Upload
mike-mckinna
View
218
Download
0
Embed Size (px)
Citation preview
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 1/20
Prepared By:
Kolton Chapman, Petroleum Engineering Technology Student
Prepared For:
Craig Sinclair, Manager Tupper Operations, Murphy Oil Company Ltd.
& Anthony Wallace, Petroleum Engineering Technology Instructor
Artificial Lift ProductionEvaluation and Optimization on
Gas Wells
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 2/20
Agenda1) Background2) Introduction
3) Tupper GGS SCADASystem
4) Intermitter Graph (WellB)
5) BJ Services (BakerHughes)
6)Weighted FoamerDecline Curve
7) Tundra PetroleumServices
8) Plunger Lift Explanation
9) Production Control
10) PCS Quotes &Economics
11) Premier IntegratedTechnologies
12) PIT Quotes &Economics
13) Tupper Field Feedback
14) PIT Plunger DeclineCurve
15) PCS Plunger DeclineCurve (G Well)
16) Conclusion
17) Recommendations
18) Question Period
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 3/20
Background Murphy Oil Company Ltd. (MOCL) appointed Mr.
Craig Sinclair as my mentor for this project. Craigis an experienced Chemical EngineeringTechnologist, R.E.T. and is Manager of Tupper
Operations The field analyzed is the Tupper field located in
North Eastern British Columbia South of DawsonCreek
This field was purchased by MOCL in 2007 fromBear Ridge Resources, and the first day ofproduction out of this field was December of 2008
The Tupper field produces shale gas
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 4/20
Introduction To determine the best approach for Murphy Oil
Company Ltd. towards installing artificial lift inseven currently liquid loaded gas wells
Analyzed based upon simple economics,attainable production rates, maintenance costs,and installation costs
MOCL Approved Service Companies/
Control System
Artificial Lift Application
Capillary String Foamer Plunger Intermitter
BJ Services (Baker Hughes) x Tundra Petroleum Services x
Production Control Services x
Premier Integrated Technologies x
Tupper GGS SCADA System x
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 5/20
Tupper GGS SCADA System• The systems full name is “Tupper Gas Gathering System
Supervisory Control and Data Acquisition System”
• The Tupper GGS SCADA System controls the entireTupper field and plant
• The operator can enable or disable an “Intermitter timer”
which closes and opens the flow choke, therefore havingthe ability to shut-in the well and build formation pressure
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 6/20
Intermitter Graph (Well B)
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 7/20
BJ Services (Baker Hughes) The company has last conducted water sampling out
of the producing formation on July 7, 2009. The watersamples were analyzed using a “Foam Blender Test”
and “Foam Tower Test”
Foamer
Supplier Product Cost
($/L FOB)
Initial
Batch Cost
(25 L)
Daily
Operating Cost
($/day)
Monthly
Operating Cost
($/month)
Comments
BJ Services
(Baker Hughes) $ 5.75 $ 143.75 $ 57.50 $ 1750.15
No noticeable production
increase yet shut in times
slightly reduced.
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 8/20
Weighted Foamer DeclineCurve
It was suspected that this batching was unsuccessful due to theinability to get the foamer through the high level of liquid in thewell, therefore MOCL did not proceed to inject foamer into any
wells
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 9/20
Tundra Petroleum Services Tundra Petroleum Services is a Western
Canadian based capillary tubing service company
Capillary String Quote Unit cost Unit Amount Total
Line Cost ($/meter) $ 7.50 2785m $21,037.50
Mileage- Capillary Unit ($/km) $ 3.75 700 km $2,625.00
Mileage- Support Pickup ($/km) $ 1.25 700 km $1,085.00
Capillary Hanger w/ Injection Control Valve n/a n/a $2,350.00
Set Up/Installation Charge n/a n/a $2,445.00
Surface Equipment n/a n/a $7,150.00
Well A: Total Estimated Cost $ 37,192.50
Well
Prod.Volume
Prior To
Capillary
String
(e3m³/d)
ExpectedProd.
Volume
After
Install
(e3m³/d)
Expected
Prod.
Volume
Increase
(e3m³/d)
Capital Cost
(Including Cap.
String and initial
foamer batch of
25L)
Operating Cost
($/d)
Expecting
injection rate of
10L/d
Application
Payback
Period
(days)
A 10 16 6 $37,336.25 $ 57.50 45.8
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 10/20
Plunger Lift Explanation Plunger lift technology is a type of artificial lift
(AFL) that is very accepted in the oil and gasindustry because it only uses the wells natural
energy to help lift fluids out of the wellbore rather
than an external power source
http://www.fergusonbeauregard.com/downloads/Introduction_to_Plunger_Lift.pdf
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 11/20
Production Control Services(PCS) Data Sheets filled out and sent to PCS
Plunger lift evaluation completed by PCS using:Fekete Virtuwell Software, and Foss & GaulEquations
Once calculations completed PCS produced aconventional plunger recommendation for eachwell stating : whether a plunger lift candidate ornot, size of plunger to be used, and cycle times
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 12/20
PCS Quotes & Economics
Actual Conventional 63.0mm Plunger Quote Unit cost
Swabbing Cost $ 3,100.00 Standard Plunger Lift Components $ 7,555.50
Service Charges & Installation Estimate $ 2,500.00
Estimated Total $ 13,155.50
Actual Conventional 73.0mm Plunger Quote Unit cost
Swabbing Cost $ 3,100.00
Standard Plunger Lift Components $ 11,127.25
Service Charges & Installation Estimate $ 2,500.00
Estimated Total $ 16,727.25
Well
Prod.
Volume
Prior To
Plunger
Lift
(e3m³/d)
Expected
Prod.
Volume
After
Install
(e3m³/d)
Expected
Prod.
Volume
Increase(e3m³/d)
Capital Cost
($)
Operating Cost ($/d)
*Expecting
replacement due to
solids wear in 2years
Application
Payback
Period
(days)
A 10 14 4 $ 13,155.50 $ 18.00 24.4
B 11 15 4 $ 13,155.50 $ 18.00 24.4
C 11 16 5 $ 13,155.50 $ 18.00 19.4
D 11 14 3 $ 16,727.25 $ 22.89 41.9
E 24 26 2 $ 13,155.50 $ 18.00 50.8
F 19 21 2 $ 13,155.50 $ 18.00 50.8
G 10 12 3 $ 13,155.50 $ 18.00 33.1
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 13/20
Premier IntegratedTechnologies Premier Integrated Technologies (PIT) is the only
Canadian provider of the Pacemaker Plunger Lifttechnology
The Pacemaker plunger is a two piece plunger
Pacemaker plunger technology allows continuousgas flow rates from wellhead to plant inlet, whichcreates less problems regarding gas processing
http://www.mgmwellservice.com/images/variety-new.jpg
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 14/20
PIT Quotes & Economics
Actual Pacemaker Technology 63.0mm
Plunger Quote Unit cost
Swabbing Cost $ 3,100.00 Standard Plunger Lift Components $ 9,022.00
Service Charges & Installation Estimate $ 2,700.00
Estimated Total $ 14,822.00
Actual Conventional 73.0mm Plunger Quote Unit cost Swabbing Cost $ 3,100.00
Standard Plunger Lift Components $ 6,336.90
Service Charges & Installation Estimate $ 2,500.00
Estimated Total $ 12,136.90
Well
Location
Prod.
Volume
Prior To
Plunger
Lift
(e3m³/d)
Expected
Prod.
Volume
After
Install
(e3m³/d)
Expected
Prod.
Volume
Increase(e3m³/d)
Capital Cost
($)
Operating Cost ($/d)
*Expecting
replacement due to
solids wear in 2years
Application
Payback
Period
(days)
A 10 14 4 $ 14,822.00 $ 20.29 27.4
B 11 15 4 $ 14,822.00 $ 20.29 27.4
C 11 16 5 $ 14,822.00 $ 20.29 22.0
D 11 14 3 $ 12,136.90 $ 16.61 30.6
E 24 26 2 $ 14,822.00 $ 20.29 57.7
F 19 21 2 $ 14,822.00 $ 20.29 57.7
G 10 12 3 $ 14,822.00 $ 20.29 37.4
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 15/20
Tupper Field Feedback In the past year there has been three plunger lift
applications installed in the Tupper field
Two PIT Pacemaker plungers & one PCSconventional plunger
During the evaluation of report the Tupper fieldexperienced salt precipitation (halite) occurring ina few producing wells
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 16/20
PIT Plunger Decline Curve
Plunger Lift
Applied
Intermitter Enabled
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 17/20
PCS Plunger Decline Curve
Intermitter Enabled Plunger Installed
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 18/20
Conclusions
Premier Integrated Technologies Pacemaker technology is thebest solution for removing liquid loading due to the Tupper fieldspast experiences with this technology installed on wells that areno longer able to flow on intermitters
Capillary Strings are very expensive compared to plunger lift,therefore making this application not as economical as plunger
lift technology. Further weighted foamer analysis needs to takeplace before this AFL application is considered, which will allow abetter understanding towards achievable production rates whenusing capillary strings
Production Control Services does not sell Pacemaker PlungerLift Technology, which allows a well to flow 24 hours a daytherefore allowing less pipeline, and gas processing problems.
Also PIT’s conventional plungers are more economical for Murphy Oil Company than the PCS’s conventional plunger applications
Weighted foamer is currently not a solution for unloading liquidloaded gas wells in the Tupper Field
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 19/20
Recommendations After analysis has been completed it is concurred thatthere is no single artificial lift option that can solve every
liquid loaded well problem in the Tupper field. It isrecommended that liquid loaded wells that flow less than10 E3m³/d, should immediately have an intermitter timerenabled to increase daily gas production. Once a well is
experiencing serious liquid loading to the point that anintermitter is not effective at keeping it flowing; PITPacemaker plunger technology should be installed if thewell meets all criteria. If the well doesn’t meet Pacemaker plunger lift criteria I recommend installing a PITconventional plunger application. Plunger lift will help with
future salt precipitation in the majority of the tubing, yet it isnot a completely effective solution. I don’t recommendusing the BJ RCI 08025W weighted foamer again in theTupper field, because in the past it has not removed anyliquid loading due to high liquid columns in the wellbore.
8/2/2019 Project 310 PP
http://slidepdf.com/reader/full/project-310-pp 20/20
Question Period