AL UDEID POWER PLANT GT5 Installation | Page 1 of 3 Doc#: PROJ/14/GT5/12-034 Report#: PROJ/14/GT5/12-034 Start Date: 17 Nov 2014 Workforce : Equipment / Tools: 1. Al-Dana-4 1. Phase E-Piping (Client Scope) by Powertech. 70% completed a) Excavation(Hand digging) 100%completed b) Gas pipe line 80%completed Fabrication Radiography Hydro test Nitrogen purging Air blow Sand Bedding & Back Filling Tie-in 100%completed 100%completed - - - 50%completed - c) Compressed air and service water & Deminlines 95%completed d) Drain lines To be started Current Work Activity Piping 1. Fabrication and erection of compressed air line(1”) to ventilation and combustion filters. 2. Compressed air line Pre fabrication (Final spool from main header to turbine nozzle). 3. Sand Bedding. 4. Radiography. Status / % completed: 100%completed 100%completed 50%completed 100%completed Planned Work Activity (Monday). Piping . 1. Compressed air line erection .(Till turbine Nozzle.) 2. Installation of gas line final spool. 3. Hydro test (If RT result finds good) Delays & Stoppage of Work Issues 1. HSE Issues 1. Nil Remarks: 1. Photos 1. Please refer to next page. \ Day / Date: Sunday,28/12/2014 Weather: Sunny,windy Ambient condition: ˚C Working Hours: 7.30 – 19.00hrs Prepared by: Raghuram Reviewed by: Afsal

PROJ-14-GT-5-12-034

Embed Size (px)

DESCRIPTION

[po

Citation preview

  • AL UDEID POWER PLANT GT5 Installation | Page 1 of 3

    Doc#: PROJ/14/GT5/12-034

    Report#: PROJ/14/GT5/12-034 Start Date: 17 Nov 2014

    Workforce: Equipment / Tools: 1. Al-Dana-4 1. Phase E-Piping (Client Scope) by Powertech. 70% completed

    a) Excavation(Hand digging) 100%completed b) Gas pipe line 80%completed

    Fabrication Radiography Hydro test Nitrogen purging Air blow Sand Bedding & Back Filling Tie-in

    100%completed 100%completed

    - - -

    50%completed -

    c) Compressed air and service water & Deminlines 95%completed d) Drain lines To be started

    Current Work Activity Piping

    1. Fabrication and erection of compressed air line(1) to ventilation and combustion filters.

    2. Compressed air line Pre fabrication (Final spool from main header to turbine nozzle).

    3. Sand Bedding. 4. Radiography.

    Status / % completed: 100%completed 100%completed 50%completed 100%completed

    Planned Work Activity (Monday). Piping.

    1. Compressed air line erection .(Till turbine Nozzle.) 2. Installation of gas line final spool. 3. Hydro test (If RT result finds good)

    Delays & Stoppage of Work Issues 1.

    HSE Issues 1. Nil

    Remarks: 1.

    Photos 1. Please refer to next page.

    \

    Day / Date: Sunday,28/12/2014 Weather: Sunny,windy Ambient condition: C Working Hours: 7.30 19.00hrs Prepared by: Raghuram Reviewed by: Afsal

  • AL UDEID POWER PLANT GT5 Installation | Page 2 of 3

    Doc#: PROJ/14/GT5/12-034

    Figure1SandBedding

    Figure2Prefabricationofcompressedairlinefinalspool(Frommainheadertoturbinenozzle)

  • AL UDEID POWER PLANT GT5 Installation | Page 3 of 3

    Doc#: PROJ/14/GT5/12-034

    Figure3Alldropins(Compressedair,Demin,Servicewater)

    Figure3Compressedairline(1)connectiontoCombustionairFilter