countries, the two should be valued differently (economic analysis)

v.Concern for Redistribution: Private firms are not concerned about the way their benefits are distributed across various groups in the society but this is important from the social point of view

Note: Initial section will focus on Financial Analysis

Page 69: Project Analysis and Planning

Investment Analysis cont’d.Investment Analysis cont’d.• The steps for investment decisions are:

i. Setting objectives that we wish to achieve by means of our investment

ii. Examining alternative means of achieving the set objectives

iii. Predicting the consequences of each alternative path to the desired objective

iv. Evaluation of alternatives

v. Selecting best alternative & making the expenditure (decision making)

vi. Monitoring Project(s)

Page 70: Project Analysis and Planning

Investment decision procedureInvestment decision procedureIndividual Company Public Entity

Objective Maximize annual profit

Profit & market expansion Increased capacity of Port

Alternative ways Stocks or Bonds or combination

-New trucks & warehouses - Expanded sales program-New product line

-New docking facilities with 7, 8 or 9 berths

Consequences of each Alternative

-12% pa. for bondStocks: Predicted with less accuracy

- How much cost & how much profit from each alternative

7, 8 or 9 berth will involve different costs & benefits

Evaluation of Alternatives

Compare NPV for each alternative

Compare cash flow NPV, IRR for each alternative

Compare Benefit: Cost Ratio for each alternative

Selecting or decision-making

Page 71: Project Analysis and Planning

Investment Appraisal MethodsInvestment Appraisal Methods

• Investment appraisal methods mainly focus on weighing project benefits against the costs, using financial and economic analyses.

• The various methods used to decide the merits of projects include:– Non-discounted methods like Payback period & Average

Rate of Return (ARR)

– Discounted cash flow methods like NPV, Benefit-Cost Ratio & IRR

Page 72: Project Analysis and Planning

Payback PeriodPayback Period• The pay-back method computes the time or

number of years it takes to recover the initial outlay from earnings generated by the investment.

• It can be determined from the formula: P=I/E, where: – P= the pay back period in years– I= Initial Investment– E= Annual after-tax earnings

• Example: If GH¢4000 is invest in a project with the aim of earning GH¢500 a year, the pay back is 4000÷500 = 8 years

• Decision criteria: Investments with shorter pay back periods more desirable.

Page 73: Project Analysis and Planning

Payback Period Cont’d.Payback Period Cont’d.• If however the project has uneven cash inflows, the

payback period will be determined by the cumulative cash flow over the duration of the project as indicated below:

Note: the payback period is 5 years

Year Cash Flow (Gh¢) Cumulative cash flow

0 (4000) (4000)

1 750 (3250)

2 750 (2500)

3 900 (1600)

4 1000 (600)

5 600 zero

6 400 400

Page 74: Project Analysis and Planning

Payback Period Cont’d.Payback Period Cont’d.

year Project1 Project 2 Project 3 Project 4 Project 5

0 (50) (100) (80) (100) (100)

1 5 50 40 40 30

2 10 30 20 30 30

3 15 20 20 20 10

4 20 10 20 10 10

5 20 20 5 20

6 10 20 10 40

Payback period (yrs)

Page 75: Project Analysis and Planning

Average Rate of Return (ARR)Average Rate of Return (ARR)• ARR expresses the profits or the average annual income

arising from a project, as a percentage of the initial capital cost

• It captures return on capital employed• ARR = (Average annual revenue/initial capital cost) x 100• Example: A project to replace a machinery is being appraised.

The machine will cost 240,000 and is expected to generate total revenues of 45,000 the projects five year life. What is the ARR of project?

Answer: ARR= (45,000/5)÷240,000 x100

= 9000 ÷ 24000 x 100 = 3.75%

Page 76: Project Analysis and Planning

Discounted Cash flow methods Discounted Cash flow methods

• Discounting is a technique that converts all benefits and costs into their value in the present.

• It is the process of finding the present worth of a future amount.

• The present worth is determined by multiplying the future amount by the expression 1/(1 + r)n , where:– r= interest rate and n= the year

• Generally, this expression is obtained in the form of DISCOUNT FACTOR from compounding and discounting tables.

Page 77: Project Analysis and Planning

Discounting cont’d.Discounting cont’d.• Discounting is based on the premise that a Cedi

received today is worth more than a cedi received in the future.

• This is based on the fact that any amount of money that is offered to be paid to you in future has lower worth than it's face value, mainly due to interest rate and inflation. Hence the need to discount

• Discounting is the opposite of compounding, which is the process of finding the future value of a present amount, growing at compound interest

Page 78: Project Analysis and Planning

Discounting Cont’d.Discounting Cont’d.

• The future value is determined by multiplying the present amount by the expression (1+r)n, where r= interest rate and n=year

• For example, if the interest rate is 10%, then GH¢100 placed in the bank today will be worth GH¢110 a year from now

• This means that if the interest rate is 10%, then GH¢110 to be received next year is worth only GH¢100 today.

Page 79: Project Analysis and Planning

Discounting Cont’d.Discounting Cont’d.

• If the interest rate is r, then the following formula can be used to find the present value (PV) of an amount (Pt) received at some time t in the future:

Page 80: Project Analysis and Planning

Discounting MethodsDiscounting Methods

• The most commonly discounted methods of measuring profitability of projects include:– Net Present Worth (Value)– The Benefit Cost Ratio– Internal Rate of Return

Page 81: Project Analysis and Planning

Net Present Value (NPV)Net Present Value (NPV)• Net present value of a project is the difference

between discounted benefits and discounted costs associated with a project.

• Net present value is the sum of discounted future cash flows to reflect their worth as of present day

• It is sum of the discounted benefits-discounted costs t=n

• NPV = Σ (Bt – Ct) / (1 + i)t t=0

where i = the discount factor t = time in years; Bt = Benefits in each

year Ct = Costs in each year• Note: present value for 0 years is always 1

Page 82: Project Analysis and Planning

Example of NPVExample of NPV

• Calculate the NPV of this project’s cash flows, using a discount rate of 10%

Year Cash Flow (GH¢) Discount Factor Present Value (GH¢)

0 (75,000) 1.000 (75,000)

1 10,000 0.909 9090

2 25,000 0.826 20,650

3 35,000 0.751 26,285

4 35,000 0.683 23,905

5 30,000 0.621 18,630

Page 83: Project Analysis and Planning

NPV Cont’d.NPV Cont’d.

• A positive NPV means the project is worthwhile, because the cost of tying up the investment in the project is compensated for by the resulting cash inflows

• If NPV>0 for a given discount rate, then project is acceptable, and not acceptable if NPV<0.

• If NPV =0, then project breaks even• When more than one project is being appraised,

choose the one that produces the highest NPV.

Page 84: Project Analysis and Planning

Benefit Cost RatioBenefit Cost Ratio• This is the ratio of Present Value of the Benefits to

the Present Worth of the Costs

• BCR=[Bt/(1+r)t] / [Ct/(1+r)t ]

• If B/C>1 for a given discount rate, then the project is acceptable and

• If B/C<1, then project not acceptable• If B/C=1, then Project breaks even• If more than I project, chose one with highest B/C• Example, calculate the CBR of the same project

that was used to calculate NPV (previous slide)

Page 85: Project Analysis and Planning

Calculation of BCRCalculation of BCR

• The BCR = PV of Benefit = 98560 = 1.31• PV of Cost 75,000

Year Initial cost

Discount factor

PV of Costs

Benefit DiscountFactor

PV of Benefit

0 75,000 1.000 75,000 -------- 1.000

1 0.909 10,000 0.909 9090

2 0.826 25,000 0.826 20,650

3 0.751 35,000 0.751 26,285

4 0.683 35,000 0.683 23,905

5 0.621 30,000 0.621 18,630

Present Value 75,000 Present Value 98,560

Page 86: Project Analysis and Planning

• Cost–benefit analysis is often used by governments and businesses, to evaluate the desirability of a given policy.

• It is an analysis of the expected balance of benefits and costs, including an account of foregone alternatives and the status quo, helping predict whether the benefits of a policy outweigh its costs, and by how much (i.e. one can rank alternate policies in terms of the ratio of costs and benefit).

Page 87: Project Analysis and Planning

Internal Rate of ReturnInternal Rate of Return

• The IRR is the discount rate, which reduces NPV to zero

t=n

IRR = Σ (Bt – Ct) / (1 + i)t = 0. t=0

• The project is acceptable if IRR opportunity cost of capital

• IRR answers the question: 'What level of interest will this project be able to withstand?’

Page 88: Project Analysis and Planning

• To compute IRR, guess the discount rate and compute the NPV.

• If the NPV is Positive, select a larger discount rate, If NPV is Negative, select smaller discount rate

• Recomputed NPV until value is zero • Or extrapolate by first using two discount rates that

will give a positive and negative NPV and extrapolate, using the formula:

• IRR = Discount rate with +ve NPV + Difference between the two discount rates x Positive NPV  

• Range of +ve to -ve NPVs

Page 89: Project Analysis and Planning

Illustration of NPV and IRRIllustration of NPV and IRR• An initial investment of GH¢2 500 in a project produces cash inflows of

GH¢750, GH¢750, GH¢900, GH¢900 and GH¢595 at 12 month intervals. The cost of capital to finance the project is 12 %. 

• You are required to decide whether the project is worthwhile using:• The Net Present Value • The Internal Rate of Return

Year 0 1 2 3 4 5

Cash flow (2500) 750 750 900 900 595

Page 90: Project Analysis and Planning

AnswerAnswer

Year Cash flow Discount factor @ 12% Present value

0 (2500) 1.000 (2500)

1 750 0.893 669.75

2 750 0.797 597.75

3 900 0.712 640.80

4 900 0.636 572.40

5 595 0.567 337.37

Net present value £318.07

1) Computing NPV

The NPV is positive which makes the project worthwhile

Page 91: Project Analysis and Planning

Answer Cont’d.Answer Cont’d.2) Computing for IRR• The above calculation for NPV used a 12% discount rate and

produced a positive value of GH¢318.07. • We need to find a discount rate that produces a negative

NPV. Let's try 20 %.

• The IRR lies between 12 % and 20 %. But we can get much closer to the precise answer by using arithmetic.

Year Cash flow Discount factor @ 20%

Present value

0 (2500) 1.000 (2500)

1 750 0.833 624.75

2 750 0.694 520.50

3 900 0.579 521.10

4 900 0.482 433.80

5 595 0.402 239.19

Net present value (£160.66)

Page 92: Project Analysis and Planning

Answer on computing IRR cont’dAnswer on computing IRR cont’d

• IRR = 12 % + Difference between the two discount rates x positive NPV NPV  

range of +ve to -ve NPVs  

• IRR = 12 % + (8 % * 318.07) 478.73 

• IRR = 12 % + 5.32IRR = 17.32 %

Page 93: Project Analysis and Planning

Economic AnalysisEconomic Analysis• This is undertaken to ascertain the overall impact of

the project on a country's economy and wider society.

• In the financial analysis, which was the focus of the previous analyses, the emphasis is mainly on financial or monetary costs and benefits at the neglect of wider economic benefits or costs

• In economic and social analysis ( social cost benefit analysis) the project is examined using the whole country as the accounting entity with broader development objectives of the country.

Page 94: Project Analysis and Planning

Economic Analysis Cont.Economic Analysis Cont.

• Critical questions during economic and social analysis (social cost benefit analysis) the analysis include the following:– What are the direct economic benefits and costs

measured in terms of shadow (efficiency) prices & not market prices?

– What will be the impact of the project on the level of savings & investment in the society (country)?

– What would be the impact of the project on distribution of income?

Page 95: Project Analysis and Planning

Economic Analysis Cont.Economic Analysis Cont.

• In computing economic NPV and Economic Rate of Return (ERR) use the stream of financial costs and benefits and remove from them identifiable transfer payments such as taxes and direct subsidies

• Similarly, for the economic NPV the discount factor “i” will be the opportunity cost of capital for the economy, which is the Bank of Ghana prime rate, as against the interest rate of the project credit facility used for the financial appraisals.

Page 96: Project Analysis and Planning

Other Dimensions of Social Other Dimensions of Social AnalysisAnalysis

• A project will not be effective & sustainable if:– it is inconsistent with the socio-cultural realities

of the people– There is wide perception of injustice (may lead to

conflicts & instability)– Local people are not organized around the

project to continue with the project activities, or project linked to existing institutions to continue project activities after it ends

Page 97: Project Analysis and Planning

Social Analysis cont’d.Social Analysis cont’d.• The social analysis examines broader social implications of

proposed investments (project), including the following:– Extent project addresses felt needs of the people.– Sense of ownership & commitment to project by

beneficiaries– Level of support or acceptability of project objectives and

activities by wider community members– Sense of equity in sharing of project benefits– Employment opportunities and Income distribution– Effects of project on particular groups– Consistency of project with values & beliefs of community– What modification in the target groups’ behaviour pattern is

anticipated?

Page 98: Project Analysis and Planning

Environmental Impact Assessment (EIA)Environmental Impact Assessment (EIA)

• EIA is a process that ensures that environmental matters are taken into account early used early in the project planning process

• The EIA process identifies, predicts interprets & communicates information about impact of the project on biophysical environment (air, water, land, plants & animals)

• This is necessary because there is likely to be self destruction or system failure if the environmental impact of a project is so severe

• E.g if an agric project leads to severe degradation of the soil, then the soil will eventually fail to support the crops

Page 99: Project Analysis and Planning

Environmental Assessment Cont’dEnvironmental Assessment Cont’d

• A Sustainable Project should seek to enhance the natural resource base, but not to deplete or severely damage it

• Environmental Impact Assessment is often required to determine the possible environmental effects and any mitigation measures to take.

• Development projects such as dam, road, & power line construction bring about changes in the ecosystem in which they are undertaken. Such changes affect both the environment and well being of man, unless mitigation measures are taken

Page 100: Project Analysis and Planning

Environmental Assessment Cont’dEnvironmental Assessment Cont’d

• Key questions during Env’tal Assessment: i. What are the likely environmental impacts from

undertaking a project?ii. What is the cost of reducing the negative

impact?iii.Are there alternative ways of supplying the good

or service of project without incurring these environmental costs?

iv.What are the costs of these alternatives

Page 101: Project Analysis and Planning

PROJECT IMPLEMENTATION PROJECT IMPLEMENTATION TECHNIQUESTECHNIQUES

Key Activity Areas During project Implementation:• Establish an appropriate project organization.• Prepare and maintain a project workplan.• Mobilize project resources.• Manage staff.• Manage funds.• Manage materials and facilities.• Maintain facilities.• Monitor and evaluate progress.• Maintain Communications.• Review project relevance

Page 102: Project Analysis and Planning

Establish Appropriate Project OrganizationEstablish Appropriate Project Organization

• Responsibility for project implementation must be assigned to an appropriate organization.

• If one does not exist, then a new one must be designed and staffed.  

• This may begin with the appointment of a project manager who may be charged with the task of designing the project organization structure, if non-exists

• In designing the project organization, we must relate the positions to the work that has to be accomplished.

• A useful technique or tool that can be used is the Work Breakdown Structure (WBS).

• Various forms of organization structures are designed to implement projects.

Page 103: Project Analysis and Planning

What is WBSWhat is WBS• The work breakdown structure is a technique for

breaking down a job (a project) into its component elements which can be displayed to show the relationship of the elements to each other and to the whole project

• It is a sub division of the project into smaller and manageable bits

• It seeks to break the project down into “work packages” which are assignable and for which accountability can be expected

Page 104: Project Analysis and Planning

WBS cont’d.WBS cont’d.• The WBS ensures that all the work required to

achieve the project objectives is included in the project plan

• It forms a logical organized base from which to:– establish cost accounts– define work packages– develop budgets– establish schedules– establish life cycle costs

• The WBS can be represented either in a graphical tree format (like an organizational chart) or in an indentured or textual format

Page 105: Project Analysis and Planning

HOUSEHOUSE

CIVILCIVILPLUMBINGPLUMBING ELECTRICALELECTRICAL

FOUNDATIONFOUNDATION WALLS/ROOFWALLS/ROOF PIPINGPIPING SEWERAGESEWERAGE WIRING APPLIANCES

FIGURE 1 House Project WBS Subdivided into Boxes

Page 106: Project Analysis and Planning

The Numbering or Coding SystemThe Numbering or Coding System -WBS -WBS

HOUSE1.0.0

CIVIL1.1.0

PLUMBING1.2.0

ELECTRICAL1.3.0

Foundations1.1.1

Walls/Roof1.1.2

Piping1.2.1

Wiring1.3.1

Fitting1.3.2

H/C Water

1.2.2

Page 107: Project Analysis and Planning

Various forms of organizationVarious forms of organization

• Various forms of organization structures are designed to implement projects. These are:

i. Project as part of a functional organization (Department-led)

ii. Matrix Structureiii. Separate project organizationiv. Project as a staff function.

Page 108: Project Analysis and Planning

Project as part of a functional Project as part of a functional organizationorganization

Finance Production Engineering Marketing

Project A Mechanical Electrical Civil Transport

MANAGING DIRECTOR

ADMINISTRATION ENGINEERING FINANCE OPERATIONS

Page 109: Project Analysis and Planning

Matrix StructureMatrix Structure

MD

PROJ ECT A PROJ ECT B

PROJECTS FINANCE PRODUCTION ENGINEERING

MANAGING DIRECTOR

Page 110: Project Analysis and Planning

Pure Project StructurePure Project Structure

PROJECT MANAGER

ADMINISTRATION OPERATION ENGINEERING FINANCE

MECHANICAL ELECTRICAL CIVIL TRANSPORT

Page 111: Project Analysis and Planning

Tips for effective organization of Tips for effective organization of workwork

• Once the structure has been agreed upon, job descriptions have to be prepared for the various positions.

• This will include responsibilities, limits of authority, how performance will be measured and personnel specifications.

• There is also the need to formulate and document administrative policies and operational procedures, which can guide both the project team and other staff.

• Terms of reference for all expatriate and external personnel, consultants and technical experts should also be prepared.

• After all these preparatory work the project team is then recruited with the active involvement of the Project manager

Page 112: Project Analysis and Planning

• The project manager must possess leadership qualities;

• He/she must be a facilitator giving equal attention to all critical areas of the project

• He/She must also have technical administrative, and political credibility.

Page 113: Project Analysis and Planning

Prepare and Maintain a Project WorkplanPrepare and Maintain a Project Workplan

• A workplan is a written statement, which describes in concrete terms the specific activities required to execute the project, the duration of each activity, who is responsible and the resources needed.

• Prior to preparing a detailed Workplan for implementation, it is, important to review project priorities to ascertain their relevance.

• This is necessary because usually, there is a long time span between project design and project implementation.

• During the time lapse, a lot of things may have changed on the ground to perhaps warrant a review of the project plan or design.

Page 114: Project Analysis and Planning

Steps in preparing workplanSteps in preparing workplan

i.    Breakdown the project into its constituent activities.ii. Determine the duration of each activity.iii.   Determine start and finish dates of each activity. iv.   Assign responsibility v.    Determine the resources required • Various advance techniques are used to prepare

detailed plans for implementation. These include Critical Path Method, Gantt or Bar Charts.

• Workplans have to be updated periodically depending on the progress of work.

Page 115: Project Analysis and Planning

• The work plan does the following: – Guides plan or project implementation– Serves as a means of control– Helps to do the right things in the right order

since we have to do many different things– Tells us when to start and finish each activity

and the project as a whole

Page 116: Project Analysis and Planning

A FORMAT OF A WORKPLANA FORMAT OF A WORKPLAN

Activity Action Step

Responsibility

Time Frame Resources Milestone /Intermediate Output

Remarks

1.

2.

3.

4.

5.

6.

7.

Start Finish

Page 117: Project Analysis and Planning

Gantt or bar ChartGantt or bar Chart• One of the most popular project planning techniques

for scheduling, reporting, and control of simple projects is the Gantt or bar chart.

• This technique graphically represents the progress of a project versus the time frame within which it must be completed

• They can be used as simple and easily understood models for communicating information to all levels or for project management & supervisors supervision.

• Gantt charts allow project managers to plan all activities, estimate the time necessary to complete each, the time required to complete overall project

Page 118: Project Analysis and Planning

Gantt Chart Cont’dGantt Chart Cont’d• To prepare a Gantt chart:

– List each of the discrete project activities or tasks that needs to be completed

– Establish the execution sequence of these activities– Estimate the duration of these activities (done in

collaboration with those responsible for completing the activities)

– List all activities in chronological order and determine those that can be carried out simultaneously & those that must be carried out sequentially.

Page 119: Project Analysis and Planning

Gantt Chart Project Example Gantt Chart Project Example

10/21 10/28 11/4 11/11 11/18 11/25 12/2

Dig basement

Pour footing

Lay block

Finish base work

Install main floor

Erect frame

Secure sheathing

Install roof boards

Install windows

Finish frames

Activity

Milestone

1 2 3 4 5 6 7Week

Task Bar

Milestone

Page 120: Project Analysis and Planning
Page 121: Project Analysis and Planning

Monitoring & Evaluation of ProjectsMonitoring & Evaluation of Projects

• Monitoring and evaluation are important components of project implementation

• There is usually need to design a monitoring and evaluation system to help track the implementation and performance of a project.

Page 122: Project Analysis and Planning

What is Monitoring? What is Monitoring? • Monitoring is the systematic and continuous

assessment or tracking of the progress of a piece of work or a project.

• It means constantly checking how things are going & comparing actual progress to what was planned.

• Within project context, monitoring is the tracking of resource acquisition & allocation, cost, production of goods & services, delivery of goods/services, and intermediate outcomes.

Page 123: Project Analysis and Planning

Why Monitor?Why Monitor?• Monitoring provides managers with information to:

– analyze current situation, – keep project activities on schedule, – track progress of a project towards set objectives– enhance accountability– draw lessons to guide decision making.

• The prime purpose of monitoring is to learn and adapt in order to maximize the value of the intervention.

• However, the monitoring information can feed into any external evaluation

Page 124: Project Analysis and Planning

Key Questions that Monitoring Key Questions that Monitoring Seeks to AddressSeeks to Address

• To what extent is the project execution consistent with the design or plan?

• To what extent are planned activities actually realized?

• Are we making progress toward achieving the set targets and objectives?

• What services are provided, to whom, when, how often, for how long, and in what context?

• How well are the services/ products provided?• What is the quality of the services/ products

provided?• What is the cost per unit service/ product?•

Page 125: Project Analysis and Planning

Domains of MonitoringDomains of Monitoring

• Inputs—Resources/ Investments going into conducting and carrying out the project or programme. These could include staff, finance, materials, and time.

• Process --- Project activities and how they are being carried out

• Outputs—Immediate visible, concrete and tangible results obtained through the execution of activities (e.g., number of water points, number of staff trained)

• Outcomes: Observable changes as a result of the outputs

Page 126: Project Analysis and Planning

What to monitor: What to monitor: 1. 1. Management/Administration

Information to be collected Sources of Information Use of InformationStaff/Personnel Issues

Performance Absenteeism Problems Expectations How staff Work as Team Whether Staffing Structures Work

Staff/Team Meetings Staff Reviews Supervision Informal Meetings Observation

Give Staff support and Feedback Training and Staff Development Improve Management Practices Modify/Clarify Job Descriptions

Vehicles Fuel Consumption Mileage Repairs New Parts Capital and Running Costs Performance

Log Book of Fuel and Mileage

Record Sheets of Repairs and Spare

Records of Money spent on each Vehicle

Meetings with Driver Observation

Decisions about replacing Old Vehicles when the become uneconomical to run

Compare different makes of Vehicle Check Mechanic’s Performance re:parts

fitted, frequency of repairs, etc. Identify problems, e.g. excessive fuel

consumption

Supplies Where to Obtain Supplies Cost from Different Supplies Stock levels Re-order Levels Items about to Run Out Time Needed to Supply

Suppliers, Catalogues Inventory of Stocks

Stock-keeping Record System

Obtain best value supplies Obtain supplies on time Maintain adequate stock levels

Page 127: Project Analysis and Planning

What to monitor cont’d.What to monitor cont’d.2. Finance2. Finance

Information to be Collected Sources of Information

Use of Information

project Budget and Expenditure

• Expenditure by budget headBalance of budget remaining this yearRegularly recurring items of expenditure,Previous year’s budget and expenditureRates of inflationExchange rates

Invoices & vouchers Budget break-down Analysis of budget

and expenditure, Newspapers, banks

Predict expenditure for budgeting Compare costs of different projects Identify areas of excessive expenditure Identify any savings Compare costs with project achievements

to assess cost- effectivenessStaff Salaries

Salaries Tax, insurance, etc. Annual increments Final pay Other payments: e.g. health allowance, staff

loans

Staff records Payslips Salary records

Ensure staff are paid according to pay scale reflecting nature of job and length of service

Ensure other payments are made according to correct procedures

Ensure all staff know what benefits they are entitled to

Cash Flow Analysis

When is cash needed for project? Where will cash come from? (might include

loan repayments, sales etc) What and when are cash outgoings? (regular

and irregular)

Cash record system To ensure sufficient but not excessive cash is available

Page 128: Project Analysis and Planning

What to monitor cont’d.What to monitor cont’d.3. 3. Project ActivitiesProject Activities

Information to be collected Sources of Information Use of Information

Results of Activities, Project Outputs

What has been done What has not been done but was

planned What problems have been uncounted How the problems have been

addressed How external situation has changed

Regular records of activities Supervision reports Meetings with staff, project

partners, and people affected by the work

Informal discussion Observation Surveys

Plan future work Identify project successes & opportunities Identify problems /weaknesses, & plan

strategy Review priorities Identify training needs Identify need for further information or

research, Project Inputs

What is needed, when & where to find it and at what cost

From suppliers, other organizations, etc.

Plan and schedule activities Monitor costs and budget

Progress of Project According to Objectives

Progress towards achieving objectives Are objectives still relevant?

Information about key indicators

Observation

Modify strategy and/or objectives if necessary

Feedback Identify need for further improvements

in monitoring systems

The Way project is managed how things are done (process)

How are decisions made? Are the people who are supposed to

be involved really involved? Do beneficiaries feel a sense of

ownership of the programme?

Indicators which show degree of participation

Meetings, discussions Observation

Show need to change management style Identify need to change methods to

encourage more participation Identify problems in relationship

between partners, people affected by the work , staff, etc and address them

Page 129: Project Analysis and Planning

Performance-Based MonitoringPerformance-Based Monitoring

• Traditional monitoring focuses on implementation issues (i.e., tracking of inputs, activities and outputs)

• performance–based monitoring goes beyond the tracking of inputs and outputs to the regular collection and analysis of actual results (i.e., outcomes and impacts).

Page 130: Project Analysis and Planning

What is Evaluation?What is Evaluation?

• In ordinary usage, evaluation is the process of determining the merit, worth, or value of a programme

• In a technical sense, evaluation is the process of making judgments about a project based on systematic data collection and analysis relative to specific issues of interest, like project relevance, effectiveness, efficiency etc.

Page 131: Project Analysis and Planning

Areas of Evaluation.Areas of Evaluation.

• Evaluation exercises often seek to collect & analyse data on the following:

i. Relevance: Are the programme objectives clear and appropriate? Are the activities the best way of achieving the objectives?

ii. Effectiveness: To what extent have the objectives been achieved or the progress being made towards achieving the programmme objectives

Page 132: Project Analysis and Planning

Areas of Evaluation Cont’d.Areas of Evaluation Cont’d.

iii. Efficiency: How well activities are being carried out. i.e cost effectiveness or value for money. For example is the organizational arrangement or the way activities are carried out conducive to efficient mode of operations?

iv. Results: What difference has the programme made in the life of the beneficiaries?

Page 133: Project Analysis and Planning

Areas of Evaluation Cont’d.Areas of Evaluation Cont’d.

v. Sustainability: Refers to the capacity of a project to continue the activities and deliver the intended benefits for a long time after the financing period.

• Sustainability analysis of a project may be examined under 5 dimensions: – Social– Economic– Environmental– Technical– Organizational capacity