AL UDEID POWER PLANT GT5 Installation | Page 1 of 3
Doc#: PROJ/14/GT5/12-034
Report#: PROJ/14/GT5/12-034 Start Date: 17 Nov 2014
Workforce: Equipment / Tools: 1. Al-Dana-4 1. Phase E-Piping (Client Scope) by Powertech. 70% completed
a) Excavation(Hand digging) 100%completed b) Gas pipe line 80%completed
Fabrication Radiography Hydro test Nitrogen purging Air blow Sand Bedding & Back Filling Tie-in
100%completed 100%completed
- - -
50%completed -
c) Compressed air and service water & Deminlines 95%completed d) Drain lines To be started
Current Work Activity Piping
1. Fabrication and erection of compressed air line(1) to ventilation and combustion filters.
2. Compressed air line Pre fabrication (Final spool from main header to turbine nozzle).
3. Sand Bedding. 4. Radiography.
Status / % completed: 100%completed 100%completed 50%completed 100%completed
Planned Work Activity (Monday). Piping.
1. Compressed air line erection .(Till turbine Nozzle.) 2. Installation of gas line final spool. 3. Hydro test (If RT result finds good)
Delays & Stoppage of Work Issues 1.
HSE Issues 1. Nil
Remarks: 1.
Photos 1. Please refer to next page.
\
Day / Date: Sunday,28/12/2014 Weather: Sunny,windy Ambient condition: C Working Hours: 7.30 19.00hrs Prepared by: Raghuram Reviewed by: Afsal
AL UDEID POWER PLANT GT5 Installation | Page 2 of 3
Doc#: PROJ/14/GT5/12-034
Figure1SandBedding
Figure2Prefabricationofcompressedairlinefinalspool(Frommainheadertoturbinenozzle)
AL UDEID POWER PLANT GT5 Installation | Page 3 of 3
Doc#: PROJ/14/GT5/12-034
Figure3Alldropins(Compressedair,Demin,Servicewater)
Figure3Compressedairline(1)connectiontoCombustionairFilter